Letter Sequence Request |
---|
|
Results
Other: ML20056G180, ML20094P419, ML20134G924, ML20135D395, ML20151W366, ML20196B705, ML20198Q703, ML20202H368, ML20205R563, ML20206F984, ML20211C466, ML20217E441, ML20217H367, TXX-9402, Responds to 931222 RAI by Informing NRC Last C/A Completing GL 92-08 Is Field Work Installing Thermo-Lag Upgrades, TXX-9500, Provides Addl Info Describing Activities That Util Has Performed to Verify Quality of Procured & Installed Thermo- Lag & to Ensure That Thermo-Lag at Plant Properly Qualified, TXX-9906, Forwards Final Fire Endurance Test Rept,Per Closure of Remaining Open Issues Re Thermo-Lag Fire Barriers as Described by Items 1 & 4 in NRC 960522 SER
|
MONTHYEARML20056G1801993-08-17017 August 1993 Documents 930722 Telcon W/Util Re Thermo-Lag Mfg Specs.Info Did Not Change NRC Previous Conclusions Re Thermo-Lag Fire Barriers or Affect NRC Ongoing Review Activities Project stage: Other ML20059C2831993-12-22022 December 1993 Discusses RAI Re GL 92-08, Thermo-Lag 330-1 Fire Barriers, Per 10CFR50.54(f) for Plant.Notifies That Requested Schedule Must Be Submitted within 45 Days from Receipt of Ltr Project stage: RAI TXX-9402, Responds to 931222 RAI by Informing NRC Last C/A Completing GL 92-08 Is Field Work Installing Thermo-Lag Upgrades1994-01-28028 January 1994 Responds to 931222 RAI by Informing NRC Last C/A Completing GL 92-08 Is Field Work Installing Thermo-Lag Upgrades Project stage: Other TXX-9415, Forwards Response to Request for Addl Info Re Thermo-Lag Certification.Rev 2 to ER-ME-082, Engineering Rept Evaluation of Unit 1 & Unit 2 Thermo-Lag Configurations1994-06-16016 June 1994 Forwards Response to Request for Addl Info Re Thermo-Lag Certification.Rev 2 to ER-ME-082, Engineering Rept Evaluation of Unit 1 & Unit 2 Thermo-Lag Configurations Project stage: Request ML20072A8331994-08-0808 August 1994 Submits Response to Request for Addl Info Re thermo-lag Cable Functionally Issues.Rev 2 to Calculation Change Notice 071 Encl Project stage: Request TXX-9426, Forwards Response to Request for Addl Info Re Thermo-Lag Cable Functionality Issues1994-11-0909 November 1994 Forwards Response to Request for Addl Info Re Thermo-Lag Cable Functionality Issues Project stage: Request ML20077A7251994-11-18018 November 1994 Forwards Response to Request for Addl Info Re Ampacity Tests Project stage: Request TXX-9500, Provides Addl Info Describing Activities That Util Has Performed to Verify Quality of Procured & Installed Thermo- Lag & to Ensure That Thermo-Lag at Plant Properly Qualified1995-02-24024 February 1995 Provides Addl Info Describing Activities That Util Has Performed to Verify Quality of Procured & Installed Thermo- Lag & to Ensure That Thermo-Lag at Plant Properly Qualified Project stage: Other ML20086D9881995-07-0707 July 1995 Informs That Request for Extension to Respond to NRC 950517 RAI on Util 950224 Response to GL 92-08 Re Thermo-Lag Fire Barrier Matl Received & Installed at Facility Discussed W/ Tj Polich & Granted on 950707 Project stage: Request ML20087E2701995-08-0808 August 1995 Forwards Response to Request for Addl Info Re Followup to GL 92-08 for Thermo-Lag Fire Barrier Matl Received & Installed at Facility Project stage: Request ML20094P4191995-11-22022 November 1995 Forwards Nucon 06TU935/01, Pyrolysis Gas Chromatography Analysis of 10 Thermo-Lag Fire Barrier Samples Project stage: Other ML20134P8661996-11-22022 November 1996 Informs That 961024 Response to Open Items Re thermo-lag Cable Functionality Issues Does Not Address Staff Original Concerns.Advises of 961205 Meeting to Reach Final Technical Resolution on Cable Functionality Issues at Plant,Unit 1 Project stage: Meeting ML20134G9241997-02-0404 February 1997 Informs That Util Intends to Submit Addl Info to NRC on or About 970228 Re Response to SE Open Items on Unit 1 for Thermo-Lag Cable Functionality Issues Project stage: Other IR 05000445/19970021997-02-28028 February 1997 Insp Repts 50-445/97-02 & 50-446/97-02 on 970210-14.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Radioactive Waste Effluent Mgt Program,Organization & Mgt Controls,Radioactive Effluent Monitoring for Plant Support Project stage: Request ML20135D3951997-02-28028 February 1997 Provides Response to SE Open Items on CPSES Unit 1 Re Thermo-Lag Cable Functionality Issues Project stage: Other ML20217E4411997-10-0101 October 1997 Discusses Licensee 970228 Revised Response to SE Open Items on Plant,Unit 1 Re thermo-lag Cable Functionality Issues. Requests That Revs to CPSES Engineering Rept ER-ME-067 Be Provided within 30 Days of Receipt of Ltr Project stage: Other ML20198Q7031997-11-0606 November 1997 Submits Response to SE Open Items Re Thermo-Lag Cable Functionality Issue,Per 970916 Telcon W/Nrc & as Stated in Ref 1 of NRC .Rev 5 to ER-ME-067 & Bisco Test Rept 748-105 Encl.Bisco Test Rept Withheld Project stage: Other ML20202H3681998-02-13013 February 1998 Provides follow-up to Licensee Re Thermo-Lag Raceway Testing.Util Has Concluded That It Is Important for Util Not Change Testing Criteria mid-stream. Commitment Made by Util,Listed Project stage: Other ML20217H3671998-04-0101 April 1998 Requests That TU Electric Respond to Staff Comments Re Thermo-Lag Raceway Testing Proposal Concerning Thermo-Lag Fire Barriers at CP Steam Electric Station,Unit 1 to Resolve Issues Prior to Start of Any Fire Endurance Tests Project stage: Other ML20151W3661998-09-0808 September 1998 Informs That Addl Thermo-Lag Testing Currently Scheduled for Last Wk in Oct 1998 at Omega Point Labs,Inc.Detailed Description of Route to Lab Can Be Downloaded or Printed from Internet Project stage: Other ML20196B7051998-11-25025 November 1998 Forwards Preliminary Fire Endurance Test Results,As Part of Action Plan for Closure of Remaining Open Items Associated with CPSES Unit 1 Thermo-Lag Fire Barriers & 980520 Confirmatory Order Project stage: Other TXX-9906, Forwards Final Fire Endurance Test Rept,Per Closure of Remaining Open Issues Re Thermo-Lag Fire Barriers as Described by Items 1 & 4 in NRC 960522 SER1999-03-0202 March 1999 Forwards Final Fire Endurance Test Rept,Per Closure of Remaining Open Issues Re Thermo-Lag Fire Barriers as Described by Items 1 & 4 in NRC 960522 SER Project stage: Other ML20205R5631999-04-15015 April 1999 Forwards Rev 6 to CPSES Engineering Rept ER-ME-067, Evaluation of Thermo-Lag Fire Barrier Sys. Rept Was Revised to Incorporate Technical Justification for Closure of Open Items 1 & 4 Described in NRC Project stage: Other IR 05000445/19990061999-04-30030 April 1999 Insp Repts 50-445/99-06 & 50-446/99-06 on 990329-0402.No Violations Noted.Major Areas Inspected:Planning & Preparation,External Exposure Controls & Quality Assurance of Radiation Protection Activities Project stage: Request ML20206F9841999-04-30030 April 1999 Requests That NRC Return Bisco Tests & Remove Them from Docket Re Thermo-Lag Cable Functionality Issues for CPSES, Unit 1 Project stage: Other ML20206Q0031999-05-14014 May 1999 Forwards Safety Evaluation Accepting Licensee Response to GL 92-08, Thermo-Lag 330-1 Fire Barriers, Dtd 921217,for Comanche Peak Steam Electric Station,Unit 1 Project stage: Approval ML20211C4661999-08-18018 August 1999 Discusses Proprietary Info Re Thermo-Lag.NRC Treated Bisco Test Rept 748-105 as Proprietary & Withheld It from Public Disclosure,Iaw 10CFR2.790 Project stage: Other 1997-10-01
[Table View] |
Insp Repts 50-445/99-06 & 50-446/99-06 on 990329-0402.No Violations Noted.Major Areas Inspected:Planning & Preparation,External Exposure Controls & Quality Assurance of Radiation Protection ActivitiesML20206F578 |
Person / Time |
---|
Site: |
