ML111610249

From kanterella
Revision as of 11:45, 6 April 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
IR 05000282-11-010 & 05000306-11-010; on 05/13/21011 - 05/20/2011; Prairie Island Nuclear Generating Plant, Units 1 and 2, Other Activities
ML111610249
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 06/09/2011
From:
Division Reactor Projects III
To: Schimmel M A
Northern States Power Co
References
EA-11-110 IR-11-010
Download: ML111610249 (20)


See also: IR 05000282/2011010

Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 9, 2011 EA-11-110

Mr. Mark A. Schimmel Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company, Minnesota 1717 Wakonade Drive East Welch, MN 55089 SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2, NRC INSPECTION REPORT 05000282/2011010; 05000306/2011010 PRELIMINARY WHITE FINDING Dear Mr. Schimmel: On May 20, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Prairie Island Nuclear Generating Plant, Units 1 and 2. The enclosed report documents the results of this inspection, which were discussed on May 20, 2011, with you and other members of your staff. The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. This report documents a finding for Unit 1 that has preliminarily been determined to be White or a finding with low-to-moderate increased safety significance. In addition, this same finding was preliminarily determined to be Green, a finding of very low safety significance, for Unit 2. As documented in Section 4OA5 of this report both trains of safety-related battery chargers were not capable of performing their safety function from initial installation in 1994 due to being susceptible to failure during certain design basis events. This finding was assessed based on the best available information, including influential assumptions, using the applicable Significance Determination Process (SDP).

Upon identification of this issue and after interaction with the NRC, you concluded that a designated operator position needed to be established to ensure that a specific individual could perform actions to recover the battery charger(s) prior to the safety-related batteries being

M. Schimmel -2- depleted. Lastly, during your past operability review you concluded that there was reasonable doubt that the battery chargers would have performed their safety function if called upon prior to October 22, 2010, (the date the designated operator position was established). Because of the compensatory actions taken, no current safety concern exists. This finding is also an apparent violation of NRC requirements and is being considered for escalated enforcement action in accordance with the NRC Enforcement Policy. The current Enforcement Policy can be found at the NRC's Web site at http://www.nrc.gov/reading-rm/doc-collections/enforcement. In accordance with Inspection Manual Chapter (IMC) 0609, we intend to complete our

evaluation using the best available information and issue our final determination of safety significance within 90 days of the date of this letter. The SDP encourages an open dialogue between the NRC staff and the licensee; however, the dialogue should not impact the timeliness of the staff's final determination. Before the NRC makes its enforcement decision, we are providing you an opportunity to either: (1) present to the NRC your perspectives on the facts and assumptions used by the NRC to arrive at the finding and its significance at a Regulatory Conference, or (2) submit your position on the finding to the NRC in writing. If you request a Regulatory Conference, it should be held within 30 days of the receipt of this letter and we encourage you to submit supporting documentation at least one week prior to the conference in an effort to make the conference more efficient and effective. If a conference is held, it will be open for public observation. The NRC will also issue a press release to announce the conference. If you decide to submit only a written response, such submittal should be sent to the NRC within 30 days of the receipt

of this letter. If you decline to request a Regulatory Conference or to submit a written response, you relinquish your right to appeal the final SDP determination; in that, by not doing either you fail to meet the appeal requirements stated in the Prerequisite and Limitation Sections of Attachment 2 of IMC 0609. Please contact John Giessner at (630) 829-9619 in writing within 10 days of the date of this letter to notify the NRC of your intended response. If we have not heard from you within 10 days, we will continue with our significance determination and enforcement decision. The final resolution of this matter will be conveyed in separate correspondence. Since the NRC has not made a final determination in this matter, no Notice of Violation is being issued for this inspection finding at this time. Please be advised that the number and characterization of the apparent violation described in the enclosed inspection report may

change as a result of further NRC review.

M. Schimmel -3- In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely, /RA/

Steven West, Director Division of Reactor Projects Docket Nos.: 50-282; 50-306;72-010 License Nos.: DPR-42; DPR-60; SNM-2506 Enclosure: Inspection Report 05000282/2011010; 05000306/2011010 w/Attachment: Supplemental Information cc w/encl: Distribution via ListServ

Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION III Docket Nos: 50-282; 50-306;72-010 License Nos: DPR-42; DPR-60; SNM-2506 Report Nos: 05000282/2011010; 05000306/2011010 Licensee: Northern States Power Company, Minnesota Facility: Prairie Island Nuclear Generating Plant, Units 1 and 2 Location: Welch, MN Dates: May 13 through 20, 2011 Inspectors: K. Stoedter, Senior Resident Inspector P. Zurawski, Resident Inspector C. Brown, Reactor Engineer L. Kozak, Senior Reactor Analyst Observer: S. Lynch, Nuclear Safety Professional Development Program Participant Approved by: John B. Giessner, Chief Branch 4 Division of Reactor Projects

Enclosure TABLE OF CONTENTS SUMMARY OF FINDINGS ......................................................................................................... 1 4. OTHER ACTIVITIES .................................................................................................... 3 4OA3 Follow-Up of Events and Notices of Enforcement Discretion (71153) ............. 3 4OA5 Other Activities ............................................................................................... 3 4OA6 Management Meetings ................................................................................... 9 SUPPLEMENTAL INFORMATION ............................................................................................. 1 Key Points of Contact ............................................................................................................. 1 List of Items Opened, Closed and Discussed ......................................................................... 1 List of Documents Reviewed .................................................................................................. 1 List of Acronyms Used ............................................................................................................ 4

1 Enclosure SUMMARY OF FINDINGS IR 05000282/2011010; 05000306/2011010; 05/13/21011 - 05/20/2011; Prairie Island Nuclear Generating Plant, Units 1 and 2; Other Activities. This report covers the review of a potential common cause failure of the safety-related battery chargers. The inspectors identified one apparent violation (AV) with a preliminary significance of White for Unit 1 and a preliminary significance of Green for Unit 2. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance Determination Process" (SDP). Findings for which the SDP does not apply may be Green or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 4, dated December 2006. A. Cornerstone: Mitigating Systems NRC-Identified and Self-Revealed Findings Preliminary WhiteThis finding was determined to be more than minor because it was associated with the design control and equipment performance attributes of the Mitigating Systems Cornerstone. In addition, this performance deficiency impacted the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors performed a Phase 1 SDP evaluation and determined that a Phase 2 evaluation was required

because this finding represented an actual loss of safety function of a single train of equipment for greater than the TS allowed outage time. The inspectors performed a Phase 2 evaluation using the pre-solved SDP worksheets for Prairie Island and determined that this finding screened as Red. A Phase 3 SDP evaluation was required to assess reasonable credit for recovery by operators. The results of the Phase 3 SDP evaluation showed that this finding was preliminarily determined to be White for Unit 1, and Green for Unit 2. No cross-cutting aspect was assigned to this finding because licensee decisions made in regards to evaluating the performance of the battery chargers were made many years ago and therefore, not reflective of current plant performance. (Section 4OA5.1) . An apparent violation of Technical Specification (TS) 3.8.4 was identified by the inspectors due to the licensee's failure to maintain the train A and

train B direct current electrical power subsystems operable while operating the reactor in Modes 1 through 4. Specifically, the licensee installed safety-related battery chargers which were susceptible to failure during certain design basis events. This issue was entered into the licensee's corrective action program (CAP) as CAP 1250561. Upon identifying this issue, the licensee performed an operability evaluation and determined that the battery chargers remained operable because procedures were in place to recover the battery chargers if a failure occurred. After further interaction with the NRC, the licensee concluded that a designated operator position needed to be established to ensure that a specific individual would perform the battery charger recovery actions prior to the safety-related batteries being depleted. Long term corrective actions included replacing all four battery chargers.

2 Enclosure B. No violations of significance were identified. Licensee-Identified Violations

3 Enclosure REPORT DETAILS 4. OTHER ACTIVITIES 4OA3 Follow-Up of Events and Notices of Enforcement Discretion.1 (71153) a. (Closed) Licensee Event Report 05000282/2010-004: Battery Charger Inoperability due to Potential Undervoltage Conditions The inspectors reviewed the licensee's response to discovering that safety-related battery chargers installed in 1994 were susceptible to failure during certain design basis accidents. Specifically, these battery chargers had the potential to stop providing an output, or "lock-up," if their alternating current input voltage dropped below the nameplate minimum voltage of 90 percent at the battery charger motor control center (MCC). This item was documented as an unresolved item in NRC Inspection Report 05000282/2010005; 05000306/201005. Documents reviewed during this inspection are listed in the Attachment to this report. Inspection Scope This event follow-up review constituted one sample as defined in Inspection Procedure 71153-05. b. See Section 4OA5.1 below for a discussion of this issue. Findings 4OA5 .1 Other Activities a. (Closed) Unresolved Item 05000282/2010005-05; 05000306/2010005-05: Potential for Common Mode Failure of Safety-Related Battery Chargers The inspectors reviewed the circumstances surrounding the licensee's failure to maintain the both direct current (DC) electrical power subsystems operable during reactor operation in Modes 1 through 4. Inspection Scope b. Findings IntroductionDescription: In NRC Inspection Report 05000282/2010005; 05000306/2010005, the NRC documented several issues regarding the safety-related battery chargers, specifically with the 12 battery charger "locking up" during a simulated loss of offsite power (LOOP) event concurrent with a simulated loss of coolant accident (LOCA). In the same inspection report, the NRC opened an unresolved item to address the potential for a common mode failure of all of the safety-related battery chargers. : An apparent violation of Technical Specification (TS) 3.8.4, "DC Sources - Operating," was identified by the inspectors due to the licensee's failure to maintain both DC electrical power subsystems operable during reactor operation in Modes 1 through 4.

4 Enclosure The inspectors reviewed the licensee's evaluation of the potential for a common mode failure. The evaluation contained information that the safety-related battery chargers had the potential to stop providing an output, or "lock-up", if the input alternating current (AC) voltage dropped below the nameplate minimum voltage of 90 percent of 480 Volts at the battery charger motor control center (MCC). Specifically, the NRC learned that the lock-up of the battery charger was related to the operation of the silicon controlled rectifiers (SCRs) on the battery charger control circuitry. As a low voltage condition occurred in response to the simulated LOOP/LOCA, the firing angle of the SCRs advanced to maintain output voltage. If the firing angle advanced too far on a low voltage condition, the control circuitry became reverse biased and unable produce any

output. The licensee was unable to determine the exact voltage, the duration of voltage dip, and the battery charger loading conditions which caused the lock-up to occur. In reviewing plant data from the periodic LOOP/LOCA tests, the inspectors determined that at certain points in the loading sequence the input voltage to the battery chargers decreased to less than 90 percent, the design minimum, for all four chargers (two on Unit 1 and two on Unit 2). In addition, the licensee further determined that the LOOP/LOCA tests did not include all possible loads, including the 121 motor-driven cooling water pump, and other loads such as an instrument air compressor. These loads could further decrease 480V bus voltage and contribute to the battery charger locking up. On October 22, 2010, the licensee completed an operability evaluation and concluded that the chargers could be considered operable but non-conforming if compensatory measures were put in place. These compensatory measures included revising abnormal and emergency operating procedures, placing copies of needed abnormal operating procedures and tools needed within the battery charger rooms, and establishing a specific designated operator (with no other duties) to perform the manual actions needed

to recover the battery chargers if needed. At the end of 2010, the licensee completed a past operability review of the safety-related battery chargers and concluded that there was reasonable doubt that the chargers would have performed their safety function if called upon during specific design basis accidents. This was documented in LER 2010-004-00 submitted at the end of January 2011. As a result, the inspectors concluded that the DC electrical power subsystems (specifically the safety-related battery chargers) had been inoperable since their initial installation in December 1994. In May 2011, the licensee replaced and tested both Unit 1 battery chargers. The licensee planned to replace the Unit 2 battery chargers during the next refueling outage. The licensee's compensatory actions remain in place for Unit 2. Analysis: The inspectors determined that the licensee's failure to ensure that the DC electrical power subsystems remained operable during reactor operation in Modes 1 through 4 was a performance deficiency that required an evaluation using the Significance Determination Process (SDP) described in NRC Inspection Manual Chapter (IMC) 0609. The inspectors also determined that this finding should be assigned to the Mitigating Systems Cornerstone because it impacted systems used in short term and long term heat removal. The inspectors performed a Phase 1 SDP analysis and concluded that the finding represented the actual loss of safety function of

