MONTHYEARML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) ML23118A1032023-04-28028 April 2023 PI&R Inspection Document Request IR 05000354/20220062023-03-0101 March 2023 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2022006) IR 05000354/20220052022-08-31031 August 2022 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2022005) IR 05000354/20220122022-04-13013 April 2022 Information Request to Support Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000354/2022012 IR 05000354/20210062022-03-0202 March 2022 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2021006) ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection IR 05000354/20210052021-09-0101 September 2021 Updated Inspection Plan for the Hope Creek Nuclear Generating Station (Report 05000354/2021005) IR 05000354/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000354/2020005) IR 05000354/20190062020-03-0303 March 2020 Annual Assessment Letter for Hope Creek Generating Station, Unit 1 (Report 05000354/2019006) IR 05000354/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000354/2019005) ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000354/20180062019-03-0404 March 2019 Annual Assessment Letter for Hope Creek Generating Station, Unit 1 (Report 05000354/2018006) ML18340A2492018-12-0303 December 2018 Notification of Conduct of a Triennial Fire Protection Baseline Inspection and Request for Information IR 05000354/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000354/2018005) IR 05000354/20170062018-02-28028 February 2018 Annual Assessment Letter for Hope Creek Generating Station Unit 1 (Reports 05000354/2017006, 05000354/2017402, and 05000354/2017501) IR 05000354/20170052017-08-28028 August 2017 Updated Inspection Plan for Hope Creek Generating Station, Unit 1(Report 05000354/2017005) IR 05000354/20160062017-03-0101 March 2017 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2016006) IR 05000354/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Hope Creek Generating Station Report (05000354/2016005) IR 05000354/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2015006) IR 05000354/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Hope Creek Generating Station (Report 05000354/2015005) IR 05000354/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2014001) IR 05000354/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000354/2014006 IR 05000354/20130012014-03-0404 March 2014 ROP-14 2013 Hope Creek Generating Station Annual Assessment Letter, Report 05000354-13-001, and Inspection Plan IR 05000354/20130062013-09-0303 September 2013 ROP-14 Mid-Cycle Performance Review and Inspection Plan Report 05000354-13-006 IR 05000354/20120012013-03-0404 March 2013 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354-12-001) ML12334A0052012-11-28028 November 2012 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML12248A0422012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Hope Creek Generating Station, Unit 1 IR 05000354/20110012012-03-0505 March 2012 Annual Assessment Letter for Hope Creek Generating Station Unit 1 (Report 05000354/2011001) ML1124113152011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Hope Creek Generating Station IR 05000354/20100012011-03-0404 March 2011 Annual Assessment Letter for Hope Creek Generating Station, EOC-11 (05000354-10-001) ML1024403372010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Hope Creek Generating Station ML1006208502010-03-0303 March 2010 2009 EOC Hope Creek Annual Assessment Letter and Report 22 IR 05000354/20090012009-03-0404 March 2009 Annual Assessment Letter - Hope Creek Nuclear Generating Station (05000354-09-001) ML0824607952008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Hope Creek Generating Station IR 05000354/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Hope Creek (05000354/2008001) ML0724309452007-08-31031 August 2007 Mid-Cycle Review and Inspection Plan IR 05000354/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Hope Creek Generating Station (Report 05000354-07-001) IR 05000354/20060012006-03-0202 March 2006 Annual Assessment Letter - Hope Creek Nuclear Generating Station (Report 05000354/2006001) ML0424402332004-08-30030 August 2004 Hope Creek ROP5 Mid-Cycle Performance Review and Inspection Plan LR-N04-0036, Correction PSEG Letter LR-N04-0036, Risk-Informed Inservice Inspection Submittal2004-03-11011 March 2004 Correction PSEG Letter LR-N04-0036, Risk-Informed Inservice Inspection Submittal ML0406308562004-03-0303 March 2004 2003-04 Annual Assessment Letter - Hope Creek ML0323904242003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for Hope Creek Generating Station ML0306207722003-03-0303 March 2003 2003 Annual Assessment Letter - Hope Creek Nuclear Generating Station ML0223501752002-08-23023 August 2002 2002 Hope Creek Mid-Cycle Performance Review and Inspection Plan IR 05000354/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - Hope Creek Nuclear Plant (Report 50-354/02-001) 2024-09-11
[Table view] Category:Letter
MONTHYEARML24295A3742024-10-23023 October 2024 Project Manager Assignment IR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 ML24291A0572024-10-17017 October 2024 License Amendment Request (LAR) – Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 1 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities 05000354/LER-2024-001-01, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement2024-09-0505 September 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24197A0552024-07-15015 July 2024 Requalification Program Inspection 05000354/LER-2024-001, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 LR-N24-0021, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums 05000354/LER-2023-003-01, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges 05000354/LER-2023-003, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-02-12012 February 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers 2024-09-05
[Table view] |
Text
September 1, 2021
SUBJECT:
UPDATED INSPECTION PLAN FOR THE HOPE CREEK NUCLEAR GENERATING STATION (REPORT 05000354/2021005)
Dear Mr. Carr,
The enclosed inspection plan lists the inspections scheduled through June 30, 2023, for Hope Creek Generating Station (Hope Creek). The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:
https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections is being developed by the NRC staff.The staff expects to communicate the schedule for these inspections to each utility separately.
