OPERATING DATA REPORT OPERATING STATUS DOCKET NO 50 - 335 DATE 11/04/96 FPL LICENSING GROUP
- PSL TELEPHONE 561/467/7073 1.
UNIT NAME: ST.
LUCIE UNIT 1 2.
REPORTING PERIOD:
OCTOBER 1996 3.
LICENSED THERMAL POWER (MWT):
2700 4.
NAMEPLATE RATING (GROSS MWE):
850 5.
DESIGN ELECTRICAL RATING (NET MWE):
830 6.
MAXIMUMDEPEMDABLE CAPACITY (GROSS MWE):
872 7.
"MAXIMUMDEPENDABLE CAPACITY (NET MWE):
839 8.
IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7)
SINCE LAST
- REPORT, GIVE REASONS:
9 POWER LEVEL TO WHICH RESTRICTED'F ANY (NET MWE) 10.
REASONS FOR RESTRICTIONS, ZF ANY:
MONTHLY
-YTD-CUMULATIVE 11.
HOURS IN REPORT PERIOD:
12.
NUMBER OF HOURS REACTOR WAS CRITICAL 13.
REACTOR RESERVE SHUTDOWN HOURS 14.
HOURS GENERATOR ON LINE 15.
UNIT RESERVE SHUTDOWN HOURS 16.
GROSS THERMAL ENERGY GENERATED (MWH) 17.
GROSS ELECTRICAL ENERGY GENERATED (MWH) 18.
NET ELECTRICAL ENERGY GENERATED (MWH) 19.
UNIT SERVICE FACTOR 20.
UNIT AVAILABILITYFACTOR 21.
CAPACITY FACTOR (USING MDC NET) 22.
CAPACITY FACTOR (USING DER NET) 23.
UNIT FORCED OUTAGE RATE 745.0 745.0 0.0 745.0 0.0 1983487 652660 619473 100.0 100.0 99.1 100.2 0.0 7320.0 5163.7 0.0 5017.6 0.0 12958712 4237340 3995617 68.5 68.5 65.1 65.8 3.6 174120.0 135203.6 0.0 133639.2 0.0 346435401 114226360 107940890 76.8 76.8 73.9 74.7 5.0 24.
SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS:
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
vsiaiioiax vixsxs (t
PDR ADQCK 05000335 R
AVERAGE DAILY POWER LEVEL MONTH October 1996 DOCKET NO.
50 - 335 UNIT Saint Lucio //1 DATE Nov 04, 1996 COMPLETED BY xxxxxxxxxxxxxxxxxxx TELEPHONE I000) 000 - 0000 DAY 10/01/96 10/02/96 10/03/96 10/04/96 10/05/96 10/06/96 10/07/96 10/08/96 10/09/96 10/10/96 10/11/96 10/12/96 10/13/96 10/14/96 10/15/96 10/16/96 10/17/96 10/18/96 10/19/96 10/20/96 10/21/96 10/22/96 10/23/96 10/24/96 10/25/96 10/26/96 10/27/96 10/28/96 10/29/96 10/30/96 10/31/96 AVERAGE DAILY POWER LEVEL IMWe-Not) 839 842 842 841 843 843 843 844 842 844 845 846 849 848 849 848 810 615 693 844 848 847 847 847 846 847 847 844 845 845 845
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.:
UNITNAME:
DATE:
COMPLETED BY:
TELEPHONE:
50-335 ST LUCIE UNIX 1 November 4, 1996 J.A.ROGERS (407) 467-7296 0
ONE~
No.
Date Type'uration (Hours)
Reasons Method of Shutting Down Reactor'icensee Event Report System Code'omponent Code'ause Ec Corrective Action to Prevent Recurrence 17 10/17/96 0.0 N/A HF HTEXCH Unit 1 downpowered to approximately 78% power due to a condenser tube leak.
F Forced S
Scheduled Reason A - Equipment failure (explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training tb License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
Method I - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continued 5 - Load Reduction 9 - Other (Explain)
Exhibit G - Instructions for Prcpamtion of Data Entry Sheets Licensee Event Report (LER) File (NUREG4I61) 5 Exhibit I - Same Source oslssr Fpl
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-335 St. Lucie ¹1 November 4, 1996 Z.A.ROGERS (561) 467-7296 REPORT MONTH Unit 1 operated at essentially full power through October 17.
