IR 05000341/2025001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000341/2025001
ML25132A227
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 05/12/2025
From: Sanchez-Santiago E
NRC/RGN-III/DORS/RPB2
To: Peter Dietrich
DTE Electric Company
References
IR 2025001
Download: ML25132A227 (1)


Text

SUBJECT:

FERMI POWER PLANT, UNIT 2-INTEGRATED INSPECTION REPORT 05000341/2025001

Dear Peter Dietrich:

On March 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Fermi Power Plant, Unit 2. On April 10, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as an NCV consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Fermi Power Plant, Unit 2.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Fermi Power Plant, Unit 2.

May 12, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Elba M. Sanchez Santiago, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000341 License No. NPF-43 Enclosure:

As stated cc: Distribution via LISTSERV Signed by Sanchez Santiago, Elba on 05/12/25

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Fermi Power Plant, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 7115

List of Findings and Violations

Safety-Related Control Air Relief Valve Lifts During Scaffold Construction Activity Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/202500101 Open/Closed

[H.5] - Work Management 71111.13 A self-revealed Green finding and associated non-cited violation (NCV) of Technical Specifications (TS) 5.4, Procedures, occurred when contact was made with the division 2 safety-related non-interruptible air system (NIAS) receiver relief valve during scaffold construction activities. The relief valve lifted and did not reseat, resulting in several supported safety-related systems being declared inoperable. Contrary to procedure MGA24, Human Performance Program and Field Worker Tools, workers failed to realize fall protection equipment could make contact with the relief valve.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000341/2024002-00 LER 2024002-00, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 71153 Closed

PLANT STATUS

Unit 2 began the inspection period at or near 100 percent power. On January 12, 2025, in response to spurious actuation of the east turbine bypass valve, power was lowered to approximately 85 percent power. Power was restored to 100 percent on January 13, 2025, following initial troubleshooting of the east turbine bypass valve and its subsequent removal from service. On February 14, 2025, power was reduced to approximately 70 percent for a routine rod pattern adjustment and surveillances. Power was restored to 100 percent on February 16, 2025, and remained there for the rest of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe cold weather on January 22, 2025.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Division 1 core spray system during division 2 maintenance, completed the week ending January 18, 2025
(2) High pressure coolant injection (HPCI) prior to reactor core isolation cooling (RCIC)maintenance, completed the week ending January 25, 2025
(3) Nitrogen bottle supply to hardened containment ventilation post-division II control air relief valve repairs, completed the week ending March 15, 2025

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

The inspectors evaluated system configurations during full walkdowns of the following systems/trains:

(1) The inspectors evaluated system configurations during a complete walkdown of the reactor core isolation cooling system, completed the week ending March 29, 2025.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Reactor building second floor north fire zone on January 23, 2025
(2) Reactor building second floor south fire zone on January 23, 2025
(3) Emergency diesel generator (EDG) 11 engine room, completed the week ending January 25, 2025
(4) EDG 12 engine room, completed the week ending January 25, 2025
(5) Reactor building CO2 cardox tank, compressor level, and pressure during cold weather, completed the week ending March 15, 2025

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an announced fire drill on January 23, 2025.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during power ascension from 83 percent to 100 percent following shutdown of the east turbine bypass valve unitized actuator on January 3, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated training in the control room simulator associated with a failed jet pump and loss of all reactor level indication on February 5, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Safety-related battery chargers, completed the week ending March 8, 2025
(2) Residual heat removal (RHR), and an in-depth review of capacitor, inverter, and relay replacement preventive maintenance (PM) frequencies, completed the week ending March 22, 2025
(3) Scheduling and execution of EDG maintenance activities in accordance with technical requirements, completed the week ending March 29, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Response to, and repair of, steam leak from the north reheater seal tank emergency drain piping, completed the week ending February 15, 2025
(2) Oil leak on 120 kV transformer 1, completed the week ending February 15, 2025
(3) Division 2 safety-related air receiver relief valve lift during scaffold-building activities, completed the week ending March 15, 2025
(4) Spurious opening of the east turbine bypass valve, completed the week ending March 15, 2025
(5) Elevated temperatures on fuses for 120VAC instrumentation power supply MPU3, completed the week ending March 29, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples 1 Partial)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) Division 2 control center heating ventilation and cooling (CCHVAC) lower chill waterflow, completed the week ending February 8, 2025
(2) Review of increased reactor water cleanup system leakage in terms of alternate source term dose assumptions, completed the week ending February 15, 2025
(3) RCIC flow switch past operability review, completed the week ending March 29, 2025 (4)

(Partial)

Degraded linkage pin associated with the HPCI pump governor valve

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (7 Samples)

(1) RCIC steam exhaust master trip unit perceived failure and subsequent functional testing on January 14, 2025
(2) Division 2 core spray safety system outage on January 22, 2025
(3) Reactor protection system (RPS) B agastat relay replacements on January 23, 2025
(4) EDG 12 auxiliary motor control center hot spot repair, completed the week ending February 1, 2025
(5) RCIC maintenance outage, completed the week ending February 22, 2025
(6) Preventative maintenance on breakers and mechanical components associated with the B mechanical draft cooling tower fan, completed the week ending March 15, 2025
(7) RPS A motor generator set replacement, completed the week ending March 22, 2025

Surveillance Testing (IP Section 03.01) (5 Samples)

(1) EDG 12 24-hour surveillance run on January 14, 2025
(2) Emergency equipment service water B heat exchanger differential pressure measurements, completed the week ending February 15, 2025
(3) Standby feedwater (SBFW) B test, completed the week ending February 22, 2025
(4) Division 1 emergency equipment cooling water testing, completed the week ending March 15, 2025
(5) Division 1 core spray pump and valve test, completed the week ending March 15, 2025

Inservice Testing (IST) (IP Section 03.01) (2 Samples)

(1) HPCI testing, completed the week ending February 28, 2025
(2) Low Pressure Coolant Injection (LPCI) testing, completed the week ending February 28, 2025

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) FLEX N and N+1 550 kW diesel generator full load test, completed the week ending March 29,

OTHER ACTIVITIES-BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 2 (January 1, 2024, through December 31, 2024)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)

(1) Unit 2 (January 1, 2024, through December 31, 2024)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

(1) Unit 2 (January 1,2024, through December 31, 2024)

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (1 Sample)

(1) Unit 2 (January 1, 2024, through December 31, 2024)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) A history of spurious nuclear steam supply shutoff system channel D signals for group 1 (main steam) isolation, most recently documented in CR202545091, completed the week ending March 15, 2025
(2) Design question regarding interaction of the core spray (CS) pump circuits with EDG load-shedding circuits, completed on March 24. 2025

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 2024002-00, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Plant Technical Specifications (ADAMS Accession No. ML24137A008). The issue involved a licensee-identified finding of very low safety significance associated with the initial operability determination. The results are documented in this report under Section 71153. This LER is Closed.

INSPECTION RESULTS

Safety-Related Control Air Relief Valve Lifts During Scaffold Construction Activity Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000341/202500101 Open/Closed

[H.5] - Work Management 71111.13 A self-revealed Green finding and associated non-cited violation (NCV) of Technical Specifications (TS) 5.4, Procedures, occurred when contact was made with the division 2 safety-related non-interruptible air system (NIAS) receiver relief valve during scaffold construction activities. The relief valve lifted and did not reseat, resulting in several supported safety-related systems being declared inoperable. Contrary to procedure MGA24, Human Performance Program and Field Worker Tools, workers failed to realize fall protection equipment could make contact with the relief valve.

Description:

On February 6, 2025, Work Order (WO) 950011441, Scaffold Support for WO 65211150 T82N455D, RBFD, RB Zone 4 Ionization Fire Detector Sensitivity Test, was being performed to build scaffold near the division 2 NIAS receiver tank to facilitate an upcoming surveillance for a fire detector near the ceiling of the room. While assembling upper levels of the scaffold, workers heard a noise and discovered valve P5000F223B, NIAS control air receiver P5002A002 relief valve, leaking. Operations staff were promptly informed and work was stopped. The division 2 NIAS supplies various safety-related division 2 systems, such as the reactor building to torus vacuum breakers, the standby gas treatment system (SGTS), and the control center heating, ventilation, and air conditioning (CCHVAC) systems.

Pressure in the system started to lower slowly as operations and mechanical maintenance staff arrived at the component location. Maintenance personnel attempted to manually operate the valve to get it to reseat but were unsuccessful. Operations staff elected to start the associated safety-related air compressor to maintain system pressure above the setpoints where compressors would auto-start and automatic isolations between safety and non-safety portions of the air system would occur. This was successful; however, approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> later, a high-temperature alarm was received for the running division 2 safety-related air compressor. Operations secured the air compressor and in accordance with the abnormal operating procedure for a loss of station and/or control air, opened the crosstie between the non-safety-related instrument air system and the division 2 NIAS. This restored and maintained pressure to the division 2 safety-related air loads until the relief valve was repaired later that evening.

No spurious actuations of equipment occurred; however, as a result of the above events, several TS action statements were entered for division 2 NIAS supported systems, including a 72-hour shutdown action for the reactor building to torus vacuum breakers, and 7-day shutdown actions for secondary containment (railway airlock door seal), SGTS, and CCHVAC. Following relief valve replacement, inspections and tests were performed on the division 2 control air compressor. No abnormalities were noted, and surveillance tests were completed satisfactorily. The machines are not expected to operate continuously while performing their safety functions, therefore the high aftercooler temperature was expected for the particular circumstances.

Work Order 950011441 directed the scaffold be constructed in accordance with numerous site procedures, including MGA24, Human Performance Program and Field Worker Tools.

Procedure MGA24 contains requirements and tools for personnel to use while performing work to prevent impacts to the plant. Specifically, Section 4.1.8 of MGA24 directs workers to use human performance tools rigorously, to anticipate problems and take precautions or countermeasures before and during activities individuals perform or supervise, and to watch for incorrect conditions or activities that can have an undesirable effect on plant performance.

To facilitate implementation of those steps, Appendix F of MGA24 describes tools to accomplish those steps, including questioning attitude/take two, which involves improving situational awareness at the jobsite to gain an accurate understanding of the work environment and hazards. The post-event licensee investigation documented in CR202545501 concluded that during scaffold construction, a workers fall protection equipment contacted the relief valve and caused it to lift. The cause documented was that a human performance tool was not properly used, specifically in terms of situational awareness and risk perception. The potential interaction of fall protection equipment and plant equipment was not recognized while assessing and performing work in the vicinity of the air receiver.

Corrective Actions: The relief valve was replaced, restoring the functionality of the division 2 NIAS.

Corrective Action References: CR202545497, CR202545501

Performance Assessment:

Performance Deficiency: The licensees failure to properly use a human performance tool, to recognize the potential interaction between fall arrest equipment and the relief valve during scaffold construction in accordance with MGA24, Human Performance Program and Field Worker Tools, was a performance deficiency that was within the licensees ability to foresee and correct, and the issue of concern should have been prevented.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Human Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, a safety-related valve was damaged, resulting in an abnormal operating procedure entry and several safety-related TS systems to be declared inoperable pending emergent repair work.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Specifically, all questions in Exhibit 2 for Mitigating Systems were answered no.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. Specifically, the nuclear safety risk associated with working around a passive component, such as a relief valve, was not apparent to the work group.

Enforcement:

Violation: Technical Specification Section 5.4 requires, in part, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978.

NRC Regulatory Guide 1.33, Revision 2, Appendix A, Section 9 addresses Procedures for Performing Maintenance and Section 9.a addresses maintenance that can affect the performance of safety-related equipment.

Since WO 950011441, Scaffold Support for WO 65211150 T82N455D, RBFD, RB Zone 4 Ionization Fire Detector Sensitivity Test, involved scaffold construction in close proximity to safety-related equipment, it involved maintenance that can affect the performance of safety-related equipment. and directed procedure MGA24, Human Performance Program and Field Worker Tools, to be followed as part of the scaffold construction activities. MGA24, Revision 14, issued April 3, 2023, has a stated purpose to address prevention and minimization of the adverse impact of human error on the physical plant. Procedure MGA24, Step 4.1.8 requires workers to, in part, anticipate problems and take precautions or countermeasures before and during activities individuals perform or supervise. Further, that workers watch for incorrect conditions or activities that can have an undesirable effect on plant performance.

Contrary to the above, on February 6, 2025, the licensee failed to implement a TS 5.4 required procedure. Specifically, the licensee did not implement Step 4.1.8 of procedure MGA24 to anticipate problems and take precautions or countermeasures before and during activities individuals perform or supervise. Further, the licensee did not watch for incorrect conditions or activities that can have an undesirable effect on plant performance. Specifically, while utilizing fall protection equipment in close proximity to safety-related relief valve P5000F223B while constructing scaffold, the licensee failed to recognize the equipment could contact the relief valve. As a result, an appropriate countermeasure was not instituted to prevent the relief valve from being actuated during the maintenance activity.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Licensee-Identified Non-Cited Violation 71153 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Technical Specifications (TS) Section 3.6.1.3, Primary Containment Isolation Valves (PCIVs), Limiting Condition of Operation (LCO) 3.6.1.3 states, Each PCIV, except reactor building-to-suppression chamber vacuum breakers, shall be operable.

TS LCO 3.6.1.3 Condition C states that if the following condition exists, One or more penetration flow paths with one PCIV inoperable except due to leakage not within limits then perform the required action to isolate the affected penetration flow path by use of at least one closed and de-activated automatic valve, closed manual valve, or blind flange in the required completion time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> for EFCVs and penetrations with a closed system.