5 Enclosure a single train for greater than its TS allowed outage time which required a Phase 2 SDP evaluation. The Phase 2 SDP result was potentially greater than very low safety significance. The exposure time was assumed to be 1 year since the battery chargers have been susceptible to failure since they were installed. For the SDP, the initiating events that could result in one or more battery charger failures were determined to be those events where input AC voltage at the battery charger MCC would be less than 90 percent and charger output demand would be high. These initiating events were any non-station blackout (SBO) LOOP event and any event that resulted in a safety injection (SI) signal. These events included small LOCAs, medium LOCAs, large LOCAs, stuck-open power operated relief valves (PORVs), a steam generator tube rupture (SGTR), and a main steam line break. The pre-solved SDP worksheets modeled the "Train A" or 11 battery charger. Consistent with the SDP usage rules defined in IMC 0609A, "Determining the

Significance of Reactor Inspection Findings - At Power," the pre-solved worksheet assumed that a finding involving a battery charger would increase the Loss of DC initiating event frequency. However, this finding only involved failure of the battery charger in response to specific initiating events and would not increase the Loss of DC initiating event frequency. Therefore, the worksheets were individually solved assuming

that one train of mitigating equipment would be failed as a result of a battery charger failure. A recovery credit of "1" was applied in all sequences because recovery of the battery charger was possible. The dominant sequence was a LOOP, a failure of all auxiliary feedwater, and the failure of feed and bleed. A Region III Senior Reactor Analyst (SRA) conducted a Phase 3 SDP evaluation to provide a more realistic estimate of the change in core damage frequency (CDF) for the finding. Similar to the Phase 2 SDP evaluation, the exposure time was 1 year and the initiating events that could result in one or more battery charger failures was assumed to be either a non-SBO LOOP event or an event that resulted in an SI signal. Loss of coolant accidents and SGTR were considered to be the events that would result in an SI signal. The Standardized Plant Analysis Risk (SPAR) model for Prairie Island, Revision 8.15, was used in the evaluation. The SPAR model represents Prairie Island Unit 1 only, so the results of the Unit 1 evaluation were generally assumed to be applicable to Unit 2. The model was modified to (1) require battery charger operation for DC system success in non-SBO events because the safety-related batteries cannot function for the entire 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> mission time and (2) to account for the potential for common cause failure (CCF) of the battery chargers. The model was solved assuming one charger would fail in response to the applicable initiating events and the opposite

train charger had the potential to fail. The dominant cut-sets were reviewed and the potential for recovery of the failed battery charger was evaluated and applied at the sequence level. The inspectors performed a review of the licensee's abnormal operating procedures and

determined that a locked-up charger could be recovered by locally turning the charger off and then turning it back on. However, the operators would be required to diagnose that the charger had locked-up and to restart the charger prior to the safety-related battery depleting. The DC battery depletion times for each of the batteries were variable

due to loading differences. In addition, the depletion times were uncertain due to assumptions regarding operation of equipment in response to initiating events.

6 Enclosure In general, the battery life estimates for the Unit 1 batteries were shorter than Unit 2 batteries in non-SBO LOOP events, due to differences in battery loading. Also, for both units, the battery life for non-LOOP events was generally longer because AC power was available to carry emergency lighting loads. NUREG/CR-6883, "The SPAR-H Human Reliability Analysis Method," was used to estimate the human error probability (HEP) for the failure to recover a battery charger prior to safety-related battery depletion. For this HEP, the SRA considered both diagnosis and action failures but determined that diagnosis was the dominant failure

mode. In response to LOOP events, the only performance shaping factor (PSF) that

was considered a "performance driver" was stress. During this event operators would be receiving many alarms in the control room and would have a high workload in responding to the event. The initial alarm indicating battery charger failure received in the control room would be "DC System Trouble." The alarm response procedure instructed operators to check the "DC Panel Undervoltage" alarm and if it was also lit to proceed to Abnormal Operating Procedure 1C20.9 AOP3 or 1C20.9 AOP4, "Failure of 11(12) Battery Charger." The inspectors and the SRA determined that the "DC System Trouble" alarm would be expected to come in during LOOP events even if the battery

charger functioned properly. After some period of time, with all equipment functioning normally, the alarm would clear. If the battery charger failed to function, the alarm would remain lit. The SRA considered that during an event, operators would likely prioritize other alarms associated with the initiating event and other potential complications before attending to the "DC System Trouble" alarm. Once operators entered the Abnormal Operating Procedure (AOP), an operator in the plant would record data associated with the DC system in the battery charger room in order to determine that one or more battery chargers had locked up. Once diagnosis had occurred, the operator would reset the charger by opening the input breaker, waiting 10 seconds, and then closing the input

breaker. Stress was considered to be "high" given that the dominant sequences involved a complicated LOOP. All other PSFs were considered nominal. The SRA also concluded that procedures existed for resetting the battery charger(s) and that adequate time existed for diagnosis and action. Based upon this information, the SRA estimated an HEP for failure to recover the battery charger as 2.2E-2 for most LOOP sequences on Unit 1. For all other events, (LOCAs and SGTRs, Unit 2 LOOP events, and Unit 1 LOOP events that do not involve failures other than battery charger failures) the SRA also considered "time available" to be a performance driver. For these events, the licensee's battery depletion calculations showed that much more time was available for operator to respond to a locked up battery charger(s) prior to safety-related battery depletion. Therefore, "extra time" was considered for diagnosis of the condition. The HEP for failure to recover a battery charger in these scenarios was estimated to be 2.2E-3. After reviewing the cut-sets, the SRA determined that for certain LOOP events, recovery of offsite power within the battery depletion time would also mitigate the event by allowing power to be restored to the train that was unaffected by a failed battery charger. To account for this, the SRA applied a factor to the applicable Unit 1 LOOP sequences

that represented the probability that the LOOP event exceeds 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. This value was obtained from NUREG/CR-6890, "Reevaluation of Station Blackout Risk at Nuclear Power Plants," Table 3-3. The value is the composite probability of exceedance for all categories of LOOP events. For Unit 2 LOOP sequences, a factor that represented the probability that the LOOP event exceeded 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> was used.

7 Enclosure The SRA determined that the risk contribution from seismic events and internal flooding events for this finding was negligible. For internal fire events, the SRA used the licensee's Individual Plant Examination of External Events (IPEEE) to consider fire-induced LOOP scenarios and concluded that there was a small contribution to the risk of the finding from Unit 2 fire scenarios. The potential risk contribution to large early release frequency (LERF) was evaluated using IMC 0609 Appendix H, "Containment Integrity Significance Determination Process." Prairie Island is a 2-loop Westinghouse pressurized water reactor with a large dry containment. Sequences important to LERF included SGTR events and inter-system LOCA events. These were not the dominant core damage sequences for this finding and thus the risk significance due to LERF was evaluated to be of very low safety significance. The total delta CDF for Unit 1 was estimated as 1.9E-6/yr and for Unit 2, 5.2E-7/yr. This represented a preliminary White finding for Unit 1 and a preliminary Green finding for Unit 2. The dominant core damage sequence cut-set for Unit 1 was a LOOP event followed by common cause failure of the battery chargers and the failure to recover a battery charger. Other important cut-sets involved a LOOP event, failure of a single battery charger, and failure of the opposite train emergency AC power sources. The Unit 2 results were dominated by the fire contribution which was not fully developed since the initial estimates for total delta CDF, including the fire contribution, were less than 1.0E-6/yr. The SRA reviewed a risk evaluation performed by the licensee for this finding. The licensee concluded that the delta CDF for both units was less than 1.0E-6/yr (Green). The major differences between the NRC's SDP evaluation and the licensee's risk assessment were HEPs estimated for failing to recover a battery charger and the assessment of the potential for common cause failure of both chargers on a single unit. Both evaluations considered the potential for recovering a charger; however, the licensee's HEP estimate was more optimistic than the NRC's. The NRC believes the potential for operators to miss or misinterpret the alarms during diagnosis of the failed charger was higher than estimated by the licensee. With regard to the common cause failure potential, the licensee assumed that both battery chargers on a single unit could not lock-up in response to the same initiating event. The NRC concluded that since all the battery chargers were of the same design and would be modeled as part of the same common cause component group in a PRA model, that it was appropriate to treat the potential for common cause failure of both battery charger trains probabilistically, consistent with the "failure memory approach" used in NRC risk assessments. In the risk assessment of inspection findings, the "failure memory approach" models observed successful components as having a probability of failure rather than concluding that the component would

always be successful. The results of the SDP evaluation were sensitive to both assumptions on recovery and common cause failure and therefore, the NRC performed sensitivity evaluations to

vary the "best-estimate" assumptions. In particular, the NRC considered higher probabilities of common cause failure due to concerns that the actual potential for common cause failure was under-represented by SPAR model. The sensitivity evaluations varied the battery charger common cause failure probability and the human error probabilities used the analysis. The results of the sensitivity evaluations were generally higher than the "best-estimate" SDP evaluation but overall supported the preliminary conclusion of a White finding for Unit 1 and a Green finding for Unit 2.

8 Enclosure Inspection Manual Chapter 0305, "Operating Reactor Assessment Program," Section 12.01, states that the NRC may refrain from considering safety significant inspection findings in the assessment program for a design-related finding in the engineering calculations or analysis, associated operating procedure, or installation of plant equipment if the following statements were true: Old Design Issue Review The issue was licensee-identified as a result of a voluntary initiative such as a design basis reconstitution; The performance issue was or will be corrected within a reasonable period of time following identification; The issue was not likely to have been previously identified by routine efforts such

as normal surveillance or quality assurance activities; and The issue does not reflect a current performance deficiency associated with existing licensee programs, policy or procedures. Based upon the information provided above, the inspectors have determined that this

finding did not meet the criteria to be considered an old design issue for the following reasons: The finding was not licensee-identified as a result of a voluntary initiative. Although the licensee initiated a CAP document in late September 2010 regarding the possibility of charger lock up during grid voltage fluctuations, NRC prompting was needed and specifically requested during the October 2010 exigent TS change discussions to ensure that the licensee addressed the

susceptibility of all chargers to a lock-up condition during other design basis accidents. The failure of the battery chargers to operate as expected following a design basis event was first discovered in 1996 during the performance of testing which simulated a LOOP/LOCA event. However, the licensee failed to recognize the significance of this issue and dispositioned the item as "use as is." As a result, the issue was not corrected within a reasonable period of time. The finding was likely to be identified by past activities such as surveillance testing. Specifically, the licensee was unable to successfully perform the simulated LOOP/LOCA test following the 1994 battery charger installation. After performing at least two additional LOOP/LOCA tests which resulted in the lock-up of the 12 battery charger, the licensee ultimately changed the LOOP/LOCA test procedure to ensure that the 12 battery charger was turned off prior to performing the surveillance test. No cross-cutting aspect was assigned to this finding, because licensee decisions made in regards to evaluating the performance of the battery chargers were made many years ago and therefore, not reflective of current plant performance. Enforcement: Technical Specification 3.8.4, "DC Sources - Operating," requires that the train A and train B DC electrical power subsystems be operable in Modes 1 through 4.

9 Enclosure With one battery charger inoperable, TS 3.8.4, Condition A, requires that the battery charger be restored to an operable status in 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or that actions be taken to shut the plant down within the following 42 hours4.861111e-4 days <br />0.0117 hours <br />6.944444e-5 weeks <br />1.5981e-5 months <br />. With both battery chargers inoperable, Limiting Condition for Operation (LCO) 3.0.3 requires that when an LCO is not met and the associated actions are not met, an associated action is not provided, or if directed by the associated actions, the unit shall be placed in a mode or other specified condition in which the LCO is not applicable. Action shall be initiated within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to place the unit, as applicable, in: Mode 3 within 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />; Mode 4 within 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br />; and Mode 5 within 37 hours4.282407e-4 days <br />0.0103 hours <br />6.117725e-5 weeks <br />1.40785e-5 months <br />. Contrary to the above, from December 21, 1994, to approximately October 22, 2010, the safety-related battery chargers on both Unit 1 and 2 failed to maintain the DC electrical power subsystems operable in Modes 1 through 4. Specifically, under design basis accident conditions, all battery chargers were susceptible to a common cause failure under design basis accident conditions whereby the battery chargers would stop providing an output, or "lock-up", when their AC input voltage dropped below their nameplate minimum voltage at the battery charger MCC. This is an apparent violation of TS 3.8.4 pending the completion of the final significance determination (AV 05000282/2011010-01; 05000306/2011010-01, Failure to Ensure that the Train A and Train B DC Electrical Power Subsystems Remained Operable in Modes 1 through 4). 4OA6 .1 Management Meetings On May 20, 2011, the inspectors presented the inspection results to Mr. M. Schimmel, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors confirmed that none of the potential report input discussed was considered proprietary. Exit Meeting Summary ATTACHMENT: SUPPLEMENTAL INFORMATION

1 Attachment SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT M. Schimmel, Site Vice President Licensee K. Davison, Plant Manager T. Allen, Site Engineering Director - Acting J. Anderson, Regulatory Affairs Manager C. Bough, Chemistry and Environmental Manager B. Boyer, Radiation Protection Manager K. DeFusco, Emergency Preparedness Manager D. Goble, Safety and Human Performance Manager J. Hamilton, Security Manager J. Lash, Nuclear Oversight Manager M. Milly, Maintenance Manager J. Muth, Operations Manager S. Northard, Recovery Manager A. Notbohm, Performance Assessment Supervisor K. Peterson, Business Support Manager A. Pullam, Training Manager R. Womack, Outage Manager J. Ritter, Risk Analyst J. Giessner, Chief, Reactor Projects Branch 4 Nuclear Regulatory Commission T. Wengert, Project Manager, NRR LIST OF ITEMS OPENED, CLOSED AND DISCUSSED 05000282/2011010-01; Opened 05000306/2011010-01 AV Failure to Ensure that the Train A and Train B DC Electrical Power Subsystems Remained Operable in Modes 1 through 4 (Section 4OA5.1) 05000282/2010-004 Closed LER Battery Charger Inoperability due to Potential Undervoltage Conditions05000282/2010005-05; 05000306/2010005-05 URI Potential for Common Mode Failure of Safety-Related Battery Chargers Discussed None.

2 Attachment LIST OF DOCUMENTS REVIEWED The following is a partial list of documents reviewed during the inspection. Inclusion on this list does not imply that the NRC inspector reviewed the documents in their entirety, but rather that selected sections or portions of the documents were evaluated as part of the overall inspection effort. Inclusion of a document on this list does not imply NRC acceptance of the document or any part of it, unless this is stated in the body of the inspection report. - Risk Assessment of Operational Events RASP Handbook; Volume 1 (Internal Events) and Volume 2 (External Events). Sections 4OA3 and 4OA5 - The Prairie Island Standardized Plant Analysis Risk Model - NUREG/CR-6890; Reevaluation of Station Blackout Risk at Nuclear Power Plants - NUREG/CR-6883; The SPAR-H Human Reliability Analysis Method - INL-EXT-10-18533; SPAR-H Step-by-Step Guidance; Revision 1 - V.SPA.10.013; Battery Depletion Calculation; November 4, 2010 - V.SPA.11.001; Evaluation of Battery Charger Operation for a Loss of Offsite Power (LOOP) Event; Revision 0; January 17, 2011 - V.SPA.11.002; Evaluation of Battery Charger Operation for a Safety Injection Event While on

Offsite Power; February 25, 2011 - V.SPA.11.003; Prairie Island Battery Depletion Study PRA LOOP with Emergency Lighting and ISI Steady State Test Loads; Revision 0; February 16, 2011 - V.SPA.11.004; Prairie Island PRA SI Only Battery Depletion Study; Revision 0;

February 3, 2011 - V.SPA.11.008; Evaluation of Battery Charger Operation During Bus Crosstie Operation; Revision 0; March 7, 2011 - V.SPA.11.012; Battery Charger Significance Determination Process Fault Tree Analysis";

Revision 0; March 23, 2011 - V.SPA.11.013; Battery Charger Significance Determination Process Accident Sequence

Analysis; Revision 0; March 22, 2011 - V.SPA.11.014; Battery Charger Significance Determination Process Human Reliability Analysis; Revision 0; March 22, 2011 - V.SPA.11.015; Battery Charger Significance Determination Process Quantification Analysis;

Revision 0; March 24, 2011 - V.SPA.11.018; Battery Charger Significance Determination Process Accident Sequence Analysis (121 Cooling Water Pump Sensitivity); Revision 0; March 29, 2011 - V.SPA.11.019; Battery Charger Significance Determination Process Human Reliability

Analysis (121 Cooling Water Pump Sensitivity); Revision 0; March 31, 2011 - V.SPA.11.020; Battery Charger Significance Determination Process Quantification Analysis (121 Cooling Water Pump Sensitivity); Revision 0; March 31, 2011 - Work Order 9712763; "12 Battery Charger Test during SP 1083" - CAP 19971622; Intermittent Operation during SP 1083; December 5, 1997 - CAP 19960452; 12 Battery Charger Intermittent Operation During SP 1083; February 22, 1996 - CAP 1250561; Battery Chargers may stop Operating if Undervoltage Setpoint is Reached; September 21, 2010 - CAP 1252265; Questions Related to Operability Review and Reportability for CAP 1238842; September 30, 2010 - CAP 1253478; Concerns with the Operability Review from CAP 1238842 on 12 Battery Charger; October 9, 2010 - CAP 1254359; Compensatory Measures not Evaluated Properly; October 16, 2010

3 Attachment - CAP 1238842; CDBI 2010 Prep SP 1083 Revised without Proper 50.59 Screening; June 24, 2010 - CAP 1270104; Non-conservative Assumption in Unit 1 Battery Calculations; February 9, 2011 - Operability Review 1238842-01; Continued Operability of D2 Emergency Diesel Generator due to Testing Question; October 22, 2010 - Operability Review 1250561-02; Continued Operability of Safety-Related Battery Chargers; October 22, 2010 - Alarm Response Procedure C47024; 12 DC System Trouble; Revision 35 - 1C20.9 AOP4; Failure of 12 Battery Charger; Revision 010-A - 1C20.9 AOP3; Failure of 11 Battery Charger; Revision 9 - 1C20.5 AOP 1; Re-energizing 4.16 KV Bus 15; Revision 12 - 1C20.5 AOP2; Re-energizing 4.16 KV Bus 16; Revision 14 - 1C20.5 AOP4; Reenergizing 4.16 KV Bus 15 Via Bus-Tie Breakers; Revision 3W - 1C20.5 AOP5; Reenergizing 4.16 KV Bus 16 Via Bus-Tie Breakers; Revision 3W

4 Attachment LIST OF ACRONYMS USED AC Alternating Current ADAMS Agencywide Document Access Management System AOP Abnormal Operating Procedure AV Apparent Violation CAP Corrective Action Program CCF Common Cause Failure CDF Core Damage Frequency CFR Code of Federal Regulations DC Direct Current DRP Division of Reactor Projects HEP Human Error Probability IMC Inspection Manual Chapter IPEEE Individual Plant Examination of External Events LCO Limiting Condition for Operation LER Licensee Event Report LERF Large Early Release Frequency LOCA Loss of Coolant Accident LOOP Loss of Off-Site Power MCC Motor Control Center NRC U.S. Nuclear Regulatory Commission NRR Office of Nuclear Reactor Regulation PARS Publically Available Records System PORV Power Operated Relief Valve PSF Performance Shaping Factor SBO Station Blackout SCR Silicon Controlled Rectifier SDP Significance Determination Process SGTR Steam Generator Tube Rupture SI Safety Injection SPAR Standardized Plant Analysis Risk SRA Senior Reactor Analyst TS Technical Specification URI Unresolved Item

M. Schimmel -3- In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely, /RA/

Steven West, Director Division of Reactor Projects Docket Nos.: 50-282; 50-306;72-010 License Nos.: DPR-42; DPR-60; SNM-2506 Enclosure: Inspection Report 05000282/2011010; 05000306/2011010 w/Attachment: Supplemental Information cc w/encl: Distribution via ListServ DOCUMENT NAME: G:\DRPIII\PRAI\Prairie Island 2011 010 Greater than Green Rpt.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME JGiessner:dtp PLougheeed for SOrth LKozak SWest DATE 06/06/11 06/06/11 06/06/11 06/09/11 OFFICIAL RECORD COPY

Letter to M. Schimmel from S. West dated June 9, 2011 SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2, NRC INSPECTION REPORT 05000282/2011010; 05000306/2011010 PRELIMINARY WHITE FINDING DISTRIBUTION: Daniel Merzke RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3-1 Resource RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn

DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource