01-03-2018 | On 10/09/17, during the bi-weekly Emergency Diesel Generator ( EDG) #2 Load Test, a Generator Lockout signal (86G) was received which tripped the EDG output breaker. This failure resulted in EDG #2 being declared inoperable, and entry into an unplanned 7-day Limiting Condition for Operation (LCO) at 0312.
Troubleshooting identified a broken electrical ring lug connector on a current transformer that provides an input to the protective relay logic. The investigation determined the connector failure was due to fatigue cracking that was initiated by stresses caused by bending and twisting of the electrical lug beyond limits specified in industry guidelines. The ring lug was most likely distressed during initial installation in the 1990's. The condition that led to the EDG #2 trip existed for greater than the allowed outage time in the plant's Technical Specification (TS) and is reportable under 10 CFR 50.73(a)(2)(i)(B). |
---|
|
---|
Category:Letter
MONTHYEARIR 07200015/20244012024-10-30030 October 2024 NRC Independent Spent Fuel Storage Installation Security Inspection Report No. 07200015/2024401 ML24303A2822024-10-29029 October 2024 License Termination Plan Supplemental Submittal for Technical Bases Documents ML24284A1972024-10-10010 October 2024 Cover Letter Oyster Creek, License Termination Plan Acceptance Review ML24269A0462024-10-0404 October 2024 Cover Letter for Oyster Creek Nuclear Generating Station, License Amendment Request, License Termination Plan, Acceptance Review Request for Additional Information ML24274A0822024-09-25025 September 2024 Independent Spent Fuel Storage Installation Security Plan, Training Qualification Plan, Safeguards Contingency Plan, Revisions 1 and 2 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000219/20240022024-09-0505 September 2024 – NRC Inspection Report 05000219/2024002 and 07200015/2024001 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24214A0372024-08-0101 August 2024 License Amendment Request to Revise Renewed Facility Operating License to Add License Condition 2.C.(18) to Include License Termination Plan Requirements ML24179A1842024-07-23023 July 2024 June 20, 2024, Clarification Call on Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000219/20240012024-05-14014 May 2024 Decommissioning Intl, LLC Oyster Creek Nuclear Generating Station - NRC Inspection Report No. 05000219/2024001 ML24120A0412024-04-29029 April 2024 Annual Radioactive Environmental Operating Report for 2023 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24120A0402024-04-29029 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24094A2142024-04-19019 April 2024 Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML24089A2492024-03-29029 March 2024 Reply to Notice of Violation EA-2024-024 ML24085A7902024-03-28028 March 2024 – Preapplication Readiness Assessment of the License Termination Plan ML24081A2882024-03-21021 March 2024 Request Preliminary Review and Feedback on Chapter 6 of the Draft License Termination Plan ML24046A1242024-02-29029 February 2024 – NRC Inspection Report 05000219/2023003 ML24033A3272024-02-0202 February 2024 Request Preliminary Review and Feedback on Chapter 5 of the Draft License Termination Plan ML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 – NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report – January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 – NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 – NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 – NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages 2024-09-05
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000219/LER-2022-001, Compensatory Measures Not Implemented Per Sites Physical Security Plan Due to Multiplexer (Mux) Power Supply Failure2022-01-21021 January 2022 Compensatory Measures Not Implemented Per Sites Physical Security Plan Due to Multiplexer (Mux) Power Supply Failure 05000219/LER-2017-0052018-01-0303 January 2018 1 OF 3, LER 17-005-00 for Oyster Creek Nuclear Generating Station Regarding Failure of the Emergency Diesel Generator #2 During Surveillance Testing Due to a Broken Electrical Connector 05000219/LER-2017-0032017-08-31031 August 2017 Automatic Scram while Suberitical due to Low Reactor Level, LER 17-003-00 for Oyster Creek Regarding Automatic Scram while Subcritical due to Low Reactor Level 05000219/LER-2017-0022017-08-31031 August 2017 Manual Reactor Scram due to Degrading Main Condenser Vacuum, LER 17-002-00 for Oyster Creek Regarding Manual Scram due to Degraded Main Condenser Vacuum 05000219/LER-2016-0022017-06-23023 June 2017 Control Rod Drive Cooling Water System Isolation Scram Time Testing Was Not Performed, LER 16-002-01 for Oyster Creek Regarding Control Rod Drive Cooling Water System Isolation Scram Time Testing Was Not Performed 05000219/LER-2017-0012017-05-0303 May 2017 Automatic SCRAM due to APRM High Flux during Turbine Valve Testing, LER 17-001-01 for Oyster Creek, Regarding Transfer of Automatic SCRAM due to APRM High Flux during Turbine Valve Testing ML17129A6032017-05-0303 May 2017 LER 16-S01-01 for Oyster Creek, Regarding Special Nuclear Material Discovered Outside of Material Access Area 05000219/LER-2016-0012017-01-24024 January 2017 1 OF 4, LER 16-001-01 for Oyster Creek Nuclear Generating Station Regarding Failure of the #1 Emergency Diesel Generator During Surveillance Testing due to a Cooling Water System Leak RA-16-107, LER 16-S01-00 for Oyster Creek Nuclear Generating Station Regarding Special Nuclear Material Discovered Outside of Material Access Area2016-12-0505 December 2016 LER 16-S01-00 for Oyster Creek Nuclear Generating Station Regarding Special Nuclear Material Discovered Outside of Material Access Area 05000219/LER-2016-0052016-11-17017 November 2016 Technical Specification Prohibited Condition Caused by One Electromatic Relief Valve Inoperable for Greater than Allowed Outage Time, LER 16-005-00 for Oyster Creek Nuclear Generating Station Regarding Technical Specification Prohibited Condition Caused by One Electromatic Relief Valve Inoperable for Greater than Allowed Outage Time 05000219/LER-2016-0032016-06-29029 June 2016 Manual SCRAM Inserted due to Leakage from the D' Reactor Recirculation Pump Seal, LER 16-003-00 for Oyster Creek, Unit 1, Regarding Manual SCRAM Inserted due to Leakage from the 'D' Reactor Recirculation Pump Seal RA-16-001, Special Report for Inoperability of the Turbine Building High Range Radioactive Noble Gas Monitor2016-01-15015 January 2016 Special Report for Inoperability of the Turbine Building High Range Radioactive Noble Gas Monitor ML1015505702009-08-26026 August 2009 Event Notification for Oyster Creek on Offsite Notification Due to a Water Leak Containing Tritium ML0932006252009-07-24024 July 2009 NRC Operations Center Event Report - Oyster Creek ML1015505672009-04-15015 April 2009 Event Notification for Oyster Creek on Offsite Notification Due to Potential Release of Tritium ML0506107132005-02-16016 February 2005 LER 04-03-001 Oyster Creek, Unit 1, Regarding Actuation of Reactor Protection System Due to Spurious Hi-Hi Trip Signals on Intermediate Range Monitors Caused by Electromagnetic Interference 2022-01-21
[Table view] |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Oyster Creek Nuclear Generating Station
3. LER NUMBER
2017 - 00 005
Plant Conditions Prior To Event
Event Date:
October 09, 2017 Event Time: 03:12 hours ET Unit 1 Mode: Run Power Level: 100%
Description of Event
On 10/09/17, during the bi-weekly EDG #2 Load Test (station procedure 636.4.013), a Generator Lockout (86G) signal was received which tripped the EDG output breaker. The diesel had run for 4 minutes loaded in the procedurally prescribed band of 2600-2800 KW prior to receiving the 86G lockout signal. The EDG #2 trip is documented under Issue Report (IR) 04060815. This failure resulted in EDG #2 being declared inoperable, and entry into an unplanned 7-day LCO (TS Section 3.7.D) at 0312.
Troubleshooting identified a broken electrical ring lug connector on one current transformer (CT5) that provides an input to a differential current relay (87G). When the ring lug connector became detached from the terminal point, the relay sensed a current imbalance and the protective relay logic actuated. The differential current relay (87G) provided an input to the Generator Lockout circuit, causing the lockout relay (86G) to trip the EDG#2 output breaker. Repairs were completed on 10/10/17 at 0557. EDG #2 was satisfactorily tested and declared operable at 0805, and the 7-day LCO was exited.
Cause of Event
The investigation determined the electrical ring lug connector failure was due to fatigue cracking that was initiated by stresses caused by bending and twisting of the electrical lug beyond limits specified in industry guidelines.
Analysis of the Event
The ring lug that failed was sent to a metallurgical lab for failure analysis. The metallurgical analysis determined the ring lug had failed due to fatigue cracking. The investigation performed for the EDG#2 trip concluded the fatigue cracking was initiated by historical stresses caused by bending and twisting of the electrical lug beyond limits specified in industry guidelines. Based on a review of recent maintenance records for EDG#2 and a review of plant procedures and work practices, the investigation concluded the ring lug was most likely distressed during initial installation in the 1990's.
Assessment of Safety Consequences
Two EDG units serve as the Standby Power Supply for Oyster Creek Nuclear Generating Station (OCNGS) by providing an emergency source of power to the 4.16 kV buses 1C and 1D in the event of a loss of normal power.
The EDG units are designed to start and load automatically, if required. Non-essential loads are automatically shed by under-voltage sensing devices on loss of offsite power to ensure that the EDG units are not overloaded. The capacity of the EDG units is sufficient to sequentially energize for starting all safety-related pumps and auxiliaries required for a safe shutdown of the reactor in the event of a Design Basis Accident. The EDG units are independent of each other, except for a common bulk fuel storage supply, and are provided with auxiliary systems to ensure reliable starting and continuous operation with no Operator attention. Power to start the EDG units is self-contained and is not dependent on the availability of any other source of normal plant power at the moment of initiation.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Oyster Creek Nuclear Generating Station
3. LER NUMBER
2017 - 00 005 The Generator Lockout relay (86G) is an auxiliary relay that is operated upon the occurrence of abnormal conditions to maintain associated equipment out of service until it is reset. The lockout (86G) relay is sealed-in when the Differential Current Relay (87G) is initiated. The failure of the wire lug would not have prevented EDG #2 from being able to start. However, in the as found condition EDG#2 was unable to start and load to supply power to the safety buses for the required mission time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Because EDG #1 was operable and available to supply power to its associated loads in the event of a loss of offsite power, there was no loss of safety function.
Corrective Actions
1. The broken ring lug connector forthe current transformer (CT5) was replaced. EDG#2 was tested and restored to operable status on 10/10/17 at 0805 hours0.00932 days <br />0.224 hours <br />0.00133 weeks <br />3.063025e-4 months <br />.
2. All ring lug connectors were inspected in the current transformer and potential transformer cabinet for EDG#2.
Four other bent and/or twisted ring lug connectors were identified and replaced on 10/10/17.
3. Extent of condition inspections were performed on all ring lug connectors in the current transformer and potential transformer cabinet for EDG#1.
4. Two bent and/or twisted ring lug connectors were replaced on EDG#1 on 12/28/17.
5. Revise electrical ring lug installation and EDG inspection procedures to include inspection for bent and/or twisted lugs.
Previous Occurrences
There have been no similar, previous events resulting from a failure of a wire lug on an EDG at Oyster Creek.
Component Data Component IEEE 805 System ID IEEE 803A Component Emergency Diesel Generator EK DG