ML19347F953

From kanterella
Jump to navigation Jump to search
Responds to NRC 810206 & 0413 Ltrs Re IE Insp Rept 50-458/80-13.Time Allowed for Discharge of Concrete After Batching Increased,Correcting Encl 1 Typographical Error
ML19347F953
Person / Time
Site: River Bend Entergy icon.png
Issue date: 04/10/1981
From: Draper E
GULF STATES UTILITIES CO.
To: Madsen G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML19347F951 List:
References
RBG-10-091, RBG-10-91, NUDOCS 8105260688
Download: ML19347F953 (1)


Text

  • . p.

h ~

.s _ ~7

^~"'

GULF STATES UTILITIES COMPANY A O S T O F FIC E B O X 2951 . BEAUMONT. TEXAS 77704 AREA CODE 713 838 3843 April 10, 1981 RBG - 10,091 File Nos. G9.5 G15.4.1 Mr. G. L. Madsen, Chief Reactor Projects Branch U.S. Nuclear Regulatory Commission Region IV Office of Inspection & Enforcement 611 Ryan Plaza, Suite 1000 Arlington, Tx. 76011

Dear Mr. Madsen:

River Bend Station-Unit I Refer To: RIV Docket No. 50-458/ Report 80-13 With regard to Gulf States Utilities Company's (GSU) letter dated March 2, 1981, concerning Inspection Report 80-13, GSU has made the i following correction.

In Enclosure 1 under " Corrective Steps Which Have Been Taken and Results Achieved", number 3 should read:

l "3. E&DCR No. C-1966 has been issued to limit discharge of concrete to 90 minutec after batching or 300 revolutions of the truck mixers."

l This correction is due to a typographical error which originally stated 50 minutes instead of the 90 minutes allowed for discharge of concrete af ter batching.

l This report completes our response to Inspection Report 80-13.

Sincerely, 1

. - nu .

E. L. Draper Vice President l

Nuclear Technology ELD /RJK/sj 8105260 ( 7'S

.