IR 05000341/1985011

From kanterella
Jump to navigation Jump to search
Forwards Insp Rept 50-341/85-11 for Use in Ofc of Investigation Rept 3-84-019 Re Allegation on Cut Radiographs at Facility
ML20212K793
Person / Time
Site: 05000000, Fermi
Issue date: 03/25/1985
From: Weil C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Pawlik E
NRC OFFICE OF INVESTIGATIONS (OI)
Shared Package
ML20212J657 List:
References
FOIA-86-202 NUDOCS 8701290202
Download: ML20212K793 (1)


Text

/

,

s

_

4 gA taru UNITED STATES

+*

'g NUCLEAR REGULATORY COMMisslON

,

f

e(

REGIONlli 3-799 ROOSEVELT RO AD g

d,ee GLEN ELLYN, ILLINOt$ 60137

,5

%

.....

March 25, 1985

.

MEMORANDUM FOR:

E. T. Pawlik, Director, Office of Investigations Field Office, RIII FROM:

Charles H. Weil, Investigation and Compliance Specialist SUBJECT:

ALLEGATION RE:

CUT RADIOGRAPHS AT FERMI DOCKET NO. 50-341 (ATS NO. RIII-84-A-0175)

The enclosed Inspection Report is forwarded for the use by your staff in 01 Report No. 3-84-019.

-

Charles H. Weil (

Investigation and Compliance Specialist

Enclosure:

Inspection Report

No. 50-341/85-11

l

l

l

EXHIBIT 29

8701290202 870116

PDR

FOIA

CARDE86-202

/

PDR

i

.

. - -

-

?W

'

o

.s

hwy ( 191985

'

.

Docket No. 50-341

The Detroit Edison Company

ATTN:

Wayne H. Jens

Vice President

Nuclear Operr.tions

6400 North Dixie Highway

Newport, MI 48166

Gentlemen:

This refers to the routine safety inspection conducted by Messrs. P. D. Kaufman

and J. W. Muffett of this office on February 19-22 and March 4,1985, of

activities at Fermi Nuclear Power Plant, Unit 2, authorized by NRC Construction

Permit No. CPPR-87, and to the discussion of our findings with you and others

of your staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection.

Within these areas, the inspection consisted of a selective

cxamination of procedures and representative records, observations, and

l

interviews with personnel.

During this inspection, certain of your activities appeared to be in non-

compliance with NRC requirements, as specified in the enclosed Appendix.

A written response is required.

In a

REGION III==

Report No. 50-341/85011(DRS)

Docket No. 50-341

License No. CPPR-87

Licensee:

Detroit Edison Company

2000 Second Avenue

Detroit, MI 48224

Facility Name:

Enrico Fermi Nuclear Power Plant, Unit 2

Inspection At:

Enrico Fermi 2 Site, Monroe, Michigan

Inspection Dates:

February 19-22 and March 4, 1985

/

/

3 /f M

Inspectors-

. D. Kaufman

//

Date

jdh

3 e/e.s

.

J. W. Muffet

Date

k

_

Approved By:

D.

. Danielson, Chief

3 / 9!/f

Materials & Processes Section

Date'

Inspection Summary

Inspection on February 19-22 and March 4, 1985 (Report No. 50-341/85011(DRS))

Areas Inspected:

Routine, announced safety inspection to review licensee

action on IE Bulletin 79-02 and to review a reactor internal welds allegation.

The inspection involved a total of 63 inspector-hours by two NRC inspectors,

including 9 inspector-hours during offshifts,-and 10 inspector-hours of

in-office review.

Results:

In the areas inspected, two items of noncompliance were identified.

(Failure to take appropriate corrective action - Paragraph 2.b.(3); inadequate

design control - Paragraph 2.c.)

-

.

-.

-

-- -

-

.

DETAILS

1.

Persons Contacted

Detroit Edison Company (Deco)

  • W.

H. Jens, Vice President

  • 0. K. Earle, Supervisor / Licensing
  • J. E. Conen, Engineer / Licensing
  • F. Schwartz, Supervisor NQA
  • W. M. Street, Supervising Engineer / Civil
  • A. F. Colandrea, Principal Civil Engineer
  • J. F. Malaric, Supervisor / Field Engineering

G. M. Trahey, Director NQA

F. Agosti, Manager / Nuclear Operations

S. Noetzel, Assistant Man.ager, E.F.2.

  • Denotes those attending the onsite exit interview of February 22, 1985.

2.

Licensee Action on IE Bulletins

(Closed) IE Bulletin 79-02 (341/79-02-BB, 341/79-02-1B, 341/79-02-2B,

341/79-02-3B):

" Pipe Support Base Plate Designs using Concrete

Expansion Anchor Bolts."

a.

RIII Inspection Report No. 50-341/84-59 addresses certain remaining

open items to be accomplished by the licensee.

The following actions

were to be performed by the licensee:

(1) Verify that the as-built reconciliation stress report

loads have been accounted for in the reduced capacity

anchor qualification calculations.

