MONTHYEARIR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) ML23090A0192023-03-31031 March 2023 Information Request for the Cyber Security Baseline Inspection; Notification to Perform Inspection 05000334/2023401 and 05000412/2023401 IR 05000334/20220062023-03-0101 March 2023 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2022006 and 05000412/2022006) IR 05000334/20220052022-08-31031 August 2022 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2022005 and 05000412/2022005) IR 05000334/20210062022-03-0202 March 2022 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2021006 and 05000412/2021006) IR 05000334/20210052021-09-0101 September 2021 Updated Inspection Plan for the Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2021005 and 05000412/2021005) ML21124A1322021-05-0404 May 2021 Notification of Conduct of a Fire Protection Team Inspection IR 05000334/20200062021-03-0303 March 2021 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2020006 and 05000412/2020006) IR 05000334/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000334/2020005 and 05000412/2020005) IR 05000334/20190062020-03-0303 March 2020 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2019006 and 05000412/2019006) IR 05000334/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000334/2019005 and 05000412/2019005 IR 05000334/20180062019-03-0404 March 2019 Annual Assessment Letter for Beaver Valley Power Station, Unit Nos. 1 and 2 (Reports 05000334/2018006 and 05000412/2018006) IR 05000334/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000334/2018005 and 05000412/2018005 IR 05000334/20170062018-02-28028 February 2018 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2(Reports 05000334/2017006 and 0500412/2017006; 05000334/2017402 and 05000412/2017402 and 05000334-2017501 and 05000412/2017501) ML17271A0662017-09-28028 September 2017 Information Request for the Cyber Security Baseline Inspection Notification to Perform Inspection 05000334/2018403 and 05000412/2018403 IR 05000334/20160062017-03-0101 March 2017 Annual Assessment Letter for Beaver Valley Power Station, Unit Nos. 1 and 2 (Report 05000334/2016006 and 05000412/2016006) with Report 22 IR 05000334/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2016005 and 05000412/2016005) IR 05000334/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Beaver Valley Power Station, Units 1 & 2 (Report 05000334/2015006 and 05000412/2015006) IR 05000334/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Beaver Valley Power Station (Report 05000334/2015005 and 05000412/2015005) IR 05000334/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2, (Report 05000334/2014001 and 05000412/2014001) IR 05000334/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000334/2014006 and 05000412/2014006 IR 05000334/20130012014-03-0404 March 2014 ROP-14 2013 Beaver Valley Power Station Units 1 and 2, Annual Assessment Letter, Report 05000334/2013001 and 05000412/2013001, and Inspection Plan IR 05000334/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000334/2013006 and 05000412/2013006 IR 05000334/20120012013-03-0404 March 2013 Annual Assessment Letter for Beaver Valley Units 1 and 2 (Report 05000334/2012001 and 05000412/2012001) IR 05000334/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Beaver Valley Power Station (Report 05000334/2012006 and 05000412/2012006) IR 05000334/20110012012-03-0505 March 2012 Annual Assessment Letter for Beaver Valley Power Station Units 1 and 2 (Report 05000334-11-001 and 05000412-11-001) ML1124206842011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Beaver Valley Units 1 and 2 IR 05000334/20100012011-03-0404 March 2011 Annual Assessment Letter for Beaver Valley Units 1 and 2, EOC 11 (Report 05000334/2010001 and 05000412/2010001) ML1024406392010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Beaver Valley Units 1 and 2 IR 05000334/20010012010-03-0303 March 2010 Annual Performance Review and Inspection Plan - Beaver Valley Power Station (Beaver Valley) Units 1 and 2 (05000334-01-001 and 05000412-01-001) ML0924401272009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Beaver Valley Units 1 and 2 IR 05000334/20090012009-03-0404 March 2009 Annual Assessment Letter - Beaver Valley Power Station Units 1 and 2 (05000334/2009001 and 05000412/2009001) ML0824704722008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Beaver Valley IR 05000334/20080012008-03-0303 March 2008 (05000334-08-001, 