ML111400351

From kanterella
Jump to navigation Jump to search
IR 05000482-11-006, 02/07-03/31/2011, Wolf Creek Generating Station - NRC Inspection Procedure 95002 Supplemental Inspection Report and Assessment Followup Letter
ML111400351
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 05/20/2011
From: Geoffrey Miller
NRC Region 4
To: Matthew Sunseri
Wolf Creek
References
IR-11-006
Download: ML111400351 (34)


See also: IR 05000482/2011006

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

May 20, 2011

Matthew W. Sunseri, President and

Chief Executive Officer

Wolf Creek Nuclear Operating Corporation

P.O. Box 411

Burlington, KS 66839

SUBJECT: WOLF CREEK GENERATING STATION - NRC INSPECTION

PROCEDURE 95002 SUPPLEMENTAL INSPECTION REPORT AND

ASSESSMENT FOLLOWUP LETTER 05000482/2011006

Dear Mr. Sunseri:

On March 31, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a supplemental

inspection pursuant to Inspection Procedure 95002, "Supplemental Inspection for One

Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area," at your

Wolf Creek Generating Station facility. The supplemental inspection also covered the

performance issues associated with Inspection Procedure 92723, "Follow Up Inspection for

Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a

12-Month Period. The enclosed inspection report documents the inspection results, which

were discussed at the exit meeting on April 5, 2011, with yourself and other members of your

staff.

As required by the NRC Reactor Oversight Process Action Matrix, this supplemental inspection

was performed to address three white performance indicators associated with unplanned

scrams, unplanned scrams with complications, and safety system functional failures. These

performance issues were documented previously on the NRC public web page

(http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/WC/wc_chart.html). The NRC staff was

informed on October 29, 2010, of your staff's readiness for this inspection.

The objectives of this supplemental inspection were to: 1) provide assurance that the root

causes and the contributing causes for the risk-significant performance issues were understood;

2) provide assurance that the extent-of-condition and extent-of-cause of the issues were

identified; and 3) provide assurance that corrective actions were sufficient to address and

prevent the recurrence of the root and contributing causes. This inspection also included

independent NRC reviews of the extent-of-condition and extent-of-cause for the three white

performance indicators and assessments of whether any safety culture component caused or

significantly contributed to the issue. The inspection consisted of examination of activities

conducted under your license as they relate to safety, compliance with the Commission's rules

and regulations, and the conditions of your operating license.

Wolf Creek Nuclear Operating Corporation -2-

The inspectors determined that your staff performed a comprehensive evaluation of individual

and collective causes of the three White performance indicators. Your staff's evaluation

identified root causes of the issues to be: 1) inadequate management oversight/standards

enforcement, 2) lack of knowledge across the station concerning the components of nuclear

safety culture and crosscutting issues, and 3) inadequate hardware monitoring. The inspectors

determined that your staff proposed appropriate corrective actions to upgrade preventative

maintenance practices, improve system health through operating experience reviews, improve

the effectiveness of management review processes, and address deficiencies related to safety

culture which, if successfully implemented, will resolve the identified performance issues. With

respect to Inspection Procedure 92723, the inspectors determined that your staff identified the

causes of the traditional enforcement violations, performed an adequate review of the extent-of-

condition and extent-of-cause, and identified appropriate corrective actions sufficient to address

the causes.

On May 3, 2011, using the results of this inspection, the NRC staff completed a quarterly review

of plant performance of Wolf Creek Generating Station. The assessment also evaluated the

performance indicators and the remaining inspection results for the first quarter of calendar year

2011. We noted that the Safety Systems Functional Failure Performance Indicator returned to

Green at the beginning of the second quarter of 2010. This letter supplements, but does not

supersede, our end-of-cycle assessment letter issued on March 4, 2011.

Overall, Wolf Creek operated in a manner that preserved the publics health and safety and fully

met the cornerstone objectives. All inspection findings for the assessment period were

classified as having very low safety significance (Green) and all performance indicators

indicated performance within the nominal, expected range (Green). As a result, we have

assessed Wolf Creek to be in the Licensee Response column of the NRCs Action Matrix.

Therefore we plan to conduct baseline inspection during the remainder of the assessment cycle.

Based on the results of this inspection, the NRC has identified one issue that was evaluated

under the risk significance determination process as having very low safety significance

(Green). The NRC has also determined that a violation is associated with this issue. Because

of the very low safety significance and because it is entered into your corrective action program,

the NRC staff is treating this finding as a noncited violation consistent with Section 2.3.2 of the

NRC Enforcement Policy. If you contest any noncited violation in this report, you should provide

a response within 30 days of the date of this inspection report, with the basis for your denial, to

the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-

0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement,

United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC

Resident Inspector at the Wolf Creek Generating Station.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records component of NRC's

Wolf Creek Nuclear Operating Corporation -3-

document system (ADAMS). ADAMS is accessible from the NRC Website at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/Rick Deese for

Geoffrey B. Miller, Chief

Project Branch B

Division of Reactor Projects

Docket: 50-482

License: NPF-42

Enclosure:

Inspection Report 05000482/2011006

w/Attachment 1: Supplemental Information

Distribution via ListServ for Wolf Creek Nuclear Operating Corporation

Wolf Creek Nuclear Operating Corporation -4-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Troy.Pruett@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Vacant)

Senior Resident Inspector (Chris.Long@nrc.gov)

Resident Inspector (Charles.Peabody@nrc.gov)

WC Administrative Assistant (Shirley.Allen@nrc.gov)

Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov)

Senior Project Engineer, DRP/B (Leonard.Willoughby@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Randy.Hall@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

ROPreports

Executive Technical Assistant (Stephanie.Bush-Goddard@nrc.gov)

DRS/TSB STA (Dale.Powers@nrc.gov)

R:\ _REACTORS\_WC\2011\ WC2011006 ded-rp.docx

ADAMS: No Yes SUNSI Review Complete Reviewer Initials: GM

Publicly Available Non-Sensitive

Non-publicly Available Sensitive

DDumbacher KKennedy GMiller

RIV:SRI/B D/DRP C/DRPB

/E-DDumbacher for/ /VGG for/ /RA/

5/17/11 5/20/11 5/18/11

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 05000482

License: NPF-42

Report: 05000482/2011006

Licensee: Wolf Creek Nuclear Operating Corporation

Facility: Wolf Creek Generating Station

Location: 1550 Oxen Lane SE

Burlington, Kansas

Dates: February 7 through March 31, 2011

Inspectors: D. Dumbacher, Senior Resident Inspector (Team Lead)

B. Correll, Reactor Inspector

J. Dixon, Senior Resident Inspector

J. Drake, Senior Reactor Inspector

N. Makris, Project Engineer

L. Willoughby, Senior Project Engineer

Approved By: G. Miller, Branch Chief

Division of Reactor Projects

1 Enclosure

SUMMARY OF FINDINGS

IR 05000482/2011006, 02/07- 03/31/2011, Wolf Creek Generating Station, Supplemental

Inspection - Inspection Procedure 95002.

This supplemental inspection was conducted by two senior resident inspectors, a reactor

inspector, a senior reactor inspector, a project engineer, and a senior project engineer. One

Green noncited violation was identified. The significance of most findings is indicated by their

color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, "Significance

Determination Process." The crosscutting aspect is determined using Inspection Manual

Chapter 0310, "Components Within the Cross Cutting Areas." Findings for which the

significance determination process does not apply may be Green or be assigned a severity level

after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process,"

Revision 4, dated December 2006.

Cornerstones: Initiating Events and Mitigating Systems

The NRC staff performed this supplemental inspection in accordance with Inspection

Procedure 95002, "Supplemental Inspection for One Degraded Cornerstone or Any Three White

Inputs in a Strategic Performance Area," to assess the licensee's evaluations associated with

White performance indicators for unplanned scrams per 7000 critical hours, safety system

functional failures, and unplanned scrams with complications. Inspection Procedure 92723,

"Follow Up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in

the Same Area in a 12 Month Period," was also performed.

