November 19, 2021
SUBJECT:
HOPE CREEK GENERATING STATION AND SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 - SECURITY BASELINE INSPECTION REPORT 05000354/2021402, 05000272/2021402 AND 05000311/2021402
Dear Mr. Carr:
On November 10, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 2. On November 17, 2021, the NRC inspectors discussed the results of this inspection with Mr. Charles V. Mcfeaters, Senior Vice President of Nuclear Operations and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Fred L. Bower, III, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety and Security
Docket Nos. 05000354, 05000272 and 05000311 License Nos. NPF-57, DPR-70 and DPR-75
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000354, 05000272 and 05000311
License Numbers:
Report Numbers:
05000354/2021402, 05000272/2021402 and 05000311/2021402
Enterprise Identifier: I-2021-402-0076
I-2021-402-0077
Licensee:
Facility:
Hope Creek Generating Station and Salem Nuclear Generating Station,
Units 1 and 2
Location:
Hancocks Bridge, NJ
Inspection Dates:
November 8, 2021 to November 10, 2021
Inspectors:
S. McCarver, Physical Security Inspector
Approved By:
Fred L. Bower, III, Chief
Security, Emergency Preparedness and Incident Response Branch
Division of Radiological Safety and Security
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.09 - Security Plan Changes
The inspectors evaluated the security plan changes through completion of the following procedure elements:
Review Security Plan Changes (IP Section 02.01) (1 Sample)
- (1) Since the last NRC inspection of this program area (Inspection Report 05000354/2021401, 05000272/2021401 and 05000311/2021401 dated February 23, 2021) PSEG has not revised site Physical Security Plan (PSP), Revision 21. In response to planned construction by the State of New Jersey of an offshore wind port facility in Salem County on Artificial Island north of the Hope Creek Generating Station (HCGS), PSEG performed a 10 CFR 50.54(p) screening and concluded the proposed wind port would not inhibit PSEGs ability to meet security requirements and does not decrease the safeguards effectiveness of the current PSP. Inspectors reviewed the current PSP and the 10 CFR 50.54(p) screen and verified there have not been changes to the site PSP or implementing procedures. Inspectors also conducted field walkdowns and interviewed licensee security personnel. No issues of concern, findings, or violations of more than minor significance were identified by the inspectors.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On November 17, 2021, the inspectors presented the security baseline inspection results to Mr. Charles V. Mcfeaters, Senior Vice President of Nuclear Operations and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Miscellaneous
Salem/Hope Creek Security Plan, Training and Qualification
Plan, Safeguards Contingency Plan, and Independent Spent
Fuel Storage Installation Security Program
Revision 21
Miscellaneous
CFR 50.54(p) Evaluation 2021-02
03/08/2021