B12567, Informs NRC of Change in Mgt Structure Effective 870701 So That All NRC Mailing Lists May Be Revised Accordingly

From kanterella
Jump to navigation Jump to search
Informs NRC of Change in Mgt Structure Effective 870701 So That All NRC Mailing Lists May Be Revised Accordingly
ML20234D768
Person / Time
Site: Millstone, Haddam Neck, 05000000
Issue date: 06/29/1987
From: Mroczka E
CONNECTICUT YANKEE ATOMIC POWER CO., NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
B12567, NUDOCS 8707070333
Download: ML20234D768 (2)


Text

- - _ _ _ _ _ - - - - _ . - . _ _ _ - - - _--__ _

MEAST UTILITIES cenerai offices . seiden street. Bernn. Connecticut .

l U5[NaIN I sI EcNE

.o m ww.<;ma cc"*^*

P.O. BOX 270 HARTFORD. CONNECTICUT 06141-0270 L L J CZ ((M,'$*,', (203) 665-5000 June 29,1987 Docket Nos. 50-213 50-245 50-336 50-423 B12567 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 Gentlemen:

Haddam Neck Plant Millstone Nuclear Power Station, Unit Nos.1,2 and 3 Management Change In the near future, a change will take place in our management structure. The purpose of this letter is to inform the NRC Staff of this change so that all NRC mailing lists may be revised accordingly. The following change will become effective July 1,1987.

o Donald O. Nordquist, currently Manager of Quality Assurance, will become Director of Quality Services Department.

The establishment of the Quality Services Department reflects a reorganization of the current Quality Organizations at the Haddam Neck Plant, Millstone Nuclear Power Station, Generation Construction Department, and Northeast Utilities Service Company (NUSCO).

Mr. Nordquist currently receives copies of all correspondence for Northeast Utilities, Connecticut Yankee Atomic Power Company and Northeast Nuclear Energy Company. Effective July 1,1987, correspondence should be directed to Donald O. Nordquist, Director of Quality Services.

We will initiate technical specification changes in the near future to revise our unit organization charts for all four nuclear plants, accordingly.

If any questions arise as a result of this change, please feel free to contact my staff.

Very truly yours, CONNECTICUT YANKEE ATOMIC POWER COMPANY NORTHEAST NUCLEAR ENERGY COMPANY n . /

WJ#Mroczka a Sento'r Vice ident Pres // &

8707070333 870629 PDR ADOCK 05000213 PDR yy 10

U.S. Nuclear Regulatory Commission B12567/Page 2 June 29,1987 cc: W. T. Russell, Region 1 Administrator M. L. Boyle, NRC Project Manager, Millstone Unit No. I D. H. Jaffe, NRC Project Manager, Millstone Unit No. 2 R. L. Ferguson, NRC Project Manager, Millstone Unit No. 3 F. M. Akstulewicz, NRC Project Manager, Haddam Neck Plant T. Rebelowski, Resident Inspector, Millstone Unit Nos. I and 2

3. T. Shediosky, Resident Inspector, Millstone Unit No. 3 P. D. Swetland, Senior Resident Inspector, Haddam Neck Plant I

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - -