Site: Crystal River Duke Energy icon.png
Issue date: 02/17/2011
From: Brian Holian
Division of License Renewal
To: Franke J
Progress Energy Florida
KUNTZ R, NRR/DLR, 415-2989
References
TAC ME0274, TAC ME0278
Download: ML110320090 (3)


Text

UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555*0001 February 17, 2011 Mr. Jon Franke, Vice President Crystal River Nuclear Plant (NA 1 B) ATTN: Supervisor, Licensing

& Regulatory Programs 15760 West Power Line Street Crystal River, FL 34428-6708 SCHEDULE REVISION FOR THE REVIEW OF THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION (TAC NOS. ME0274 AND ME0278)

Dear Mr. Franke:

By letter dated December 16, 2008, the U.S. Nuclear Regulatory Commission (NRC or the staff) received the Florida Power Corporation application for renewal of Operating License No. DPR-72 for Crystal River Unit 3 Nuclear Generating Plant (CR-3) in accordance with Title 10 of the Code of Federal Regulations Section 54.17. By letter dated May 22, 2009 (ADAMS Accession No. ML091200415), the staff issued a proposed schedule for the review of the CR-3 license renewal application.

By letter dated November 5,2010 (ADAMS Accession No. ML103070380), the NRC issued a revised schedule in order to accommodate multiple concurrent license renewal reviews. Due to additional constraints on staff resources affecting the environmental review and the necessity of having an additional Advisory Committee for Reactor Safeguards sub-committee meeting to discuss containment-related issues, the current schedule must be revised. The enclosed schedule contains revised milestone dates. This change has been discussed with Mr. Mike Heath of your staff. If you have any questions, please contact Mr. Robert Kuntz, Project Manager for the review of the CR-3 license renewal application, by telephone at 301-415-3733 or bye-mail at Robert. Kuntz@nrc.gov.

Sincerely, Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302

Enclosure:

As stated cc w/encl: Distribution via Listserv CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING LICENSE RENEWAL UPDATED REVI EW Milestone Scheduled Actual Receive license renewal application (LRA) 12/18/08 12/18/08 Publish Federal Register Notice (FRN) -LRA availability 1/7/09 1/7/09 Publish FRN -acceptancelrejection and opportunity for hearing 3/9/09 3/9/09 Publish FRN -Intent to conduct Environmental Scoping 4/6/09 4/6/09 Public Meeting -License Renewal Overview and Environmental Scoping 4/16/09 4/16/09 Deadline for filing hearing requests and petitions for intervention 5/8109 5/8/09 Environmental scoping period ends 6/8/09 6/8/09 Audit -Scoping & Screening Methodology 6/26/09 6/26/09 Audit -Aging Management Programs 7/17/09 7/17/09 Audit -Environmental 7/24/09 7/24/09 Inspection

-Regional 7/31/09 7/31/09 Issue safety evaluation report (SER) with open items 12/10/10 12/14110 AdviSOry Committee on Reactor Safeguards (ACRS) Subcommittee meeting 1/12/11 1/12/11 Issue draft supplemental environmental impact statement (SEIS) May 2011 Issue SER May 2011 Public Meeting -draft SEIS meeting Jun 2011 ACRS Subcommittee meeting Jun 2011 End of draft SEIS comment period Jul2011 ACRS Full Committee meeting Jul2011 Issue final SEIS Aug 2011 Decision -Director, NRR Sep 2011=

February 17, 2011 Mr. Jon Franke, Vice President Crystal River Nuclear Plant (NA 1 B) ATTN: Supervisor, Licensing

&Regulatory Programs 15760 West Power Line Street Crystal River, FL 34428-6708 SCHEDULE REVISION FOR THE REVIEW OF THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION (TAC NOS. ME0274 AND ME0278)

Dear Mr. Franke:

By letter dated December 16, 2008, the U.S. Nuclear Regulatory Commission (NRC or the staff) received the Florida Power Corporation application for renewal of Operating License No. DPR-72 for Crystal River Unit 3 Nuclear Generating Plant (CR-3) in accordance with Title 10 of the Code of Federal Regulations Section 54.17. By letter dated May 22, 2009 (ADAMS Accession No. ML091200415), the staff issued a proposed schedule for the review of the CR-3 license renewal application.

By letter dated November 5,2010 (ADAMS Accession No. ML103070380), the NRC issued a revised schedule in order to accommodate multiple concurrent license renewal reviews. Due to additional constraints on staff resources affecting the environmental review and the necessity of having an additional Advisory Committee for Reactor Safeguards sub-committee meeting to discuss containment-related issues, the current schedule must be revised. The enclosed schedule contains revised milestone dates. This change has been discussed with Mr. Mike Heath of your staff. If you have any questions, please contact Mr. Robert Kuntz, Project Manager for the review of the CR-3license renewal application, by telephone at 301-415-3733 or bye-mail at Robert. Kuntz@nrc.gov.

Sincerely, IRA! Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302

Enclosure:

As stated cc w/encl: Distribution via Listserv DISTRIBUTION:

See next page ADAMS Accession Number: ML110320090 "concurrence via e-mail E PM:RPB1 :DLR NAME SFigueroa DDoyle DATE 02/01/2011 02/01/2011 BC:RPB2:DL

============jJ D:DLR PM:RPB2:DLR" RKuntz DWrona BHolian 02/01/2011 02/07/2011 02/17/2011 OFFICIAL RECORD COpy Letter to Jon Franke from Brian E. Holian dated February 17, 2011 SCHEDULE REVISION FOR THE REVIEW OF THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION (TAC NOS. ME0274 AND ME0278) HARDCOPY: