MONTHYEARML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) ML23118A1032023-04-28028 April 2023 PI&R Inspection Document Request IR 05000354/20220062023-03-0101 March 2023 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2022006) IR 05000354/20220052022-08-31031 August 2022 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2022005) ML22103A0662022-04-13013 April 2022 Information Request to Support Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000354/2022012 IR 05000354/20210062022-03-0202 March 2022 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2021006) ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection IR 05000354/20210052021-09-0101 September 2021 Updated Inspection Plan for the Hope Creek Nuclear Generating Station (Report 05000354/2021005) IR 05000354/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000354/2020005) IR 05000354/20190062020-03-0303 March 2020 Annual Assessment Letter for Hope Creek Generating Station, Unit 1 (Report 05000354/2019006) IR 05000354/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000354/2019005) ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000354/20180062019-03-0404 March 2019 Annual Assessment Letter for Hope Creek Generating Station, Unit 1 (Report 05000354/2018006) ML18340A2492018-12-0303 December 2018 Notification of Conduct of a Triennial Fire Protection Baseline Inspection and Request for Information IR 05000354/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000354/2018005) IR 05000354/20170062018-02-28028 February 2018 Annual Assessment Letter for Hope Creek Generating Station Unit 1 (Reports 05000354/2017006, 05000354/2017402, and 05000354/2017501) IR 05000354/20170052017-08-28028 August 2017 Updated Inspection Plan for Hope Creek Generating Station, Unit 1(Report 05000354/2017005) IR 05000354/20160062017-03-0101 March 2017 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2016006) IR 05000354/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Hope Creek Generating Station Report (05000354/2016005) IR 05000354/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2015006) IR 05000354/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Hope Creek Generating Station (Report 05000354/2015005) IR 05000354/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2014001) IR 05000354/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000354/2014006 IR 05000354/20130012014-03-0404 March 2014 ROP-14 2013 Hope Creek Generating Station Annual Assessment Letter, Report 05000354-13-001, and Inspection Plan IR 05000354/20130062013-09-0303 September 2013 ROP-14 Mid-Cycle Performance Review and Inspection Plan Report 05000354-13-006 IR 05000354/20120012013-03-0404 March 2013 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354-12-001) ML12334A0052012-11-28028 November 2012 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML12248A0422012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Hope Creek Generating Station, Unit 1 IR 05000354/20110012012-03-0505 March 2012 Annual Assessment Letter for Hope Creek Generating Station Unit 1 (Report 05000354/2011001) ML1124113152011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Hope Creek Generating Station IR 05000354/20100012011-03-0404 March 2011 Annual Assessment Letter for Hope Creek Generating Station, EOC-11 (05000354-10-001) ML1024403372010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Hope Creek Generating Station ML1006208502010-03-0303 March 2010 2009 EOC Hope Creek Annual Assessment Letter and Report 22 IR 05000354/20090012009-03-0404 March 2009 Annual Assessment Letter - Hope Creek Nuclear Generating Station (05000354-09-001) ML0824607952008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Hope Creek Generating Station IR 05000354/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Hope Creek (05000354/2008001) ML0724309452007-08-31031 August 2007 Mid-Cycle Review and Inspection Plan IR 05000354/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Hope Creek Generating Station (Report 05000354-07-001) IR 05000354/20060012006-03-0202 March 2006 Annual Assessment Letter - Hope Creek Nuclear Generating Station (Report 05000354/2006001) ML0424402332004-08-30030 August 2004 Hope Creek ROP5 Mid-Cycle Performance Review and Inspection Plan LR-N04-0036, Correction PSEG Letter LR-N04-0036, Risk-Informed Inservice Inspection Submittal2004-03-11011 March 2004 Correction PSEG Letter LR-N04-0036, Risk-Informed Inservice Inspection Submittal ML0406308562004-03-0303 March 2004 2003-04 Annual Assessment Letter - Hope Creek ML0323904242003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for Hope Creek Generating Station ML0306207722003-03-0303 March 2003 2003 Annual Assessment Letter - Hope Creek Nuclear Generating Station ML0223501752002-08-23023 August 2002 2002 Hope Creek Mid-Cycle Performance Review and Inspection Plan IR 05000354/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - Hope Creek Nuclear Plant (Report 50-354/02-001) 2024-09-11
[Table view] Category:Letter
MONTHYEARIR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 ML24295A3742024-10-23023 October 2024 Project Manager Assignment ML24291A0572024-10-17017 October 2024 License Amendment Request (LAR) – Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 1 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle IR 05000272/20244032024-09-25025 September 2024 and Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) IR 05000272/20244022024-09-23023 September 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24145A1772024-07-15015 July 2024 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24197A0552024-07-15015 July 2024 Requalification Program Inspection 05000354/LER-2024-001, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23307A1532023-12-15015 December 2023 NRC Investigation Report No. 1-2023-001 ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation 2024-09-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION I
