IR 05000354/2021010

From kanterella
Jump to navigation Jump to search
Design Bases Assurance Inspection (Teams) Inspection Report 05000354/2021010
ML21259A194
Person / Time
Site: Hope Creek 
(NPF-057)
Issue date: 09/16/2021
From: Mel Gray
Division of Operating Reactors
To: Carr E
Public Service Enterprise Group
Gray M
References
IR 2021010
Download: ML21259A194 (12)


Text

September 16, 2021

SUBJECT:

HOPE CREEK NUCLEAR GENERATING STATION - DESIGN BASES ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000354/2021010

Dear Mr. Carr:

On August 19, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Hope Creek Nuclear Generating Station and discussed the results of this inspection with Mr. Steven Poorman, Plant Manager and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety

Docket No. 05000354 License No. NPF-57

Enclosure:

As stated

Inspection Report

Docket Number:

05000354

License Number:

NPF-57

Report Number:

05000354/2021010

Enterprise Identifier: I-2021-010-0023

Licensee:

PSEG Nuclear, LLC

Facility:

Hope Creek Nuclear Generating Station

Location:

Hancock's Bridge, New Jersey

Inspection Dates:

August 1, 2021, to August 19, 2021

Inspectors:

J. Ayala, Health Physicist

T. Corcoran, Project Engineer

J. Kulp, Senior Reactor Inspector

K. Mangan, Senior Reactor Inspector

N. Mentzer, Reactor Inspector

J. Schoppy, Senior Reactor Inspector

Approved By:

Mel Gray, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design bases assurance inspection (teams) inspection at Hope Creek Nuclear Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02)

=

(1) D Service Water Pump and Strainer
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Equipment/environmental controls and qualification
  • Design calculations
  • Surveillance testing and recent test results
  • System and component level performance monitoring
  • Equipment protection from fire, flood, and water intrusion or spray

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(2) C Emergency Diesel Generator (Mechanical)
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Design calculations
  • Surveillance testing and recent test results
  • Environmental conditions
  • Equipment protection from fire, flood, and water intrusion or spray
  • Heat removal cooling water and ventilation

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(3) A Emergency Diesel Generator (Electrical) and A 4 KV Bus
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Control logic
  • Design calculations
  • Surveillance testing and recent test results
  • Environmental conditions
  • Contactor and fuse ratings; Component adequacy for minimum voltage

The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electric Loads, and As-Built System.

(4) A 125 Vdc Battery and Bus
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Operator actions
  • Design calculations
  • Surveillance testing and recent test results
  • Verify that component degradation is monitored

The team used Appendix B guidance for Valves, Instrumentation, and As-Built System.

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02) (1 Sample)

(1) Risk Significant Operator Action: Vent Containment
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents and procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Operator actions
  • Design calculations
  • Surveillance testing and recent test results
  • Equipment protection from fire, flood, and water intrusion or spray

The team used Appendix B guidance for Valves, Instrumentation, and As-Built System.

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

(1) Determine Maximum Pressure Difference across Residual Heat Removal Valve H1BC-BC-HV-F003B (80122981)
(2) High Pressure Core Injection (HPCI) Turbine Supply and Exhaust Valve Replacement (80120777)
(3) Removal of N2 Pressure and Floating Roofs from STACS Accumulators (80103199)
(4) Hope Creek Power Range Nuclear Monitor (PRNM) Cable Installation (80111348)
(5) DCC - Replace Hope Creek Reactor Recirculation Pump Motor M-G Set with Siemens Variable Frequency Drive (VFD) (80115139)

Review of Operating Experience Issues (IP Section 02.06) (3 Samples)

(1) NRC Information Notice 2019-01: Inadequate Evaluation of Temporary Alterations
(2) NRC Information Notice 2020-02: Flex Diesel Generator Operational Challenges
(3) NRC Information Notice 2019-08: Flow-Accelerated Corrosion Events

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 19, 2021, the inspectors presented the design bases assurance inspection (teams) inspection results to Mr. Steven Poorman, Plant Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculation

E-15.16

Hope Creek FLEX Electrical System Loading Analysis

Revision 1

E-17D

Hope Creek Generating Station 125 VDC: Voltage Drop from

Distribution Panel to Load

Revision 6

E-4.1(Q)