E. Carr 2
Additionally, during this period the NRC will schedule an additional inspection per a revised version of Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electrical Power Systems (NRC Bulletin 2012- 01) for any sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (ML19163A176), which included an option for relying on annunciation and operator manual actions instead of automatic protective features to isolate a power supply affected by an open phase condition. Licensees will be individually notified when the NRC schedules these inspections.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 610-337-5312 with any questions you have regarding this letter.
Sincerely, Brice A. Bickett, Chief Projects Branch 3 Division of Operating Reactor Safety
Docket No. 50- 354 License No. NPF-57
Enclosure:
Hope Creek Inspection Plan
Distribution via ListServ E. Carr 3
SUBJECT: UPDATED INSPECTION PLAN FOR THE HOPE CREEK NUCLEAR GENERATING STATION (R EPORT 05000354/2021005) DATED SEPTEMBER 1, 2021
Distribution w/encl: (via E-mail)
BBickett, DORS PFinney, DORS GWalbert, DORS JPatel, DORS, SRI DBeacon, D ORS, RI SCalabrese, DORS AMcCraw, RI, OEDO RidsNrrPMHopeCreek Resource RidsNrrDorlLpl1 Resource ROPReports Resource DORS Specialist Branch Chiefs DRSS Reactor Branch Chiefs DTifft, RI, SLO DScrenci, RI, PAO NSheehan, RI, PAO RidsNrrDirslpab Resource ROPassessment Resource
DOCUMENT NAME: https://usnrc.sharepoint.com/teams/ROPAssessmentMeetings/Shared Documents/ROP-2 2 Second Quarter Process/Branch 3/ROP-2 2 MC ltr Hope CreekFINAL.docx ADAMS Accession No. ML21242A024 SUNSI Review n -Sensitive Publvlle Sensitive n -Publiclyvlable
OFFICE RI/DORS RI/DORS ME PFinney BBictt TE /30/2021 0 011 OFFIAL RERD CO IP 22b Site Inspection Activity Plan Hope Creek
07/01/2021 - 06/30/2023
Unit Start End Activity CAC Title Staff Count
DESIGN BASIS ASSURANCE INSPECTION - TEAMS 6
1 8/1/2021 8/7/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
1 8/15/2021 8/21/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
PI&R BIENNIAL - HC 4
1 8/30/2021 9/3/2021 IP 71152B 000747 Problem Identification and Resolution
1 9/13/2021 9/17/2021 IP 71152B 000747 Problem Identification and Resolution
TI-194 Open Phase Condition Inspection - Hope Creek 2
1 9/20/2021 9/24/2021 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
EP EXERCISE INSPECTION - HOPE CREEK 5
1 11/1/2021 11/5/2021 IP 71114.01 000716 Exercise Evaluation
1 11/1/2021 11/5/2021 IP 71151 001397 Performance Indicator Verification
Security Baseline Inspection-HC 1
1 11/8/2021 11/10/2021 IP 71130.09 001656 Security Plan Changes
RP Rad Hazard; ALARA; In-Plant Airborne; Dose Assess; PIs 71124.01/.02/.03/.04/71151 1
1 11/15/2021 11/19/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
1 11/15/2021 11/19/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls
1 11/15/2021 11/19/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation
1 11/15/2021 11/19/2021 IP 71124.04 000728 Occupational Dose Assessment
1 11/15/2021 11/19/2021 IP 71151 000746 Performance Indicator Verification
RP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 1
1 1/24/2022 1/28/2022 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment
Fire Protection - Hope Creek 3
1 2/14/2022 2/18/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
1 2/28/2022 3/4/2022 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
EP EXERCISE INSPECTION - HOPE CREEK 4
1 5/9/2022 5/13/2022 IP 71114.01 000716 Exercise Evaluation
1 5/9/2022 5/13/2022 IP 71151 001397 Performance Indicator Verification
Access Control, Protective Strat, TSR, SPR, PI-HC 4
1 6/6/2022 6/10/2022 IP 71130.02 000734 Access Control
1 6/6/2022 6/10/2022 IP 71130.05 000737 Protective Strategy Evaluation
1 6/6/2022 6/10/2022 IP 71130.09 001656 Security Plan Changes
1 6/6/2022 6/10/2022 IP 71130.14 000743 Review of Power Reactor Target Sets
Prepared on 8/25/2021 9:26:08 AM 1 of 3 IP 22b Site Inspection Activity Plan
1 6/6/2022 6/10/2022 IP 71151 001338 Performance Indicator Verification
Design Basis Assurance Inspection - Power Operated Valves - Hope Creek 3
1 7/11/2022 7/15/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 1 7/25/2022 7/29/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements
RP Rad Environmental Monitoring Program 71124.07 1
1 8/1/2022 8/5/2022 IP 71124.07 000731 Radiological Environmental Monitoring Program
FY22 Hope Creek Initial Licensing Examination 4
1 6/26/2022 7/1/2022 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 8/7/2022 8/19/2022 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
Hope Creek Requal Inspection with P/F Results 2
1 9/12/2022 9/16/2022 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 1 9/12/2022 9/16/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance
Inservice Inspection - Hope Creek 1
1 10/3/2022 10/7/2022 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
RP Rad Hazard Assessment; Performance Indicator Verification 71124.01/71151 1
1 10/17/2022 10/21/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
1 10/17/2022 10/21/2022 IP 71151 000746 Performance Indicator Verification
RP Rad Airborne / Dose Assessment 71124.03/.04 1
1 11/28/2022 12/2/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation
1 11/28/2022 12/2/2022 IP 71124.04 000728 Occupational Dose Assessment
RP Rad Instrumentation 71124.05 1
1 1/16/2023 1/20/2023 IP 71124.05 000729 Radiation Monitoring Instrumentation
Heat Sink Inspection - Hope Creek 1
1 2/26/2023 3/4/2023 IP 71111.07T 000700 Heat Sink Performance
FORCE-ON-FORCE PLANNING AND EXERCISE - SL/HC 4
1 2/27/2023 3/3/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing
1 3/20/2023 3/24/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing
RP Rad Hazard Assess & Control 71124.01 1
1 3/6/2023 3/10/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
Access Control, Equipment, Sec Trng, Sec Plan Review, PI-HC 3
1 5/8/2023 5/12/2023 IP 71130.02 000734 Access Control
1 5/8/2023 5/12/2023 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance
1 5/8/2023 5/12/2023 IP 71130.07 000739 Security Training
1 5/8/2023 5/12/2023 IP 71130.09 001656 Security Plan Changes
Prepared on 8/25/2021 9:26:08 AM 2 of 3 IP 22b Site Inspection Activity Plan
1 5/8/2023 5/12/2023 IP 71151 001338 Performance Indicator Verification
EP PROGRAM INSPECTION - HOPE CREEK 1
1 6/5/2023 6/9/2023 IP 71114.02 000717 Alert and Notification System Testing
1 6/5/2023 6/9/2023 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System
1 6/5/2023 6/9/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
1 6/5/2023 6/9/2023 IP 71114.05 000720 Maintenance of Emergency Preparedness
1 6/5/2023 6/9/2023 IP 71151 001397 Performance Indicator Verification
PI&R Team Inspection - HC 4
1 6/12/2023 6/16/2023 IP 71152B 000747 Problem Identification and Resolution
1 6/26/2023 6/30/2023 IP 71152B 000747 Problem Identification and Resolution
Prepared on 8/25/2021 9:26:08 AM 3 of 3