August 23, 2002 Mr. Harold Keiser Chief Nuclear Officer and President PSEG Nuclear LLC - N09 P. O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN HOPE CREEK
Dear Mr. Keiser:
On August 7, 2002, the NRC staff completed its mid-cycle plant performance assessment of Hope Creek. In accordance with NRC Inspection Manual Chapter 0305 Operating Reactor Assessment Program, the mid-cycle review involved the participation of all technical divisions in evaluating the performance of your Hope Creek facility for the first half of the current assessment cycle, January 1 - December 31, 2002. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections which may conflict with your plant activities.
Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all performance indicators (PIs) indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only baseline inspections at your facility through September 30, 2003.
The enclosed inspection plan details the inspections scheduled through September 30, 2003.
The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The last six months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In addition, the NRC is in the process of finalizing a Temporary Instruction (TI) that will be used to review implementation of the Interim Compensatory Measures required by the Agencys Security Order to all commercial nuclear power plants dated February 25, 2002. Schedules have not yet been finalized, but it is anticipated that these inspections will begin within the next calendar quarter. Once finalized, the details will be communicated by separate correspondence.
2 Mr. Harold Keiser In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (610) 337-5211 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Glenn W. Meyer, Chief Projects Branch 3 Division of Reactor Projects Docket No. 50-354 Licensee No. NPF-57
Enclosure:
Hope Creek Inspection/ Activity Plan cc w/encl:
M. Friedlander, Director - Business Support J. Carlin, Vice President - Nuclear Reliability and Technical Support.
D. Garchow, Vice President - Operations G. Salamon, Manager - Licensing R. Kankus, Joint Owner Affairs J. J. Keenan, Esquire Consumer Advocate, Office of Consumer Advocate F. Pompper, Chief of Police and Emergency Management Coordinator M. Wetterhahn, Esquire N. Cohen, Coordinator - Unplug Salem Campaign E. Gbur, Coordinator - Jersey Shore Nuclear Watch E. Zobian, Coordinator - Jersey Shore Anti Nuclear Alliance State of New Jersey State of Delaware
3 Mr. Harold Keiser Distribution w/encl:
Region I Docket Room (with concurrences)
J. Schoppy - NRC Resident Inspector H. Miller, RA J. Wiggins, DRA G. Meyer, DRP R. Barkley, DRP L. Prividy, DRS DRS Director, Region I L. Prividy, DRS J. Furia, DRS G. Smith, DRS N. McNamara, DRS H. Nieh, OEDO S. Richards, NRR G. Wunder, PM, NRR R. Fretz, Backup PM, NRR RidsNrrDipmIipb DOCUMENT NAME: G:\\BRANCH3\\midcycle letter - hope creek 2002.wpd After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME Rbarkley GWM for Gmeyer GWM DATE 08/23/02 08/23/02 OFFICIAL RECORD COPY
Hope Creek Inspection / Activity Plan 06/30/2002 - 09/30/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/22/2002 14:30:48 Report 22 1
7/19 EXM
- OPERATOR LICENSING INITIAL RETAKE EXAMS Not Applicable 07/19/2002 07/19/2002 HOPE CREEK RETAKE EXAM (7/19/02)
U01546 1
1 71121
- OCC RAD SAFETY Baseline Inspections 09/16/2002 09/20/2002 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 09/16/2002 09/20/2002 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 09/16/2002 09/20/2002 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
Baseline Inspections 09/16/2002 09/20/2002 Performance Indicator Verification IP 71151 1
2 71130
- SECURITY-RESPONSE ATT3 Baseline Inspections 11/04/2002 11/08/2002 Response to Contingency Events (Protective Strategy and Implementation of Protective Strategy)
7 7111121
- SSDI Baseline Inspections 11/18/2002 11/22/2002 Safety System Design and Performance Capability IP 7111121 1
Baseline Inspections 12/09/2002 12/13/2002 Safety System Design and Performance Capability IP 7111121 1
2 7111111B
- L.O.REQUALIFICATION PROGRAM Baseline Inspections 12/02/2002 12/06/2002 Licensed Operator Requalification IP 7111111B 1
1 71121
- OCC RAD SAFETY Baseline Inspections 01/06/2003 01/10/2003 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 01/06/2003 01/10/2003 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 01/06/2003 01/10/2003 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
3 7111117B
- MODS Baseline Inspections 01/13/2003 01/17/2003 Evaluation of Changes, Tests, or Experiments IP 7111102 1
Baseline Inspections 01/13/2003 01/17/2003 Permanent Plant Modifications IP 7111117B 1
1 7112203
- PUB RAD SAFETY - REMP Baseline Inspections 02/17/2003 02/21/2003 Radiological Environmental Monitoring Program IP 7112203 1
6 71152B
- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 03/10/2003 03/14/2003 Identification and Resolution of Problems IP 71152B 1
Baseline Inspections 03/24/2003 03/28/2003 Identification and Resolution of Problems IP 71152B 1
1 71121
- OCC RAD SAFETY Baseline Inspections 04/07/2003 04/11/2003 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 04/07/2003 04/11/2003 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 04/07/2003 04/11/2003 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
1 7111108
- INSERVICE INSPECTION Baseline Inspections 04/21/2003 04/25/2003 Inservice Inspection Activities IP 7111108 1
4 6/16 EXM
- OPERATOR LICENSING INITIAL EXAMS Not Applicable 05/19/2003 05/23/2003 HOPE CREEK INITIAL EXAM (6/17/03)
U01499 1
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Hope Creek Inspection / Activity Plan 06/30/2002 - 09/30/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/22/2002 14:30:48 Report 22 Not Applicable 06/16/2003 06/20/2003 HOPE CREEK INITIAL EXAM (6/17/03)
U01499 1
1 71130
- SECURITY Baseline Inspections 07/21/2003 07/25/2003 Access Authorization Program (Behavior Observation Only)
Baseline Inspections 07/21/2003 07/25/2003 Access Control (Search of Personnel, Packages, and Vehicles: Identification and Authorization)
1 71121
- OCC RAD SAFETY Baseline Inspections 08/18/2003 08/22/2003 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 08/18/2003 08/22/2003 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 08/18/2003 08/22/2003 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
Baseline Inspections 08/18/2003 08/22/2003 Performance Indicator Verification IP 71151 1
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.