2100 RENAISSANCE BLVD.
KING OF PRUSSIA, PA 19406-2713 March 1, 2017 Mr. Peter Sena President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P.O. Box 236 Hancocks Bridge, NJ 08038 SUBJECT: ANNUAL ASSESSMENT LETTER FOR HOPE CREEK GENERATING STATION (REPORT 05000354/2016006)
Dear Mr. Sena:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Hope Creek Generating Station Unit 1 (Hope Creek), reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2016, through December 31, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Hope Creek during the most recent quarter was within the Regulatory Response Column (Column 2) of the NRCs Reactor Oversight Process (ROP)
Action Matrix in Inspection Manual Chapter 0305, Operating Assessment Program. This conclusion was based on a single inspection finding related to maintenance of the high-pressure coolant injection system having low-to-moderate safety significance (i.e., White) in the Mitigating Systems Cornerstone, and all PIs within the expected range (i.e., Green). As stated in our final significance determination and follow-up assessment letter (Report 05000354/2016008; ML17033B541 1) dated February 06, 2017, the NRC has assessed Hope Creek to be in the Regulatory Response column, retroactive to the third calendar quarter of 2016 when this performance issue was identified. Therefore, in addition to ROP baseline inspections, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure (IP)
95001, Supplemental Inspection Response to Action Matrix Column 2 Inputs, after you notify the NRC of your readiness for this inspection. This inspection is conducted to provide assurance that the root causes and contributing causes of any performance issues are understood, the extent of condition is identified, and the corrective actions are sufficient to prevent recurrence.
The enclosed inspection plan lists the inspections scheduled through December 31, 2018.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the 1 The designation in parentheses refers to an Agencywide Documents Access and Management System (ADAMS) Accession Number. Documents referenced in this letter are publicly available using the Accession Number in ADAMS. inspection plan are tentative and may be revised. In addition to baseline inspections, the NRC will perform IP 60855.1, Operation of an Independent Spent Fuel Storage Installation at Operating Plants, and Temporary Instruction 2515/192, Inspection of the Licensees Interim Compensatory Measures Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Fred Bower at (610) 337-5200 with any questions you have regarding this letter.
Sincerely,
/RA/
Michael L. Scott, Director Division of Reactor Projects Docket No.: 50-354 License No.: NPF-57 Enclosure:
Hope Creek Inspection/Activity Plan cc w/encl: Distribution via ListServ
ML17058A408 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME RBarkley FBower MScott DATE 2/22/17 2/27/17 2/27/17/17
Page 1 of 2 Hope Creek 02/02/2017 15:25:29 Inspection / Activity Plan Report 22 01/01/2017 - 12/31/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71152B - PI&R BIENNIAL 4 1 01/30/2017 02/03/2017 IP 71152B Problem Identification and Resolution 1 02/13/2017 02/17/2017 IP 71152B Problem Identification and Resolution ISFSI - ISFSI LOADING CAMPAIGN INSPECTION 1 1 03/06/2017 03/10/2017 IP 60855 Operation Of An ISFSI 1 03/06/2017 03/10/2017 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 71124 - RAD PROTECTION 1 1 02/27/2017 03/03/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 02/27/2017 03/03/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 02/27/2017 03/03/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 02/27/2017 03/03/2017 IP 71124.05 Radiation Monitoring Instrumentation 50.59 - EVALS OF CHANGES, TESTS, & EXPERIMENTS 3 1 03/27/2017 03/31/2017 IP 7111117T-5059scrn screenings and/or applicability determinations EP - EP PROGRAM INSPECTION 1 1 06/05/2017 06/09/2017 IP 7111402 Alert and Notification System Testing 1 06/05/2017 06/09/2017 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 06/05/2017 06/09/2017 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 06/05/2017 06/09/2017 IP 71151 Performance Indicator Verification 7111121N - EQ PROGRAM 3 1 05/08/2017 05/12/2017 IP 7111121N Component Design Bases Inspection (Programs)
1 05/22/2017 05/26/2017 IP 7111121N Component Design Bases Inspection (Programs)
71124.06 - RETS 1 1 06/12/2017 06/16/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 7111107T - TRIENNIAL HEAT SINK 1 1 06/19/2017 06/23/2017 IP 7111107T Heat Sink Performance 2/12EXAM - HOPE CREEK INITIAL EXAM 4 1 01/08/2018 01/12/2018 U01958 FY18 HOPE CREEK EXAM (FEBRUARY 2018)
1 02/12/2018 02/23/2018 U01958 FY18 HOPE CREEK EXAM (FEBRUARY 2018)
71124 - RAD PROTECTION 1 1 07/31/2017 08/04/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 07/31/2017 08/04/2017 IP 71124.02 Occupational ALARA Planning and Controls 71124 - RAD PROTECTION 1 1 09/18/2017 09/22/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 09/18/2017 09/22/2017 IP 71124.02 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Hope Creek 02/02/2017 15:25:29 Inspection / Activity Plan Report 22 01/01/2017 - 12/31/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - RAD PROTECTION 1 1 09/18/2017 09/22/2017 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 09/18/2017 09/22/2017 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71124.08 - RADWASTE 1 1 10/16/2017 10/20/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124 - BASELINE HP 1 1 01/22/2018 01/26/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 01/22/2018 01/26/2018 IP 71124.02 Occupational ALARA Planning and Controls 1 01/22/2018 01/26/2018 IP 71124.04 Occupational Dose Assessment U1 ISI - UNIT 1 INSERVICE INSPECTION 2 1 04/23/2018 04/27/2018 IP 7111108G Inservice Inspection Activities - BWR 71124 - BASELINE HP 1 1 04/30/2018 05/04/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 04/30/2018 05/04/2018 IP 71124.02 Occupational ALARA Planning and Controls 1 04/30/2018 05/04/2018 IP 71124.04 Occupational Dose Assessment 71124.07 - REMP 1 1 06/25/2018 06/29/2018 IP 71124.07 Radiological Environmental Monitoring Program 7111121M - DESIGN BASES ASSURANCE INSPECTION (TEAM) 6 1 07/16/2018 07/20/2018 IP 7111121M Component Design Bases Inspection (Teams)
1 07/30/2018 08/03/2018 IP 7111121M Component Design Bases Inspection (Teams)
REQUAL - HC REQUAL INSP WITH P/F RESULTS 2 1 10/08/2018 10/12/2018 IP 7111111A Licensed Operator Requalification Program - Annual Review 1 10/08/2018 10/12/2018 IP 7111111B Licensed Operator Requalification Program 71124 - BASELINE HP 1 1 11/26/2018 11/30/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 11/26/2018 11/30/2018 IP 71124.02 Occupational ALARA Planning and Controls 1 11/26/2018 11/30/2018 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 11/26/2018 11/30/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 11/26/2018 11/30/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.