05000412-08-001), Annual Assessment Letter ML0734706972007-12-13013 December 2007 ROP 8 - Beaver Valley - Change to Inspection Plan, 12/13/07 ML0724309412007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan ML0706104772007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Beaver Valley Station ML0624305972006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Beaver Valley Power Station Units 1 and 2 ML0606201582006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Beaver Valley Power Station Units 1 and 2 (Reports 05-334-2006001 and 05-412-2006001) ML0524207222005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Beaver Valley ML0406301322004-03-0202 March 2004 2003-04 Annual Assessment Letter - Beaver Valley ML0323906412003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for Beaver Valley Power Station ML0306205872003-03-0303 March 2003 2003 Annual Assessment Letter - Beaver Valley Power Station, Units 1 & 2 IR 05000334/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - Beaver Valley Power Station Units 1 & 2 (Report 50-334/02-01, 50-412/02-01) 2024-08-29
[Table view] Category:Letter
MONTHYEARML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) IR 05000334/20240102024-08-20020 August 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010 L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-158, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 L-24-157, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations L-24-114, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation L-24-115, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 the Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 ML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 L-23-198, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0707 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 2024-09-17
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 September 1. 2010 Mr. Paul Harden Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P. O. Box 4 Shippingport, PA 15077
SUBJECT:
MID CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN BEAVER VALLEY UNITS 1 AND 2
Dear Mr. Harden:
On August 11, 2010, the NRC staff completed its performance review of Beaver Valley Units 1 and 2 for the first half of calendar year 2010 assessment cycle. Our technical staff reviewed performance indicators (Pis) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Information" will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter of 2010 at Beaver Valley Units 1 and 2 was within the Licensee Response column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all Pis indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2011. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuolls nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice,n a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).
P. Harden 2 As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible.
Please contact me at 610-337-5200 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
~~.\I~
Ronald R. Bellamy, Ph.D., Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-334,50-412 License Nos: DPR-66, NPF-73
Enclosure:
Beaver Valley Units 1 and 2 Inspection/Activity Plan cc w/enels: Distribution via ListServ I
P. Harden 2 As you may know, the NRC is currently evaluating the scope and frequency of aU the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible.
Please contact me at 61 0~337 -5200 with any questions you may have regarding this leHer or the inspection plan.
Sincerely, Ronald R Bellamy, Ph.D., Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-334,50-412 License Nos: DPR-66, NPF-73
Enclosure:
Beaver Valley Units 1 and 2 Inspection/Activity Plan cc w/encls: Distribution via ListServ Distribution w/encl:
M. Dapas, Acting RA N. McNamara, SLO D. Lew, Acting DRA D. Tifft, SLO J. Clifford, ORP D. Screnci, PAD R. Bellamy, DRP N. Sheehan, PAO G. Barber, DRP R. Barkley, ORA C.Newport,DRP John Thompson, NRR L Trocine, RI OEDO RidsNrrDirslpab@nrc.gov D. Werkheiser. SRI, ORP RidsNrrPMBeaver Valley Resource E. Bonney, RI, ORP RidsNrr OorlLpl1-1 Resource P. Garrett, OA. DRP ROPreportsResources@nrc.gov DRS Director DRS Deputy Director DRS Branch Chiefs (6)
SUNSI Review Complete: RRB (Reviewer's Initials) ML102440639 DOCUMENT NAME: S:\ROP-11 Mrd-Cycle Review\Branch 6\Bv\BV ROP-11 MC Cover Ltr.Doc After declaring this document "An Official Agency Record" it will be released to the Public.
To receive a OOfPJ of this document, Indicate in tlla box; "C* K Copy without attachmen!!encloS'Jre "E" = Copy wilh attachment/enclosure "N": No copy RJlDRP SBarberl RRB for 08/24/10 OFFICIAL RECORD COPY
Page 1 of2 '.,' , ,,Beaver Valley 08/30/2010 14:45:15 Inspection I Activity Plan Report 22 07/01/2010
- 12/31/2011 Planned Dates Start End Title 08f16EXM
- U2 INITIAL OPERATOR LICENSING EXAM 4 07/12/2010 07/16/2010 U01821 FY*10 BEAVER VALLEY UNIT 2 INITIAL OPERATOR LICENSING EXAM 08/1612010 08/20f2010 U01821 FY-10 BEAVER VAllEY UNIT 2 INITIAL OPERATOR LICENSING EXAM 71124 - PUB RAD SAFETY - RADWASTE 1 1.2 06/28/2010 07/02f2010 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling. Storage. and Transportation TI179 - 25151T1179 NSTS VERIFICATION 1 1.2 06128/2010 01102/2010 IP 2515/179 Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 71124 - OCC RAD SAFETY
- OCC RAD SAFETY 1 1 1011712010 10/22/2010 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/17/2010 10/22/2010 IP 71124.02 Occupational ALARA Planning and Controls 10/17/2010 10/2212010 IP 71124.04 Occupational Dose Assessment 1.2 10/17/2010 10/2212010 IP 71151 Performance Indicator Verification 71124 - OCC RAD SAFETY 1 1.2 02/1412011 0211812011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1,2 02/14/2011 02/1S/2011 IP 71124.02 Occupational ALARA Planning and Controls 7111108P - U2 INSERVICE INSPECTION 1 2 03/14/2011 03/25/2011 IP 7111108P Inservice Inspection Activities - PWR 71124 -oce RAD SAFETY 1,2 03121/2011 03/2512011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1,2 03/21/2011 03/25/2011 IP 71124.02 Occupational ALARA Planning and Controls 1,2 03/21/2011 03/25/2011 IP 71124.04 Occupational Dose Assessment 711111B - BV2 REQUAL lNSP WI P/F RESULTS 3 1.2 06127/2011 07/01/2011 IP 7111111B L1censed Operator Requaiification Program EP PROGR
- EP PROGRAM INSPECTION 1 1.2 05/16/2011 05/2012011 IP 7111402 Alert and Notification System Testing 1.2 05/16/2011 05/20/2011 lP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1.2 05/16/2011 05/20/2011 IP 7111404 Emergency Action Level and Emergency Plan Changes 1.2 05/1612011 05/20/2011 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1,2 05/16/2011 05/20/2011 IP 71151-EP01 Drill/Exercise Performance his report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of2 Beaver Valley 08/30/2010 14:45:15 Inspection I Activity Plan Report 22 07/01/2010 - 12/31/2011 Planned Dates Start End Title EP PROGR - EP PROGRAM INSPECTION 1.2 05/16/2011 05/20/2011 IP 71151-EP02 ERO Drill Participation 1.2 05/16/2011 05/20/2011 IP 71151-EP03 Alert & Notification System 7111121 - COBI 6 1.2 05/23/2011 05/28/2011 IP 7111121 Component Design Bases Inspection 1.2 0610612011 06/10/2011 IP 7111121 Component Design Bases Inspection 1.2 06/1312011 06/17/2011 IP 7111121 Component Design Bases Inspection 71124 - EFFLUENTS 1.2 06120/2011 06/2412011 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 71124 - OCC RAO SAFETY - REMP 1 1.2 07/18/2011 07/2212011 IP 71124.07 Radiological Environmental Monitoring Program TI-177 - MANAGING GAS ACCUMULATION IN ECCS 3 1.2 07118/2011 07/22/2011 IP 25151177 Managing Gas Accumulation In Emergency Core Cooling. Decay Heat Removal & Containment Spray System 71152B - PI&R 4 08/29/2011 09/02/2011 IP 711528 Identification and Resolution of Problems 1.2 09/12/2011 0911612011 IP 71152B Identification and Resolution of Problems his report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.