Responds to NRC 800426 Ltr Re Violations Noted in IE Insp Rept 50-483/80-07.Corrective Actions:Arranging Meeting W/Bechtel & P-W Industries to Resolve Questions Re Welding Procedures Used for Cable Tray Fittings
ML19310A740
Person / Time
Site: Callaway Ameren icon.png
Issue date: 05/28/1980
From: Bryan J
UNION ELECTRIC CO.
To: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19310A733 List:
References
ULNRC-355, NUDOCS 8006230069
Download: ML19310A740 (2)


Text

3 .

UNION ELECTRIC COMPANY 1908 GMATIOT STREET ST. Louis. Missount s.~~ ~...,,~ ~^;";;*:::," ."'

May 28, 1980 Mr. Gaston Fiorelli, Chief Reactor Construction & Engineering Support Branch U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Rd.

Glen Ellyn, IL 60137 ULNRC- 355

Dear Mr. Fiorelli:

INSPECTION REPORT NO. 50-483/80-07 This is in response to your letter of April 26, 1980 reporting results of an inspection at Union Electric Company's Callaway Plant Site on March 11-14, 1980 and as detailed in inspec-tion report number 50-483/80-07.

None of the material in the inspection report or in this response are considered proprietary by Union Electric Company.

The following is in response to the item listed in Appendix A, Notice of Violation, of the inspection report.

Infraction (483/80-07-01) 10 CFR 50, Appendix B, Criterion IX states in part, that, " Measures shall be established to assure that special processes, including welding, . . .are controlled and accomplished I by qualified personnel using qualified proce- i dures in accordance with applicable codes, i standards, specifications, . . . " SNUPPS PSAR, l paragraph 17.1.9 states, in part, that "The i SNUPPS utilities require that special processes  !

be controlled. Special pr asses will be l accomplished under specified and controlled  !

conditions by qualified personnel using l qualified procedures and equipment in accor- l dance with applicable codes, standards, specifi- l cations, criteria or other special requirements." i l

Contrary to the above, measures were not established to control welding in that, there was no welding procedure specification or quali-fication of the as welded / brazed condition for the cable tray fittings, i.e. T's, EL's, etc.

MAY 3 01980 8006230 c)6 A l

-1 -m a',..Mr.-Gaston Fiorelli May 28, 1980

. idf0' ' / - - .

' 'Mrf 3; ry.i;._. RESPONSE

...tm ', _ .;_

There are still outstanding questions ~ regard-

.ing welding procedures used for cabld tray fittings and a meeting with Bechtel and P-W m Industries is being arranged to resolve these

- ~ - - questions. As.soon as the meeting.results are known a supplement to this response will be'provided.

e -

Yours very truly,

'~

\ x sh G4g John K. Bryan [

FDF/jds i

cc: Mr. H. M. Wescott, NRC Region III Mr. W. A. Hansen (NRC Resident Inspector, Callaway Plant)