IR 05000445/1988003

From kanterella
Jump to navigation Jump to search
Insp Repts 50-445/88-03 & 50-446/88-02 on 880106-0202.No Violations or Deviations Noted.Major Areas Inspected: Applicant Actions on Previous Insp Findings & Followup on Violations/Deviations
ML20149L617
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/16/1988
From: Livermore H, Phillips H
NRC OFFICE OF SPECIAL PROJECTS
To:
Shared Package
ML20149L601 List:
References
50-445-88-03, 50-445-88-3, 50-446-88-02, 50-446-88-2, NUDOCS 8802240323
Download: ML20149L617 (9)


Text

- _

, . ~ . -

.

a i

,

,

U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF SPECIAL PROJECTS P

NRC Inspection Report: 50-445/88-03 Permits: CPPR-126 .

'

50-446/88-02 CPPR-127

'

,

Dockets: 50-445 Category: A2 ,

50-446 ,

'

., Construction Permit i Expiration Dates:

!

Unit 1: August 1, 1988 i Unit 2: Extension request !

submitted

, Applicant: TU Electric [

Skyway Tower ,

400 North Olive Street i Lock Box 01  !

Dallas, Texas 75201 i

Facility Name: Comanche Peak Steam Electric Station (CPSES) I Units 1 and 2  ;

i Inspection At: Comanche Peak Site, Glen Rose, Texas l i

,

Inspection Conducted: January 6 through February 2, 1988 ,

l I

n j Inspector: / # E ' /4 * J'8

.

H. S. Phillips, Senior Resident Reactor Date l Inspector, Construction

1

Reviewed by: le F Oba Gr 2//4/78 H. H. Livermore, Lead Senior Inspector Dat'e i

1 8802240323 880216 PDR ADOCK 05000445

-

0 DCD

.

.

Inspection Summary Inspection Conducted: January 6 through February 2, 1988 (Report 50-445/88-03: 50-446/88-02)

Areas Inspected: Unannounced resident safety inspection including (1) applicant actions on previous inspection findings; (2) follow-up on violations / deviations; (3) applicant action on 50.55(e) deficiencies; (4) general plant inspections; and (5) quality programs and administrative controls relative to civil, electrical, and mechanical hardware deficiencies.

I

'

Results: Within the areas inspected, no violations or deviations were identifie Paragraph 5 below discusses past NRC inspections !

,

'

which documented perceived weaknesses in TU Electric's t f

nonconformance reporting system; however, several additional inspections have subsequently led the NRC inspectors to conclude that the nonconformance program meets the NRC requirements.

I

I i r t

I

-

i i

!

I

,

_ - - - - -

. . . . _ . . - ..

.. ,

.

J DETAILS  ! Persons Contacted

  • C. Aldridge, Engineering Assurance (EA), Stone & Webster Engineering Corporation (SWEC)
  • P. Baker, EA Regulatory Compliance Manager, TU Electric
  • L. Barker, Manager, EA, TU Electric
  • P. Barry, Manager, ESG, SWEC ,
  • N. Bize, EA Regulatory Compliance Supervisor, TU Electric
  • R. Blevins, Manager, Technical Support, TU Electric
  • C. Finneran, CPE-FSE, TU Electric
  • M. Fitzgerald, HVAC Program Manager, Ebasco
  • P. E. Halstead, Manager, Quality Control (QC), TU Electric
  • L. Heatherly, EA Regulatory Compliance Engineer, ,

TU Electric i * R. Hooten, CPE-Civil Engineering Unit Manager, TU Electric '

  • J. Kelley, Manager, Plant Operations, TU Electric
  • W. Lowe, Director of Engineering, TU Electric
  • W. Madden, Mechanical Engineering Manager, TU Electric

. * M. McAfee, Manager, Quality Assurance (QA), TU Electric

  • E. Noss, QA Issue Interface Coordinator, TU Electric
* Odar, Project Engineering Manager, Ebasco 1 * D. Palmer, Plant Evaluation, Nuclear Operations, TU Electric
  • L. Ramsey, Project Manager Civil / Structural, TU Electric
  • M. Reynercon, Director of Construction, TU Electric '
  • J. Riggs, Plant Evaluation Manager, Operations, TU Electric
  • B. Scott, Vice President, Nuclear Operations, TU Electric
  • E. Scott, Manager, Startup, TU Electric

'

  • C. Smith, Plant Operations Staff, TU Electric
  • R. Steciman, CPRT, TU Electric
  • B. Stevens, Manager, Electrical Engineering, TU Electric
  • F. Streeter, Director, QA, TU Electric i
  • L. Terry, Unit 1 Project Manager, TU Electric
  • D. Walker, Manager of Nuclear Licensing, TU Electric  !