Comanche Peak |
---|
Issue date: |
04/30/1999 |
---|
From: |
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
---|
To: |
|
---|
Shared Package |
---|
ML20206F575 |
List: |
---|
References |
---|
50-445-99-06, 50-445-99-6, 50-446-99-06, 50-446-99-6, NUDOCS 9905060177 |
Download: ML20206F578 (15) |
|
|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000445/19990151999-10-20020 October 1999 Insp Repts 50-445/99-15 & 50-446/99-15 on 990822-1002. Non-cited Violations.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000445/19990141999-09-14014 September 1999 Insp Repts 50-445/99-14 & 50-446/99-14 on 990707-0821.Four Violations Occurred & Being Treated as Ncvs.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000445/19990131999-08-18018 August 1999 Insp Repts 50-445/99-13 & 50-446/99-13 on 990720-23.No Violations Noted.Major Areas Inspected:Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures IR 05000445/19990101999-08-12012 August 1999 Insp Repts 50-445/99-10 & 50-446/99-10 on 990510-0628. Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Engineering & Plant Support IR 05000445/19990121999-07-29029 July 1999 Insp Repts 50-445/99-12 & 50-446/99-12 on 990530-0710.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19990111999-06-22022 June 1999 Insp Repts 50-445/99-11 & 50-446/99-11 on 990418-0529.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000445/19990081999-06-0909 June 1999 Insp Repts 50-445/99-08 & 50-446/99-08 on 990503-11.Noncited Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19990091999-05-12012 May 1999 Insp Repts 50-445/99-09 & 50-446/99-09 on 990419-23.No Violations Noted.Major Areas Inspected:Reviewed Implementation of Liquid & Gaseous Radioactive Waste Effluent Mgt Program IR 05000445/19990071999-05-11011 May 1999 Insp Repts 50-445/99-07 & 50-446/99-07 on 990307-0417.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000445/19990061999-04-30030 April 1999 Insp Repts 50-445/99-06 & 50-446/99-06 on 990329-0402.No Violations Noted.Major Areas Inspected:Planning & Preparation,External Exposure Controls & Quality Assurance of Radiation Protection Activities IR 05000445/19990031999-04-0707 April 1999 Insp Repts 50-445/99-03 & 50-446/99-03 on 990124-0306.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19990051999-03-19019 March 1999 Insp Repts 50-445/99-05 & 50-446/99-05 on 990222-26.One Violation Noted.Major Areas Inspected:Implementation of Solid Radwaste Mgt & Radioactive Matls Transportation Programs IR 05000445/19990011999-03-0909 March 1999 Insp Repts 50-445/99-01 & 50-446/99-01 on 990208-12.No Violations Noted.Major Areas Inspected:Licensed Operator Requalification Program IR 05000445/19990021999-01-10010 January 1999 Insp Repts 50-445/99-02 & 50-446/99-02 on 990119-22.No Violations Noted.Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000445/19980081998-12-30030 December 1998 Insp Repts 50-445/98-08 & 50-446/98-08 on 981025-1205.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Licensee Emergency Response Organization IR 05000445/19980071998-11-19019 November 1998 Insp Repts 50-445/98-07 & 50-446/98-07 on 980913-1024.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000445/19980151998-11-19019 November 1998 Insp Repts 50-445/98-15 & 50-446/98-15 on 981102-06.No Violations Noted.Major Areas Inspected:Radiation Program Activities,Including External & Internal Exposure Controls & Controls of Radioactive Matl & Contamination IR 05000445/19980161998-10-29029 October 1998 Insp Repts 50-445/98-16 & 50-446/98-16 on 981019-23.No Violations Noted.Major Areas Inspected:Testing & Maint, Protected Area Barrier & Detection Aids,Vital Area Barriers & Detection Aids & Security Sys Power Supply IR 05000445/19980141998-10-21021 October 1998 Insp Repts 50-445/98-14 & 50-446/98-14 Has Been Canceled.No Insp Rept Will Be Issued IR 05000445/19980061998-09-30030 September 1998 Insp Repts 50-445/98-06 & 50-446/98-06 on 980802-0912.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000445/19980121998-09-16016 September 1998 Insp Repts 50-445/98-12 & 50-446/98-12 Cancelled IR 05000445/19980051998-08-20020 August 1998 Insp Repts 50-445/98-05 & 50-446/98-05 on 980621-0801.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000445/19980041998-07-16016 July 1998 Insp Repts 50-445/98-04 & 50-446/98-04 on 980510-0620.No Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000445/19983011998-07-10010 July 1998 Insp Repts 50-445/98-301 & 50-446/98-301 on 980619-26.No Violations Noted.Major Areas Inspected:Operations.All 9 License Applicants Passed Exam IR 05000445/19980031998-07-0202 July 1998 Insp Repts 50-445/98-03 & 50-446/98-03 on 980329-0509. Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000445/19980131998-06-26026 June 1998 Insp Repts 50-445/98-13 & 50-446/98-13 on 980615-19.No Violations Noted.Major Areas Inspected:Licensee Physical Security Program IR 05000445/19980021998-04-24024 April 1998 Insp Repts 50-445/98-02 & 50-446/98-02 on 980215-0328. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20216H3501998-04-16016 April 1998 Insp Repts 50-445/98-11 & 50-446/98-11 on 980323-27.No Violations Noted.Major Areas Inspected:Physical Security Program IR 05000445/19980011998-03-19019 March 1998 Insp Repts 50-445/98-01 & 50-446/98-02 on 980104-0214. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19970211998-02-11011 February 1998 Errata to Insp Repts 50-445/97-21 & 50-446/97-21,correcting Errors in Insp follow-up Sys Number Associated W/Items Described in Rept IR 05000445/19970231998-01-30030 January 1998 Insp Repts 50-445/97-23 & 50-446/97-23 on 971123-980103.No Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support ML20198S1891998-01-16016 January 1998 Insp Repts 50-445/97-20 & 50-446/97-20 on 971012-1122. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199H0241997-11-21021 November 1997 Insp Repts 50-445/97-18 & 50-446/97-18 on 970831-1011. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000445/19970221997-11-17017 November 1997 Insp Repts 50-445/97-22 & 50-446/97-22 on 971103-07.No Violations Noted.Major Areas Inspected:Maint ML20199E6481997-11-13013 November 1997 Insp Repts 50-445/97-21 & 50-446/97-21 on 971027-31.No Violations Noted.Major Areas Inspected:Licensee Physical Security Program Including Records & Repts,Test & Maint and Access control-vehicle IR 05000445/19970191997-10-10010 October 1997 Insp Repts 50-445/97-19 & 50-446/97-19 on 970922-25. Violations Noted.Major Areas Inspected:Rev 25 to Comanche Peak Steam Electric Emergency Plan ML20211A1051997-09-19019 September 1997 Insp Repts 50-445/97-17 & 50-446/97-17 on 970720-0830. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19970161997-08-13013 August 1997 Insp Repts 50-445/97-16 & 50-446/97-16 on 970722-25.No Violations Noted.Major Areas Inspected:Insp of Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures ML20151L9231997-08-0505 August 1997 Insp Repts 50-445/97-15 & 50-446/97-15 on 970608-0719. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20149L3361997-07-25025 July 1997 Corected Pages 13,17,19,22,28 & Page 2 of Supplemental Info for Insp Repts 50-445/97-12 & 50-446/97-12 Issued on 970611 IR 05000445/19970141997-06-30030 June 1997 Insp Repts 50-445/97-14 & 50-446/97-14 on 970427-0607. Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support ML20148K2851997-06-11011 June 1997 Insp Repts 50-445/97-12 & 50-446/97-12 on 970421-0502. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000445/19970061997-06-0606 June 1997 Insp Repts 50-445/97-06 & 50-446/97-06 on 970428-0502. Violations Noted.Major Areas Inspected:Operations & Plant Support & Assessment of Licensed Operator Requalification Program ML20148F8791997-06-0303 June 1997 Insp Repts 50-445/97-09 & 50-446/97-09 on 970317-21. Violations Noted.Major Areas Inspected:Maint & Engineering IR 05000445/19970131997-05-21021 May 1997 Insp Repts 50-445/97-13 & 50-446/97-13 on 970428-0502.No Violations Noted.Major Areas Inspected:Licensee Physical Security Program IR 05000445/19970081997-05-21021 May 1997 Insp Repts 50-445/97-08 & 50-446/97-08 on 970316-0426.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000445/19970011997-05-21021 May 1997 Insp Repts 50-445/97-01 & 50-446/97-01 on 970127-31,0428 & 0502.No Violations Noted.Major Areas Inspected:Licensee self-assessment Effort IR 05000445/19970101997-05-20020 May 1997 Insp Repts 50-445/97-10 & 50-446/97-10 on 970421-25.No Violations Noted.Major Areas Inspected:Plant Support ML20148B5891997-05-0808 May 1997 Insp Repts 50-445/97-11 & 50-446/97-11 on 970407-10.No Violations Noted.Major Areas Inspected:Plant Support,Solid Radwaste Mgt & Radioactive Matls Transportation Programs IR 05000445/19970071997-04-16016 April 1997 Insp Repts 50-445/97-07 & 50-446/97-07 on 970324-27.No Violations Noted.Major Areas Inspected:Plant Support 1999-09-14
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000445/19990151999-10-20020 October 1999 Insp Repts 50-445/99-15 & 50-446/99-15 on 990822-1002. Non-cited Violations.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000445/19990141999-09-14014 September 1999 Insp Repts 50-445/99-14 & 50-446/99-14 on 990707-0821.Four Violations Occurred & Being Treated as Ncvs.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000445/19990131999-08-18018 August 1999 Insp Repts 50-445/99-13 & 50-446/99-13 on 990720-23.No Violations Noted.Major Areas Inspected:Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures IR 05000445/19990101999-08-12012 August 1999 Insp Repts 50-445/99-10 & 50-446/99-10 on 990510-0628. Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Engineering & Plant Support IR 05000445/19990121999-07-29029 July 1999 Insp Repts 50-445/99-12 & 50-446/99-12 on 990530-0710.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19990111999-06-22022 June 1999 Insp Repts 50-445/99-11 & 50-446/99-11 on 990418-0529.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000445/19990081999-06-0909 June 1999 Insp Repts 50-445/99-08 & 50-446/99-08 on 990503-11.Noncited Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19990091999-05-12012 May 1999 Insp Repts 50-445/99-09 & 50-446/99-09 on 990419-23.No Violations Noted.Major Areas Inspected:Reviewed Implementation of Liquid & Gaseous Radioactive Waste Effluent Mgt Program IR 05000445/19990071999-05-11011 May 1999 Insp Repts 50-445/99-07 & 50-446/99-07 on 990307-0417.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000445/19990061999-04-30030 April 1999 Insp Repts 50-445/99-06 & 50-446/99-06 on 990329-0402.No Violations Noted.Major Areas Inspected:Planning & Preparation,External Exposure Controls & Quality Assurance of Radiation Protection Activities IR 05000445/19990031999-04-0707 April 1999 Insp Repts 50-445/99-03 & 50-446/99-03 on 990124-0306.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19990051999-03-19019 March 1999 Insp Repts 50-445/99-05 & 50-446/99-05 on 990222-26.One Violation Noted.Major Areas Inspected:Implementation of Solid Radwaste Mgt & Radioactive Matls Transportation Programs IR 05000445/19990011999-03-0909 March 1999 Insp Repts 50-445/99-01 & 50-446/99-01 on 990208-12.No Violations Noted.Major Areas Inspected:Licensed Operator Requalification Program IR 05000445/19990021999-01-10010 January 1999 Insp Repts 50-445/99-02 & 50-446/99-02 on 990119-22.No Violations Noted.Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000445/19980081998-12-30030 December 1998 Insp Repts 50-445/98-08 & 50-446/98-08 on 981025-1205.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Licensee Emergency Response Organization IR 05000445/19980071998-11-19019 November 1998 Insp Repts 50-445/98-07 & 50-446/98-07 on 980913-1024.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000445/19980151998-11-19019 November 1998 Insp Repts 50-445/98-15 & 50-446/98-15 on 981102-06.No Violations Noted.Major Areas Inspected:Radiation Program Activities,Including External & Internal Exposure Controls & Controls of Radioactive Matl & Contamination IR 05000445/19980161998-10-29029 October 1998 Insp Repts 50-445/98-16 & 50-446/98-16 on 981019-23.No Violations Noted.Major Areas Inspected:Testing & Maint, Protected Area Barrier & Detection Aids,Vital Area Barriers & Detection Aids & Security Sys Power Supply IR 05000445/19980141998-10-21021 October 1998 Insp Repts 50-445/98-14 & 50-446/98-14 Has Been Canceled.No Insp Rept Will Be Issued IR 05000445/19980061998-09-30030 September 1998 Insp Repts 50-445/98-06 & 50-446/98-06 on 980802-0912.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000445/19980121998-09-16016 September 1998 Insp Repts 50-445/98-12 & 50-446/98-12 Cancelled IR 05000445/19980051998-08-20020 August 1998 Insp Repts 50-445/98-05 & 50-446/98-05 on 980621-0801.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000445/19980041998-07-16016 July 1998 Insp Repts 50-445/98-04 & 50-446/98-04 on 980510-0620.No Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000445/19983011998-07-10010 July 1998 Insp Repts 50-445/98-301 & 50-446/98-301 on 980619-26.No Violations Noted.Major Areas Inspected:Operations.All 9 License Applicants Passed Exam IR 05000445/19980031998-07-0202 July 1998 Insp Repts 50-445/98-03 & 50-446/98-03 on 980329-0509. Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000445/19980131998-06-26026 June 1998 Insp Repts 50-445/98-13 & 50-446/98-13 on 980615-19.No Violations Noted.Major Areas Inspected:Licensee Physical Security Program IR 05000445/19980021998-04-24024 April 1998 Insp Repts 50-445/98-02 & 50-446/98-02 on 980215-0328. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20216H3501998-04-16016 April 1998 Insp Repts 50-445/98-11 & 50-446/98-11 on 980323-27.No Violations Noted.Major Areas Inspected:Physical Security Program IR 05000445/19980011998-03-19019 March 1998 Insp Repts 50-445/98-01 & 50-446/98-02 on 980104-0214. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19970211998-02-11011 February 1998 Errata to Insp Repts 50-445/97-21 & 50-446/97-21,correcting Errors in Insp follow-up Sys Number Associated W/Items Described in Rept IR 05000445/19970231998-01-30030 January 1998 Insp Repts 50-445/97-23 & 50-446/97-23 on 971123-980103.No Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support ML20198S1891998-01-16016 January 1998 Insp Repts 50-445/97-20 & 50-446/97-20 on 971012-1122. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199H0241997-11-21021 November 1997 Insp Repts 50-445/97-18 & 50-446/97-18 on 970831-1011. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000445/19970221997-11-17017 November 1997 Insp Repts 50-445/97-22 & 50-446/97-22 on 971103-07.No Violations Noted.Major Areas Inspected:Maint ML20199E6481997-11-13013 November 1997 Insp Repts 50-445/97-21 & 50-446/97-21 on 971027-31.No Violations Noted.Major Areas Inspected:Licensee Physical Security Program Including Records & Repts,Test & Maint and Access control-vehicle IR 05000445/19970191997-10-10010 October 1997 Insp Repts 50-445/97-19 & 50-446/97-19 on 970922-25. Violations Noted.Major Areas Inspected:Rev 25 to Comanche Peak Steam Electric Emergency Plan ML20211A1051997-09-19019 September 1997 Insp Repts 50-445/97-17 & 50-446/97-17 on 970720-0830. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19970161997-08-13013 August 1997 Insp Repts 50-445/97-16 & 50-446/97-16 on 970722-25.No Violations Noted.Major Areas Inspected:Insp of Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures ML20151L9231997-08-0505 August 1997 Insp Repts 50-445/97-15 & 50-446/97-15 on 970608-0719. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20149L3361997-07-25025 July 1997 Corected Pages 13,17,19,22,28 & Page 2 of Supplemental Info for Insp Repts 50-445/97-12 & 50-446/97-12 Issued on 970611 IR 05000445/19970141997-06-30030 June 1997 Insp Repts 50-445/97-14 & 50-446/97-14 on 970427-0607. Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support ML20148K2851997-06-11011 June 1997 Insp Repts 50-445/97-12 & 50-446/97-12 on 970421-0502. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000445/19970061997-06-0606 June 1997 Insp Repts 50-445/97-06 & 50-446/97-06 on 970428-0502. Violations Noted.Major Areas Inspected:Operations & Plant Support & Assessment of Licensed Operator Requalification Program ML20148F8791997-06-0303 June 1997 Insp Repts 50-445/97-09 & 50-446/97-09 on 970317-21. Violations Noted.Major Areas Inspected:Maint & Engineering IR 05000445/19970131997-05-21021 May 1997 Insp Repts 50-445/97-13 & 50-446/97-13 on 970428-0502.No Violations Noted.Major Areas Inspected:Licensee Physical Security Program IR 05000445/19970081997-05-21021 May 1997 Insp Repts 50-445/97-08 & 50-446/97-08 on 970316-0426.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000445/19970011997-05-21021 May 1997 Insp Repts 50-445/97-01 & 50-446/97-01 on 970127-31,0428 & 0502.No Violations Noted.Major Areas Inspected:Licensee self-assessment Effort IR 05000445/19970101997-05-20020 May 1997 Insp Repts 50-445/97-10 & 50-446/97-10 on 970421-25.No Violations Noted.Major Areas Inspected:Plant Support ML20148B5891997-05-0808 May 1997 Insp Repts 50-445/97-11 & 50-446/97-11 on 970407-10.No Violations Noted.Major Areas Inspected:Plant Support,Solid Radwaste Mgt & Radioactive Matls Transportation Programs IR 05000445/19970071997-04-16016 April 1997 Insp Repts 50-445/97-07 & 50-446/97-07 on 970324-27.No Violations Noted.Major Areas Inspected:Plant Support 1999-09-14
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000445/19990151999-10-20020 October 1999 Insp Repts 50-445/99-15 & 50-446/99-15 on 990822-1002. Non-cited Violations.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000445/19990141999-09-14014 September 1999 Insp Repts 50-445/99-14 & 50-446/99-14 on 990707-0821.Four Violations Occurred & Being Treated as Ncvs.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000445/19990131999-08-18018 August 1999 Insp Repts 50-445/99-13 & 50-446/99-13 on 990720-23.No Violations Noted.Major Areas Inspected:Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures IR 05000445/19990101999-08-12012 August 1999 Insp Repts 50-445/99-10 & 50-446/99-10 on 990510-0628. Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Engineering & Plant Support IR 05000445/19990121999-07-29029 July 1999 Insp Repts 50-445/99-12 & 50-446/99-12 on 990530-0710.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19993011999-07-16016 July 1999 Exam Repts 50-445/99-301 & 50-446/99-301 on 990618-24.Exam Results:Six Applicants for Senior Operator Licenses Passed Exams IR 05000445/19990111999-06-22022 June 1999 Insp Repts 50-445/99-11 & 50-446/99-11 on 990418-0529.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000445/19990081999-06-0909 June 1999 Insp Repts 50-445/99-08 & 50-446/99-08 on 990503-11.Noncited Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19990091999-05-12012 May 1999 Insp Repts 50-445/99-09 & 50-446/99-09 on 990419-23.No Violations Noted.Major Areas Inspected:Reviewed Implementation of Liquid & Gaseous Radioactive Waste Effluent Mgt Program IR 05000445/19990071999-05-11011 May 1999 Insp Repts 50-445/99-07 & 50-446/99-07 on 990307-0417.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000445/19990061999-04-30030 April 1999 Insp Repts 50-445/99-06 & 50-446/99-06 on 990329-0402.No Violations Noted.Major Areas Inspected:Planning & Preparation,External Exposure Controls & Quality Assurance of Radiation Protection Activities IR 05000445/19990031999-04-0707 April 1999 Insp Repts 50-445/99-03 & 50-446/99-03 on 990124-0306.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000445/19990051999-03-19019 March 1999 Insp Repts 50-445/99-05 & 50-446/99-05 on 990222-26.One Violation Noted.Major Areas Inspected:Implementation of Solid Radwaste Mgt & Radioactive Matls Transportation Programs IR 05000445/19990011999-03-0909 March 1999 Insp Repts 50-445/99-01 & 50-446/99-01 on 990208-12.No Violations Noted.Major Areas Inspected:Licensed Operator Requalification Program IR 05000445/19990021999-01-10010 January 1999 Insp Repts 50-445/99-02 & 50-446/99-02 on 990119-22.No Violations Noted.Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000445/19980081998-12-30030 December 1998 Insp Repts 50-445/98-08 & 50-446/98-08 on 981025-1205.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Licensee Emergency Response Organization IR 05000445/19980151998-11-19019 November 1998 Insp Repts 50-445/98-15 & 50-446/98-15 on 981102-06.No Violations Noted.Major Areas Inspected:Radiation Program Activities,Including External & Internal Exposure Controls & Controls of Radioactive Matl & Contamination IR 05000445/19980071998-11-19019 November 1998 Insp Repts 50-445/98-07 & 50-446/98-07 on 980913-1024.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000445/19980161998-10-29029 October 1998 Insp Repts 50-445/98-16 & 50-446/98-16 on 981019-23.No Violations Noted.Major Areas Inspected:Testing & Maint, Protected Area Barrier & Detection Aids,Vital Area Barriers & Detection Aids & Security Sys Power Supply IR 05000445/19980141998-10-21021 October 1998 Insp Repts 50-445/98-14 & 50-446/98-14 Has Been Canceled.No Insp Rept Will Be Issued IR 05000445/19980061998-09-30030 September 1998 Insp Repts 50-445/98-06 & 50-446/98-06 on 980802-0912.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000445/19980121998-09-16016 September 1998 Insp Repts 50-445/98-12 & 50-446/98-12 Cancelled IR 05000445/19980051998-08-20020 August 1998 Insp Repts 50-445/98-05 & 50-446/98-05 on 980621-0801.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000445/19980041998-07-16016 July 1998 Insp Repts 50-445/98-04 & 50-446/98-04 on 980510-0620.No Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000445/19983011998-07-10010 July 1998 Insp Repts 50-445/98-301 & 50-446/98-301 on 980619-26.No Violations Noted.Major Areas Inspected:Operations.All 9 License Applicants Passed Exam ML20236G9321998-07-0202 July 1998 Notice of Violation from Insp on 980329-0509.Violation Noted:Four Examples Were Identified,Where Licensee Failed to Meet Requirement for Design of ECCS Switchover from Refueling Water Storage Tank to Containment Recirculation IR 05000445/19980031998-07-0202 July 1998 Insp Repts 50-445/98-03 & 50-446/98-03 on 980329-0509. Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000445/19980131998-06-26026 June 1998 Insp Repts 50-445/98-13 & 50-446/98-13 on 980615-19.No Violations Noted.Major Areas Inspected:Licensee Physical Security Program IR 05000445/19980021998-04-24024 April 1998 Insp Repts 50-445/98-02 & 50-446/98-02 on 980215-0328. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20217F6051998-04-24024 April 1998 Notice of Violation from Insp on 980215-0328.Violations Noted:Corrective Actions Were Not Sufficient to Identify That Excessive Leakage in ECC Sys Check Valves During Unit 1 Cycle 6 Required Unit 1 Safety Injection Pumps Be Started ML20216H3501998-04-16016 April 1998 Insp Repts 50-445/98-11 & 50-446/98-11 on 980323-27.No Violations Noted.Major Areas Inspected:Physical Security Program IR 05000445/19980011998-03-19019 March 1998 Insp Repts 50-445/98-01 & 50-446/98-02 on 980104-0214. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20248L8831998-03-19019 March 1998 Notice of Violation from Insp on 980104-0214.Violation Noted:Licensee Failed to Document Heat Related Degredation of Unit 2,Train B Solid State Safeguards Sequencer IR 05000445/19970211998-02-11011 February 1998 Errata to Insp Repts 50-445/97-21 & 50-446/97-21,correcting Errors in Insp follow-up Sys Number Associated W/Items Described in Rept IR 05000445/19970231998-01-30030 January 1998 Insp Repts 50-445/97-23 & 50-446/97-23 on 971123-980103.No Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 07100012/20110221998-01-16016 January 1998 Notice of Violation from Insp on 971012-1122.Violation Noted:Procedure IPO-005B,rev 2,not Appropriate to Circumstances in That Procedure Did Not Require Pressure Be Maintained Below Rc System Pressure & Temp Limits ML20198S1891998-01-16016 January 1998 Insp Repts 50-445/97-20 & 50-446/97-20 on 971012-1122. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20198R6571998-01-16016 January 1998 Notice of Violation from Insp on 970922-25.Violation Noted: on 961029,licensee Made Changes to Emergency Plan,W/O Commission Approval,That Decreased Effectiveness of Plan & Did Not Continue to Meet Planning Standard 50.47(b)(2) ML20198N2071998-01-14014 January 1998 Notice of Violation from Insp on 970608-0719 & Subsequent Inoffice Reviews Concluded on 971114.Violation Noted: Procedures OPT-102A & 102B Did Not Include Appropriate Quantitative Acceptance Criteria ML20199H0131997-11-21021 November 1997 Notice of Violation from Insp on 970831-1011.Violation Noted:Thermometer IC1473,was Used During Performance of Procedure PPT-SX-7505A on 970807 ML20199H0241997-11-21021 November 1997 Insp Repts 50-445/97-18 & 50-446/97-18 on 970831-1011. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering PNO-IV-97-067, on 971117,medical Emergency Declared in Unit 1 Electrical Switchgear Room.Licensee Issued Stop Work Order for Electrical Maint While Investigation Conducted.Nrc Resident Insp Staff Will Be Following Licensee1997-11-17017 November 1997 PNO-IV-97-067:on 971117,medical Emergency Declared in Unit 1 Electrical Switchgear Room.Licensee Issued Stop Work Order for Electrical Maint While Investigation Conducted.Nrc Resident Insp Staff Will Be Following Licensee PNO-IV-97-066, on 971115,new Fuel Damage Occurred.Licensee Suspended Fuel on-load & Conducting Investigation Into Why Damage Occurred.Licensee Expects Delivery of Replacement Fuel Assembly on 971123.State of Tx Informed1997-11-17017 November 1997 PNO-IV-97-066:on 971115,new Fuel Damage Occurred.Licensee Suspended Fuel on-load & Conducting Investigation Into Why Damage Occurred.Licensee Expects Delivery of Replacement Fuel Assembly on 971123.State of Tx Informed IR 05000445/19970221997-11-17017 November 1997 Insp Repts 50-445/97-22 & 50-446/97-22 on 971103-07.No Violations Noted.Major Areas Inspected:Maint ML20199E6481997-11-13013 November 1997 Insp Repts 50-445/97-21 & 50-446/97-21 on 971027-31.No Violations Noted.Major Areas Inspected:Licensee Physical Security Program Including Records & Repts,Test & Maint and Access control-vehicle PNO-IV-97-061, on 971027,Unit 1 Experienced Main Generator Lockout,Turbine Trip & Reactor Trip from 100% Power.Afw Manually Started Shortly Following Trip,In Anticipation of Automatic Initiation of AFW Sys.State of Tx Informed1997-10-30030 October 1997 PNO-IV-97-061:on 971027,Unit 1 Experienced Main Generator Lockout,Turbine Trip & Reactor Trip from 100% Power.Afw Manually Started Shortly Following Trip,In Anticipation of Automatic Initiation of AFW Sys.State of Tx Informed IR 05000445/19970191997-10-10010 October 1997 Insp Repts 50-445/97-19 & 50-446/97-19 on 970922-25. Violations Noted.Major Areas Inspected:Rev 25 to Comanche Peak Steam Electric Emergency Plan ML20211A1051997-09-19019 September 1997 Insp Repts 50-445/97-17 & 50-446/97-17 on 970720-0830. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20211A0691997-09-19019 September 1997 Notice of Violation from Insp on 970720-0830.Violation Noted:On 970507,while Performing Procedure OPT-457B,licensed Operator Failed to Close Valve 2-8812A Per Step 8.8 ML20198G1821997-09-12012 September 1997 Notice of Violation from Investigation on 970606.Violation Noted:Mn Shook Submitted Falsified Info to NRC Re Being Denied Access to Nuclear Power Plant as Result of fitness-for-duty Policy 1999-09-14
[Table view] |
Text
E
.
ENCLOSURE U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
l Docket Nos.: 50-445 l 50-446
)
License Nos.: NPF-87 NPF-89 Report No.: 50-445/99-06 50-446/99-06 Licensee: TU Electric Facility: Comanche Peak Steam Electric Station, Units 1 and 2 Location: FM-56 Glen Rose, Texas Dates: March 29 through April 2,1999 Inspector: J. Blair Nicholas, Ph.D., Senior Radiation Specialist Plant Support Branch l
Accompanied By: James S. Dodson, Radiation Specialist Plant Support Branch Approved By: Gail M. Good, Chief Plant Support Branch Division of Reactor Safety Attachment: Supplemental Information 9905060177 990430 PDR G ADOCK 05000445 PDR
.
.
-2-
. EXECUTIVE SUMMARY -
Comanche Peak Steam Electric Station, Units 1 and 2 NRC Inspection Report No. 50 445/99-06; 50 446/99-06
~ This announced inspection focused on the radiation protection program during Unit 2 refueling outage activities (2RF04).' Areas reviewed included: planning and preparation; external exposure controls; internal exposure controls; controls of radioactive material and contamination, surveying and monitoring; the program to maintain occupational exposure as i low as is reasonably achievable (ALARA); contract radiation protection technician training and qualifications; and quality assurance of radiation protection activitie Plant Sucoqd -
.
The ALARA program was acceptably irnplemented. ALARA considerations were properly incorporated into the outage schedule and were generally well implemente Radiological work packages were effectively planned, and ALARA personnel were involved during the implementation stage. Lessons learned from past similar work were incorporated into the radiological work packages. Station and task activity doses were tracked and trended by the ALARA staff. The Unit 2 refueling outage dose as of March 31,1999, was approximately 36 person rem. Effective chemistry shutdown plans and controls were implemented. Appropriate radiation protection instrumentation, protective clothing, and consumable supplies were available to support radiological work (Sections R1.1 and R1.5).
i in general, the external exposure control program was effectively implemented. High and locked high radiation areas were properly controlled and posted. Radiation workers wore dosimetry properly and knew the correct response to electronic dosimeter alarms (Section R1.2).
.
On two occasions, radiation workers, in a high traffic. area of containment, did not respond to continuous air monitor audible and visual alert / fault alarms in accordance with management expectations (Section R1.2).
A violation of 10 CFR 20.1501(a) was identified for failure to evaluate the airborne
- concentrations and potential radiological hazards that could be present in the spent fuel pool work area on the 860-foot elevation of the fuel building. This is the first example of a Severity Level IV violation that is being treated as a non-cited violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was placed in the licensee's
- corrective action program as SMART Form SMF-1999-000808-00 (Section R1.2).
.
The internal exposure controls program was acceptably implemented. In general, continuous air monitors and high efficiency particul ate air filter ventilation units were used correctly to monitor and limit airborne exposures. The total effective dose equivalent /as low as is reasonably achievable (TEDE/ALARA) evaluations reviewed were acceptable for respiratory protection equipment use determination (Section R1.3).
-
l I
i
.
.3-
A violation of 10 CFR 20.1501(a) was identifie'd for failure to ensure the radioactive airborne quality from Steam Generators 1 and 4 portable ventilation units. This is the second example of a Severity Level IV violation that is being treated as a non-cited
. violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was placed in the licensee's corrective action program as SMART Form SMF-1999-000808-00 (Section R1.3).
. .
l
. Radiation workers used the personnel and equipment contamination monitors in -
accordance with station procedures. Minor personnel contamination incidents and -
events were properly handled. ' Personnel stationed at the radiologically controlled area exit provided appropriate guidance to station workers who alarmad the personnel and equipment contamination monitors. Good controls were in place to prevent the spread of radioactive contamination. Portable radiation detection survey instrumentation was calibrated and source response checked in accordance with station procedures (Section R1.4).
.
A violation of 10 CFR 20.1501(a) was identified for failure to evaluate the airborne concentrations and potential radiological hazards that could be present inside Steam l Generator 3. This is the third example of a Severity Level IV violation that is being treated as a non-cited violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was placed in the licensee's corrective action program as SMART Form SMF-1999-000818-00 (Section R1.4).
. : Radiation protection personnel failed to evaluate radiation levels and post hot spots in
'
accordance with expectations (Section R1.4).
'.~ A violation of Technical Specification 6.8.1 was identified for failure to perform complete radiological exposure evaluations on three separate temporary shielding packages as -
required by a radiation protection program procedure. This Severity Level IV violation is being treated as a non-cited violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was placed in the licensee's corrective action program as SMART Form SMF 1999-000813-00 (Section R1.5).
. The contract radiation protection technician training program was effectively implemented. Radiation protection management was involved in the development of the contract radiation protection technician training program and quahfication task topic Qualification tasks included all the tasks assigned to contract senior radiation protection technicians. Contract senior radiation protection technicians met the technical experience requirement of Technical Specification 6.3.1.b and the training requirements
. delineated in station procedures (Section RS).
. The radiological SMART Forms reviewed were closed in a timely manner. No problems
.or negative trends were identified from the review of radiological SMART Forms written since November 1,1998; however, the inspectors noted that the licensee had not documented in Radiological SMART Forms survey problems similar to those identified by the NRC during this inspection (Section R7).
'
-
.
l l
Recort Details Summarv of Plant Status During the inspection, Unit 1 operated at 100 percent power, and Unit 2 was in the second week of Refueling Outage 2RF0 IV. Plant Support l
R1 Radiological Protection and Chemistry Controls R Plannina and Preoaration Insoection Scope (83750)
Radiation protection personnel involved in planning and preparation for the 2RF04 refueling outage were interviewed. The following items were reviewed:
ALARA considerations !
- Incorporation of lessons learned from similar work l
l
Supplies of radiation protection instrumentation, protective clothing, and l consumable items i i Observations and Findinas !
$
On March 30,1999, the inspectors attended the pre-job ALARA briefing for the transfer !
of five spent filters to a shielded high integrity container. The highest dose rate on l contact with the filter was 50 rems per hour. The briefing was conducted in a i professional manner and addressed task sequences, radiological conditions, i radiological hazards, contingencies derived from past spent filter transfers, precautions, l and postings. Following the briefing, the inspectors observed the transfer of the five spent filters. The task was completed in accordance with station procedures and ,,
~ Radiation Work Permit 99-2500, Task 1. The job planning, ALARA considerations, incorporation of lessons learned from similar work, and radiation protection job coverage were appropriate for the observed work activit On March 31,1999, the inspectors attended the pre. job ALARA briefing for the removal of Steam Generators 3 and 4 manways and diaphragms. The briefing was conducted in a professional manner and addressed: task sequences, ALARA work initiatives within the work sequence, radiological conditions, radiological hazards, radiological hold points, contingencies derived from past outages and industry experience, precautions, l
!
,
g
.
s
. and postings. The work package was well planned, and lessons learned were incorporated into job plannin Other radiological work package tasks were well planned, and ALARA personnel were involved during the outage planning stage. ALARA based initiatives were incorporated into the outage schedule. The following initiatives were included: steam generator secondary side drain down to maximize the shielding effect of the water, installation and
._ use of job. specific remote cameras with communications, use of remote wireless; ,
transmitting dosimetry, and chemistry shutdown controls to effectively reduce the source i ter The inspectors determined from field observations that there was appropriate radiation protection instrumentation, protective clothing, and consumable supplies to support radiological wor Conclusions ALARA considerations were properly incorporated into the outage schedule and were generally well implemented. Radiological work packages were effectively planned, and ALARA personnel were involved during the implementation stage. Lessons learned 4 from past similar work were incorporated into the radiological work package l Appropriate radiation protection instrumentation, protective clothing, and consumable
- supplies were available to support radiological wor R1.2 Extemal Exposure Controls Insoection Scope (83750)
Radiation protection personnel involved in the external exposure control program were interviewed. The inspectors conducted frequent tours of the radiologically controlled areas, including the reactor containment building. _The following were reviewed:
~* General access permits and radiation work permits -
- Job coverage by radiation protection personnel
- Personnel dosimetry use Observations and Findinas -
The inspectors conducted several tours of the radiologically controlled areas and observed that high radiation areas (where the dose rates were greater than 100 but less than 1000 millirems in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> at 30 centimeters) and locked high radiation areas (areas where the dose rates were greater than 1000 millirems per hour at 30 centimeters but less than 500 rads in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> at 1 meter) were controlled and posted in accordance with station procedures and regulatory requirement The inspector's reviewed a random selection of general access permits and radiation work permits. In general, radiation work permits and general access permits were
.
t
.. written in a clear, consistent manner and provided radiation workers with the appropriate I controls and radiological information to safely accomplish assigned tasks. However, during a tour of the fuel building, the inspectors observed that the continuous air monitor was located in the dress-out room, adjacent to the spent fuel pool work area on the 860-foot elevation. The general access permit, GAP 99-06, Task 1, Revision 0, required, in part, that airborne sampling be performed during refuel bridge activities involving spent fuel or irradiated components. Since spent fuel movement was in progress, the inspectors notified radiation protection personnel of the continuous air monitor location. The inspectors were informed that this was not the normal monitoring location.' The licensee relocated the continuous air monitor to the normal monitoring location adjacent to the spent fuel pool. There was no evaluation to justify the as-found locatio CFR 20.1501(a), states, in part, that each licensee shall make or cause to be made, surveys that are reasonable under the circumstances to evaluate concentrations or quantities of radioactive material and the potential radiological hazards that could be present. The failure to evaluate the airborne concentrations and potential radiological j hazards that could be present in the spent fuel pool work area on the 860-foot elevation !
of the fuel building was identified as the first example of a 10 CFR 20.1501(a) violation and is being treated as a non-cited violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was placed in the licensee's corrective action program as SMART Form SMF-1999-000808-00 (50-445; 446/9906-01).
During tours of the radiologically controlled area, the inspectors noted that radiation j protection job coverage was appropriate for radiological work observed. Radiation I workers observed wore dosimetry properly. When questioned, workers knew to leave the work area and contact radiation protection personnel if their electronic dosimeter alarmed. However, during a tour of the 808-foot elevation of the reactor containment ;
building on March 29,1999, the inspectors observed a continuous air monitor in a visual . ;
and audible fault alarm condition. This monitor was located in a high traffic are Workers in that area did not respond to the alert / fault alarm. Subsequently, the
'
. Inspectors notified the radiation protection staff, and the fault alarm was cleared by providing an alternate power source. When the monitor began the start up sequence, it went into visual and audible alarm. Again, workers in the area did not respond to the alert / fault alarm. This observation was discussed with radiation protection management
. and was promptly addressed with the licensee staff. On March 31,1999, inspectors observed another continuous air monitor audible and visual alarm in the same locatio This alarm was immediately acknowledged and addressed by radiation protection staf Conclusions :
In general, the external exposure control program was effectively implemented. High
.and locked high radiation areas were properly controlled and posted. Radiation workers wore dosimetry properly and knew the correct response to electronic dosimeter alarm Radiation workers, in a high traffic area of containment, did not respond to continuous air monitor audible and visual alert / fault alarms in accordance with management expectation m,J
.
A violation of 10 CFR 20.1501(a) was identified for failure to evaluate the airborne concentrations and potential radiological hazards that could be present in the spent fuel pool work area on the 860-foot elevation of the fuel building. This is the first example of ,
a Severity Level IV violation that is being treated as a 'non-cited violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was placed in the licensee's
- corrective action program as SMART Form SMF-1999-000808-0 R1.3 Internal Exoosure Controls Insoection Scope (83750)
Selected radiation protection personnel involved with the internal exposure control program were interviewed. Additionally, several tours of the radiologically controlled areas were performed. The following programs were reviewed:
- Respiratory protection Observations and Findinas
- in general, continuous air monitors and high efficiency particulate air filter ventilation units were used correctly throughout the radiologically controlled area to monitor and i limit radiation workers' airborne exposures. However, the inspectors observed on the 905-foot elevation of the reactor containment building, that there was no air sampler or continuous air monitor placed to ensure that the radioactive airborne quality of the exhaust from the portable ventilation equipment was monitored from Steam Generators 1 and 4. Additionally, the portable ventilation equipment exhaust was not directed to the plant ventilation syste Section 6.4.6 of Procedure RPI 612, " Steam Generator Work Control," Revision 6, stated, in part,-" perform airborne radioactivity surveys to ensure that the air quality at the exhaust of the portable ventilation equipment is monitored if the exhaust is not directed to the plant ventilation system. A continuous air monitor may be used for continuous j monitoring in lieu of performing airborne surveys at the portable ventilation exhausts."
'
The failure to perform airborne radioactivity surveys, use a continuous air monitor, or direct the exhaust from the portable ventilation equipment to the plant ventilation system ;
to ensure the radioactive airborne quality from Steam Generators 1 and 4 portable i ventilation units was identified as a second example of a 10 CFR 20.1501(a) violation l and is being treated as a non cited violation, consistent with Appendix C of the NRC i Enforcement Policy. This violation was placed in the licensee's corrective action
-
program as SMART Form SMF-1999-000808-00 (50-445;446/9906-01). j
. The inspectors reviewed a random selection of the TEDE/ALARA evaluations for various i tasks which involved the use of respiratory protection equipment. The inspectors concluded that these evaluations were acceptable.
e
e
.
8- Conclusions
- The internal exposure controls program was acceptably implemented. In general, continuous air monitors and high efficiency particulate air filter ventilation units were used correctly to monitor and limit airborne exposures. The TEDE/ALARA evaluations reviewed were acceptable for respiratory protection equipment use determinatio A violation of 10 CFR 20.1501(a) was identified for failure to ensure the radioactive airbome quality from Steam Generators 1 and 4 portable ventilation units. This is the -
second example of a Severity Level IV violation that is being treated as a non-cited - (
violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was i placed in the licensee's corrective action program as SMART Form SMF-1999-000808- )
0 {
l R1.4 Control of Radioactive Materials and Contamination: Survevina and Monitorina )
I Inspection Scope (83750) '
Frequent tours of the radiologically controlled areas were conducted by the inspector Areas reviewed included: .
- Radiologically controlled area controls l
=' Control of radioactive material I
=
Adequacy of the surveys necessary to assess personnel exposure
=
Housekeeping within the radiologically controlled area l
. Observations and Findinas i
Observations at the radiologically controlled area egress point revealed that workers ;
used the personnel and equipment contamination monitors in accordance with station -
'
procedures. Personnel stationed at the radiologically controlled area exit provided appropriate and timely guldance to workers who alarmed the monitors. Personnel l contamination incidents and events were properly handle The licensee provided good controis to prevent the spread of radioactive contaminatio ' During tours of the radiologically controlled area, the inspectors noted that radioactive l material containers observed were generally labeled, posted, and controlled in accordance with station procedures and regulatory requirernents. However, a contaminated trash drum was observed partially in/out of a contaminated area. The radiation protection staff was notified and promptly ensured that the drum was positioned fully inside the contaminated area. Contaminated areas were clearly identified and posted. Step-off pads were placed at the exits from contaminated area The inspectors observed radiation workers exit contaminated areas. In general, personnel used proper radiation protection practices during the removal of potentially contaminated protective clothin .
%
. . During a tour of the reactor containment building, the inspectors observed the removal of manways and diaphrams from Steam Generators 3 and 4.' Radiation and contamination surveys were performed inside the steam generators prior to installation of the eddy current testing equipment. The inspectors reviewed the radiological survey documentation and noted that an airborne radioactivity survey was performed in Steam ,
Generator 4, but not inside Steam Generator ~
10 CFR 20.1501(a), states, in part, that each licensee shall make or cause to be made, surveys that are reasonable under the circumstances to evaluate concentrations or ~
quantities of radioactive material and the potential radiological hazards that could be -
present. The failure to evaluate the airborne concentrations and potential radiological hazards that could be present inside Steam Generator 3 was identified as a third example of a 10 CFR 20.1501(a) violation that is being treated as a non-cited violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was placed in the licensee's corrective action program as SMART Form SMF-1999-000808-00 (50-445;446/9906-01). j independent radiological survey measurements performed by the inspectors during radiologically controlled area tours generally confirmed that area radiological postings I were in compliance with station procedures and regulatory requirements. Section 3.15 and Attachment 1 of Procedure RPI-602," Radiological Surveillance and Posting," ,
Revision 17, stated, in part, that if the radiation levels from a 30 centimeter dose rate I are 5 times the average background general area dose rate and the contact dose rate is greater than or equal to 100 millirems per hour (mR/hr) the location should be posted as a hot spot. During a tour of the 808-fcot elevation of the reactor containment building on
'
March 29,1999, the inspectors identified two locations on the reactor cavity drain line at Valvo 2-SF-0027 and another downstream of that valve, where radiation levels met the conditions for hot spot identification and should have been posted in accordance with station radiation protection program procedure expectation Radiation Survey 99-03-5468, conducted on March 20,1999, indicated a maximum contact dose rate on the reactor cavity drain line of 100 mR/hr on contact and 30 mR/hr at 30 centimeters. On March 29,1999, radiation protection personnel were requested to accompany the inspectors to this area to perform a confirmation radiation survey. The licensee's radiation survey (99-03-2221) indicated a maximum dose rate at Valve 2-SF-0027 of 240 mR/hr o.n contact and 15 mR/hr at 30 centimeters and, at the open end of the drain line, a contact dose rate of 180 mR/hr and 12 mR/hr at 30 centimeters. This observation was discussed with radiation protection management, and the hot spots were posted in accordance with procedural expectation Housekeeping throughout the radiologically controlled areas was generally good. The
, inspectors noted that areas were free of debris, i
- All portable radiation protection survey instruments observed throughout the station were calibrated and source response checked in accordance with station procedure ;
. _ - -
'
l
-10-
-
i Conclusions Radiation workers used the personnel and equipment contamination monitors in accordance with station procedures. Minor personnel contamination incidents and events were properly handled. Personnel stationed at the radiologically controlled area exit provided appropriate guidance to station workers who alarmed the personnel and i equipment contamination monitors. Good controls were in place to prevent the spread {
of radioactive contamination. Portable radiation detection sun /ey instrumentation was !
calibrated and source response checked in accordance with station procedure {
Radiation protection personnel failed to evaluate radiation levels and post hot spots in !