A further required action states to verify the affected penetration flowpath is isolated with a required completion time of once per 31 days.

TS LCO 3.6.1.3 Condition E states that if the following condition exists, required action and associated completion time of Condition A, B, C, or D not met in Mode 1, 2, or 3, then perform the required action E.1 to Be in Mode 3 in the completion time of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, and perform the required action to Be in Mode 4 in the completion time of 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

Contrary to the above, from May 26, 2023, to March 19, 2024, the licensee failed to perform the required actions within the associated completion times of TS LCO 3.6.1.3 Conditions C and E. Specifically, on May 26, 2023, the licensee did not recognize valve E4150F042, high pressure coolant injection booster pump suction valve from the suppression pool, was inoperable when operators had to hold the close pushbutton down to make the valve close (versus one momentary push of the button). When identified by licensee staff on March 19, 2024, the appropriate TS LCO condition was entered, the valves circuit was repaired, and the TS LCO condition was subsequently exited.

Significance/Severity: Green. The finding was screened to Green under the barrier integrity and mitigating systems cornerstones using IMC 0609 App A, The Significance Determination Process for Findings AtPower. For barrier integrity, all questions in Exhibit 3, Section C, Reactor Containment, were answered no due to no actual open pathway in the physical integrity of the reactor containment. For mitigating systems, the Exhibit 2 screening questions in Section A were answered no due to no impact on the PRA functionality of the HPCI system.

Corrective Action References: CR202436970

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 10, 2025, the inspectors presented the integrated inspection results to P. Dietrich, Senior VP and Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Miscellaneous

X4103

Design Basis Document for the Residual Heat Removal

Complex Heating and Ventilating System

B

6M7312034

Diagram Core Spray System (CSS) Reactor Building

M2043

High Pressure Coolant Injection System Barometric

Condenser (HPCI) Reactor Building

AJ

M2044

Diagram Reactor Core Isolation Cooling System

M2045

Diagram RCIC System Barometric Condenser

AT

M57081

High Pressure Coolant Injection System Functional

Operating Sketch

M57082

HPCI Turbine Lube Oil/Control Oil Functional Operating

Sketch

L

M57091

RCIC System Functional Operating Sketch

Drawings

M57371

Hardened Containment Vent System for Standby Gas

Treatment Purge System Functional Operating Sketch

B

Miscellaneous

E21D2000039

Perform MOV Thermal O/L Test E2150F004B

(MCC 72F4A POS 4B). (C983)

01/14/2025

23.203

Core Spray System

23.203 Att. 1A

Core Spray System Division 1 Initial Valve Lineup

71111.04

Procedures

EF-PRA005.27

Containment Venting System Information Notebook

CR202444028

RB Cardox Level is LOOS Red Reading

11/29/2024

CR202544930

RB Cardox Compressor is Cycling On and Off

01/10/2025

Corrective Action

Documents

CR202545188

RB Cardox Issues

01/22/2025

M4548

Fire Protection Diagrams CO2, Halon & FM - 200 Systems

for Auxiliary Service, Radwaste, Security Diesel Generator

Buildings, Guardhouse and Security Building

S

M5050

Low Pressure CO2 Fire Protection System General

Schematic Arrangement

C

71111.05

Drawings

M57733

CO2, Halon & FM - 200 Systems for Auxiliary Service,

Radwaste, Security Diesel Generator Buildings, Guardhouse

and Security Building Functional Operating Sketch

N

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

FP-RB210a

Reactor Building Emergency Equipment Cooling Water,

North, Zone 10, EL. 613' 6"

FP-RB210b

Reactor Building, Emergency Equipment Cooling Water,

South, Zone 10, EL. 613' 6"

Fire Plans

FP-RB210c

Reactor Building, 2nd Floor Cable Tray Area, Zone 10,

EL. 613' 6"

Miscellaneous

LP-FP9401013

Fire Drill Guide/Evaluation: Main Turbine Generator TB3

FP-RHR111-

EDG

RHR Complex, EDG 11 Room, EL 590' 0"

FP-RHR112-

EDG

RHR Complex, EDG 12 Room, EL 590' 0"