The inspectors determined that the Wolf Creek staff performed a comprehensive evaluation of

the events that led to the degraded Initiating Events Cornerstone and three white inputs in the

reactor safety strategic performance area. Wolf Creek's evaluation identified root causes of the

collective issues to be related to: 1) inadequate management oversight/standards enforcement,

2) lack of knowledge concerning the components of nuclear safety culture and crosscutting

issues, and 3) inadequate hardware monitoring.

In addition to assessing the licensee's evaluations, the inspection team performed an

independent extent-of-condition and extent-of-cause review and a focused inspection of the site

safety culture as it related to the root cause evaluations. The team concluded that the Wolf

Creek root cause evaluations and corrective actions, both completed and planned, addressed

the extent-of-condition and extent-of-cause, determined if safety culture contributed to the issue,

and established and scheduled corrective actions that are sufficient to address the causes and

prevent recurrence of the White performance indicators.

Based on independent inspection, the team also determined that the licensee's assessment of

Wolf Creek's safety culture was accurate and reflected the conditions at the site.

The root cause evaluations appropriately identified needed improvements associated with

safety culture behaviors.

2 Enclosure

A. NRC-Identified or Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The inspectors identified a noncited violation of 10 CFR Part 50, Appendix B,

Criterion V, "Instructions, Procedures, and Drawings," for the failure to follow Procedure

AP 28A-0100, "Condition Reports," Revision 13. On February 17, 2011, the licensee

received laboratory test results on the emergency diesel generator B fuel oil storage tank

and determined that the cloud point parameter was out of specification at -8° Celsius.

However, Procedure AP 28A-0100, step 5.13.3, required the licensee to evaluate

condition report data to identify and evaluate potential trends. The emergency diesel fuel

oil storage tank cloud point parameter had been trending closer to the acceptance

criteria over the last several fuel oil additions. The licensee had allowed the original fuel

oil vendor to continue to deliver fuel that was out of specification which resulted in a

gradual trend toward the limits of the chemistry parameters. This trend was not

appropriately evaluated because the licensee had not performed training to ensure that

consistent and appropriate evaluations would be performed.

This finding was more than minor because it affected the Mitigating Systems

Cornerstone attribute of equipment performance by impacting the cornerstone objective

to ensure the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. This deficiency directly resulted in

emergency diesel generator B being declared inoperable due to its fuel oil storage tank

being out of specification. The inspectors performed the significance determination

using NRC Inspection Manual Chapter 0609.04, "Phase 1 - Initial Screening and

Characterization of Findings," because it affected the Mitigating Systems Cornerstone

while the plant was at power. The finding was determined to be of very low safety

significance (Green) because it was not a design or qualification deficiency; it did not

result in the loss of a system safety function; it did not represent the loss of a single train

for greater than technical specification allowed time; it did not represent a loss of one or

more non-technical specification risk-significant equipment for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />;

and it did not screen as potentially risk significant due to seismic, flooding, or severe

weather. In addition, this finding had a human performance crosscutting aspect

associated with resources in that the licensee did not ensure that the corrective action

program coordinators were effectively trained to cognitively and analytically trend

condition reports H.2(b)(Section 4OA4).

B. Licensee-Identified Violations

A violation of very low safety significance, which was identified by the licensee, has been

reviewed by the inspectors. Corrective actions taken or planned by the licensee have

been entered into the licensee's corrective action program. This violation and

associated condition report numbers are listed in Section 4OA7.

3 Enclosure

REPORT DETAILS

4. OTHER ACTIVITIES

4OA3 Event Follow-up

.1 (Closed) Licensee Event Report 05000482/2010-005-00: Reactor Trip due to Low

Steam Generator Level from Trip of Main Feedwater Pump

On March 2, 2010, a trip of the Train A main feedwater pump caused a low-low steam

generator water level reactor trip. The trip of the main feedwater pump was due to

nonsafety-related inverter PN09 failing to transfer to the alternate supply during

preparation for minor maintenance. During performance of Procedure SYS PN-200,

"Energizing and Deenergizing Inverters PN09 and PN10," inverter PN09 failed to

transfer from the normal to alternate power supply due to sticking of the reed relay on

the static transfer switch circuit board after exceeding its design life. The failure to

transfer caused a loss of speed signal to main feedwater pump A resulting in an

overspeed trip and caused a loss of steam dump capability. The unit received a

feedwater isolation signal and an auxiliary feedwater actuation signal.

The inspectors determined the licensee's root cause evaluation inappropriately identified

the direct cause as the root cause and incorrectly stated the actions taken to replace the

cards were sufficient such that no corrective actions to prevent recurrence were

necessary. The NRC inspectors concluded that a contributing cause identified in the

root cause evaluation, the decision to continue operating with equipment beyond its

design life, was more appropriate as a root cause. The inspectors also identified that the

root cause evaluation for extent-of-condition was narrowly focused, in that the licensee

only identified other inverters as being within the extent-of-condition. A broader extent-

of-condition would have included any electronic circuit boards with design life limitations

and would not be limited to inverters. Corrective actions taken by the licensee to

address the contributing cause included replacing the circuit cards and preventative

maintenance frequency changes to prevent exceeding the design life of the circuit cards.

The inspectors determined the corrective actions were appropriate to prevent

recurrence.

The inspectors concluded the failure to identify the lowest level root cause and the

narrowly focused extent-of-condition determination were a violation of 10 CFR Part 50,

Appendix B, Criterion V, "Instructions, Procedures, and Drawings," involving a failure to

follow root cause Procedure AI 28A-001, "Level 1 CR Evaluation (IIT)," Revision 12.

Since the licensee took appropriate corrective actions as part of an identified contributing

cause, the inspectors determined this violation was of minor safety significance.

Violations of minor safety or security concern generally do not warrant enforcement

action but must be corrected.

Event follow-up inspections by NRC inspectors identified two Green findings associated

with this event: FIN 05000482/2010002-04 and NCV 05000482/2010002-05, The

inspectors reviewed the licensee event report and determined that the report adequately

documented the summary of the event, including the potential safety consequences,

cause of the event, and corrective actions required to address the performance

deficiency. No additional findings were identified. This licensee event report is closed.

4 Enclosure

.2 (Closed) Licensee Event Report 05000482/2010-012-00: Reactor Trip due to Operator

Inability to Control Steam Generator Level Oscillations at Low Power

On October 17, 2010, a reactor trip occurred due to inadequate steam generator water

level control during low power operations. During plant startup following a forced

outage, reactor power was increased above 10 percent to approximately 17 percent

when starting to roll the main turbine and synchronize to the grid. While rolling the main

turbine, feedwater temperature began to drop due to insufficient feedwater preheating.

The operators took manual control of steam generator water level but were unable to

maintain level below the high-high steam generator water level turbine trip and

feedwater isolation signal. Auxiliary feedwater was unable to match steam demand and

the reactor tripped on low-low steam generator water level. The inability to control

steam generator water level was due to the decreased feedwater temperature caused by

insufficient feedwater preheating during the power increase associated with placing the

main turbine on line. Operators failed to recognize that feedwater preheating from the

main steam system had a capacity limit of 10 percent until the main turbine is brought on

line.

The licensee submitted a licensee event report for the reactor trip on December 16,

2010. The licensee made procedure changes to require the main turbine to be

synchronized to the grid prior to exceeding 10 percent reactor power. Event follow-up

inspections by NRC inspectors identified four Green noncited violations associated with

this event;05000482/2010005-08; 05000482/2010005-09; 05000482/2010005-10; and

05000482/2010005-11. The inspectors reviewed the licensee event report and

determined that the report adequately documented the summary of the event including

the potential safety consequences, cause of the event, and corrective actions required to

address the performance deficiency. No additional findings were identified. This

licensee event report is closed.

