Forwards Quad Cities Nuclea Power Station Unit 1,Cycle 14 Startup Test Result Summary
ML20078M877
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 11/23/1994
From: Pearce L
COMMONWEALTH EDISON CO.
To: Murley T
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
Shared Package
ML20078M880 List:
References
LWP-94-003, LWP-94-3, NUDOCS 9412050192
Download: ML20078M877 (2)


Text

o Commonwealth Edison 4 Cuad Cities Nuclear Power Station 22710 206 Avenue North Cordova. Illinois 61242 Telephone 309/654-2241 LWP-94-003 November 23. 1994 Dr. Thomas Murley, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington. D.C. 20555 Attn: Document Control Desk ,

Subject:

Quad Cities Nuclear Power Station Unit One Startup Test Report Summary NRC Docket No. 50-254

Dear Dr. Murley:

Enclosed for your information and use is the Quad Cities Station Unit One Cycle 14 Startup Test Report Summary. This report is submitted in accordance with Technical Specification DPR-29. Section 6.6. A.1.

Quad Cities Unit One Cycle 14 began commercial operation on August 28. 1994 following a refueling outage. The Unit One Cycle 14 core loading consists of 144 fresh fuel bundles (8x8 GE10 fuel) and 580 reload bundles.

All test data taken to date has been reviewed in accordance with applicable station procedures. Exceptions from any criteria were evaluated to verify compliance with Technical Specification limits to ensure the acceptability of subsequent test results.

Attached are the evaluations of the following tests:

  • Core Verification
  • Initial Critical Prediction Due to a forced shutdown, the Core Power Symmetry Analysis test has not been completed. In accordance with Technical Specification DPR-29. Section 6.6. A.1, a su)plemental report will be submitted in three months or when the test is completed, whichever is earlier.

i STMGRWKO941.WP 010003 9412O50192 941123

[

4 PDR ADOCK 0500 P l

LWP-94-003 Page 2 November 23, 1994 Please contact the Nuclear Engineering Group if there are any questions.

Sincerely, l

2. d. M [

L. W. Pearce Station Manager LWP/FA/kjv Attachment cc: J. Martin Regional Administrator-RIII C. Miller. Resident Inspector-Quad Cities  :

R. Pulsifer. Project Manager-NRR l Office of Nuclear Safety-IDNS  :