Procedures

MOP23

Plant Storage

Work Orders

WO 950010300

Perform Fire Drill for Operations Shift Number 3

01/23/2025

Miscellaneous

SS-OP2022451

License Operator Requalification Simulation Lesson Plan

2.000.03

Power Operation 25% to 100% to 25%

108

Emergency

Procedure

Appendix B, Vol 2

Emergency Procedure Guidelines for Hot Conditions

71111.11Q

Procedures

EP101

RERP Pan Implementing Procedure: Classification of

Emergencies

27914

High Voltage Shutdown Card Failed on Battery Charger

2A12 R3200S020C During PM Testing

07/13/2022

CR 1928886

The As-Found Was Out of Tolerance. Adjusted Relays to

Acceptance Criteria

09/12/2023

CR 2024630

As-Found Testing Did Not Pass Acceptance Criteria

09/08/2023

CR202333588

E1150F016A Grade 3 and 4 Grease

10/08/2023

CR202437487

E11A-K067B HFA Relay Failed As-Found Testing

03/29/2024

CR202442192

Blown Fuse E41F2B in H21P081 Panel

09/12/2024

Cr-202442809

Load Bank Not Working Properly

10/09/2024

CR202442844

Phasing Balance Acceptance Criteria Unsat for 2A2 Battery

Charger

10/10/2024

71111.12

Corrective Action

Documents

CR202544897

10D68 Div II ESS 130V Battery 2PB Trouble

(2B1 Battery Charge)

01/09/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR202545366

Multiple Issues with EDG PM Events

01/30/2025

CR-202546155

Discrepancy in 35.307.010 Rev 30

03/11/2025

6SD7212530-10

One-Line Diagram 260/130V Ess. Dual Battery 2PA

Distribution Division I

AP

6SD7212530-11

One-Line Diagram 260/130V Ess. Dual Battery 2Pb

Distribution - Division II

EFA-E1116-004

Impact of Additional Containment Penetration Min-K on

ECCS Suction Strainer Design

A

Drawings

I220505

Schematic Diagram RHR Relay Logic B Circuit Part 1

Y

Miscellaneous

Residual Heat

Removal System

Health Report

Residual Heat Removal System Health Report

24

34.307.001

Emergency Diesel Generators - Inspection and Preventive

Maintenance

34.307.010

Emergency Diesel Fuel Injector Maintenance

35.309.010

Division 1, 130 Volt Battery Charger Testing, Calibration and

General Maintenance

Procedures

MMR Appendix E

Maintenance Rule SSC Specific Functions

44151708

Functional Testing Clean and Inspection of HFA Relay

E11A-K067B at H11P618

03/27/2024

44151943

Test E11A-K7B 125V HFA Relay in H11P618 RHR Logic B

04/16/2020

50171383

Inspect and Test Relays at Breaker Position 65E-E5

11/19/2019

57862577

Test Div. 1 130VDC Spare Battery Charger 2A12

2/03/2025

57862577

Test Div. 1 130VDC Spare Battery Charger

2A1207/05/2022

2314076

Perform 24-Month PM Tasks per 34.307.001 on Emergency

Diesel Generator 14

03/25/2025

Work Orders

67331003

Perform 44.030.252 ECCS Reactor Water Level 1, 2 and 8

Division 2 Channel B Functional

09/17/2024

Calculations

DC4931

Non-Interruptible Control Air System (NIAS) Calculations

04/12/2019

CR202444994

East Turbine Bypass Valve Spurious Opening

01/13/2025

71111.13

Corrective Action

Documents

CR202544778

N22-F413 (N Reheater Seal Tank EDL Valve) Leaking

01/01/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR202544865

NQA - Concerns on Weld Procedures Specifications Used to

Replace N22F413 in 2020

01/07/2025

CR202545182

Control Room Not Receiving Alarm from Transformer One

Low Oil

01/22/2025

CR202545400

Potential Electrical Hot Spot on MPU 3

2/01/2025

CR202545497

Div-2 NIS Receiver Relief Valve Failed Open

2/06/2025

Cr-202545501

Div. 2 CA P5000F223B Receiver Relief Valve Identified by

Crew Having Leak By During Scaffold Installation

2/06/2025

CR202545506

Div-2 Control Air Compressor-Loaded Run

2/06/2025

Cr-202545528

P5000F223B Failed As-Found Testing

2/07/2025

Drawings

6SD7212530-02

One-Line Diagram 120V AC Inst. & Cont. Power Feeders

BOP1 & BOP2 Reactor Building

AD

Engineering

Changes

250001

Online Leak Repair of N22F413

ACMP 25002

Adverse Condition Monitoring Plan - MPU 3

DBD: P5002,03

Design Basis Document: Control Air and Breathing Air

System

DER 961057

Notice 961057: Adequacy of the Control Air Compressor to

Perform their Function

08/29/1996

ODMI25001

East Turbine Bypass Valve Spurious Opening

01/13/2025

Miscellaneous

TSC 18191011

NIAS Operability and Compliance of Limiting Condition for

Operation

20.129.01

Loss of Station and/or Control Air

23.129

Station and Control Air System

25

23.129.01

Alternate Air Supply System

23.308

20V AC Instrument and Control Power System

24.129.01

Station and Control Air System Valve Operability Test

ARP 7D52

Division II Control Air System Trouble

EF2-PRA005.23

System Information Notebook: Compressed Air Systems

MES 90

Standard Design Process Interface

4.3

MGA 24

Human Performance Program and Field Worker Tools

Procedures

MMA 08

Scaffolding

2.1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

VMB114.1

Vendor Manual: Joy Manufacturing Class WGO9 5" Stroke

Oil Free Air Compressor

B

950008550

Repair Flange Gasket Containment Leak on XFMR 1

11/05/2024

Work Orders

950011441

Scaffold Support for WO 65211150 T82N455D, RBFD,

RB Zone 4 Ionization Fire Detector Sensitivity Test

01/28/2025

DC0758

CCHVAC System Chilled Water Pump Head

03/28/2016

Calculations

DC4321

Control Center Complex HVAC Cooling Heating Loads

Trend Only

27219

Suspect Leakage from RWCU Demin A Vessel

09/12/2016

28212

RWCU A Demin Pit Inspection Results

11/15/2017

1730418

Flange Face of Demin A Dome Needs Repair

2/27/2017

23545

E51N002 Barton HI/LOW Flow Switch Found Broken during

PM E830

06/24/2019

CARD 0721255

2007 RCIC Safety System Outage

03/03/2007

CARD 0728005

Revise Design Calculations to Support IST Criteria

(RHR/LPCI, CCHVAC, EECW MU)

2/13/2007

CARD 0828226

Request PM Deferral for Event E830 (WO 26004245)

2/09/2008

CARD 1021478

February 2010 RCIC SSO Work Lost

2/17/2010

CARD 1324395

AFCC 4 for E51N002 during PM E830

06/19/2023

CARD 1625792

E51N002 RCIC Pump Discharge Hi/Low Flow Switch Found

Broken (AFCC 2)

07/21/2016

CARD 1923545

E51N002 Barton Hi/Low Flow Switch Found Broken during

PM E830

05/07/2019

CARD 2320880

RCIC Discharge Pump D/P Switch As-Found Outside of

APT (AFCC 3)

