Updated Inspection Plan (Inspection Report 05000354/2018005)
ML18228A555
Person / Time
Site: Hope Creek 
Issue date: 08/28/2018
From: Fred Bower
Reactor Projects Branch 3
To: Sena P
Public Service Enterprise Group
References
IR 2018005
Download: ML18228A555 (6)


Text

August 28, 2018

SUBJECT:

HOPE CREEK GENERATING STATION UNIT 1 UPDATED INSPECTION PLAN (INSPECTION REPORT 05000354/2018005)

Dear Mr. Sena:

The enclosed inspection plan lists the inspections scheduled through June 30, 2020, for Hope Creek Generating Station Unit 1 (Hope Creek). The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5200 with any questions you have regarding this letter.

Sincerely,

/RA/

Fred L. Bower, III, Chief Project Branch 3 Division of Reactor Projects

Docket No. 50-354 License No. NPF-57

Enclosure:

Hope Creek Inspection Plan

cc: Distribution via ListServ

ML18228A555

SUNSI Review

Non-Sensitive Sensitive

Publicly Available Non-Publicly Available

OFFICE RI/DRP RI/DRP RI/DRP

NAME CLally/CML via email JHawkins/JRH via email FBower

DATE 8/15/18 8/15/18 8/28/18

Hope Creek 07/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count Hope Creek REMP

1 08/27/2018 08/31/2018 IP 71124.07 000731 Radiological Environmental Monitoring Program CYBER FULL IMP

1 09/03/2018 09/07/2018 IP 71130.10P 000741 Cyber Security

09/17/2018 09/21/2018 IP 71130.10P 000741 Cyber Security HC REQUAL INSP WITH P/F RESULTS

1 10/08/2018 10/12/2018 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance (Annual)

10/08/2018 10/12/2018 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)

BASELINE HP

1 11/26/2018 11/30/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

11/26/2018 11/30/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls

11/26/2018 11/30/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

11/26/2018 11/30/2018 IP 71151 000746 Performance Indicator Verification HP

1 01/07/2019 01/11/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

01/07/2019 01/11/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls EP PROGRAM INSPECTION

1 02/11/2019 02/15/2019 IP 71114.02 000717 Alert and Notification System Testing

02/11/2019 02/15/2019 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System

02/11/2019 02/15/2019 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies

02/11/2019 02/15/2019 IP 71151 001397 Performance Indicator Verification TRIENNIAL FIRE PROTECTION

1 03/11/2019 03/15/2019 IP 71111.05T 000696 Fire Protection (Triennial)

03/25/2019 03/29/2019 IP 71111.05T 000696 Fire Protection (Triennial)

MC&A

1 05/20/2019 05/24/2019 IP 71130.11 000742 Material Control and Accounting (MC&A)

8/14/2018 12:16:52 PM Page 1 of 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Hope Creek 07/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count ACCESS CONTROL, PROTECTIVE STRATEGY, TSR

1 06/17/2019 06/21/2019 IP 71130.02 000734 Access Control

06/17/2019 06/21/2019 IP 71130.05 000737 Protective Strategy Evaluation

06/17/2019 06/21/2019 IP 71130.14 000743 Review of Power Reactor Target Sets

06/17/2019 06/21/2019 IP 71151 001338 Performance Indicator Verification PI&R BIENNIAL

1 07/15/2019 07/19/2019 IP 71152B 000747 Problem Identification and Resolution

07/29/2019 08/02/2019 IP 71152B 000747 Problem Identification and Resolution HOPE CREEK INITIAL OL EXAM

1 07/15/2019 07/19/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

08/12/2019 08/23/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

HC RETS

1 08/05/2019 08/09/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment HP

1 08/19/2019 08/23/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

08/19/2019 08/23/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls

08/19/2019 08/23/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

08/19/2019 08/23/2019 IP 71124.04 000729 Occupational Dose Assessment

08/19/2019 08/23/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation Unit 1 ISI INSPECTION

1 10/21/2019 10/25/2019 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

HP

1 10/21/2019 10/25/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

10/21/2019 10/25/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls Radwaste

1 12/02/2019 12/06/2019 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation

12/02/2019 12/06/2019 IP 71151 000746 Performance Indicator Verification 8/14/2018 12:16:52 PM Page 2 of 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Hope Creek 07/01/2018 - 06/30/2020 Unit Start End Activity CAC Title Staff Count 50.59 Inspection

1 01/13/2020 01/17/2020 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments HP

1 02/17/2020 02/21/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

02/17/2020 02/21/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls

02/17/2020 02/21/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

02/17/2020 02/21/2020 IP 71124.04 000729 Occupational Dose Assessment

02/17/2020 02/21/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS

1 02/24/2020 02/28/2020 IP 71130.03 000735 Contingency Response - Force-On-Force Testing

03/16/2020 03/20/2020 IP 71130.03 000735 Contingency Response - Force-On-Force Testing HOPE CREEK EP EXERCISE INSPECTION

1 05/18/2020 05/22/2020 IP 71114.01 000716 Exercise Evaluation

05/18/2020 05/22/2020 IP 71151 001397 Performance Indicator Verification HP

1 06/01/2020 06/05/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

06/01/2020 06/05/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls

06/01/2020 06/05/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

06/01/2020 06/05/2020 IP 71124.04 000729 Occupational Dose Assessment

06/01/2020 06/05/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation 8/14/2018 12:16:52 PM Page 3 of 3 This report does not include INPO and OUTAGE activities.