IR 05000445/1988002

From kanterella
Jump to navigation Jump to search
Insp Rept 50-445/88-02 on 880106-0202.No Violations or Deviations Noted.Major Areas Inspected:Plant Tours & Part 21 Followup
ML20149J950
Person / Time
Site: Comanche Peak 
Issue date: 02/10/1988
From: Kelley D, Joel Wiebe
NRC OFFICE OF SPECIAL PROJECTS
To:
Shared Package
ML20149J941 List:
References
50-445-88-02, 50-445-88-2, NUDOCS 8802230297
Download: ML20149J950 (4)


Text

.

.

'

U.

S. NUCLEAR REGULATORY COMMISSION OFFICE OF SPECIAL PROJECTS NRC Inspection Report:

50-445/88-02 Permit: CPPR-126 Docket: 50-445 Category: A2 l

Construction Permit t

Expiration Date:

Unit 1: August 1, 1988 Applicant:

TU Electric

Skyway Tower 400 North Olive Street Lock Box 81 Dallas, Texas 75201

-

Facility Name:

Comanche Peak Steam Electric Station (CPSES),

!

Unit 1 Inspection At:

Comanche Peak Site, Glen Rose, Texas l

spection Conducted: January 6 through February 2, 1988

.

Inspector:

.

5O, cR!/4 88~

dOperations~. Kelley, Seniof,Rosident Inspector,Cate L

t (

I l

Reviewed by:

. h4 8//pl//'

0{j/. S. Wicbo, Load Project Inspector ba(e Inspection Sunmary i

l Inspection Conducted: January 6 through February 2, 1988 (Report

!

50-445/88-02)

Areas Inspected:

Unannounced resident safety inspection including (1) Plant tours; and (2) Part 21 follow up.

Results:

Within the areas inspected, no violations or deviations were identified.

8802230297 800210 PDR ADOCK 05000445 Q

PDH

.

DETAILS 1.

Persons Contacted

  • J.

C. Aldridge, Engineering Assurance (EA), Stone & Webster Engineering Corporation (SWEC)

  • R.

P.

Baker, EA Regulatory Compliance Manager, TU Electric

  • J.

L. Barker, Manager, EA, TU Electric

  • D.

P. Barry, Manager, ESG, SWEC

  • D.

N. Bize, EA Regulatory Compliance Supervisor, TU Electric

  • M.

R.

Blevins, Manager, Technical Support, TU Electric

  • J.

T.

Conly, Lead Licensing Engineer, SWEC

  • J.

C.

Finneran, CPE-PSE, TU Electric

  • K.

M. Fitzgerald, HVAC Progr.tm Manager, Ebasco

  • P.

E. Halstead, Manager, Quality Control (QC), TU Electric

  • T.

L. Heatherly, EA Regulatory Compliance Engineer, TU Electric

  • C.

R. Hooten, CPE-Civil Engineering Unit Manager, TU Electric

  • J.

J. Kelley, Manager, Plant Operations, TU Electric

  • 0.

W.

Lowe, Director of Engineering, TU Electric

  • F. W. Madden, Mechanical Engineering Manager, TU Electric
  • D.

M. McAfee, Manager, Quality Assurance (QA), TU Electric

  • D.

E. Noss, QA Issue Interface Coordinator, TU Electric

  • E.

Odar, Project Engineering Manager, Ebasco

  • M.

D. Palmer, Plant Evaluation, Nuclear Operations, TU Electric

  • B.

L. Ramsey, Project Manager Civil / Structural, TU Electric

  • D.

M. Reynorson, Director of Construction, TU Electric

  • M.

J. Riggs, Plant Evaluation Manager, Operations, TU Electric

  • A.

B.

Scott, Vice President, Nuclear Operations, TU Electric

  • C.

E. Scott, Manager, Startup, TU Electric

  • J.

C. Smith, Plant Operations Staff, TU Electric

  • M.

R. Steelman, CPRT, TU Electric

  • P.

B. Stevens, Manager, Eleccrical Engineering, TU Electric

  • J.

F. Streeter. Director, QA, TU Electric

  • C.

L. Terry, * hit i Project Manager, TU Electric

  • R. D. Walker, Manager of Nuclear Licensing, TU Electric The NRC inspecr?r also interviewed other applicant employees during this inspection period.
  • Denotes personnel present at the February 2, 1988, exit interview.

2.

Plant Tours (71302)

The NRC inspector performed frequent tours of Unit 1 and common plant areas during this inspection period.

In addition to the general housekeeping activities and general cicanliness of the facility, specific attention was given to areas where safety-related equipment was installed and where activities were in progress involving safety-related equipment.

These areas were inspected to ensure that:

-

-

-

-

.

-

_

.

,

t

Work in progress was being accomplished using approved

.

procedures.

'

,

Special precautions for protection of equipment were

<

t

.

implemented and additional cleanliness requirements were

,

'

being adhered to for maintenance and welding activities.

Installed safety-related equipment and components were

'

.

'

being protected and maintained to prevent damage or deterioration.

[

,

The NRC inspector also observed control room activities

,

including operator response to alarms, control of maintenance and tagging activities, and the general demeanor of plant

[

operations.

,

!

No violations or deviations were identified.

.

I 3.

Part 21 Follow Up (92700)

!

'

The NRC inspector reviewed a 10 CFR Part 21 notification relating to Salem Unit 1 and 2 Containment Hydrogen Analyzer Systems.

The Part 21 notification noted that CPSES was one of three other sites using the same system.

,

The NRC inspector discussed the notification with several

!

applicant representatives and learned that TU Electric had not

'

i received the notification as of January 29, 1988.

The Office j

of Special Projects received a copy from NRC Headquarters on

,

January 11, 1988.

When the applicant receives notification, i

the NRC inspector will review the applicant's evaluation and

j resulting actions.

This item is considered open pending

'

resolution (445/8802-0-01).

4.

Open Items

,

,

Open items are matters which have been discussed with the applicant, which will be reviewed further by the inspector,

'

and which involve some action on the part of the NRC or

l applicant or both.

Open items identified during the

inspection are discussed in paragraph 3.

t t

5.

Exit Intervj ew ( 30703)

i j

On Januaty 10, 1988, R. F. Warnick, H. H. Livermore and

J. S. WAeve met with L. D. Nace and A. B. Scott to discuss i

)

January inspection findings and the following items of

'

interest

i a.

Random errors by Ebasco and Impell during walkdowns I

documented in recent inspection reports were discussed in r

i meetings with TU Electric and the contractors on

!

January 28.

The error rate was reported by TU Electric

.-

!

!

!

!

,

.

_

_ -.

.

.

.

_

-

_.

i

,,

-

i to be consistent with reinspection programs conducted at other nuclear plants.

b.

HVAC gasket material nonconforming condition report has progressed satisfactorily since the stop work was issued, i

,

i c.

TU Electric has committed to provide a supplemental

response to Inspection Report 50-445/8704; 50-446/8704.

d.

The program for resolution of ASME issues is progressing satisfactorily.

.

e.

NCRs are being generated faster than they are being

'

i closed out.

The NRC will be monitoring TU Electric's

progress over the next several months.

l f.

The NRC thinks tne responses to SDAR-Cp-83-08 and l

!

l Inspection Report 50-445/8432; 50-446/8413 need to be

supplemented.

A meeting to discuss the NRC's views will l

be held first week in February, i

g.

Response to NRC Compliance Bulletin 87-02 was lacking in

!

detail, h.

TU Electric stop work in the HVAC area was considered to be very responsive.

!

I An exit interview was conducted on February 2,

^88, with the applicant's representatives identified in paragraph 1 of this

-

report.

No written material was provided to the licensee by the resident inspectors during this reporting period.

The

!

licensee did not identify as proprietary any of the materials l

provided to or reviewed by the resident inspectors during this

inspection.

During this interview, the NRC inspectors f

rummarized the scope of the inspection.

t i

l

t f

i

!

l

<

i

!

)

I l

l

)

!

i

,

i i

,

,