August 28, 2017
SUBJECT:
UPDATED INSPECTION PLAN FOR HOPE CREEK GENERATING STATION UNIT 1 (REPORT 05000354/2017005)
Dear Mr. Sena:
The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for Hope Creek Generating Station Unit 1. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.
In addition to baseline inspections, the NRC plans to conduct Inspection Procedure (IP) 92702, Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirmatory Orders, as described in Inspection Report 05000354/2017010 (ADAMS Accession No.:
ML17122A2821). Also, as previously noted in the annual assessment letter dated March 1, 2017 (Report 05000354/2016006; ADAMS Accession No.: ML17058A408), in addition to baseline inspections, the NRC conducted a supplemental inspection in accordance with IP 95001, Supplemental Inspection Response to Action Matrix Column 2 Inputs, onsite between August 7 and 11, 2017. The results of that inspection and a follow-up assessment letter are expected to be issued within 45 days of the completion of that onsite inspection.
The NRC will also be performing Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.
1 The designation in parentheses refers to an Agencywide Documents Access and Management System (ADAMS) Accession Number. Documents referenced in this letter are publicly available using the Accession Number in ADAMS. Please contact me at (610) 337-5200 with any questions you have regarding this letter.
Sincerely,
/RA/
Fred L. Bower, III, Chief Project Branch 3 Division of Reactor Projects
Docket No. 50-354 License No. NPF-57
Enclosure: Hope Creek Inspection Plan
cc: Distribution via ListServ
SUNSI Review
Non-Sensitive Sensitive
Publicly Available Non-Publicly Available
OFFICE RI/DRP RI/DRP RI/DRP
NAME JHawkins/per email MD MDraxton FBower
DATE 8/17/17 8/17/17 8/21/17
Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Hope Creek Inspection / Activity Plan 08/29/2017 - 06/30/2019 Page 1 of 2 08/29/2017 09:29:39 2/12EXAM
- HOPE CREEK INITIAL OL EXAM
1 FY18 HOPE CREEK EXAM (FEBRUARY 2018)
U01958 01/08/2018 01/12/2018
FY18 HOPE CREEK EXAM (FEBRUARY 2018)
U01958 02/12/2018 02/23/2018 71124
- RAD PROTECTION
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/18/2017 09/22/2017
IP Occupational ALARA Planning and Controls 71124.02 09/18/2017 09/22/2017
IP Occupational Exposure Control Effectiveness 71151-OR01 09/18/2017 09/22/2017
IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 09/18/2017 09/22/2017 T1-191
- FUKUSHIMA LESSONS-LEARNED
1 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 09/18/2017 09/22/2017 71124.08
- RADWASTE
1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 10/16/2017 10/20/2017 71124
- BASELINE HP
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 01/22/2018 01/26/2018
IP Occupational ALARA Planning and Controls 71124.02 01/22/2018 01/26/2018
IP Occupational Dose Assessment 71124.04 01/22/2018 01/26/2018 U1 ISI
- UNIT 1 INSERVICE INSPECTION
1 IP Inservice Inspection Activities - BWR 7111108G 04/23/2018 04/27/2018 71124
- BASELINE HP
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/30/2018 05/04/2018
IP Occupational ALARA Planning and Controls 71124.02 04/30/2018 05/04/2018
IP Occupational Dose Assessment 71124.04 04/30/2018 05/04/2018 7111121M
- DESIGN BASES ASSURANCE INSPECTION (TEAM)
1 IP Design Bases Assurance Inspection (Teams)
7111121M 06/04/2018 06/08/2018
IP Design Bases Assurance Inspection (Teams)
7111121M 06/18/2018 06/22/2018 71124.07
- REMP
1 IP Radiological Environmental Monitoring Program 71124.07 06/25/2018 06/29/2018 REQUAL
- HC REQUAL INSP WITH P/F RESULTS
1 IP Licensed Operator Requalification Program - Annual Review 7111111A 10/08/2018 10/12/2018
IP Licensed Operator Requalification Program 7111111B 10/08/2018 10/12/2018 71124
- BASELINE HP
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/26/2018 11/30/2018
IP Occupational ALARA Planning and Controls 71124.02 11/26/2018 11/30/2018
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/26/2018 11/30/2018 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Hope Creek Inspection / Activity Plan 08/29/2017 - 06/30/2019 Page 2 of 2 08/29/2017 09:29:39 71124
- BASELINE HP
1 IP Occupational Exposure Control Effectiveness 71151-OR01 11/26/2018 11/30/2018
IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 11/26/2018 11/30/2018 71124
- HP
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 01/07/2019 01/11/2019
IP Occupational ALARA Planning and Controls 71124.02 01/07/2019 01/11/2019 EP
- EP PROGRAM INSPECTION
1 IP Alert and Notification System Testing 7111402 02/11/2019 02/15/2019
IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 02/11/2019 02/15/2019
IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 02/11/2019 02/15/2019
IP Performance Indicator Verification 71151 02/11/2019 02/15/2019 7111105T
- TRIENNIAL FIRE PROTECTION
1 IP Fire Protection [Triennial]
7111105T 03/11/2019 03/15/2019
IP Fire Protection [Triennial]
7111105T 03/25/2019 03/29/2019 71124.06
- RETS
1 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/24/2019 06/28/2019 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.