Mid-Cycle Performance Review and Inspection Plan 2010 - Hope Creek Generating Station
ML102440337
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 09/01/2010
From: Arthur Burritt
Reactor Projects Branch 3
To: Joyce T
Public Service Enterprise Group
BURRITT AL
References
Download: ML102440337 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 September 1, 2010 Mr. Thomas p, Joyce President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P.O. Box 236 Hancocks Bridge, NJ 08038

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - HOPE CREEK GENERATING STATION

Dear Mr. Joyce:

On August 10, 2010, the NRC staff completed its performance review of Hope Creek Generating Station (Hope Creek). Our technical staff reviewed performance indicators (Pis) for the most recent quarter and inspection results for the period from July 1, 2009 through June 30, 2010. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter at Hope Creek was within the Licensee Response column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all Pis indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to physical protection scheduled throug h December 31, 2011. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

If circumstances arise that cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 61 0-337 -5069 with any questions you may have regarding this letter or the inspection plan.

T. Joyce 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy ofthis letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html (the Public Electronic Reading Room).

Sincerely,

~~&:::Jt-Arthur L Burritt, Chief Projects Branch 3 Division of Reactor Projects Docket Nos. 50-354 License Nos. NPF-57

Enclosure:

Hope Creek Generating Station Inspection I Activity Plan cc w/encl: Distribution via ListServ

T. Joyce 3 In accordance with 10 CFR 2.390 ofthe NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html (the Public Electronic Reading Room).

Sincerely, IRAt Arthur L. Burritt, Chief Projects Branch 3 Division of Reactor Projects Docket Nos. 50-354 license Nos. NPF-57

Enclosure:

Hope Creek Generating Station Inspection I Activity Plan cc w/enel: Distribution via ListServ Distribution w/encl: DRS Branch Chiefs (6)

M. Dapas, Acting RA N. McNamara, SLO D. Lew, Acting ORA D. Tifft, SLO J. Clifford, DRP D. Screne;, PAD A. Burritt, DRP N. Sheehan, PAO L. Cline, DRP R. Barkley, ORA A. Turilin, DRP John Thompson, NRR I C. Douglas, DRP B. Welling, DRP, SRI RidsNrrDirslpab Resource RidsNrrPMHopeCreek Resource i

A. Patel, DRP, RJ K. McKenzie, DRP, OA RidsNrrDorlLpl1-2 Resource ROPreportsResource@nrc.gov I.

L Trocine, Rl OEOO DRS Director DRS Deputy Director I i

SUNSI REVIEW COMPLETE: ALB (Reviewer's Initials) ML102440337 DOCUMENT NAME: S:\ROP-11 MID-CYCLE REVfEw\BRANCH 3\HC MID-CYCLE LETTER2010.DOCX After declaring this document "An Official Agency Record" it will be released to the Public.

To receive acopy of this document, indicate in box:"C' = Copy wlo attachment/enclosure, E' = Copy wI attachmenllenclosure'N'=No copy OFFICE mmt RI/DRP I RI/DRP I RlDRP I NAME i!3Welling/ LC for LCJine! LC ABurriWAL8 DATE P8/31/10 08/31/10 08/31/10 OFFICIAL RECORD COpy

Page 1 of2 Hope Creek 08130/2010 15:04:42 Inspection I Activity Plan Report 22 07/01/2010 - 12/31/2011 Planned Dates Start End Title 8/23EXAM -INITIAL OPERATOR LICENSING EXAM 5 07/26/2010 07/30/2010 U01788 FY10 - HOPE CREEK OPERATOR LICENSING EXAM 08/23/2010 09/03/2010 U01788 FY10 - HOPE CREEK OPERATOR LICENSING EXAM 7111111 - REQUAL INSP WITH P/F RESULTS 3 09/20/2010 09/24/2010 IP 7111111 B Licensed Operator Requalification Program 71002 - LICENSE RENEWAL INSPECTION 6 08109/2010 08/13/2010 IP 71002 License Renewal Inspection 08/26/2010 08/26/2010 IP 71002 LIcense Renewal Inspection TI-177 - MANAGING GAS ACCUMULATION IN ECCS 3 08/30/2010 09/03/2010 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 71124 - HP 09/13/2010 0911712010 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 09/13/2010 09/17/2010 IP 71124.02 Occupational ALARA Planning and Controls 09/1312010 09/1712010 IP 71124.05 Radiation Monitoring Instrumentation 09/13/2010 09/1712010 IP 71151-0R01 Occupational Exposure Control Effectiveness 09/13/2010 09/17/2010 IP 71151-PR01 RETS10DCM Radiological Effluent ISFSI - 60855.1 - ISFSI (DRS INSPECTION) 2 09/2712010 10/01/2010 IP 60855.1 Operation of an independent Spent Fuei Storage instaiiation at Operating Piants 71124 - HP 10/18/2010 10/22/2010 IP 71124.01. Radiological Hazard Assessment and Exposure Controls 10/18/2010 10/2212010 IP 71124.02 Occupational ALARA Planning and Controls 7111108G -INSERVICE INSPECTION 1 10125/2010 10/29/2010 IP 7111108G lnservice Inspection Activities - BWR 71152 - PI&R 1 01/10/2011 01/14/2011 IP 711528' Identification and Resolution of Problems 01/24/2011 01/28/2011 IP 711528 Identification and Resolution of Problems 71124 - HP 1 02/28/2011 03/04/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 0212812011 03104/2011 IP 71124.02 Occupational ALARA Planning and Controls 02/28/2011 0310412011 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation EP PROGR

This report shows only on-site and announced inspection procedures.

Page 2012 Hope Creek 08130/2010 .15;04:42 Inspection J Activity Plan Report 22 07/01/2010 - 12/31/2011

~~~~~~~~~~~~~~~~--

Planned Dates Start End Title EP PROGR - EP PROGRAM INSPECTION 1 03/14/2011 03/1812011 IP 71151-EP01 Drill/Exercise Performance 03/14/2011 03/18/2011 IP 71151-EP02 ERO Drill Participation 03/14/2011 03/18/2011 IP 71151-EP03 Alert & Notification System 7111117 - PERMANENT PLANT MODIFICATIONS 3 04/04/2011 04/0812011 IP 7111117T Evaluations of Changes. Tests. or Experiments and Permanent Plant Modifications 04t18/2011 0412212011 IP 7111117T Evaluations of Changes. Tests. or Experiments and Permanent Plant Modifications 7111107T - TRIENNIAL HEAT SINK '1 05116/2011 05/20/2011 IP 7111107T Heat Sink Performance 71124 - HP 1 05/1612011 05120/2011 IP 2515/179 Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked In NSTS 05116/2011 05/2012011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 0511612011 05120/2011 IP 71124.04 Occupational Dose Assessment 0511612011 0512012011 IP 71124.05 Radiation Monitoring Instrumentation 71124 - REMP 1 07/2512011 0712912011 IP 71124.07 Radiological Environmental Monitoring Program 71124

  • HP 1 1 09/19/2011 0912312011 IP 60855.1 Operation of an independent Spent Fuei Storage Instailation at Operating Plants 1 09/19/2011 0912312011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 09/19/2011 0912312011 IP 71124.03 In-Plant Airborne Radioactivity Control and Millgation 1 09/1912011 09123'2011 IP 71124.04 Occupational Dose Assessment 71124 - RADWASTE 12/12/2011 12/16/2011 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling. Storage. and Transportation IfhiS report does not include INPO and OUTAGE activities.

IThls report shows only on-site and announced inspection procedures.