On October 17 the unit downpowered to approximately 78% power to repair a condenser tube leak.
On October 19 the unit returned to full power operation.
1n accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.
OPERATING DATA REPORT OPERATING STATUS DOCKET NO 50 - 389 DATE 11/04/96 FPL LICENSING GROUP
- PSL TELEPHONE 561/467/7073 UNIT NAME: ST.
LUCIE UNIT 2 REPORTING PERIOD:
OCTOBER 1996 LICENSED THERMAL POWER (MWT):
2700 NAMEPLATE RATING (GROSS MWE):
850 DESIGN ELECTRICAL RATING (NET MWE):
830 MAXIMUMDEPEMDABLE CAPACITY (GROSS MWE):
882 MAXIMUMDEPENDABLE CAPACITY (NET MWE):
839 IF CHANGES OCCUR IN CAPACITY RATZNGS (ITEMS NUMBER 3 THROUGH 7)
SINCE LAST
- REPORT, GIVE REASONS:
9 POWER LEVEL TO WHICH RESTRICTED g ZF ANY (NET MWE) 10.
REASONS FOR RESTRICTIONS, IF ANY:
MONTHLY
-YTD-CUMULATIVE 11.
HOURS IN REPORT PERIOD:
12.
NUMBER OF HOURS REACTOR WAS CRITICAL 13.
REACTOR RESERVE SHUTDOWN HOURS 14.
HOURS GENERATOR ON LINE 15.
UNIT RESERVE SHUTDOWN HOURS 16.
GROSS THERMAL ENERGY GENERATED (MWH) 17.
GROSS ELECTRICAL ENERGY GENERATED (MWH) 18.
NET ELECTRICAL ENERGY GENERATED (MWH) 19.
UNIT SERVICE FACTOR 20.
UNIT AVAILABILITYFACTOR 21.
CAPACITY FACTOR (USING MDC NET) 22.
CAPACITY FACTOR (USING DER NET) 23.
UNIT FORCED OUTAGE RATE 745.0 745.0 0.0 745.0 0.0 2009207 657760 623933 100 100 99.8 100.9 0.0 7320.0 7111.6 0.0 6981.5 0.0 18444778 6079520 5752940 95.4 95.4 93.7 94.7 3.3 116017.0 97982.2 0.0 96420.2 0.0 250907500 83140190 78543608 83.1
- 83. 1 80.7 81.6 6.4 24.
SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS: April 15, 1997 Refueling
& Maintenance
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
AVERAGE DAILY 7 POWER LEVEL MONTH October, 1996 DOCKET NO.
50 - 389 UNIT Saint Lucis ¹2 DATE Nov 04, 1996 COMPLETED BY xxxxxxxxxxxxxxxxxxx TELEPHONE (000) 000 - 0000 DAY 10/01/96 10/02/96 10/03/96 10/04/96 10/05/96 10/06/96 10/07/96 10/08/96 10/09/96 10/10/96 10/11/96 10/12/96 10/13/96 10/14/96 10/15/96 10/16/96 10/17/96 10/18/96 10/19/96 10/20/96 10/21/96 10/22/96 10/23/96 10/24/96 10/25/96 10/26/96 10/27/96 10/28/96 10/29/96 10/30/96 10/31/96 AVERAGE DAILY POWER LEVEL (MWe-Net) 835 835 838 832 838 827 850 838 837 839 838 842 840 841 840 839 838 837 839 840
~
841 841 839 840 835 839 838 836 820 832 837
UNIT SHUTDOWNS AND POWER'REDUCTIONS DOCKET NO.:
UNITNAME:
DATE:
COMPLETED BY:
TELEPHONE:
50-339 ST LUCIEUN' November 4, 1996 J.A.ROGERS (407) 467-7296
~
REPORT MONTHQgfgbg~
No.
Date Type Duration (Hours)
Reasons Method of Shutting Down Reactor'icensee Event Report System Code'omponent Code'ause 8c Corrective Action to Prevent Recurrence Unit 2 operated at full power for the entire month.
F Forced S
Scheduled Reason A - Equipment failure (explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training k License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
Method I - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continued 5 - Load Reduction 9 - Other (Explain)
Exhibit G - Instructions for Preparation of Data Entry Sheets Licensee Event Report (LER) File (NUREG4161) 5 Exhibit I - Same Source 09lssr Frt.