4OA4 Supplemental Inspection (95002)

.01 Inspection Scope

The NRC staff performed this supplemental inspection in accordance with Inspection

Procedure 95002, "Inspection for One Degraded Cornerstone or Any Three White Inputs

in a Strategic Performance Area," to assess the degraded Initiating Events Cornerstone

and the three White inputs to the reactor safety strategic performance area. The team

also performed Inspection Procedure 92723, "Follow Up Inspection for Three or More

Severity Level IV Traditional Enforcement Violations in the Same Area in a 12 Month

Period," in conjunction with the supplemental inspection. The inspection objectives were

to:

  • provide assurance that the root and contributing causes of risk-significant issues

were understood

  • provide assurance that the extent-of-condition and extent-of-cause of risk-

significant issues were identified and to independently assess the extent-of-

condition and extent-of-cause of individual and collective risk-significant issues

  • independently determine if safety culture components caused or significantly

contributed to the risk significant issues

5 Enclosure

  • provide assurance that the licensee's corrective actions for risk-significant issues

were or will be sufficient to address the root and contributing causes and to

preclude repetition

The licensee entered the Degraded Cornerstone Column of the NRCs Action Matrix in

the first quarter of 2010 as a result of three performance indicators crossing the

threshold from Green (very low safety significance) to White (low to moderate safety

significance). The performance indicators were Unplanned Scrams per 7000 Critical

Hours, Unplanned Scrams with Complications, and Safety System Functional Failures.

The licensee staff informed the NRC that Wolf Creek was prepared for the supplemental

inspection on October 29, 2010. To determine the causes and organizational attributes

that resulted in the three White performance indicators, the licensee performed root

cause evaluations documented in Condition Reports 26805 (collective), 23119 (safety

system functional failures), 24445 (unplanned scrams) and 25817 (scrams with

complications). These condition reports were associated with many individual event

condition reports. Altogether the inspection scope and the licensee actions included well

over 1000 corrective actions. The team noted that the licensee recovery team

performed an overarching safety culture review to determine whether safety culture

components and aspects contributed to the performance issues that led to the White

NRC performance indicators. The team inspected this effort by reviewing Condition

Reports 23032 and 25896. For the traditional enforcement violations, the team reviewed

licensee efforts documented in Condition Report 23110. The inspection team reviewed

the licensee's root cause and other supporting evaluations, and the team reviewed

corrective actions that were taken or planned to address the identified causes. The

inspection team also held discussions with licensee personnel to ensure that the root

and contributing causes and the contribution of safety culture components were

understood and corrective actions taken or planned were appropriate to address the

causes and preclude repetition. The inspection team independently assessed the

extent-of-condition and extent-of-cause of the identified issues and performed an

assessment of whether any safety culture components caused or significantly

contributed to the issues.

.02 Evaluation of the Inspection Requirements

02.01 Problem Identification

a. Identification of the issue (i.e. licensee-identified, self-revealing, or NRC-identified) and

the conditions under which the issue was identified

As a result of the multiple reactor scrams and safety system functional failures in 2009

and 2010, the licensee identified three White performance indicators through the NRC's

performance indicator reporting process.

The Unplanned Scrams with Complications performance indicator crossed the threshold

from Green to White as a result of unplanned scrams in 2009 that were the subject of a

Reactor Oversight Process Working Group Frequently Asked Question. On April 28,

2009, the main feedwater regulating valve controller power supply fuses failed, isolating

flow to steam Generator B and resulting in a reactor trip from loss of power to a main

feed regulating valve controller. Also, on August 19, 2009, a complete loss of offsite

power resulted in a complicated scram. Based on the resolution of the Frequently Asked

6 Enclosure

Question, Wolf Creek reported both of these reactor trips as Unplanned Scrams with

Complications, which caused this performance indicator in the Initiating Events

cornerstone to be White starting in the third quarter of 2009.

On March 8, 2010, during a plant start up at approximately 42 percent power, operators

manually tripped the reactor following an unplanned trip of the only running feedwater

pump. This plant startup was being conducted following a previous reactor trip on

March 2, 2010, in which loss of power to an electrical inverter led to a trip of main

feedwater Pump A and resultant low steam generator water levels. These reactor trips

combined with two others from April 2009 and August 2009 caused the Unplanned

Scrams per 7000 Critical Hours performance indicator to be White. Additionally, in

April 2010 Wolf Creek reported four safety system functional failures for the first

calendar quarter of 2010. Combined with the five others previously reported, these

functional failures caused the Safety System Functional Failures performance indicator

also to be White.

The inspectors verified that this information was appropriately documented in the

licensees evaluations.

b. Issue duration and prior opportunities for identification

The degraded Initiating Events Cornerstone and the three White inputs to the reactor

safety strategic performance area existed from March 2010 when they were identified by

Wolf Creek's performance indicator submittals. The Complicated Scrams performance

indicator crossed the Green/White threshold in the third quarter 2009. The Unplanned

Scrams per 7000 Critical Hours performance indicator was White starting in the first

quarter of 2010. Both of these performance indicators returned to Green in the second

quarter of 2010. The Safety System Functional Failures performance indicator also first

crossed the Green/White threshold in the first quarter of 2010 and did not return Green

until after the first quarter of 2011. Each of the reactor scrams and safety system

functional failures was an opportunity to identify the need for corrective actions to

reverse the negative performance trend.

The inspectors concluded that the licensees evaluations adequately identified how long

each issue existed and prior opportunities for identification of the failures.

c. Licensee documentation of the plant specific risk consequences, as applicable, and

compliance concerns associated with the issues both individually and collectively

The inspectors verified that the licensee's evaluation adequately documented the plant

specific risk consequences in qualitative statements that equipment failures directly

affect nuclear safety by challenging critical safety functions and operator response.

There were no previously documented findings associated with the scrams or safety

system functional failures that were more than very low safety significance.

02.02 Root Cause, Extent-of-Condition, and Extent-of-Cause Evaluation

a. Determine that the licensee evaluated the issue using a systematic methodology to

identify the root and contributing causes

The licensee used the following methods to complete the root cause evaluation:

7 Enclosure

  • event and causal factor charting
  • hazard-barrier-target analysis
  • fault tree analysis

The NRC team concluded the licensee evaluated the issues using systematic

methodologies to identify root and contributing causes.

b. Determine that the licensee's root cause evaluation was conducted to a level of detail

commensurate with the significance of the issue

The licensees evaluation identified the root causes of collective issues to be:

1) inadequate management oversight, 2) lack of knowledge concerning components of

nuclear safety culture, and 3) inadequate hardware monitoring. The NRC team

performed a focused inspection to independently assess the validity of the licensee's

conclusions regarding the extent-of-condition and extent-of-cause of the issues. The

NRC inspection team review for each performance indicator, individually and collectively,

determined that the licensees root cause evaluation level of detail was commensurate

with the significance of the problem.

c. Consideration of prior occurrences of the issue and knowledge of operating experience

Based on the licensee's detailed evaluation and conclusions, the inspection team

determined that the licensee's root cause analysis included an appropriate consideration

of prior occurrences of the issue and knowledge of prior operating experience.

d. Determine that the licensee's root cause evaluation addresses the extent-of-condition

and extent-of-cause of the issues

The inspectors concluded that the licensees root cause analysis appropriately

addressed the extent-of-condition and the extent-of-cause of the issue. However, for

many of the root cause evaluations the documentation was high-level, difficult to follow,

and did not always provide a strong basis for implementation and closure of the

individual corrective actions. The team determined that, in these cases, appropriate

corrective actions were specified for each root and contributing cause in other condition

reports.

e. Review the licensee's root cause, extent-of-condition, and extent-of-cause evaluations in

order to verify that the licensee appropriately considered the safety culture components

as described in Inspection Manual Chapter 0305

Because multiple condition reports and several safety culture aspects were associated

with the performance issues, the licensee conducted collective reviews of the past two

safety culture assessments and the six significant contributing condition reports. This

effort resulted in the licensee creating roll-up Condition Report 26805 to prioritize safety

culture corrective actions in September 2010. The team concluded that the prioritization

was logical and that the corrective actions, while appropriate, needed increased

oversight and reinforcement. In response to the inspection teams observations, the

licensee added specific items to improve safety culture behaviors, trending, and

knowledge levels of the operating and engineering departments to the Recovery Change

8 Enclosure

Management Plan for the upcoming cycle. The licensee also strengthened the safety

culture communication plan to reinforce human performance tool usage at all levels.

