Forwards Schedule for Submittal of Info for Open/ Confirmatory Items Awaiting Info,In Response to a Schwencer 850503 Request for Addl Info
ML20128E619
Person / Time
Site: River Bend Entergy icon.png
Issue date: 05/20/1985
From: Booker J
GULF STATES UTILITIES CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8505290429
Download: ML20128E619 (2)


Text

,

e

'4 GULF STATES UTILITIES COMPANY es POSTOFFICEBOX 2951

  • BEAUMONT. TEXAS 777o4 AREA CODE 713 838-6631 May 20, 1985 RBG-File Nos. G9.5, G9.8.6.2 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation

.U.S, Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. Denton:

River Bend Station - Unit 1 Docket-No. 50-458 Pursuant- to your request for a schedule for submittal of information, Gulf States Utilities has listed the items which were identified as'OPEN/ CONFIRMATORY ITEMS AWAITING INFORMATION and provided either a reference for our submittal which provided the information or a scheduled date for the. submittal of.that information. This completes

.our response to Mr. A. Schwencer's Request for Additional Information dated May 3, 1985 (RBC-31,987).

Sincerely,

. E. M J. E. Booker Manager-Engineering, Nuclear Fuels & Licensing River Bend Nuclear Group JEB/ je-Attachment 3

9 g5290429850520 4 ADOCK 05000458-PDR .

. p.

-ISSUES STATUS FROM NRC 5-3-85 LETTER Tyge Abbs. Title Response / Schedule 01.05 Equipment Qualifetn 05/15/85 RBG-20,996&7&8

'0IN.21' Enviro Qualification; 04/26/85 RBG-20,811 CI.04 Pipe fail /chk valve 05/20/85 RBG-21,042 CI.07 Thermal / anchor loads 12/21/84 RBG-19,755 OI.04 Inservice Test Program 05/16/85 RBG-21,019 OI.13. Safe / alt. shutdown 05/17/85 RBG-21,036 CI.01 W. Creek sedent rmovl 05/13/85 RBG-20,959 01.06- Preserv Inspect Prog 05/15/85 RBG-20,992 OIN.22- SPDS 05/15/85 RBG-21,018 CI.60 TMI Item I.C.1 05/15/85 RBG-21,017 CIN.66 Particp in DCRD rev 05/14/85 RBG-20,973 CIN.67: Task Anal document 05/14/85 RBG-20,973 CIN.67 Control room mods 05/12/85 RBG-20,973 OIN.24 Control room survey 05/14/85 RBG-20,973 OIN.25 -Resolution of HEDs 05/14/85 RBG-20,973 01.03 Hi-energy line brks 05/31/85 OIN.23 Standby serv water 05/14/85 RBG-20,974 CI.47- Elect distrib system 05/31/85

  • OI.10 Diesel Generators-Load 05/1//95 RBG-20,993 OIN.19 Separtn-elec cire. 05/0',, . RBG-20,931 CI.12 -Reactr vessl cooldwn 05/15/85 Telecon CI.14 Mark III issues 03/01/85 RBG-20,270 CI.16 Inleakage limit 05/06/85 RBG-20,903 CI.19 Hydrogen control 05/31/85.
  • CI.20 PVLCS leakage 05/06/86 RBG-20,903 OI.07 Containment Loads 05/29/85
  • CI.18 Contain purge valves 05/13/85 RBG-21,037 CI,26. Isolation devices 04/02/85 RBG-20,595 CI.29- ESF reset control 05/31/85
  • CI.40 DRMS 05/10/85 RBG-20,944&5 CI.57 License operator rev 03/07/85 RBG-20,350 CI.62 Proper ESF function 05/31/85 CI.63 Safety system operab 05/17/85 IEIR 85-38
  • Not required for low power license as per 5-3-85 letter and discussions with your Staff.

>