ML20044D593

From kanterella
Jump to navigation Jump to search
LER 93-005-00:on 930414,fuse 1D11-A-f14B Blew,Resulting in Initiation of Train B of Both Standby Treatment Sys Units & Isolation of Damper B of Both Secondary Containments.Blown Fuse & Several Relays in Logic Replaced
ML20044D593
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 05/15/1993
From: Tipps S
GEORGIA POWER CO.
To:
Shared Package
ML20044D591 List:
References
LER-93-005-01, LER-93-5-1, NUDOCS 9305190382
Download: ML20044D593 (5)


Text

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ .

gnn m u.s. mtm xtuAm ma3ia Arruga . gweim LICENSEE EVENT REPORT (LER)

FAcitiir hAMt (i) petAti homets (z) rtu r-i FIANT E. I. IRTG, UNIT 1 05000321 1 Orl5 IIILE (4)

BIDWN FUSE RESULTS IN UNFIANNED, AUIORTIC ACHRTIONS OF INGINEERED SAFETY FfATURES EVEhl DATE (5) LER huMEER (6) REFORI DATE (7) DINER FACILIIILS IhvoEvED (6)

MDhIn LAV VEAR VLAR R E v' MDhin gat 1 EAR FACILIIT hAMES l5EQ hum DOCAEI huMbER(5)

PIANT IRTW, UNIT 2 05000366 04 15 93 93 005 00 05 15 93 05000 CPERATING I"U ## 0 " # # N 00DE (9) 5 ^ 50.73(a)(2)(iv) 20.402(b) 20.405(c) 73.71(b)

POUER

- 20.405(a)(1)(1) 50.36(c)(1) 50.73(a)(2)(v) 13.71(c)

LEVEL 000 ~

20.405(a)(1)(ii) 20.405(a)(1)(itt)

_ 50.36(c)(2) 50.73(a)(2)(1)

[ 50.73(a)(2)(vii) [OTHER(Specifyin

_ _ _ 50.73(a)(2)(v111)(A) Abstract below)

- 20.405(a)(1)(iv) - 50.73(a)(2)(11) - 50.73(a)(2)(viii)(B) 20.405(a)(1)(v) 50.73(a)(2)(iii) 50.73(a)(2)(x)

LICEh5EE CChTACI FOR INIS LER (li)

AAME TELEFnDhi huMbER LREA CODE STEVIN B. TIPPS, MANAGER NOCIJAR SAFETY AND COMPIJANCE, IRIG 912 367-7851 COMPLETE Chi LIhE FOR EACn FAILURE DESCRIBED Ih INIS REF0kl (13)

CAUSE SYSTEN COMP 0kEhT h T k M[g,jfAC-R RjPhPRDS CAUSE SYSTEM' COMPONENT #pgh0FAC-p RjPORT X IL FU B569 Yes SueFLEMEhlhL REPORl LAFECTED (14g M0hTH DAT TEAR SUBMISSION

] VES(If yes, complete EXPECTED SUBMISSICN DATE)  % NO DATE (15)

AE5IRACI (16)

On 4/15/93 at 0755 CDT, Unit I was in a refueling outage with the reactor core partially loaded with fuel and the reactor vessel head removed. At that time, Instrument and Control technicians were performing surveillance procedure 57SV-Dil-008-IS, " REACTOR BUILDING EXHAUST VENT RADIATION MONITOR INSTRUMENT FT," when fuse 1Dll-A-F14B blew. This resulted in initiation of the 'B' trains of both units' Standby Gas Treatment (SEGT) Systems, isolation of the 'B' dampers of both units' Secondary Containments, and closure of several Group 2 Primary Containment 1 solation System (PCIS) valves. Subsequently, when the technicians attempted to exit the procedure, the removal of a jumper resulted in initiation of the 'A' trains of both units' SBGT systems, isolation of the 'A' dampers of both units' Secondary Containments and isolation signals being sent to other Group 2 PCIS valves per design.

The cause of this event was a blown fuse. No reason for the fuse blowing could be found.

Corrective actions for this event included replacing the blown fuse, replacing several relays in the logic powered through this fuse, and examining some of the wiring in the logic which is powered by this fuse. All of these actions are comple te.

lDR305190382 930534 g ADOCK 05000321 PDR

f E. Fom 3 dea U.5. NJMLNi KL6AAW LPrmWh MMW M 0 31W-0W4 ,

4 (6-89) EXPIX 5: 4/30/92

LICENSEE EVENT REPORT (LER)

TEXT CONTINUATION

(

j  ;

FACILITY KAME (1) DOCKET NUMBER (2) LER huMBER (5) PAGE (3) j i VEAR 5EQ hum REV  !

f l PIANI E. I. IMIT, UNIT 1 05000321 93 005 00 2 0F' 5 f

'T Eu  !

1  !

1 PLANT AND SYSTEM IDENTIFICATION i i

i

, General Electric - Boiling Water Reactor l Energy Industry Identification System codes are identified in the text as (EIIS l Code XX) i j

! DESCRIPTION OF EVENT l j On 4/15/93 at 0755 CDT, Unit 1 was in a refueling outage with the reactor core l

partially loaded with fuel and the reactor vessel head removed. At that time, ,

Instrument and Control (I&C) technicians were performing surveillance procedure  !

57SV-D11-008-1S, " REACTOR BUILDING EXHAUST VENT RADIATION MONITOR INSTRUMENT f FT." This surveillance functionally tests the operation of several instruments  ;

which monitor radiation in the Reactor Building (EIIS Code NG) ventilation f

, system. A high radiation signal from certain combinations of these monitors j causes initiation of both units' Standby Gas Treatment (SBGT, EIIS Code BH) j systems, isolation of Secondary Containment (EIIS Code NG), and closure of  ;

several Group 2 Primary Containment Isolation System (PCIS. EIIS Code JE)  !

valves. In this event, I&C technicians were working on the 'B' channel logic  !

which controls these systems and had placed a jumper in the 'A' logic channel to ,

4 prevent actuations from occurring in the 'A' trains of these systems. l I

At 0755 CDT, with this surveillance underway, fuse 1Dll-A-F14B blew. When the i fuse blew, the 'B' logic systems powered through the fuse assumed the tripped i state per design, causing initiation of the 'B' trains of both units' SBGT l

systems, closure of the 'B' Secondary Containment isolation dampers, and closure i' of some Group 2 PCIS valves. Since the plant was in a refueling outage at the time of the event, many Group 2 PCIS valves were in off-normal positions and f
others were tagged out of service. Therefore, the extent of the actuations was
not immediately evident to Control Room personnel. Further, since no valid SBGT f initiation signal was present, Control Room personnel did not know what had j caused the actuations. Licensed personnel directed that all work on  ;

4 surveillances and functional tests in the Control Room be suspended until the l nature of each ongoing work activity could be reviewed. When the I&C '

j surveillance procedure was reviewed, it was determined that performance of this  !

surveillance had not been responsible for the event. Thus, the I&C technicians l

, were permitted to resume work. Minutes later, however, the I&C technicians j encountered difficulty and found it necessary to "back out" of their procedure.

At approximately 0840 CDT, when they removed the jumper which had been installed 1 earlier, the 'A' logic systems powered through the blown fuse assumed the I tripped state per design, causing the 'A' trains of both units' SBGT systems to l start, the 'A' dampers of both units' Secondary Containments to isolate, and associated Group 2 PCIS valves to receive isolation signals. 3 l

At this point, the I&C technicians stopped their work activity and consuited I with other technicians who had previously observed a similar set of actuations (See LER 50-321/1992-016 dated 07/10/92). These technicians recommended that fuse 1D11-A-F14B be checked. When the fuse was checked, it was found to have

blown. The fuse was subsequently replaced, the various logic trips were reset, and the SBGT systems were secured by 1010 CDT. When the trips were reset, 4

, , ,--~-v+ ,n.m ,--n ~- - . - - - , - - , ,,.--.-----,--n.c ~ + g------e--.,,

7n JbtA U.5. NJktMi KucLAW WTuhb1A Afrk U 3 0104 l

l LICENSEE EVENT REPORT (I2R)

TEXT CONTINUATION FAEILITY EAME 11) DOCKET NUMBER (2) LER NUMBER (5) PAGE (3)

TEAR SEQ hum REW I l

l PiANT F.. I. IRTCH, UNIT 1 05000321 93 005 00 3 0F 5 l IEAT j licensed personnel observed that several Group 2 PCIS valves returned to their pre-event condition. As stated previously, other valves which could potentially ,

have been affected by this event were either tagged out of service or were i already closed due to activities associated with the ongoing refueling outage.

When performance of the surveillance procedure was resumed at 1915 CDT on  !

4/15/93, no further problems were encountered and the Reactor Building vent radiation monitoring system (EIIS Code IL) was satisfactorily functionally I tested. j l

l s

CAUSE OF EVENT P

The cause of this event was a blown fuse. Fuse 1Dil-A-F14B supplies power to several relays in both the 'A' and 'B' logic systems whose contacts provide  ;

initiation signals to the above named systems. When the fuse blew, these relays  ;

assumed the tripped state per design, resulting in actuations in the 'B' trains j of both units' SBGT systems, Group 2 PCIS valve isolations, and closure of the j

'B' Secondary Containment isolation dampers. Components controlled by the ' A' I logic systems were not affected because the surveillance procedure in use at the I time required the installation of a jumper to prevent actuations in the 'A' logic. However, when the jumper was later removed, the ' A' logic systems l tripped.