02.03 Corrective Action

a. Determine that: 1) the licensee specified appropriate corrective actions for each root

and/or contributing cause, or 2) an evaluation that states no actions are necessary is

adequate

The licensee initiated well over 1000 corrective actions to address the root and

contributing causes from the individual and collective cause evaluations. The inspectors

concluded that the licensee had specified appropriate corrective actions for each root

and/or contributing cause. The inspectors observed some cases where the licensees

corrective actions could have been more specifically tied to causes and more generally

applied to safety culture aspects. These observations are discussed in Section 02.07 of

this report.

b. Determine that the licensee prioritized corrective actions with consideration of risk

significance and regulatory compliance

The majority of the corrective actions developed by the licensee involved long term

maintenance plans and plant modifications. The licensee also prioritized communication

of standards and newly formed additional review processes as short term items. These

short term items were still in progress at the time of the inspection. The inspection team

determined that there were no risk significant immediate corrective actions necessary.

The inspection team concluded that the corrective actions identified in the root cause

evaluations for the White performance indicators were appropriately prioritized based on

risk significance and regulatory compliance.

c. Determine that the licensee established a schedule for implementing and completing the

corrective actions

The inspection team found that the licensee's root cause evaluations established many

different, independent schedules for completion of the over 1000 corrective actions.

Tracking, evaluating and closing corrective actions was assigned to the licensee

recovery team. The NRC inspection team observed that the individual schedules did not

appear to be coordinated with one another. To address the inspection teams

observation, the licensee staff compiled and provided a table to the inspectors which

tracked each corrective action item milestone with its corresponding completion date.

The inspectors concluded the revised schedule was appropriate for effectively

implementing and completing the corrective actions.

d. Determine that the licensee developed quantitative and/or qualitative measures of

success for determining the effectiveness of the corrective actions to preclude repetition

The measures developed by the licensee for determining the effectiveness of corrective

actions included the following:

  • Corrective Action and Operating Experience Review Board external reviews
  • Increased frequency of quality assurance audits to assess the adequacy of the

corrective action program initiatives generated

9 Enclosure

  • Increased frequency of safety culture assessments

The inspection team determined that the quantitative and qualitative measures

developed by the licensee for determining the effectiveness of the corrective actions

were appropriate.

e. Determine that the licensee's planned or taken corrective actions adequately address a

Notice of Violation that was the basis for the supplemental inspection, if applicable

A Notice of Violation was not the basis for this supplemental inspection.

02.04 Independent Assessment of Extent-of-Condition and Extent-of-Cause

a. Inspection Scope

Inspection Procedure 95002 requires that the inspection staff perform a focused

inspection to independently assess the validity of the licensee's conclusions regarding

the extent-of-condition and extent-of-cause of the issue. The objective of this

requirement is to independently sample performance, as necessary, within the key

attributes of the cornerstones that are related to the subject issue to ensure that the

licensee's evaluation regarding the extent-of-condition and extent-of-cause is sufficiently

comprehensive.

The inspectors conducted independent extent-of-condition and extent-of-cause reviews

for the issues associated with the White performance indicators. The inspection staffs

independent review focused on the primary root causes associated with the performance

indicators in addition to the licensees identified contributing causes that involved more

specific aspects of the broader root causes. The inspection staff assessed whether the

licensees extent-of-condition and extent-of-cause evaluations sufficiently identified and

bounded all engineering and maintenance organizational issues. The staff also

assessed whether the licensees extent-of-condition and extent-of-cause evaluations

sufficiently determined the actual extent of similar organizational issues that potentially

existed in other station departments, programs, and processes. The team independently

sampled performance within the key attributes of the Initiating Events and Mitigating

Systems Cornerstones that are related to the contributors of the performance issues to

ensure that the licensee's evaluation regarding the extent-of-condition and extent-of-

cause were sufficiently comprehensive.

In conducting this independent review, the inspection staff interviewed station

management and personnel, reviewed program and process documentation, and

reviewed existing station program monitoring and improvement efforts, including review

of corrective action documents.

b. Assessment

The team concluded that the licensee had identified all substantive extent-of-condition

and extent-of-cause issues. However, the teams independent extent-of-condition and

extent-of-cause review identified some cases where the licensees evaluations were

narrowly focused. For example, the licensee's evaluation of scrams with complications

in Condition Report 25817 limited the review of main feedwater system health to just the

startup feedwater pump, which inappropriately excluded many components with the

10 Enclosure

potential to affect system performance. The evaluation also did not evaluate the

August 2009 loss of offsite power and condensate and heater drain bus event, making

instead a statement that a loss of offsite power will always result in a complicated scram.

The team identified this as another example where the evaluation of Condition

Report 25817 missed an opportunity to improve feedwater system reliability. The team

concluded Wolf Creek's root cause analysis procedures could be improved to enable the

licensee to consistently identify systemic causal factors.

As a result of the inspection teams observations, Wolf Creek reviewed Condition

Report 25817 to identify additional interim and long-term corrective actions. This

included a review by the Quality group and bringing in additional root cause evaluators

to ensure the root cause analysis procedures were improved as needed.

02.05 Safety Culture Consideration

a. Inspection Scope

Inspection Procedure 95002 requires that the inspection team perform a focused

inspection to independently determine that the licensee's root cause evaluation

appropriately considered whether any safety culture component caused or significantly

contributed to any risk significant issue.

The inspection team reviewed condition reports and procedures and conducted

interviews with licensee personnel to determine if the licensee properly considered

whether any safety culture component caused or contributed to the performance issues.

Additionally, the inspectors performed a review of the common cause evaluation.

b. Assessment

As part of the collective root cause evaluation, the licensee evaluated the identified root

and contributing causes against the safety culture components that could have

contributed to the issues. The licensee's root cause evaluation included a discussion of

the 13 safety culture components as described in Regulatory Issue Summary 2006-013,

"Information on the Changes Made to the Reactor Oversight Process to More Fully

Address Safety Culture."

The inspection team independently confirmed the licensees conclusion that improving

safety culture behaviors should be a high priority item for the recovery effort. The

documented station reviews indicated that every safety culture component was a

contributor to the performance issues, and all were significant contributors with the

exception of self- and independent-assessments. The inspection team concluded all the

safety culture components were significant contributors. The inspection team confirmed

that the licensee established appropriate corrective actions to address safety culture.

The team identified challenges to Wolf Creek's ensuring long-term promotion of a

positive safety culture. Specifically:

  • Although safety concept is a recognized value in the organization, it is

inconsistently accepted and understood across all levels of personnel. Some

problems still exist in the transmission, comprehension, and implementation of

the safety message.

11 Enclosure

  • Some individuals readily accept responsibility for and take ownership of

problems, while others are still reluctant to do so.

  • Observed safety behaviors were not consistently integrated into all activities in

the organization. Processes and programs are in various stages of transition,

which often reduces their effectiveness.

  • An integrated and cohesive organizational safety leadership process does not yet

exist. The values and attitudes of the workforce are generally positive, but the

team identified that personnel are not yet aligned with a common set of values.

02.06 Evaluation of Inspection Manual Chapter 0305 Criteria for Treatment of Old Design

Issues

The licensee did not request credit for self-identification of an old design issue; therefore,

the risk-significant issue was not evaluated against the Inspection Manual Chapter 0305

criteria for treatment of an old design issue.

02.07 Findings and Observations

a. Introduction. The inspectors identified a Green noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, "Instructions, Procedures, and Drawings," for the failure to

follow Procedure AP 28A-0100, "Condition Reports," Revision 13.

Description. On February 17, 2011, the licensee received laboratory test results on the

Train B emergency diesel generator fuel oil storage tank and determined that the cloud

point parameter was out of specification at -8° Celsius. The specification limit for cloud

point was no higher than -9° Celsius. The licensee subsequently declared the

emergency diesel generator inoperable and entered Technical Specification 3.8.3. As

part of the review of the event, the licensee sent an additional sample from the fuel oil

storage tank to the same laboratory, as well as to an additional laboratory for

comparison. The licensee also sent samples from the Train A emergency diesel

generator fuel oil storage tank to determine the extent-of-condition. These actions are

documented in Condition Report 33750.

