ML20083H806

From kanterella
Jump to navigation Jump to search

Notifies of Equipment Qualification Problems Which Could Result in Request for Extension of 10CFR50.49 Rulemaking Deadline
ML20083H806
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 01/06/1984
From: Gucwa L
GEORGIA POWER CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 NED-84-013, NED-84-13, TAC-42505, TAC-42506, TAC-55488, TAC-55489, NUDOCS 8401130357
Download: ML20083H806 (2)


Text

__ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _

Georgia Power Company

, _f 333 Pednont Avenue Atlanta Geo gia 30308 Telephone 404 5266526 Maibog Address:

Post oftce Box 4545 Atlanta, Gectga 30302 Georgia Power L.T.Gucwe  !*e sournern euccroc sy-tem Manager Nuclear Engineenno and Ctael Nuclear Engreer NED-84-013 January 6, 1984 Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 Division of Licensing U. S. Nuclear Regulatory Commission Washirgton, D. C. 20555 NRC DOCKET 50-366

!. OPERATIE LICENSE NPF-5 EDiIN I. HATCH NIELEAR PIANT UNIT 2 NOTIFICATION OF POTENPIAL PROBLEM REGARDIE

THE 10 CFR 50.49 EQUIPMENP QUALIFICATION DEADLINE l

l Gentlenen:

In accordance with the requirements of 10 CFR 50.49(h), Georgia Power Conpany (GPC) hereby provides notification of equipnent qualification problems which could result in a request for extension of the rulemakirg deadline (i.e., end of the second refueling outage after March 31, 1982).

The problems beirg encountered involve the qualification testirg program for the post-accident hydrogen and oxygen monitoring system heat tracing apparatus. 'Ihis heat tracing is to be installed at Plant Hatch Unit 2 during the upcoming refueling / recirculation pipe replacement outage as part of the GPC program for meetirg the requirements of NUREG-0737. GPC was informed by the equipment verxior on November 9, 1983 that the testirg program might not be conpleted by the forecast qualification deadline.

Current plans call for coupletion of the heat tracirg qualification program by September 1984; however, the currently projected Hatch Unit 2 qualification deadline (end of the upcoming outage) is before September 1984. Due to many uncertainties inherent in the recirculation pipe replacement project, it is not possible to exactly predict the end date for the scheduled outage. Once the schedules for the heat tracing qualification 8401130357 840106 PDR ADDCK 05000366 P PDR

\

e

  • GeorgiaPowerA Director of Nuclear Reactor Regulation Attention: . Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 January 6, 1984 Page Two and the pipe replacemnt have been more firmly settled, GPC will make a determination as to whether or not this equipment item can be qualified by

. the regulatory deadline. Should it be determined that the deadline cannot '

be met, or should the heat tracing equipment fail to meet the qualification testing _ criteria, then GPC will subnit a request for extension of the deadline as prescribed by 10 CFR 50.49(g) .

Very truly yours, f f & _:_ =

L. T. Gucwa CBS xc: J. T. Beckham, Jr.

H. C. Nix, Jr.

J. P. O'Reilly (NRC-Region II)

Senior Resident Inspector 700775