Notification of Conduct of a Fire Protection Team Inspection
ML24255A804
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 09/11/2024
From: Brandon Pinson
Division of Operating Reactors
To: Mcfeaters C
Public Service Enterprise Group
References
Download: ML24255A804 (1)


Text

[Type here]

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE RD, STE 102 KING OF PRUSSIA, PENNSYLVANIA 19406-1415 September 11, 2024 Charles McFeaters President and Chief Nuclear Officer PSEG Nuclear, LLC - N09 P.O. Box 236 Hancocks Bridge, NJ 08038

SUBJECT:

HOPE CREEK GENERATING STATION - NOTIFICATION OF CONDUCT OF A FIRE PROTECTION TEAM INSPECTION

Dear Charles McFeaters:

The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff will conduct a fire protection team inspection at your Hope Creek Generating Station starting in January 2025. The inspection will be conducted in accordance with Inspection Procedure 71111 1N.05, Fire Protection Team Inspection (FPTI), dated January 1, 2020. The inspection team will be led by Jenn Tifft, a Senior Reactor Inspector from the NRC Region I Office.

The inspection will verify that plant structures, systems, and components, and/or administrative controls credited in the approved fire protection program can perform their licensing basis function.

The schedule for the inspection is as follows:

Information Gathering Visit: Week of December 9, 2024 Onsite Inspection:

Weeks of January 13, 2025 and January 27, 2025 The purpose of the information gathering visit is to obtain information and documentation needed to support the inspection and to become familiar with the stations fire protection program, fire protection features, post-fire safe shutdown capabilities, and plant layout. During the information gathering visit, the team leader will select the specific samples to be reviewed during the onsite inspection weeks.

The enclosure lists the types of documents that will be needed prior to the information gathering visit. Please provide the referenced information to the Region I office by December 2, 2024.

Following sample selection, additional documents will be requested specific to those samples.

Your cooperation and support during this inspection will be appreciated.

If you have questions concerning this inspection or the inspection team's information request or logistical needs, please contact Jenn Tifft, Team Leader, at (610) 337-5315, or via email at jennifer.tifft@nrc.gov.

C. McFeaters 2

This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, under Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Brandon Pinson, Chief Engineering Branch 2 Division of Reactor Safety Docket No.

05000354 License No.

NPF-57

Enclosure:

Fire Protection Team Inspection Supporting Documentation cc: Distribution via ListServ RICHARD PINSON Digitally signed by RICHARD PINSON Date: 2024.09.11 15:11:40 -04'00'

ML24255A804 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DORS RI/DORS NAME JTifft BPinson DATE 9/11/2024 9/11/2024

Enclosure Fire Protection Team Inspection Supporting Documentation If you have any questions regarding this information request, please contact Jenn Tifft at (610) 337-5315 or via email at jennifer.tifft@nrc.gov.

Electronic format is preferred. If electronic media is made available via an internet-based document management system, then document access must allow inspectors to download, save, and print the documents in the NRC's Regional office. Additionally, word-searchable documents are preferred, if available. Paper records (hard copy) are acceptable. At the end of the inspection, the documents in the teams possession will not be retained.

This document request is based on typical documents that a generic plant might have. As such, this generic document request is not meant to imply that any specific plant is required to have all of the listed documents. It is recognized that some documents listed below may not be available for your plant. In addition, the document titles listed below are based on typical industry document names; your plant specific document titles may vary.

Note that following sample selection, additional documents will be requested specific to those samples.

Please provide these documents to the inspection team leader in the Region I Office by December 2, 2024:

1. Post-Fire Safe Shutdown Analysis.
2. List of post-fire safe shutdown components (i.e., safe shutdown equipment list), if not already included in item (1) above.
3. Fire Hazards Analysis Report.
4. Fire Protection Program and/or Fire Protection Plan Document(s).
5. Fire Protection Program implementing procedures, if not already included in item (4).

This could include procedures for programs such as transient combustible controls, hot work, changes to the fire protection program, etc.

6. Fire Protection Design Basis Document(s), if available.
7. National Fire Protection Association (NFPA) Code Compliance Report. List of NFPA Codes of Record, including edition number.
8. Copy of the Fire Probabilistic Risk Assessment (PRA) methodology overview document.

If a Fire PRA is not available, please provide the Individual Plant Examination for External Events (Fire Chapter Only).

Enclosure

9. List of all safety evaluations performed to support any plant modifications since February 2022. Include a short description and/or title of each evaluation.
10. List of all 10 CFR 50.59 applicability determinations and screens (date, number, title) performed since February 2022. Include a short description and/or title of each document.
11. List of all fire protection system impact screening reviews for any design changes, modifications, or temporary modifications completed since February 2022 (e.g., a Generic Letter 86-10 review, LS-AA-128 review, etc.). Include a short description and/or title of each review.
12. List of fire protection system, post-fire safe shutdown, or alternative shutdown design changes completed since February 2022. Include a short description and/or title of each change.
13. List of all Generic Letter 86-10 evaluations completed since February 2022. Include a short description and/or title of each evaluation.
14. List of the top 25 highest fire core damage frequency scenarios, if available.
15. List of the top 25 highest fire large early release frequency scenarios, if available.
16. From your most recent site-specific PRA, including external events and fires (if available):

Two risk rankings of components: one sorted by Risk Achievement Worth (RAW) and the other sorted by Birnbaum Importance.

A list of the top 100 cut sets.

17. List of time-critical and time sensitive operator actions and associated program procedures.
18. Risk ranking of operator actions and/or recovery actions from your site-specific PRA sorted by RAW.
19. Thermal-hydraulic calculation or analysis that determined the time requirements for time-critical and time sensitive operator actions.
20. List of current fire protection system impairments, including description.

Enclosure

21. One-line diagram of the electrical distribution system.
22. Copy of the Updated Final Safety Analysis Report.
23. Copy of the Technical Requirements Manual.
24. Copy of the Corrective Action Program Procedure(s).
25. Copy of the Quality Assurance Program Manual (including specific fire protection Quality Assurance Manual, if applicable).
26. Copy of station procedures used for fire safe shutdown from inside and outside of the control room (e.g., alarm response procedure, procedure for shutdown from the remote shutdown panel, etc.).
27. List of open and closed condition reports for post-fire safe shutdown or alternative shutdown issues since February 2022 (e.g., issues affecting safe shutdown analysis, fire hazards analysis, safe shutdown operating procedures and/or training, timeline evaluations for operator actions, etc.). Include the issue report number and a brief description.
28. List of open and closed condition reports for fire protection system issues (e.g., fire pumps, detection, suppression, etc.) since February 2022. Include the issue report number and a brief description.
29. List of open and closed condition reports related to the fire brigade or fire drills since February 2022. Include the issue report number and a brief description.
30. Copies of any self-assessments performed, and corrective action documents generated, in preparation for this fire protection team inspection.
31. Copies of aging management programs applicable to fire protection including, but not limited to, the following:

Fire protection Fire water system Above ground metallic tanks Buried and underground piping and tanks

32. Copies of procedures, work orders, preventive maintenance tasks, or other documents which implement the commitments made as part of the license extension related to fire protection.

Enclosure

33. Copies of the following condition reports:

20869865 20897251 20897314 20897315 20897561 20897657 20897659 20897675 20897677 20897741 20897743 20897899 20898071 20898072 20898073 20898077 20898078 20898088 20898100 20898182 20898186 20898243 20898248 20898288 20898331 20898355 20898358 20898371 20898374 20898376 20898424