Procedure AP 28A-0100, step 5.13.3, required licensee personnel to evaluate condition

report data to identify and evaluate potential trends. The emergency diesel fuel oil

storage tank cloud point parameter had been trending closer to the acceptance criteria

over the last several fuel oil additions. In various condition reports over the past two

years, the licensee documented that the cloud point parameter had been out of

specification in new fuel oil shipments. In addition to the sample in February 2011,

Condition Reports 21044, 25018 and 26345 documented the cloud point parameter

being an issue in October 2009, April 2010 and June 2010, respectively. Condition

Report 26345 did not receive an appropriate review to identify that the adverse trend, if

not resolved promptly, could result in the emergency diesel generator becoming

inoperable. Corrective actions from Condition Report 26345 included purchasing fuel oil

from a new vendor that would provide a low cloud point, but this was not implemented in

a timely manner to prevent the unplanned technical specification entry. As a result, on

February 17, 2011, the Train B fuel oil storage tank cloud point parameter went out of

specification requiring the licensee to withdraw fuel oil and replace it with in-specification

fuel oil from the new vendor. Two tanker loads of new fuel oil were placed into the

12 Enclosure

storage tank and a multilevel sample of the resulting mixture was analyzed to ensure

that all chemistry parameters were within specification. The licensee had allowed the

original fuel oil vendor to continue to deliver fuel that was out of specification which

resulted in a gradual trend toward the limits of the chemistry parameters. This trend was

not appropriately evaluated because the licensee had not performed training to ensure

that consistent and appropriate evaluations would be performed.

Analysis. Failure to track and trend the emergency diesel generator chemistry

parameters as required by the corrective action program procedure was a performance

deficiency. The finding was more than minor because it affected the Mitigating Systems

Cornerstone attribute of equipment performance by impacting the cornerstone objective

to ensure the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. This deficiency directly resulted in

emergency diesel generator B being declared inoperable due to its fuel oil storage tank

being out of specification. The inspectors performed the significance determination

using NRC Inspection Manual Chapter 0609.04, "Phase 1 - Initial Screening and

Characterization of Findings," because it affected the Mitigating Systems Cornerstone

while the plant was at power. The finding was determined to be of very low safety

significance (Green) because it was not a design or qualification deficiency; it did not

result in the loss of a system safety function; it did not represent the loss of a single train

for greater than technical specification allowed time; it did not represent a loss of one or

more non-technical specification risk-significant equipment for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />;

and it did not screen as potentially risk significant due to seismic, flooding, or severe

weather. In addition, this finding had human performance crosscutting aspects

associated with resources in that the licensee did not ensure that the corrective action

program coordinators were effectively trained to cognitively and analytically trend

condition reports H.2(b).

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures,

and Drawings," requires, in part, that activities affecting quality shall be prescribed by

documented procedures of a type appropriate to the circumstances and shall be

accomplished in accordance with these procedures. Procedure AP 28A-0100,

"Condition Reports," step 5.13.3 requires the licensee, in part, to evaluate condition

report data to identify and evaluate potential trends. Contrary to this, from October 2009

to February 19, 2011, the licensee failed to evaluate condition report data to identify and

evaluate potential trends in emergency diesel generator fuel oil storage tank chemistry

parameters. As a result, the station entered Technical Specification 3.8.3 for a high

cloud point on the Train B emergency diesel generator fuel oil storage tank. Immediate

corrective actions included withdrawing fuel oil and replacing it with new fuel oil until the

cloud point could be reduced to below the maximum value. Since this violation was of

very low safety significance and was documented in the licensee's corrective action

program as Condition Reports 33395, 33435, and 33750, it is being treated as a

noncited violation consistent with Section 2.3.2 of the NRC Enforcement Policy:

NCV 05000482/2011006-01, "Failure to Trend Emergency Diesel Generator Chemistry

Parameters Results in an Unplanned Technical Specification Entry."

13 Enclosure

b. NRC Team Observations

1) Maintenance to Improve Equipment Reliability

The inspection team noted that the licensees corrective actions for improving equipment

reliability focused primarily on preventative maintenance improvements. The team

determined this focus initially may not result in protecting the functionality of the key

systems inputting to the safety system functional failure performance indicator in the

short term. The team concluded that a broader root cause of inadequate maintenance in

general, versus just improved preventative maintenance, may be more appropriate to

address equipment reliability issues. This action is consistent with the licensee roll-up

root cause of tolerance for known degraded equipment conditions. The team determined

that the recent refueling water storage tank and emergency diesel generator fuel oil

storage tank degraded chemistry issues, emergency diesel generator fuel rack pin

inoperability, and component cooling water system voiding were examples that

demonstrated the importance of improvement in general maintenance practices and

represented conditions that could challenge the safety system functional failure

performance indicator.

The team concluded that corrective actions to develop a preventative maintenance

optimization plan, improve operating experience reviews, and perform significant main

feedwater modifications were appropriate. However, the corrective actions to add digital

feedwater controls will not be complete until Fall 2015.

The licensee identified inadequate equipment performance monitoring and trending as a

maintenance improvement item, but initiated actions for "new" systems/components

only. The team concluded a broader application of this action would be more

appropriate. For example, the team identified that the station thermography tool is not

being used to its full extent. This was similar to the previous limited use of ultrasonic

testing and guided wave technology for essential service water corrosion issues. The

licensee initiated Condition Report 33435 to evaluate additional corrective actions for

equipment performance and monitoring.

2) Corrective Action Documentation

The team identified several instances where the documentation of corrective actions was

not clearly defined through the corrective action program, which could provide

challenges to the timely completion of the actions and to the ability of the licensees

quality control organization to perform effectiveness reviews. For example, corrective

actions for root causes in Condition Report 23119 (safety system functional failures)

were contained in Condition Report 24445, but were not listed as corrective actions to

prevent recurrence in Condition Report 24445. This could lead to closure of the actions

out without sufficient reviews to ensure effective corrective actions occurred. As a

second example, overall station roll-up Condition Report 26805 contained no

documented corrective actions. Instead, this condition report provided a prioritization of

the common causes in the other six high level individual event roll-up condition reports

(see Attachment 2). The documentation of the corrective actions for the causes and

safety culture component concerns are embedded in various other condition reports.

The team identified this as a challenge to correctly implementing and closing out the

individual corrective actions. The licensee took actions to address this issue, including

initiating Condition Reports 33722 and 33958 and developing additional root cause

14 Enclosure

evaluators to improve documentation standards and reduce root cause evaluation

backlogs.

The team also identified that two key licensee initiatives (each a corrective action to

prevent recurrence), the Preventative Maintenance Optimization Plan and the Ops

Focus Plan, were essentially mission statements and lacked the details necessary to

guide implementation. As a result of the team inspection, the licensee developed

revisions to these plans to provide better detail and clarity.

3) Training as a Corrective Action

The licensee identified a corrective action of improved training, modeled after previous

changes made to improve the technical program for engineers and operators, to address

performance issues associated with both the safety system functional failures and

unplanned scrams performance indicators. However, training provided as a corrective

action for risk assessments failed the licensees initial effectiveness review. This was

one of the first effectiveness reviews performed by the licensee, and it identified that the

training corrective action was narrowly focused and not likely to reach everyone affected.

The team identified some additional examples where training as a corrective action had

not yet been fully effective, including:

  • A corrective action review board graded the root cause evaluation of "inadequate

clearances orders due to not isolating the energy source," as acceptable without

a training corrective action when the cause was an inability to read prints.

  • At the time of the inspection, neither engineering nor training departments had

been trained on the updated operating experience process.

  • The team observed some cases where system engineer knowledge levels were

not broad or integrated.

  • Root cause team member training was not consistently producing thorough

extent-of-cause results.

  • The team received interview comments indicative of operations and training

department dissatisfaction with support by the other department. Other

comments also identified cases where managers may have decided not to assign

training related corrective actions based on limited training resources.

The team concluded that broader training, improvements for both engineers and

operators is needed. The licensee initiated Condition Reports 34280 and 34281 to

address engineering and operations department training issues.