accordance with expectation I
A violation of 10 CFR 20.1501(a) was identified for failure to evaluate the airborne concentrations and potential radiological hazards that could be present inside Steam Generator 3. This is a third example of a Severity Level IV violation that is being treated as a non-cited violation, consistent with Appendix C of the NRC Enforcement Polic This violation was placed in the licensee's corrective action program as SMART Form SMF-1999-000818-0 R1.5 Maintainina Occuoational Exoosure As Low As is Reasonably Achievable (ALARA) Insoection Scope (83750)
Radiation protection personnelinvolved with the ALARA program were interviewed. The following programs were reviewed:
- Exposure goal establishment and status
. Chemistry controls Observations and Findinos ,
- The 2RF04 refueling outage dose goal was established at 190 person-rem. The inspectors noted that this outage dose goal was higher than the outage dose goal of 140 person-rem established for the previous Unit 2 refueling outage. The licensee attributed the difference to additional work activities planned for this refueling outag From discussions with the licensee, the inspectors determined that the total current outage dose goal was established by a summation of dose estimates from each department, based on past performance and experience, and the ALARA committee members were involved in the development of the annual dose goals, outage dose goals, and exposure reduction initiatives. The inspectors noted that as of March 31, 1999, the Unit 2 refueling outage projected dose was 75 person-rem and the cumulative dose was approximately 36 person-rem. This was attributed, in part, to excellent shutdown chemistry control and the removal of radioactive cobalt and iron source term Station and high exposure task activity doses were tracked and trended by the ALARA staff, and dose status reports were distributed daily to station department ~
p
'
.
>
-11-
. The inspectors reviewed a random selection of temporary shielding packages. During this review, the inspectors identified three temporary shielding packages which did not contain person-rem exposure estimates in the evaluation process as required by i Procedure RPI-608, " Control of Temporary Shielding," Revision 6. Technical Specification 6.8.1 requires, in part, that written procedures be established, implemented, and maintained covering the activities recommended in Appendix A, of ' l Regulatory Guide 1.33, Revision 2, February 1978. Section 7.e(9) of Appendix A of this Regulatory Guide includes procedures for implementation of the ALARA progra Section 6.1.3 of Procedure RPl-608, " Control of Temporary Shielding," Revision 6,
.
stated, in part, "pedorm an evaluation considering person-rem exposure estimate for the'
task if no shielding was used. Compare this value with the exposure estimate for the task, if shielding was used plus the exposure estimate for the installation and removal of the proposed temporary shielding." The failure to perform these radiological exposure evaluations as required by procedure was identified as a violation of Technical Specification 6.8.1. This Severity Level IV violation is being treated as a non-cited !
violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was ;
placed in the licensee's corrective action program as SMART Form SMF-1999-000813-
- 00 (50-445;446/9906-02). I During discussions with chemistry personnel, the inspectors determined that management support for shutdown chemistry controls was excellent. The shutdown chemistry controls were effective in removing approximately 2,820 curies of cobalt-58 from the reactor coolant syste Conclusions An acceptable ALARA program was implemented. Station and task activity doses were tracked and trended by the ALARA staff. The Unit 2 refueling outage dose as of March 31,1999, was approximately 36 person-rem.' Effective chemistry shutdown plans and controls were implemente A violation of Technical Specification 6.8.1 was identified for failure to perform complete ,
'
radiological exposure evaluations on three separate temporary shielding packages as required by a radiation protection program procedure. This Severity Level IV violation is
' being treated as a non-cited violation, consistent with Appendix C of the NRC Enforcement Policy. This violation was placed in the licensee's corrective action program as SMART Form SMF-1999-000813-0 _
r
.-
..
-12 ,
?
!
'
R5L - Staff Training and Qualification ln Radiological Protection and Chemistry ! Insoection Scooe (83750)
Personnel involved with contract radiation protection technician selection, qualification, !
and training were interviewed.- The following items were reviewed:
. Resumes of contract radiation protection technicians
Contract radiation protection training prograrn
~ Observations and Findinas ~
The inspectors reviewed the qualifications and training of randomly selected contract
- senior radiation protection technicians. Training material for contract radiation protection technicians included site and industry lessons learned. Radiation protection management was involved in developing the qualification task topics. All contract i radiation protection technicians were tested on site-specific information and station radiation protection procedures. The Northeast Utilities examination was used to assess the basic radiation protection technical knowledge of the contract radiation protection
' technicians. Performance demonstrations of knowledge, skills, and abilities were also required. Qualification certifications were signed by a radiation protection supervisor and the radiation protection manager, prior to technicians being assigned radiation protection tasks. The inspectors concluded that th'ese contract senior radiation protection technicians met the technical experience requirement of Technical Specification _6.3.1.b (2 years of radiation protection experience) and the training requirements delineated in station procedure Conclusions -
The contract radiation protection technician training program was effectively
.
implemented. Radiation protection management was involved in the development of the contract radiation protection technician training program and qualification task topic Qualification tasks included all the tasks assigned to contract senior radiation protection technicians. . Contract senior radiation protection technicians met the technical experience requirement of Technical Specification 6.3.1.b and the training requirements delineated in station procedure R7 - Quality Assurance in Radiological Protection and Chemistry Activities
- The inspectors reviewed a random selection of SMART Forms written since
~ November 1,1998. The inspectors noted that the licensee had not identified any similar survey problems as discussed in the inspection report. Generally, the licensee identified and documented radiological issues which provided management with an overview to .
- assess the radiation protection program. The radiological SMART Forms reviewed were
- closed in a timely manner. No problems or negative trends were identifie ,
I
.
-13-V. Manaaement Meetinas j X1 Exit Meeting Summary The inspectors presented the inspection results to members of licensee management at an exit meeting on April 2,1999. A follow-up discussion of the inspection results was 1 conducted with members of the licensee staff on April 28,1999. The licensee acknowledged the findings presented. No proprietary information was identifie {
i
- t I
I i
i I
l
.
%
ATTACHMENT SUPPLEMENTAL INSPECTION INFORMATION PARTIAL LIST OF PERSONS CONTACTED Licensee C.L. Terry, Senior Vice President and Principal Nuclear Officer M. Blevins, Vice President, Nuclear Operations D. Davis, Nuclear Overview Manager J. Curtis, Radiation Protection Manager R. Carr, Radiation Protection Supervisor S. Bradley, Radiation Protection Supervisor D. Kay, Radiation Protection Supervisor D. O' Conner, Radiation Protection Health Physicist J. Blaikle, Radiation Protection Health Physicist A. Barnette, Radiation Protection Supervisor R. Fishencord, Radiation Protection Supervisor T. Hope, Regulatory Affairs Manager C. Wilkerson, Senior Licensing Engineer NRC A. Gody, Jr., Senior Resident inspector INSPECTION PROCEDURE USED 83750 Occupational Radiation Exposure LIST OF ITEMS OPENED CLOSED AND DISCUSSED Opened and Closed 50-445;446/9906-01 NCV Failure to perform radiological surveys 50-445;446/9906-02 NCV Failure to perform complete radiological evaluations on temporary shielding packages
r
.
.
-2-LIST OF DOCUMENTS REVIEWED Procedures TRA 301 Radiation Protection Training, Revision 12 STA-609 Reactor Coolant Water Chemistry Control Program, Revision 5 STA-650 General Health Physics Plan, Revision 5 STA-651 ALARA Program, Revision 8 STA-652 Radioactive Material Control, Revision 7 STA 656 Radiation Work Control, Revision 10 STA-659 Radiation Protection Program, Revision 8 STA-660 Control of High Radiation Areas, Revision 7 RPl 213 Survey and Release of Material and Personnel, Revision 7 RPI-602 Radiological Surveillance and Posting, Revision 17 RPI-606 Radiation Work and General Access Permits, Revision 9 RPI-607 ALARA Planning, Revision 4 RPI-612 Steam Generator Work Control, Revision 6 RPI-902 Issue and Control of Respiratory Protection Equipment, Revision 9 Other SMART Form summary listing for November 1998 through March 1999 Radiation Protection Contractor Technician Training Guidelines Radiation Protection Conduct of Operations, Revision 5 Radiation Protection Contractor Technician Training Material Radiation Protection Contractor Technician Site Specific Procedure Exams Radiation Protection Contractor Technician Qualification Certification Sheets Radiation Protection Contractor Technician Resumes