Category:Letter
MONTHYEARML24295A3742024-10-23023 October 2024 Project Manager Assignment IR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 ML24291A0572024-10-17017 October 2024 License Amendment Request (LAR) – Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 1 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities 05000354/LER-2024-001-01, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement2024-09-0505 September 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24197A0552024-07-15015 July 2024 Requalification Program Inspection 05000354/LER-2024-001, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 LR-N24-0021, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums 05000354/LER-2023-003-01, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges 05000354/LER-2023-003, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-02-12012 February 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers 2024-09-05
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 ML22350A4692022-12-16016 December 2022 301 Exam Administrative Items (2 Year Delayed release)(ADAMS-2A-3) IR 05000354/20213012021-04-0101 April 2021 Initial Operator Licensing Examination Report 05000354/2021301 IR 05000354/20193012019-10-17017 October 2019 Initial Operator Licensing Examination Report 05000354/2019301 IR 05000354/20183022018-08-22022 August 2018 Retake Operator Licensing Examination Report 05000354/2018302 IR 05000354/20163012016-10-25025 October 2016 NRC Initial Operator Licensing Examination Report 05000354/2016301 IR 05000354/20153012015-04-28028 April 2015 Er 05000354/2015301; 02/23-27/15, 03/03, 06, 31/15, and 04/01/15; Hope Creek Generating Station; Initial Operator Licensing Examination Report IR 05000354/20123012012-04-18018 April 2012 Er 05000354-12-301; March 5-14, 2012; Hope Creek Generating Station, Unit 1; Initial Operator Licensing Examination Report IR 05000354/20113012011-02-14014 February 2011 Er 05000354-11-301, on January 27, 2011, Hope Creek Generating Station - Unit 1, Initial Operator Licensing Retake Examination Report IR 05000354/20103012010-10-0404 October 2010 Er 05000354/10-301 for Hope Creek Generating Station, Unit 1, Initial Operator Licensing Examination Report IR 05000354/20093012009-03-20020 March 2009 Er 05000354-09-301, on February 2-18, 2009, Hope Creek Generating Station, Initial Operator Licensing Examination Report IR 05000354/20073012007-11-26026 November 2007 Er 05000354-07-301; Exam Dates 9/24-28, 2007; Hope Creek Generating Station; Initial Senior Reactor Operator (SRO) Licensing Examination IR 05000354/20053012006-01-13013 January 2006 IR 05000354-05-301; November 28 to December 5, 2005; Hope Creek; Initial Operator Licensing Examination. Two of Two Applicants Passed the Examination (One Reactor Operator (Ro), One Senior Reactor Operator (SRO) Instant) NTD-05-046, Response to NRC Form 536 (RIS 2005-19) Operator Licensing Examination Data2005-10-31031 October 2005 Response to NRC Form 536 (RIS 2005-19) Operator Licensing Examination Data IR 05000354/20023022002-08-0808 August 2002 IR 05000354/2002-302, on July 19, 2002; Hope Creek Generating Station; Initial Reactor Operator (RO) Licensing Retake Examination ML0220000482002-07-10010 July 2002 Response to NRC Form 536 (RIS 2002-9) Operator Licensing Examination Data ML0213506732002-05-15015 May 2002 IR 05000387/2002-301 and IR 05000388/2002-301, Hope Creek Station, Inspection on March 11-18, 2002, Related to Initial Operator Licensing Examinations. Four of Five Reactor Operator Applicants Passed All Portions of the Examination 2024-04-10
[Table view] |
Text
April 1, 2021
SUBJECT:
HOPE CREEK GENERATING STATION - INITIAL OPERATOR LICENSING EXAMINATION REPORT 05000354/2021301
Dear Mr. Carr:
On March 3, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an examination at the Hope Creek facility. The enclosed examination report documents the examination results, which were discussed on March 25, 2021, with Mr. S. Nevelos, Senior Director Nuclear Training, and other members of your staff.
The examination included the evaluation of two applicants for reactor operator licenses and six applicants for instant senior reactor operator licenses. The written and operating examinations were developed using NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 11. The license examiners determined all applicants satisfied the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55, and the appropriate licenses were issued on March 25, 2021.
No findings were identified during this examination.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, X /RA/
Signed by: Donald E. Jackson Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 05000354 License No. NPF-57 Enclosure: Examination Report 05000354/2021301 w/Attachment: Supplementary Information cc w/encl: Distribution via ListServ
SUMMARY
ER 05000354/2021301; February 22 - March 3, 2021; Hope Creek Generating Station; Initial
Operator Licensing Examination Report.
Four NRC examiners evaluated the competency of two applicants for reactor operator licenses and six applicants for instant senior reactor operator licenses. The facility licensee developed the examinations using NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 11. The written examination was administered by the facility on March 3, 2021. NRC examiners administered the operating tests February 22-26, 2021. The NRC examiners determined that all applicants satisfied the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55, and the appropriate licenses have been issued.
NRC-Identified and Self-Revealing Findings
No findings were identified.
Licensee-Identified Violations
None.
REPORT DETAILS
OTHER ACTIVITIES (OA)
4OA5 Other Activities (Initial Operator License Examination)
.1 License Applications
a. Scope
The examiners reviewed all license applications submitted by the licensee to ensure the applications reflected that each applicant satisfied relevant license eligibility requirements. The applications were submitted on NRC Form 398, Personal Qualification Statement, and NRC Form 396, Certification of Medical Examination by Facility Licensee. The examiners also audited the license applications to confirm that they accurately reflected the subject applicants qualifications. This audit focused on the applicants experience and on-the-job training, including control manipulations that provided significant reactivity changes.
b. Findings
No findings were identified.
.2 Operator Knowledge and Performance
a. Examination Scope
On March 3, 2021, the licensee proctored the administration of the written examinations to all applicants. The licensee staff graded the written examinations, analyzed the results, and presented their analysis to the NRC on March 8, 2021.
The NRC examination team administered the various portions of the operating examination February 22-26, 2021. The applicants for reactor operator licenses participated in at least two dynamic simulator scenarios, in a control room and facilities walkthrough test consisting of eleven system tasks, and an administrative test consisting of four administrative tasks. The applicants for instant senior reactor operator licenses participated in at least two dynamic simulator scenarios, a control room and facilities walkthrough test consisting of ten system tasks, and an administrative test consisting of five administrative tasks.
b. Findings
No findings were identified.
All applicants passed the operating test and the written examination. For the written examinations, the reactor operator applicants average score was 88.0 percent and ranged from 84.0 to 92.0 percent. The senior operator applicants average score was 91.8 percent and ranged from 87.0 to 96.0 percent. The text of the examination questions may be accessed in the ADAMS system under the accession numbers noted in the Attachment. In accordance with current NRC policy, the release of the written examination in ADAMS to the public will be delayed for two years.
Chapter ES-403 and Form ES-403-1 of NUREG 1021 require the licensee to analyze the validity of any written examination questions that were missed by half or more of the applicants. The licensee conducted this analysis and submitted it to the chief examiner.
.3 Initial Licensing Examination Development
a. Examination Scope
The facility licensee developed the examinations in accordance with NUREG-1021, Revision 11. All licensee facility training and operations staff involved in examination preparation and validation were listed on a security agreement. The facility licensee submitted the operating examination outline on September 11, 2020. The chief examiner reviewed the outlines against the requirements of NUREG-1021, and provided comments to the licensee. The facility licensee submitted the draft examination package on November 20, 2020. The chief examiner reviewed the draft examination package against the requirements of NUREG-1021, and provided comments to the licensee on the examination on January 8, 2021. The NRC conducted an onsite validation of the operating examinations and provided further comments during the week of January 11, 2021. The licensee satisfactorily completed comment resolution on January 29, 2021.
b. Findings
No findings were identified.
The NRC approved the initial examination outline and advised the licensee to proceed with the operating examination development.
The examiners determined that the written and operating examinations initially submitted by the licensee were within the range of acceptability expected for a proposed examination.
.4 Simulation Facility Performance
a. Examination Scope
The examiners observed simulator performance with regard to plant fidelity during the examination validation and administration.
b. Findings
No findings were identified.
.5 Examination Security
a. Examination Scope
The examiners reviewed examination security for examination development and during both the onsite preparation week and examination administration week for compliance with NUREG-1021, Revision 11 requirements. Plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
b. Findings
No findings were identified.
4OA6 Meetings, Including Exit
The chief examiner presented the examination results to Mr. S. Nevelos, Senior Director Nuclear Training, and other members of the licensee's staff on March 25, 2021.
The licensee did not identify any information or materials used during the examination as proprietary.
ATTACHMENT:
SUPPLEMENTARY INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- S. Dennis, Exam Author
- P. Breidenbaugh, Exam Author
ITEMS OPENED, CLOSED, AND DISCUSSED
NONE
ADAMS DOCUMENTS REFERENCED