4) Problem Identification

The team concluded the various review board initiatives, specifically the corrective action

review board challenge meetings, apparent cause evaluation level corrective action and

collegial operating experience review boards, were positive efforts. However, individual

level behavior changes will be needed to identify trends or deficiencies in equipment and

engineering performance. The team noted some cases where the threshold for

15 Enclosure

identifying and trending degraded conditions in the plant could be improved. Examples

include:

  • A high level alarm indicative of actual rising essential service water vault water

level was initially assumed to be invalid in Fall 2010. This resulted in delaying an

operability assessment over two shifts.

  • The team identified that self- and independent-assessments were not being

effectively used to identify and correct problems. The licensee initiated condition

report 34076 and directed the quality assurance department to perform an

additional surveillance of the corrective action program to address this issue.

  • The team noted two examples of initial failure to act on contracted engineering

evaluations. The first example involved a contractor evaluation of the feedwater

pump suction strainer in December 2010 that stated the strainer could introduce

new failure mechanisms. The inspection team noted a failed strainer could

release debris which could impact the feedwater regulating and isolation valves.

The licensee initiated Condition Report 32445 to evaluate this condition. The

second example was previously identified in an NRC inspection of essential

service water and involved a deficient in-house engineering analysis accepted

without action despite outside contractor evaluations stating that water hammer

stresses were significant enough to warrant inclusion in the system design

calculations. At the close of the inspection the licensee was reevaluating both of

these issues.

  • The team identified some process programs that may result in tracking and

correcting problems outside of the corrective action program. One example is

the PILOT system used to record and trend management field observations. The

licensee initiated Condition Report 33316 to address this concern.

5) Management Oversight and Leadership

In Condition Report 26805, "Collective Significance of Degraded Cornerstone

Performance," the licensee identified Management/Oversight/Standards Enforcement as

one of the overall root causes of the sites performance issues. The team concluded

that licensee actions to address improving management oversight were appropriate.

However, the team identified that the additional review boards requiring management

participation had the unintended consequence of reducing the amount of time available

for managers and supervisors to conduct plant tours and field observations. The team

also identified some cases where review boards accepted quality assurance reports of

effective program performance despite identified repeat findings, and cases where the

review boards did not consistently challenge extent-of-condition and extent-of-cause

issues in root cause evaluations.

To address the teams observations the licensee developed initiatives to improve

standards for leadership meetings, division manager alignment meetings and plant wide

communication efforts.

16 Enclosure

4OA6 Meetings

Exit Meeting Summary

On April 5, 2011, the inspectors presented the inspection results to Mr. M. Sunseri and

other members of the licensee staff. The licensee acknowledged the issues presented.

The inspectors identified that proprietary information was reviewed but would not be

retained following report issuance or included in the inspection report.

4OA7 Licensee-identified Violations

The following violation of very low safety significance (Green) was identified by the

licensee and is a violation of NRC requirements which meets the criteria of Section 2.3.2

of the NRC Enforcement Policy, NUREG-1600, for being dispositioned as a noncited

violation.

  • Title 10 CFR 50.65 a(4) requires, in part, that before performing maintenance

activities, the licensee shall assess and manage the increase in risk that may

result from the proposed maintenance activities. Contrary to the above, during

the weeks of November 29, 2010, December 27, 2010 and January 17, 2011,

Wolf Creek failed to properly identify and take appropriate risk management

actions for medium and high risk maintenance activities as required by station

Procedure AP 22C-007, "Risk Management and Contingency Planning,"

Revision 4. The inspectors performed the significance determination using NRC

Inspection Manual Chapter 0609.04, "Phase 1 - Initial Screening and

Characterization of Findings," and Manual Chapter 0609, Appendix K,

"Maintenance Risk Assessment and Risk Management Significance

Determination Process" and determined the finding was of very low safety

significance (Green) because it related only to risk management actions and did

not result in an increase in core damage probability. This licensee entered this

issue into the corrective action program as Condition Reports 00032886

and 00032887.

17 Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

L. Bell, Systems Engineering

M. Blow, Operations

S. Hedges, Site Vice President

D. Hooper, Supervisor, Licensing

T. Jensen, Manager, Chemistry

S. Koenig, Manager Corrective Action

W. Norton, Manager IPS/Scheduling

L. Parmenter, Assistant to Manager, Operations Department

G. Pendergrass, Director, Plant Engineering

L. Ratzlaff, Supervisor, Support Engineering

E. Ray, Manager Quality

L. Rockers, Licensing Engineer

R. Smith, Plant Manager

M. Sunseri, President and Chief Executive Officer

S. Wahlmeier, Systems Engineering

J. Yunk, Manager, Human Resources

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000482/2011006-01 NCV Failure to Trend Emergency Diesel Generator Chemistry

Parameters Results in an Unplanned Technical Specification

Entry (Section 4OA4)

Closed

05000482/2010-005-00 LER Reactor Trip due to Low Steam Generator Level from Trip of

Main Feedwater Pump (Section 4OA3)

05000482/2010-012-00 LER Reactor Trip due to Operator's Inability to Control Steam

Generator Level Oscillations at Low Power (Section 4OA3)

LIST OF DOCUMENTS REVIEWED

Section 4OA4: Supplemental Inspection

PROCEDURES

NUMBER TITLE REVISION

AI 09A-008 Engineering Allocation 3

AI 16C-007 Work Order Planning 30

A1-1 Attachment 1

AI 17C-005 Shift Manager Selection, Initial Training and Continuing 5

Training Program

AI 18A-001 Receipt, Investigation, and Closure of Employee Concerns 2

AI 18A-002 Conducting Exit/Walk-in Interviews 1A

AI 18A-003 Preparation, Maintenance, and Security of Employee 1A

Concerns Files

AI 21-016 Operator Time Critical Actions Validation 1

AI 22C-008 Work Scoping Team 6

AI 22C-012 Quality Review Team (QRT) for Maintenance Work Planning 0

AI 22D-001 High Impact Teams 5

AI 22I-004 Project Ranking Guide 0, 1, 2

AI 23M-003 Maintenance Rule Expert Panel Duties and Responsibilities 7

AI 23O-001 Functional Importance Determination 0, 1, 2, 2A

AI 28A-001 Level 1 CR Evaluation (IIT) 12

AI 28A-003 Rapid Response To Events Of Significance 3A

AI 28A-006 Level 3 CR Evaluation 9

AI 28A-007 Level 2 CR Evaluation 4

AI 28A-010 Screening Condition Reports 6, 7

AI 28A-023 Evaluation of Maintenance Rule Functional Failure PIRs 1

AI 28E-007 Corrective Action Coding and Trend Analysis 7A

AI 28E-008 Condition Report Trend Code Assignment Process 2A

AI 34-003 Corrective Action Program Coordinators - Roles & 1A

Responsibilities

ALR KC-888 Fire Protection Panel KC-008 Alarm Response 18A

ALR 00-120A MFP A Trip 9, 10

ALR 00-120B MFP A Suct Press LO 11

ALR 00-016B PB03 / 04 Bus UV 11

AP 02-003 Chemistry Specification Manual 34B

AP 16C-006 MPAC Work Request/Work Order Process Controls 15

A1-2 Attachment 1

AP 18A-001 Employee Concerns Program 4

AP 20E-001 Industry Operating Experience Program 10, 11, 12,

13

AP 21-200 Operational Decision Making and Problem Analysis 3

AP 21C-001 WCGS/WESTAR Substation 8, 9, 11A

AP 22A-001 Screening, Prioritization and Pre-Approval 13

AP 22B-001 Outage Risk Management 9, 11, 12

AP 22C-003 Operational Risk Assessment Program 14A

AP 22C-003 On-Line Nuclear Safety and Generation Risk Assessment 15, 15A

AP 22C-005 IPS Daily Scheduling 12

AP 22C-007 Risk Management and Contingency Planning 4

AP 23M-001 WCGS Maintenance Rule Program 6

AP 23O-001 Plant Health Committee 4

AP 23-006 System Engineering Program 20, 20A

AP 23-008 Equipment Reliability Program 4

AP 24B-001 Control of Site Contractor Services 7

AP 26A-001 Reportable Events - Evaluation and Documentation 15

AP 26A-004 Communications With the Nuclear Regulatory Commission 10/11

AP 26A-007 NRC Performance Indicators 8

AP 28-011 Resolving Degraded or Nonconforming Conditions Impacting 2

SSCs

AP 28A-100 Condition Reports 13

AP 36-001 Nuclear Safety Culture 0

CKL ZL-009 Site Reading Sheets 70

GEN 00-002 Cold Shutdown to Hot Standby 71

GEN 00-003 Hot Standby to Medium Load, pages 20 and 21 29

GEN 00-003, 10 Hot Standby to Medium Load 33

GEN 00-004 Power Operation, page 36 of 63 65

GEN 00-006 Hot Standby to Cold Shutdown 70

A1-3 Attachment 1

I-ENG-005 Infrared Thermograph 4

MPE E009Q-03 Inspection and Testing of Siemens Vacuum Circuit Breakers 4

OFN BB-031 Shutdown LOCA 17

OFN MA-038 Rapid Plant Shutdown, page 2 of 45 12

OFN NB-030 Loss of AC Emergency Bus NB01 (NB02) 20

OFN NB-035 Loss of Off-Site Power Restoration 0

RNM C-130 Miscellaneous Relay and Meter Equipment 6

STN AE-007 Startup Main Feedwater Pump Operational Test 0

SYS AE-132 MFIV Pressure Open with ASU (Laptop) 0 and 1

SYS AE-200 Operation of Feedwater Heating 7

STS AE-201 Feedwater Chemical Injection Inservice Valve Test 22

STS IC-215 TADOT of Manual Reactor Trip, Trip and Bypass Breaker 13, 14

UV/Shunt Trip, Turbine Trip on Reactor Trip and P-4

STS RE-018 Multiple Rod Drop Time Measurement 11

SYS AC-120 Main turbine Generator Startup 51

SYS AE-121 Turbine Driven Main Feedwater Pump Startup 32, 33

SYS AE-320 Turbine Driven Main Feedwater Pump Shutdown 23

SYS EJ-320 Placing RHR System in Safety Injection Standby Condition 34

SYS EJ-321 Shutdown of a Residual Heat Removal Train 29

SYS SB-122 Enabling/Disabling P-4/LO Tavg FWIS 1, 2

WCRE-13 Wolf Creek Generating Station Lake Water Systems 2

Structural Integrity Program

CONDITION REPORTS

777 7499 7508 7509 7510

7511 8575 9181 9375 9519

10247 10300 11768 12913 13805

13957 14261 14262 15269 15306

15407 15520 15521 15576 16455

16467 16657 16905 17776 17900

18034 18156 18413 19245 19295

A1-4 Attachment 1

19318 19360 19369 19371 19390

19447 19913 19914 19960 20665

21002 21039 21044 21260 21509

21641 21702 21813 21816 22470

22781 22979 23008 23032 23108

23110 23114 23119 23154 23479

23852 23938 23992 24445 24852

25018 25817 25892 25896 26345

26384 26787 26805 27005 27527

27997 27998 28175 28208 28224

28474 29095 29098 29128 29181

29204 29286 29818 30271 31121

31151 31458 31800 32326 32404

32431 32434 32436 32438 32445

32446 32451 32492 32506 33041

33076 33087 33103 33109 33143

33177 33202* 33212* 33217* 33229*

33253 33316* 33320 33327 33329*

33331* 33336* 33341* 33342* 33351*

33385* 33393* 33395* 33416* 33419*

33423* 33435* 33440* 33442* 33456*

33457* 33459* 33465* 33466* 33467*

33469* 33529* 33535* 33540* 33541*

33575* 33594* 33625* 33720* 33722*

33752* 33761* 33869* 33890* 33903

33917 33922* 33928* 33929* 33958*

33983* 33990* 2006-001409 2006-001798 2006-003035

2006-003271 2006-003473 2006-003815 2007-000040 2007-000187

2007-000202 2007-001013 2007-001707 2007-001780 2007-001993

2007-002000 2007-002009 2007-002128 2007-002331 2007-002749

2007-002854 2007-003350 2007-003612 2007-003798 2007-004055

2007-004125 2007-004126 2007-004127 2007-004128 2007-004129

2007-004130 2007-004132 2008-000116 2008-000149 2008-000164

2008-000465 2008-000989 2008-001014 2008-002230 2008-002237

A1-5 Attachment 1

2008-003419 2008-003802 2008-003810 2008-004136 2008-004536

2008-004997 2008-006105 PIR 1995-0586 PIR 1995-2858 PIR 1996-3260

PIR 1997-0078 PIR 1998-2794 PIR 2000-0834 PIR 2000-0835 PIR 2000-0871

PIR 2000-2212 PIR 2001-0041 PIR 2001-2368 PIR 2002-0860 PIR 2003-2178

PIR 2003-2496 PIR 2004-0586 PIR 2004-0684 PIR 2004-2435 PIR 2004-2502

PIR 2004-2644 PIR 2004-2684 PIR 2004-2813 PIR 2004-3390 PIR 2005-0121

PIR 2005-0382 PIR 2005-0771 PIR 2005-0773 PIR 2005-0774 PIR 2005-0775

PIR 2005-0776 PIR 2005-0777 PIR 2005-0778 PIR 2005-0779 PIR 2005-0780

PIR 2005-0781 PIR 2005-0782 PIR 2005-0783 PIR 2005-0784 PIR 2005-0785

PIR 2005-0786 PIR 2005-0787 PIR 2005-0788 PIR 2005-0789 PIR 2005-0790

PIR 2005-0791 PIR 2005-0792 PIR 2005-0794 PIR 2005-0795 PIR 2005-0796

PIR 2005-1411 PIR 2005-1962 PIR 2005-2126 PIR 2005-2164 PIR 2005-2167

PIR 2005-2168 PIR 2005-2461 PIR 2005-2507 PIR 2005-2619 PIR 2007-0483

PIR 2008-1105 PIR 2008-003802

  • Condition Reports generated during the inspection

DRAWINGS

NUMBER TITLE REVISION

M-12AB03 Main Steam System 18

M-12AE01 Piping & Instrumentation Diagram Feedwater System 37

M-12AE02 Piping & Instrumentation Diagram Feedwater System 13

LERS

NUMBER TITLE DATE

2008-002-01 Technical Specification Allowed Outage Time Exceeded January 11, 2010

due to Room Cooler Leak

2008-003-00 Manual Reactor Trip due to Loss of Steam Generator May 13, 2008

Level

2008-004-02 Loss of Offsite Power Event When the Reactor was De- November 11,

fueled 2009

2008-007-00 Two Residual Heat Removal Trains Inoperable in July 10, 2007

Mode 3 due to Check Valve Leakage

2008-008-00 Potential for Residual Heat Removal Trains to be October 3, 2008

Inoperable during Mode Change

A1-6 Attachment 1

2008-008-02 Potential for Residual Heat Removal Trains to be August 25, 2009

Inoperable during Mode Change

2009-001-00 Reactor Protection System Actuation and Reactor Trip June 24, 2009

due to Main Feedwater Regulating Valve Failing Closed

2009-002-00 Loss of Offsite Power due to Lightning October 17, 2009

2009-005-00 Loss of Both Diesel Generators with all Fuel in the Spent December 21,

Fuel Pool 2009

2009-009-01 Defeating Feedwater Isolation on Low Tavg Coincident March 3, 2010

with P-4 Function Results in Missed Mode Change

2010-001-00 Automatic Start of Motor Driven Auxiliary Feedwater March 22, 2010

Pumps Inoperable During Startup in Mode 1

2010-002-00 Turbine Trip Function of Reactor Trip, P-4 Interlock March 29, 2010

Defeated During Entry into and in Mode 3

WORK ORDERS

00-223036-004 04-266765-000 05-273961-002 06-286463-000 07-291802-000

07-300375-000 08-303896-000 08-303897-000 09-316562-002 09-316566-004

09-316730-000 09-317186-000 09-317187-000 09-317188-000 09-317189-000

09-317190-000 09-317749-000 09-317750-000 09-317752-000 09-317753-000

09-317754-000 09-317755-000 09-317756-000 09-317757-000 09-317820-000

09-317821-000 09-317822-000 09-317823-000 09-321570-000 09-321571-000

09-321572-000 09-321573-000 09-322495-000 09-322503-000 10-324684-000

10-325088-000 10-325088-001 10-325205-000 10-326827-057 10-331761-000

10-332022-000 10-332233-000 10-332233-001 10-332631-000 10-332731-000

11-337163-002

MEETING NOTES

MEETING DATE

OE Collegial Review February 10, 2011

Level 4 Challenge Board February 23, 2011

Corrective Action Challenge Board February 24, 2011

A1-7 Attachment 1

MISCELLANEOUS

NUMBER TITLE DATE / REVISION

2010 Nuclear Safety Culture Assessment

Interview Responses

2010 Nuclear Safety Culture Assessment Pre-

assessment Survey

Amendment to Wolf Creek Generating Station August 13, 2010

Operating Agreement

Control Room Logs from April 7-8, 2008

Control Room Logs from November 17-20, 2008

Deficient/Corrective Maintenance Backlog January 2011

Reduction Initiative dated

Diesel Fuel Oil Strategic Plan 2

Employee Concern Program Overview 2009

Employee Concern Program Overview 2010

Engineering Technical Task Brief Desktop 1

Instruction

Essential Service Water Feasibility Study, Wolf November 2010

Creek Nuclear Operating Corporation, Burlington,

Kansas (WCNOC127)

FID Assignments for Fire Pumps, PN09, and

PB03

Feedwater Quick Hit Assessment November 12, 2010

GDC-17 Transmission Network Controls and 8

Reliability Improvement and Related Issues

HU Tools For Engineers Desktop Instruction 0

Human Performance Toolbox 3

Jan 2011 Management Observations of Ops

Letter ET 10-0011, dated March 4, 2010, from

T. J. Garrett WCNOC to NRC

List of PRA Top Ten Systems

Maintenance Rule Final Scope Evaluation

Essential Service Water (EF)

A1-8 Attachment 1

Metallurgical Failure Evaluation of a Corroded 30" November 25, 2009

Elbow from the Outlet Side of the Self-Cleaning

Strainer of an ESW Line, Report N0. 57809

Metallurgical Investigation of a Corroded 18" October 27, 2009

Welded Pipe, 150-HBC-18 from A ESW Lake

Water Line, Report No. 57652

MSDS for SPEC-AID 8Q5368ULS November 17, 2006

NERC Interface Coordination Agreement for the

Wolf Creek Substation between Westar Energy,

Inc and Wolf Creek Nuclear Operating

Corporation

Nuclear Plant Interface Coordination NUC 001-2 March 23, 2010

On the Spot Change (OTSC) 09-0084, Gen 00- November 17, 2009

002, Cold Shutdown to Hot

Standby On the Spot Change (OTSC) 09-0086, November 19, 2009

STS RE-018, Multiple Rod Drop Time

Measurement

On the Spot Change (OTSC) 10-0011, AP 22C- February 17, 2010

002, Work Controls

On the Spot Change (OTSC) 11-0014, February 22, 2011

AP 28A-100, Condition Reports

Operational Focus Plan 1

Operational Focus Plan 2 (draft)

Operations Requalification Cycle 10-04 Schedule July 7, 2010

Preventative Maintenance Optimization (PMO) 0, 1, and 2

Project Report

Project Plan for Essential Service Water Piping January 18, 2011

Integrity Project 2

Project Report, GDC-17 Transmission Network 8

Controls and Reliability Improvement and Related

Issues

Quality Oversight Report December 2010/

January 2011

Quick Hit Detail Report 1684, PM Basis Review January 14, 2010

Quick Hit Detail Report 1795, STP STARS ER June 29, 2010

Benchmarking Trip

A1-9 Attachment 1

Record Supplement/Correction Sheet K01-033 for February 24, 2011

CR 23119 - Safety System Functional Failures

Exceeding PI Threshold

Single Point of Entry Training Presentations, September 2010

PowerPoint Slides

Slide presentation on Managing Defenses

Md 0510

Slide presentation on Reducing Error Re 0510

Student Notes from USA Event Reporting, 3A

RA270RPT.H02

Student Work Book for USA Event Reporting, 3A

RA270RPT.WB1

Today's Operational Focus February 7-10, 2011

Training Lesson Materials for General Training July 8, 2010

GT1535403, Rev 009, on Reportability - Event

Notification and Reporting

Training Lesson Slides for General Training 9

GT1535403, on Reportability - Event Notification

and Reporting

Training Roster dated Apr 21, 2010 for 15

AP 26A -001, Reportable Events - Evaluation and

Documentation

Training slides from USA Event Reporting The 3A

10 CFR 50.72 and 50.73, RA270RPT.PP1

Various Fuel Oil Lab Analysis Data Sheets

WCGS_PRA_Rev5_Raw Query

WCGS_PRA_Rev5_RRW Query

WCNOC Reportability Handbook 4

Wolf Creek Change Management Process Guide 1

Wolf Creek Change Plan Process High

Complexity Worksheet

Wolf Creek Change Plan Process Introduction

Worksheet

Wolf Creek Change Plan Process Low Complexity

Worksheet

A1-10 Attachment 1

Wolf Creek Change Plan Process Moderate

Complexity Worksheet

Wolf Creek Nuclear Operating Company Nuclear August 2008

Safety Culture Assessment

Wolf Creek Nuclear Operating Company Nuclear March 2010

Safety Culture Assessment

Wolf Creek Nuclear Operating Corporation, The April 13, 2010

Daily Current

Wolf Creek Nuclear Operating Corporation, The March 17, 2010

Daily Current

Wolf Creek Technical Specifications,

Amendment 188

Wolf Creek Updated Safety Analysis Report 23

(USAR)

00-223036-000 Tank Inspection Report 100K Diesel Fuel Oil April 2002

Tanks Alpha/Bravo Wolf Creek Nuclear Operating

Corporation (Vendor Report)

02846 Feedwater Preheating Calculation 1

AIF 22I-004-01 Project Ranking Points 2

APF 21C-001-01 WCGS Substation Work Authorization 5

Audit 09-02-ENG Quality Assurance Audit Report Engineering April 3, 2009

Program

Audit 10-02-OPS Quality Assurance Audit Report Operations March 16, 2010

Program

Audit 10-07-FP Quality Assurance Audit Report Fire Protection September 23, 2010

Program

Change Package Alarm 7300 Cabinets Card Frame Fuses 0

13343

CP 013043 Diesel Fuel Oil 0

FAQ 10-03 Wolf Creek Generating Station Unplanned March 18, 2010

Scrams with Complications

FSAR 10.4.7.2.3 Feedwater System Operation

OTSC 02-0108 50.59 Screening for GEN 00-003, Rev 54 April 27, 2002

procedure change

A1-11 Attachment 1

OTSC 02-0108 50.59 Applicability Determination for GEN 00-003, April 27, 2002

Rev 54 procedure change

RA1331201 Regulatory Awareness 5

RA2331201 Ai 26A-003 Other Regulatory Evaluations for Prior 0

NRC Approval

RA270RPT.LP1 Lesson Plan for USA Event Reporting 3A

SEL 2009-152 Self Assessment Report Predictive Maintenance

(PdM) Program

SEL 2010-194 Self Assessment Report Main Feedwater

SEL-2010-188 NRC Performance Indicator Program January 11, 2011

SEL 2010-192 INPO TR10-70 Self Assessment

SEL-2010-194 Main Feedwater Self Assessment December 7, 2010

SEL 01-033 Licensing Commitments

SEL 05-01 Transformer and Switchyard Self-Assessment

STN IC-903 Cross Trip Check XNB01 Switchyard 3

TB-05-6 Westinghouse Technical Bulletin - Retrofit of 0 and 1

Printed Circuit Cards for 7300 Based Systems -

Capacitor C105 Replacement with Fuse

Protection Added

TG1645500 Safety Culture - What's at Stake? 0

TIN ES1312300 Timeliness Evaluations RIS 2005-20 2

TSA 20273-000 Bechtel Response to Reactor Trips caused by 0 and 1

Main Feedwater

USN 153113 Feed Pump Turbine Upgrades Per TIL-1206 August 26, 2010

Recommendations

A1-12 Attachment 1