(2) Perform an anchor bolt surveillance walkdown of the

drywell area.

l

(3) Demonstrate that the minimum anchor bolt spacing vio-

l

1ations observed during the NRC inspector's walkdown on

January 22, 1985 are fully QC documented, and that

qualification calculations account for the reduced

capacities of the anchor bolts.

(4) Compile the 885 Anchor Bolt Surveillance Reports (ABSRs)

generated by the Systems Completion Organization and all

necessary qualification calculations.

i

b.

The status of licensee actions regarding the above items was

determined to be as follows:

.

.

.

.

.

l

(1) A review of anchor spacing violation qualification cal-

'

culations revealed that the licensee has and is using

the latest as-built reconciliation stress report loads

in its evaluations.

l

i

(2) The licensee conducted an anchor bolt surveillance walk-

!

down of the drywell area on February 14 and 15, 1985.

'

The following supports were found which had minimum

expansion anchor spacing violations, but were neither

documented nor qualified:

l

l

  • T23-12837-39-G10
  • G33-3096-G30
  • B21-2587-G21

B21-2588-G06

T23-I2837-43-G37

T23-12837-39-G01

T23-12837-39-G38

  • 0bserved by the NRC inspector during a field walkdown

conducted on February 5, 1985.

The above supports have since been qualified and fully

documented.

No rework was required.

(3) The licensee was unable to provide adequate documentation

(

on the NRC inspector's observed anchor bolt spacing vio-

lations.

The licensee initiated a sample walkdown looking

for 50 apparent anchor spacing violations and determining

if the violations had been appropriately QC documented and

qualified as requested by the Region III office.

The

supports listed below, which were found that had anchor

spacing violations, were neither documented nor qualified:

  • P44-3368-G12A

P44-3368-G11

E11-3154-G10

G33-3244-G35

T50-7114-G39

The following support anchor spacing violations were

documented, but never technically qualified as acceptable

in any design calculations:

E41-3163-G14

T50-7432-G03

T50-7431-G07

  • E11-3178-G06
  • E11-3154-G20

E11-3152-G23

E51-3175-G30

W-P42-5242-G04

GWI-E21-7005-G05

_.

.

.

  • 0bserved by the NRC inspector during a review and

field walkdown on January 22, 1985.

Calculations have since been completed for the above

anchor spacing violations and confirm the acceptability

of the as-installed conditions.

l

The inspector, after reviewing the installation documen-

tation packages of these supports determined that the

majority of these concrete anchors were installed prior

to the licensee's March 1982 System Completion Organi-

t

zations (SCO) anchor violation surveillance walkdown.

The anchor violation surveillance program was conducted

to facilitate closure of the licensee's reported

March 26, 1981, 50.55(e) deficiency report, Item #42,

on this matter.

Upon completing their review and analyses of 885 Anchor

Bolt Surveillance Reports (ABSRs) generated by the SCO

groups walkdown of the site, without any deviations

requiring anchor relocation to achieve IE Bulletin 79-02

safety factors, the licensee submitted their final 50.55(e)

report, dated June 3, 1983.

This 50.55(e) report was

subsequently closed in Region III Inspection Report

No. 50-341/83-19.

However, this NRC inspection revealed

a significant amount of anchor bolt installations which

i

deviated from the minimum anchor design spacing require-

ments specified in DECO Project Specification 3071-226,

>

Revision F, Paragraph 3.3.3, that were neither documented

nor qualified.

Based on these findings, the inspector concludes that

the licensee did not take appropriate corrective action

regarding the reported 50.55(e) on the spacing of con-

crete anchors.

This constitutes an item of noncompliance

with Criterion XVI of 10 CFR 50, Appendix B (341/85011-01).

The following design deficiencies were noted by the NRC inspector

c.

while reviewing ABSR qualification calculations:

(1) The licensee lowered the average ultimate tensile loads

for Phillips Wedge anchor sizes 3/8",

1", and 1k", as,

indicated in DECO Project Specification 3071-226, Revision F,

Table 1-B.

This change constituted design evaluations to

verify the acceptability of anchors to the slightly lower

tensile loads.

However, these verifications were never

performed as evidenced by Stone and Webster's pipe support

calculation No. Z-E11-129, Revision 7, for support

E11-3154-620, which still shows the higher average ultimate

tensile loads being applied from Revision E of Specification

3071-226.

.. -

-.

.

.

-

- - -.

-.

. _ -

-_. _

-

-

.

.

l

~

.

-

i

.

(2) Specification 3071-226, Revision F, and Deco drawing

SC721-2002, Revision H. Note 11, requires that the Torque

and Tension Test Load be specified on the installation

.

drawing if a designer utilizes the higher tension loads

from Table 1-B of Specification 3071-226 in his calcu-

-

lations.

However, the installation drawings and all

'

applicable change documents relative to pipe support

l

E11-3154-G20 were reviewed by the NRC inspector and none

'

contained the required special installation torque and

tension note.