2/01/2023

CR202330577

G3300F165A(RB4) Leak Contributing to Water on Floor on

RB3

06/28/2023

CR202442203

D076 Input Continues to Increase RWCU F/D A Vessel Leak

and/or Valve Leak Continues to Worsen

01/02/2025

CR202444477

TMTE240026 ERVR127: Prioritize Correction of Leakage

Reduction Program External Leak from RWCU

2/16/2024

71111.15

Corrective Action

Documents

CR202545084

Division 2 CCHVAC Chill Water Pump Flow Lower than

Expected

01/16/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR202545303

During Performance of WO 67010395, E51N002, the Low

Switch Never Changed States during Cal/Functional

01/18/2025

CR202545556

Tie Pin for HPCI Control Valve Rod Linkage Broke while

Disassembling

2/10/2025

CR202546070

Failure Analysis Findings for HPCI Pilot Valve Pin

03/06/2025

CR202545090

NRC Identified: Program Administrative Limit May Have

Been Exceeded

01/23/2025

Corrective Action

Documents

Resulting from

Inspection

CR202545196

NRC Identified - Page 11 of Most Recent Performance of

24.413.01 Section 5.2 Division 2 CCHVAC Chillwater Pump

and Valve Operability Test (WO 68215566) Missing from

Record

01/16/2025

6M7215710-2

Sump Pumps System Functional Operating Sketch

Drawings

M57362

Control Center A/C Water System Functional Operating

Sketch

S

IST Evaluation

17023

Revise CCHVAC Chillwater Pump IST Criteria

Engineering

Evaluations

TE-E4125-005

HPCI Past Operability-Pilot Valve Pin on Governor Oil Relay

and Linkage System

03/06/2025

24.206.01

RCIC System Pump and Valve Operability Test

24.413.01

Division 1 and 2 Control Center Chilled Water Pump and

Valve Operability Test

43.707.001

RWCU Leakage Monitoring Test

33A

Procedures

MES 28

Leakage Reduction and Primary Containment Leakage Rate

Programs

48000508

Clean and Lubricate External Portions of Control and Stop

Valves and Linkages

03/19/2019

68147634

NEIL REQD-Clean and Lube External Portions of Control

and Stop Valves

2/11/2025

Work Orders

215566

Perform 24.314.01 Section 5.2 Division 2 CCHVAC Chilled

Water Pump and Valve Operability Test

01/16/2025

CARD 0928198

Should EDGs be Considered Inoperable During Core Spray

Surveillance while the CS CMC Switches are in Run

10/20/2009

71111.24

Corrective Action

Documents

CR202441113

RPS MG Set A Grease

07/23/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR202444655

Division 2 EECW HX Service Water dP Lower than

Expected During ST 0135 Performed 12/11/2024

01/15/2025

CR202544802

2D5 Due to Gross Failure of E51N655B

01/03/2025

CR202544851

Infrared Identified Hot Spot Found in Advisory Range,

MCC 72EB2D Position 5A

01/06/2025

CR202544999

Unbalanced Live Loading Washers Found on Gland

Follower

01/13/2025

CR202545249

E5150F012 Does Not Easily Declutch into Hand Operation

01/27/2025

CR202545257

E51N006 Switch Out of APT

01/27/2025

CR202545262

Missed Bundling Opportunities for RCIC SSO Due to Lack of

Engineering Involvement in Readiness Meetings

01/27/2025

CR202545271

Degraded Friction on As-Found Trace for E5150F025

01/27/2025

CR202545273

RCIC SSO Work Delays

01/27/2025

CR202545278

Short Brush on Motor for E5101C003

01/27/2025

CR202545303

During Performance of WO 67010395 E51N002, RCIC

Pump Discharge HI/LO Flow Switch) the Low Switch Never

Changed States During Cal/Functional

01/28/2025

CR202545456

RPS MG Set A Exhibits Abnormal Noise After Replacement

2/04/2025

CR202545858

While Performing 24.208.02 Step 5.4.23, the Voltage From

The Temporary Differential Pressure Transmitter Installed

for P44-N444A was Below Those Listed in Enclosure C

2/24/2025

CR202546192

Request Update to PMs W689, W690, W691 and W692

03/12/2025

6M7215357

Emergency Equipment Cooling Water System Division II

6M721N2053

P&ID RHR Service Water System Division 2 RHR Complex

Drawings

M57291

Division I EECW Functional Operating Sketch

24.107.03

Standby Feedwater Pump and Valve Operability and Lineup

Verification Test

24.202.01

HPCI Pump and Valve Operability Test at 1025 PSIG

27

24.203.02

Division I Core Spray System Pump and Valve Operability

and Automatic Actuation

Procedures

24.204.06

Division II Low Pressure Coolant Injection and Suppression

Pool Cooling/Spray Pump and Valve Operability Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

24.205.10

Division 2 RHR Cooling Tower Fan Operability and RHRSW

Valve Line-Up Verification

24.207.08

Division I EECW Pump and Valve Operability Test

24.208.03

Division 2 EESW and EECW Makeup Pump and Valve

Operability Test

24.307.31

Emergency Diesel Generator Number 12 24-Hour Run

Followed by Hot Fast Restart

55158151

Perform 24.307.32 EDG12 24-Hour Run Followed by Hot

Fast Restart

01/06/2025

59896755

Inspect and Test Relay at Breaker Position 65E-E10

01/14/2025

60194452

Test 4160V Breaker 65F-F10

01/14/2025

60194461

Perform Test on Medium Voltage Breaker 65E-E10

01/14/2025

60904479

Perform MOV Thermal O/L Test-E2150F036B

01/14/2025

61739631

Inspect and Test 480 VAC MCC 72E5A Position 3D-R

01/14/2025

61750603

Inspect and Test 480 VAC MCC 72F4A Pos 4B

01/14/2025

290607

Perform Electrical and Mechanical Checks on Lubrication of

RPS MG Set A

2/07/2025

67332131

Perform 24.206.01 RCIC System Pump Operability and

Valve Test at 1000 PSIG

1108/2024

67332639

Perform 550kW North Diesel K1101S001A Full Load Test

887200

03/17/2025

67338833

Perform 550kW N+1 North Diesel K1101S001B Full Load

Test 887201

03/19/2025

67339658

Check Torque on Blade clamping Hardware Bolting, Clean

Blades, Lubricate MO

03/11/2025

67340023

Perform 24.208.03 D2 EESW Pump and Valve Operability

(SEC5.1)

08/20/2024

67340026

Perform 24.208.03 D2 EESW Pump and Valve Operability

(SEC 5.1)

2/01/2024

67761592

Replace RPS Channel B Reactor Vessel High Steam Line

Pressure Agastat Relay

01/22/2025

Work Orders

67761668

Replace RPS Channel B Main Steam Line Leak Agastat

Relays

01/23/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

67790553

Perform 24.206.01 RCIC System Pump Operability and

Valve Test at 1000 PSIG

01/31/2025

67878622

Perform 24.107.03 Section 5.3 SBFW Pump B Flow Test

2/07/2025

67906861

Perform 24.202.01 HPCI Pump Flow Test and Valve Stroke

at 1025 PSIG

2/12/2025

67967167

Perform 24.204.06 Division II Low Pressure Coolant

Injection and Suppression Pool Cooling Pump and Valve

Operability Test

2/19/2025

68028897

Perform 24.207.08 Section 5.1 Division I EECW Pump and

Valve Operability Test

2/25/2025

68101668

Perform 24.203.02 Section 5.1 Division I Core Spray System

Pump and Valve Operability

03/04/2025

68922454

Perform Test on 480V Breakers 72EC2A and 72EC2B.

Test Power Shields

03/11/2025

70637840

Perform 10 Year Motor Condition Inspection and Test

01/14/2025

950010281

Hot Spot at MCC 72EB2D Pos. 5A (Feeds EDG12 Auxiliary

Skid R1600S047)

01/28/2025

Perform NSSS-

RCIC Turbine

High Exhaust

Diaphragm

Pressure Division

Functional Test

Perform NSSS-RCIC Turbine High Exhaust Diaphragm

Pressure Division 2 Functional Test

01/03/2025

Corrective Action

Documents

CR202333564

WO Request to Repair Condenser Tubes for CW Leak

10/06/2023

Operating Data Report

01/2024 -

2/2024

24 Safety System Functional Failure Report

01/07/2025

Miscellaneous

ODMI23003

Condenser Tube Leak

71151

Procedures

20.125.02

Main Condenser Tube Leak

20892

NSSSS Half MSIV Isolation Signal

09/13/2023

2032278

Received Spurious Half MSIV Isolation

11/18/2020

71152A

Corrective Action

Documents

CARD 0928198

Should EDGs be Considered Inoperable During the Core

Spray Surveillances While the CS CMC Switches are in Run

10/20/2009

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR202545091

2036 - NSSSS Isolation Channel D Trip Came in Spuriously

2/14/2025

CR202545166

NSSSS Test Box Did Not Indicate Off as Expected in

6.4.11 (44.020.068)

01/22/2025

6I7212095-15

Schematic Diagram Nuclear Steam Supply Shut Off System

Trip System B

6I7212095-17

Schematic Diagram NSSSS System Main Steam Line

Inboard Isolation Valves B2103F022A, B, C & D

W

6I7212095-33

Schematic Diagram Nuclear Steam Supply Shut Off System

Trip System A and B

S

I221101

Schematic Diagram Core Spray Pump A E2101C001A

O

I221502

Elementary Diagram Core Spray System Relay Logic

Systems 1 and 2 and Relay Schedules

AE

I257228

Schematic Diagram 4160V ESS Buses 64B and 64C

Load-Shedding Strings

V

I271425

EDG Loading Sequence List Division I EDG #11 and #12

L

SD250003

One-Line Diagram 4160V System Service Buses 64B and

64C

S

SD254803

Internal Schematic Diagram ITE Circuit Breaker K-Line Type

480 Switchgear

E

Drawings

SD254804

Internal Schematic Diagram ITE Circuit Breaker Type

5HK350 and -250 4160V Switchgear

C

Engineering

Evaluations

50.59 Screen

50.59 Screen for Core Spray System Procedure Change

2/31/2009

ERE 33991

Agastat Relay Equivalency Evaluations

06/14/2006

ODMI20007

Spurious NSSSS Channel D Isolation Signal

ODMI25002

Spurious NSSSS Channel D Isolation Signal

Miscellaneous

VMR13.6

Amerace (Agastat) Control Relays

E

44.020.438

NSSSS - Turbine Building Area Temperature Trip System B,

Channel D B21-N616D Calibration/Functional

Procedures

ARP 2D36

NSSSS Isolation CH B/D Trip

59463857

Troubleshoot/Repair Spurious NSSSS ISO Logic Chanel D

Trip (ODMI Action 2032336-09)

04/05/2022

Work Orders

65902308

Replace HFA Relay A71B-K10D at Panel H11P611

08/01/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

65915792

Replace Agastat Relay C7100M222D and Inspect and if

Required Replace Relay Base

09/14/2022

71153

Procedures

IST Program

Valve Basis

Fermi Unit 2 IST Program Valve Basis

3