1 l

REPORTABILITY ANALYSIS AND SAFETY ASSESSMENT This event is reportable per 10 CFR 50.73 (a)(2)(iv) because several ,

unanticipated actuations of Engineered Safety Features (ESFs) occurred in  !

response to a blown fuse.

The Standby Gas Treatment Systems are designed to limit the release of radioactive material to the environment following leakage of radioactive i

material into the Secondary Containment. The SBGT systems automatically filter the air from the Secondary Containment following an accident and discharge it via the Main Stack (EIIS Code VL). Each unit's SBGT system consists of two identical, redundant, 100 percent capacity air filtration trains containing the necessary heaters, filters and exhaust fans. When an SBGT system initiation signal is received, the normal building ventilation systems automatically isolate to allow the SEGT system to maintain a negative pressure on the reactor j building and refueling floor. This prevents unfiltered air from leaking out of ,

Secondary Containment into the atmosphere. l l

The Group 2 Primary Containment Isolation System is designed to isolate certain Primary Containment Isolation Valves to provide protection against accidents involving release of radioactive materials from the fuel or nuclear trocess barriers. Group 2 systems are generally those systems whose line- so not

)

communicate directly with the reactor vessel, but penetrate the Primary '

Containment and communicate with the free space inside it.

l

i

% f orm 3btA U.5. KJLMAR KLW.JdWI Wm4MiW WFKww UP5 NG 419-0104 Wen # #U#

I. CENSEE EVENT REPORT (LER)  ;

. TEXT CONTINUATION FACILITY NAME 11) DOCKET NUMBER (2) LER NUMBER (5) PAGE (3) (

VEAR SEQ hum REV  ;

PIANI E. I. HAIUI, UNIT 1 05000321 93 005 00 4 0F 5 IEAT i

In this event, a blown fuse resulted in an actuation signal for the 'B' logic ,

systems of the PCIS, the SBGT system, and the Secondary Containment isolation i dampers. Subsequently, the removal of a jumper resulted in further actuations i of the 'A' logic channels in these systems. All these systems performed as l designed given the signal generated when the fuse blew. Had a design basis l accident occurred during the event, the affected systems would have already [

initiated their safety functions and been performing as required.

Based on this analysis, it is concluded that this event had no adverse impact on .

nuclear safety. This analysis is applicable to all power levels. l i

f CORRECTIVE ACTIONS  ;

Corrective accions for this event incitded:

1. Replacing the blown fuse and returning affected systems to their pre-event f c era t tions . j i
2. Replacing relays in the circuit which are powered through fuse 1D11-A-F14B. i Georgia Power Comany committed to this action in 1.ER 50-321/1992-016 and l

completed the action following this event. In conjunction with the relay  !

replacement, wiring in this circuit was visually inspected for shorts, loose

{

connections and chafed insulation. No problems were identified during this l inspection.

l ADDITIONAL INFORMATION  !

l

1. Other Systems Affected: No systems other than those mentioned in this report were affected by this event.

{

2. Previous Similar Events: Events reported in the past two years in which l blown fuses resulted in unplanned automatic actuations of engineered safety  !

features are described in the following LERs:

50-321/1991-016, dated 09/30/91 50-321/1991-021, dated 10/25/91 50-321/1991-023, dated 11/12/91 50-321/1992-016, dated 07/10/92 50-366/1991-010, dated 05/13/91  ;

50-366/1991-011, dated 05/15/91 50-366/1991-017, dated 06/28/91 50-366/1992-018, dated 10/26/92 l

l 4

I

% tonn m u.s.mut.m nia w a weinia mww am o .nw-oim l (6-89) ##

LICENSEE EVENT REPORT (LER)  !

TEXT CONTINUATION  !

rAE!LITT NAME 11) DOCKET NUMBER (2) LER NUMBER (5) PAGE (3)  !

VEAR SEQ hum RLv i PIET E. I. IRTCH, th1T 1 05000321 93 005 00 5 0F 5 l un I

Corrective actions for these events included replacing failed fuses, counseling personnel in cases where personnel error contributed to a fuse failure, training personnel in cases where personnel error contributed to a l fuse failure, conducting an engineering evaluation of fuse design and j application, and using improved electrical jumpers. These corrective )

actions would not have prevented this event because, with one exception, they applied to other circuits and components which were not involved in this event. Additionally, neither personnel error nor jumper design was involved in this event. The inspection of components committed to in LER 50-321/1992-016 was scheduled to have been carried out during the current refueling outage, but as of the time of the event, had not yet been done.

Therefore, that corrective action could not have prevented this event because it had not yet been completed.

3. Failed Components Identification:

Master Parts List Number: 1Dll-A-F14B Manufacturer: Bussman Type: Fuse, One Ampere Model Number: KTK-R Manufacturer Code: B569 EIIS System Code: IL EIIS Component Code: FU Root Cause Code: X Reportable to NPRDS: Yes