(3) Design Change Request (DCR) No. P-5299, Revision B,

reconciliation calculation prepared by DECO-Troy design

,

office on February 14, 1985, to resolve an anchor bolt

spacing violation utilized the incorrect higher tensile

load values from the superseded Revision E of Specifi-

cation 3071-226.

.

Failure to assure adequate control of design activities or methods

constitutes an item of noncompliance with Criterion III of

10 CFR 50, Appendix B (341/85011-02).

d.

To minimize the effects of expansion anchor bolt spacing violations,

the licensee has taken the following actions:

  • Utilized the concrete compressive test results and a

g

regression analysis to enable an increase in concrete

!

compressive strength (f'c) to 5900 psi.

Shear-tension interaction evaluations utilizing a "5/3

power."

Used a shear cone reduction method instead of the straight

line reduction method.

The licensee's utilization of the above data in anchor bolt spacing

assessments will result in no modifications or reduction in safety

!

factors.

3.

Allegation (RIII-84-A-175)

An allegation received by the Fermi 2 Safeteam on August 12, 1983,

concerning radiography of reactor internal welds was reported to the

NRC resident inspector as follows:

The NDE contractor was asked to

radiograph the field installed jet pump diffuser to adapter weld on

jet pumps #2, #7, #11, and #18.

Oversize film was used and the shop

tailpipe to diffuser weld was also inadvertently radiographed.

Upon

developing the film, a decision to trim the unwanted portion, which

included the tailpipe to diffuser weld, was made.

The inadvertently

radiographed tailpipe to diffuser weld contained indications of porosity.

',

l

l

4

.. -.,,,-,_.- - _.

, _ _ _ _, - -, - - _ -

_,. -... _, -.,.., -. - _ _ -,

,. - -

- - -.,., -. _,

- - -.,,..

.

___

= _.. =--

.

- _ ___

.

_ - -.

_-

.

?

.

,

.

The alleger stated that the film was trimmed to hide unacceptable

welding.

Subsequent to the initial allegation, the alleger also stated

that the diffuser to adapter weld also contained rejectable indications

of various types.

Concerning the inadvertently radiographed tailpipe to diffuser shop welds,

only dye penetrant and visual examinations are required.

The welds in

question have passed the required acceptance standards..To provide added

assurance regarding these welds, the radiographs of the tailpipe to

diffuser welds were evaluated by both the licensee and the NRC inspector

and found to be acceptable to the extent reviewed.

However, the bases

i

for acceptance of the tailpipe to diffuser welds are the dye penetrant

and visual examinations, not the inadvertent radiographs,

i

Concerning the allegation of rejectable indications of the radiographs

of the diffuser to adapter welds, an additional inspection was performed.

During this inspection, radiographs of these welds were reviewed and

l

rejectable indications were found.

The radiographs of these welds were

.

rejected by the licensee and referred to General Electric (GE) on

'

March 31, 1982.

GE decided that radiographic acceptance standards for

these welds were inappropriate.

GE performed a fracture mechanics

evaluation and determined that ultrasonic testing and dye penetrant

-

examination were appropriate in this instance.

The welds in question

are not pressure boundary welds and, therefore, the change in acceptance

standards was appropriate and is acceptable.

Ultrasonic testing and dye

,

{

penetrant examinations were performed and indications found by dye

penetrant were removed by grinding.

The bases for acceptance of the

diffuser to adapter welds are the dye penetrant examination, visual

!

examination, ultrasonic testing and the fracture mechanics evaluation.

The rejectable radiographs of the diffuser to adapter welds were reported

j

to the NRC as a 50.55(e) deficiency.

This item was closed in RIII

Inspection Report No. 50-341/82-09.

Also, the portion of the allegation

concerning the trimming of film was closed in RIII Inspection Report

No. 50-341/84-59.

The inspection substantiated the alleged cutting of the film and

j

substantiated the rejectable indications in the radiographs of the

diffuser to adapter welds.

However, neither the governing code nor

the applicable procedures were violated by the licensee or its agents.

Based on satisfactory completion of appropriate examinations and

resolution of the radiographic issue, these welds are acceptable.

This allegation is considered closed.

4.

Exit Interview

The inspectors met with licensee representatives (denoted in Paragraph 1)

at the conclusion of the onsite portion of the inspection and discussed

the scope and concerns of this inspection.

The inspectors also discussed

the likely informational content of the inspection report with regard to

documents or processes reviewed by the inspector during the inspection.

- -

. - - - -

_.

.. - -.

...... -. -.

.

- - -

. - -

-

- -

.

-

.

-.

.

.-

.. -

,..,,

-

.

The licensee did not identify any such documents / processes as proprietary.

Additional information was discussed telephonically with a licensee

representative on March 4, 1985.

%

e

t

i

!

i

'

.

. -

. -_--_ -__.,..,._...

..,, _. _ _ _ -, _

.

..

- - -.... -.

. -

. -

. -. - -

.

-

..