Submits Third Interim Rept for Potential Reportable Deficiency Re Failures of Type 12 Auxiliry Switch Assembly Installed in 4.16 Kv Switchgear.Switch Assembly Returned to Supplier for Analysis
ML19259C721
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 07/20/1979
From: Dale L
MISSISSIPPI POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 7908140634
Download: ML19259C721 (1)


Text

4sw.

J MISSISSIPPI POWER & LIGHT COMPANY Helping Build Mississippi E

P. O. BOX 16 4 0. J A C K S O N. M I S SI S S I P P I 39205 anooucreos orwaavutst July 20, 1979 f

U. S. Nuclear Regulatory Commission y

[6 Region II 101 Marietta Street, Suite 3100 3

Atlanta, Georgia 30303 cc Attention:

Mr. J. P. O'Reilly, Director c.n

.=.

Centlemen:

SL*BJECT : Grand Gulf Nuclear Station y

Units 1.nd 2 Docket Nos. 50-416/417 File 0272/0498/15325 Interim Report No. 3 for Potential Reportable De-ficiency No. 79-06 as Defined in 10 CFR 50,55(e)

AECM-79/74 On March 2, 1979, Mr. J. K. Rausch of your effice was notified of a potential reportable deficiency at the Grand Gulf Nuclear Station construc-tion site concerning the failure of a Type L2 Auxiliary Switch Assembly installed in the 4.16 KV switchgear.

The failed switch assembly and a switch assembly with a crack in the end molding were returned to the equip-ment supplier, Gould Electric Systems Group, for analysis.

The equipment supplier's analysis and our examination of the Unit 2 switchgear have not been completed. We now estimate that the question of reportability will be resolved by October 31, 1979.

Yours truly, L. F. Dale Nuclear Project Manager JRF/pa cc:

Mr. N.

L. Stampley Mr. R. B. McGehee Mr. T.

B.

Conner 8[

0 7(

Mr. John G. Davis, Director Division of Inspection & Enforcement