HC Class 1E 125 VDC Station Battery & Charger Sizing

Revision 20

E-7.4

Class 1E 4.16 KV System Protective Relay Settings

Revision 0

E-7.6

Diesel Generator Protective Relaying

Revision 0

EA-0001

Station Service Water System Hydraulic Model

Revision 3

EA-0003

Station Service Water System Hydraulic Analysis

Revision 12

EG-0047

HCGS Ultimate Heat Sink Temperature Limits - EPU

Revision 0

M-55-1

High Pressure Coolant Injection

Revision 40

M-56-1

HPCI Pump Turbine

Revision 34

Corrective Action

Documents

20342072

20595574

20597337

20619795

20665278

20746839

20748532

20799788

20803684

20820758

20824624

20831232

20835513

20836925

20841318

20841966

20842484

20843007

20858724

20879324

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

20880246

20881375

20881971

20882031

20882345

20882386

20882476

20882477

Corrective Action

Documents

Resulting from

Inspection

20881918

20882155

20882156

20882158

20882161

20882162

20882163

20882167

20882168

20882169

20882195

20882201

20882215

20882356

20882357

20882358

20882374

20882375

20882376

20882418

20882420

20882457

20882475

20882494

20882495

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

20882498

20882499

20882516

20882536

20882677

20882708

20882727

20882740

20882747

20882769

20882771

20882772

20882809

20882821

20882829

20882830

20882831

20882833

20882866

20882876

20882947

20882986

20882990

Drawings

E-0006-2, Sheet

Single Line Meter & Relay Diagram 4.16 KV Class 1E Power

System

Revision 15

Engineering

Changes

80120777

Replacement of HPCI Steam Admission Valve H1FD-FD-

HV-F001

Revision 1

80122981

Maximum Pressure Difference Across Valve H1BC-BC-HV-

F003B

Revision 0

Engineering

Evaluations

207037

Evaluation of NRC Information Notice 2019-01

1/15/20

80111348

Hope Creek PRNM Cable Installation

Revision 0

TE 70210392-

0010

Fire Watch Change for EDG & DFOST Room CO2 Systems

in Manual Operation

11/22/19

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

Safety Evaluation by the Office of Nuclear Reactor

Regulation Related to Amendment No. 59 to Facility

Operating License No. NPF-57 Public Service Electric & Gas

Company Atlantic City Electric Company Hope Creek

Generating Station (ML20058K164)

11/22/93

18055-P-0501

Line Index for the Hope Creek Generating Station

Revision 39

2800 (010)

Hope Creek RRP VFD, Commissioning Documents

Revision 2

2800 (012)

Hope Creek RRP VFD, S7-400, FPC Cabinet

Revision 2

H-1-BJXX-MSE-

0438-0 Status

Code 52

Safety Evaluation: Overpressurization of the HPCI Discharge

Lines Hope Creek Generating Station

dated

8/18/86

HC.MD-PM.PB-

0001

4.16 KV Breaker Cleaning and PM

10/24/19

HC.OP-IS.BJ-

0001

HPCI Main and Booster Pump Set - OP204 and OP217 -

Inservice Test

dated 6/9/21

HC.OP-ISEA-

0004

Service Water Pump -DP502 - Inservice Test

dated 6/8/21

HC.OP-ST.KJ-

0005

Integrated Emergency Diesel Generator 1AG400 Test

11/19/19

Information Notice 2010-17

Common Cause Failure of Boiling-Water Reactor

Recirculation Pumps with Variable Speed Drives

dated

9/10/10

Information Notice 2010-23

Malfunctions of Emergency Diesel Generator Speed Switch

Circuits

dated

11/1/10

Information Notice 2023-006

Ineffective Use of Vendor Technical Recommendations

dated

4/24/12

PE109Q-013

4KV Switchgear

Revision 19

PM018Q-0499-

003

Emergency Diesel Generator

Revision 38

Procedures

CC-AA-201

Plant Barrier Control Program

Revision 6

Diesel Fuel Oil

Storage and

Transfer System

Operation

Emergency Diesel Generator Operation

Revision 78

ER-AA-430

Conduct of Flow Accelerated Corrosion Activities

Revision 9

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ER-AA-430-1001

Guidelines for Flow Accelerated Corrosion Activities

Revision 11

FP-HC-004

Actions for Inoperable Fire Protection - Hope Creek Station

Revision 7

HC.OP-EO.ZZ-

0318

Containment Venting

Revision 14

HC.OP-IS.BJ-

0001

HPCI Main and Booster Pump Set - OP204 and OP217 -

Inservice Test

Revision 71

HC.OP-SO.EG-

0001

Safety and Turbine Auxiliaries Cooling Water System

Operation

Revision 57

HC.OP-SO.JE-

0001

Diesel Fuel Oil Storage and Transfer System Operation

Revision 34

Work Orders

30156952

30179604

264387

264387

286640

30323052

30324962

30325063

30334179

30341497

30342467

60096929

60097059

60097061

60135941

60150262