'

The NRC inspector also interviewed other applicant employees during this inspection perio l * Denotes personnel present at the February 2, 1988, exit interview.

1 Applicant Action on Previous Inspection Findings (92701)  !

! (Closed) Unresolved Item (445/8715-U-02): Crack in the concrete ceiling in Room 83 of Unit 1 not documented on a <

l nonconformance report (NCR). The NRC inspector observed i this crack on August 20, 1987, and again en August 31, 1 i

1987. On September 1, 1987, TU Electric stated that the ;

project would not issue an NCR until the crack was .
chipped out to sound concrete and it was determined that !

i i

i i

.,. . - - ,

.

m e e .y -ng-,

,

.

it exceeded the size allowed in Specification SS-9. The NRC stated that defects should be identified as nonconforming and then disposition the defect instead of the reverse; i.e., dispositioning and then documenting the defect. The utility's position was that chipping was necessary to determine the extent of the defect and whether or not the defect met the criteria to be considered "nonconforming." If it met the criteria, an NCR was prepare On September 17, 1987, NRC management and inspectors met with TU Electric's management and technical staff to discuss this issue. The NRC was informed that Specification SS-9 allowed the practice which had been questioned by NRC management and the NRC inspecto Subsequently, the NRC inspector determined that Specification SS-9 was revised and now requires an NCR to be issued prior to exploring and dispositioning the defec This item is closed based on the revision of the specificatio b. (closed) Unresolved Item (446/8716-U-02): Attachments welded to a plate in the fabrication shop in 1985 had to be removed because the heat numbers did not match material requisition Form 34165 On September 19, 1987, the NRC inspector observed that attachments were being removed and learned that two of the attachments were not :

traceable to heat numbers on the requisition for Further, it was learned that after removal, the craftsmen i found that 2 of 7 attachments had been incorrectly identified relative to the applicable heat number on the requisition form. The numbers were on the base of the two attachments and after they were welded to the plate (with the base against the plate) the numbers were not visible. Apparently, someone later noticed that these I two attachments had no heat numbers on top of the i attachments, looked at the top of the other five I attachments that had visible heat numbers and assumed I that the two unmarked attachments were from the same '

heat. This assumption was incorrect as they were fabricated from two other different heats. The NRC asked why no NCR was written and was informed that Traveler CE84-145-0903 was not completed and all work had not been accepted by the quality control inspecto In subsequent discussions, TU Electric informed the NRC inspector that Procedure NEO 3.05, R2 allows rework without issuing an NCR. See paragraph 5 below for the basis for closing this issu c. (Closed) Open Item (445/8720-0-04): A stud broken off in i the body of containment spray motor in Room 61 of the !

safeguards building. On September 9, 1987, the NRC l I

1 I

-

.

.

inspector identified the above condition and subsequently found that no NCR was issued on this condition. During this inspection period, the inspector verified that the broken studs had been replaced. This item is closed based on verification of corrective action and the discussion in paragraph d. (Closed) Unresolved Item (445/8720-U-03): Stainless steel bristles from a cleaning brush lost in journals of Transamerica DeLaval diesel generator engine. On September 9, 1987, the NRC inspector observed work activity relative to performing baseline inspection on connecting rod (Con-rod) bolts by measuring the stretch using an ultrasonic test unit. The inspector learned that on August 29, 1987, TU Electric maintenance l mechanics used wire brushes to clean con-rod threaded l bolt holes and this was questioned by TU Electric's QC l

inspector, on September 2, 1987, the QC inspector placed a boroscope in the four upper holes of con-rod journal 46 and found wire bristles lodged in the serrated mating material. Because the mechanic could not retrieve the bristles with mechanical fingers, the work order was revised to separate the rods, clean, and inspect the area to assure removal of the wire bristles. The NRC inspector observed the disassembly and cleaning of con-rod #5. When this operation was questioned, the QC inspector explained that the problem with the brush would be eliminated in the future by keeping one upper bolt tight along with one lower bolt while cleaning and performing Eddy Current T' stin Also the wire brushes would no longer be use *

On September 29, 1987, the NRC inspector requested a copy of the nonconformance report and was informed that none was issued because the "potentially" nonconforming condition was documented in Revision 3 of the work order and the potentially nonconforming condition could be reworked to comply with existing engineering requirements

in accordance with approved procedures.

l The QC inspector also stated that when he originally i questioned the practice of using the brush and the loss

, of bristles, he was informed that the same technique had l been used at other nuclear plants and no bristles were i

'

l los Considering this statement, the NRC inspector l questioned whether this condition was considered relative to 50.55(e) construction deficiency reporting i

requirements. The answer was that no deficiency was <

identified because it coulc be reworked and was {

documented on the work orders. The NRC inspector '

reviewed the entire file on Work order C870002841 which '

also included In-process Monitoring Quality Sheets and I Inspection Report (IR) Continuation Sheets. The work ;

,

! l

'

l_-____

__ _-

.*

'

.

order and other documents do not specifically describe the loss of bristles but Revision 3 of the work order describes actions which would result in a cleaning step that would assure that the bristles were remove Similarly, the quality documents discuss cleanliness checks but do not indicate unsatisfactory conditions. As a result, the NRC inspector concluded that TU Electric managers, supervisors, or engineers would not necessarily be aware of specific conditions that were reworke Therefore, the condition would not be evaluated by these managers to determine the need for an NCR or evaluated for 50.55(e) reportability. The NRC inspector considers this to be a weakness in their nonconformance/ corrective action system; however, the policy, procedures, and practice apparently do not violate Criteria XV and XV The NRC inspector considers this item closed based on the TU Electric's NCR policy discussed in paragraph . Follow-up on Violations / Deviations (92702)

(Closed) Violation (446/8617-V-07): Failure to correct Unit 2 steam generator equipment identification numbers and documentation. The inspector found that four steam generaters identified on the drawings did not match the as-built conditions i.e., steam generator (TCX-RCPCSG-04) was actually in Loop 1 but was shown in the drawings as being in Loop TU Electric was aware of this and had written letters to Westinghouse requesting correction but had not issued NCR The NRC inspector reviewed 20 documents in the file which included the response to the violation, nonconformance reports (NCRs), and work travelers that describe subsequent corrective actions. TU Electric concluded that even though improperly identified, the steam generators are physically and technically correct as installed. Regardless, the component identifications on the name plates were corrected by ,

restamping the existing plates until new labels are installe '

The inspector observed the changes made to the plates. The applicable Westinghouse (W) quality releases, drawings and technical manuals were revised. The NRC inspector considers ,

this item closed based on the documentation review and !

verification that name plates were correcte I 4. Follow-up on 10 CFR Part 50.55(e) Applicant Identified Construction Deficiencies (92700)

The NRC inspector received and reviewed Construction Deficiency Reports CP-88-01 through CP-88-25 which were identified as potentially reportable construction deficiencies l in accordance with 10 CFR Part 50.55(e). Each report was j reviewed to assure that the deficiency was fully identified, i described, evaluated, and that the NRC was notified in l

l i

_ _ _ - -

,

7

.

accordance with TU Electric Procedure NEO-CS-1, Revision 1 and 10 CFR 50.55(e) requirement The following previously potentially reportable items were completed by TU Electric. The NRC inspector performed field verifications of hardware and corrective actions that were in ;

proces <

, (closed) SDAR CP-86-11, Construction Deficiency

-

(D1-0205): Component cooling water (CCW) impellers i contained linear indications. While cleaning the subject pumps, TU Electric's maintenance personnel visually .

inspected and observed indications that were subsequently l confirmed by magnetic particle testin ;

The NRC inspector reviewed TU Electric's SDAR CP-86-11 file which included all of the corrective action

documents and supporting documentation showing the ,

repairs made to Unit 1 CCW impellers. Selected documents were reviewed for Unit 2 CCW and spare impellers which had similar defects. This included QC verification of

'

steps to correct these parts. The NRC inspectar observed disassembly for repairing these components several times l 1 during past routine inspections. Corrective action has

been completed.

, (Closed) SDAR CP-86-62 Construction Deficiency (Dl-0254):

Misinterpretations of the polar crane load case The NRC inspector reviewed SDAR CP-86-62 file for supporting documentation which showed: (1) the specified corrective ;

action will prevent crane uplift during a seismic event,

(2) the rail is adequate for horizontal loads, and (3) the rail is stable during a safe shutdown earthquake (SSE). Stone & Webster Calculation 16345-EM(B)-001-CZC '

I showed an absence of uplift forces on the crane support 1

structure due to seismic conditions but it was found that I

i an overstress (relative to FSAR commitments) of hold down l clamps resulted. Design Change Authorization (DCA)-31296 i modified the clips to assure that they remain within FSAR l commitments; i.e., they conform to allowable stress for I

, specified loads. The NRC inspector reviewed all DCAs, work orders and work travelers for approved modifications of Unit 1 polar crane hold-down clips and selected documentation of similar work in Unit 2. In addition, I TU Electric's QC documents revealed that inspection of I these activities had been accomplished. The NRC inspector has repeatedly observed these activities in ,

both units within the last six month l Corrective action is complet l 5. Quality Programs and Administrative Controls Affecting Quality J47053, 51053, 51063)

i

- - . . . . .

.

'

.

In NRC Inspection Reports 50-445/87-03, 50-446/87-03; 50-445/87-07, 50-446/87-06; 50-445/87-15, 50-446/87-12; and 50-445/87-20, 50-446/87-16; several instances were documented where deficiencies were not placed in the NCR system to assure identification, evaluation and disposition (corrective action). In NRC Inspection Report 50-445/8703; 50-446/8703, an inspector clearly stated the issue by saying that the operations organization used work orders in lieu of NCRs but added that work orders were reviewed for nonconforming conditionc. The NRC inspector 1.oted that an NCR should be immediately written to document a deficienc In mid 1987, TU Electric and NRC management (including their staff and NRC inspectors) r.e t to discuss this issu TU Electric requested the meeting and explained how work orders and other documents could document deficiencies instead of using NCRs. NRC personnel agreed that potential nonconformances could be handled in this manner and in process repairs-may be made negating the need for an NC During a subsequent inspection, a second inspector found other hardware deficiencies as described in unresolved items 445/8715-U-02 and 445/8720-U-03, and open item 445/8720-0-0 These deficiencies were followed up to determine if the policy ,

and practice accomplished what is required by Appendix B of 10 CFR Part 50. While pursuing the resolution of these issues, the NRC inspector found that TU Electric's corporate Procedure UEO 3.05 states, in part, that NCRs shall be issued if: "(a) a potentially nonconforming condition is identified and an approved method is not provided in the work, inspection or test procedures or program to document the condition; or (b) a potentially nonconforming condition has been identified and documented in accordance with approved procedures or programs such as: Inspection Reports, Work Orders, or Test Deficiency Reports and the identified condition cannot be l corrected (reworked or scrapped) to comply with existing engineering requirements in accordance with approved ;

procedures." '

During discussions with TU Electric personnel, the NRC l

inspector questioned whether this literally complied with Criterion XVI of Appendix B to 10 CFR Part 50 which states that all conditions adverse to quality such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances shall be promptly identified and corrected. TU Electric stated that in-process repair l without issuing an NCR is an accepted industry practice. The !

NRC inspectors acknowledged 4, hat certain "in-process" I deficiencies commonly encountered (such as welding defects that are repaired by welders during welding) do not require nonconforming or deficiency report However, this is because these deficiencies have been previously encountered and dispositioned so frequently that standard procedures have

._

_

i

-

s . i

.

been developed to handle these well known in-process defect The NRC inspector stated that this appears to differ from the-issue concerning a loss of bristles in the diesel engine which had never-been encountered at the Comanche Peak site and no standard disposition had been mad Near the end of this inspection period, onsite NRC management and inspectors discussed the TU Electric policy of expanding the industry practice concerning welding; i.e., by extending

"in-process" correction to any.other defect or deficiency while the work activity is "in-process" and no NCR would be issued. The issue of not writing an NCR if the material or component is scrapped was also discussed. Although these practices may not be the :nost desirable, they were found to be consistent with NRC regulations as TU Electric trends the deficiencies work orders, inspection reports and other documents. Based on the above, the NRC inspector considers these issues resolve . General Plant Inspections (47053, 50053, 50073, 50090, 50100, 51053, 52053, 53053, 55050, 55100, 64053)

At various times during the inspection period, the NRC inspector conducted general inspections of the Unit 1 and 2 reactor containment (RCB), safeguards (SGB), auxiliary (AB),

electrical control (ECB), and diesel generator (DGB)

buildings. All accessible rooms in these buildings were inspected to observe current work activities with respect to major safety-related equipment, electrical cable / trays, mechanical components, piping, welding, coatings, Hilti bolts, and removal of debris from seismic gap between buildings. The housekeeping, storage, and handling conditions inside these buildings and various outside storage areas were also inspecte No violations or deviations were identifie . Exit Interview (30703)

An exit interview was conducted on February 2, 1988, with the applicant's representatives identified in paragraph 1 of this ;

repor No written material was provided to the licensee by J the resident inspectors during this reporting period. The :

licensee did not identify as proprietary any of the materials l provided to or reviewed by the resident inspectors during the i inspection. During this exit interview, the scope and findings of the inspection were summarize l

_ _

.