Letter Sequence Other |
---|
TAC:ME0278, Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors (Approved, Closed) |
Results
Other: 3F1109-06, State of Florida Department of Environmental Protection, Conditions of Certification, 3F1209-04, Response to Follow-up to Progress Energy RAI Responses on CR-3 SAMA Evaluation, ML090090233, ML090210171, ML090350657, ML090420362, ML090780840, ML091200415, ML091660559, ML091820465, ML092600889, ML092610309, ML093200023, ML093520079, ML100050166, ML100980517, ML100980519, ML100980520, ML100980523, ML100980524, ML100980525, ML100980526, ML100980528, ML101110235, ML101320401, ML101460577, ML110250183, ML110410597, ML110460629, ML110820185, ML110880294, ML11137A009, ML11140A100, ML11180A275, ML11343A639, ML12117A260, ML12213A058, ML12346A011
|
MONTHYEARHNP-09-016, Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Recombiners and Hydrogen Monitors2009-02-26026 February 2009 Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Recombiners and Hydrogen Monitors Project stage: Request ML0902101712009-02-27027 February 2009 Notice of Opportunity for Hearing Regarding Renewal of Facility Operating License No. DPR-72 for an Additional 20-year Period Florida Power Corporation Corporation Crystal River Unit 3 Nuclear Generating Plant Docket No. 50-302 Project stage: Other ML0900902332009-02-27027 February 2009 Determination of Acceptability and Sufficiency for Docketing, and Opportunity for a Hearing Regarding the Application from Florida Power Corp., for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant Project stage: Other ML0907808402009-03-31031 March 2009 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for License Renewal for the Crystal River Unit 3 Nuclear Generating Plant (TAC No ME0278) FRN Project stage: Other ML0903506572009-03-31031 March 2009 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for License Renewal for the Crystal River Unit 3 Nuclear Generating Plant Project stage: Other ML0908501762009-04-20020 April 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0913800232009-05-11011 May 2009 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML0912004152009-05-22022 May 2009 Proposed Review Schedule Regarding the Application from Florida Power Corporation for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant Project stage: Other ML1013204012009-05-31031 May 2009 093-89529, Environmental Support Document South Cooling Tower Laydown Area Citrus County, Florida Project stage: Other ML0904203622009-06-10010 June 2009 Nuclear Generating Plant License Renewal Review Project stage: Other ML0915900062009-07-0202 July 2009 License Amendment, Adoption of Technical Specifications Taskforce (TSTF) Standard Technical Specification Change Traveler TSTF-447, Elimination of Hydrogen Recombiners & Change to Hydrogen & Oxygen Monitors. Project stage: Acceptance Review ML0918204652009-07-0808 July 2009 Plan for the Aging Management Program Regulatory Audit Regarding the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Review Project stage: Other ML0916605592009-07-30030 July 2009 Audit Report Regarding the LRA for the Crystal River, Unit 3 Project stage: Other ML0917400702009-08-0303 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0919700682009-08-10010 August 2009 Request for Additional Information Regarding Severe Accident Mitigation Alternatives for Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0920302082009-08-14014 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0920800452009-08-14014 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0920200122009-08-20020 August 2009 RAI, License Renewal Application Project stage: RAI ML0922507012009-08-20020 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI 3F1109-06, State of Florida Department of Environmental Protection, Conditions of Certification2009-08-28028 August 2009 State of Florida Department of Environmental Protection, Conditions of Certification Project stage: Other ML0923300072009-08-31031 August 2009 RAI for the Review of the Crystal River Unit 3 Nuclear Generating Plant, LRA Project stage: RAI ML0923303432009-08-31031 August 2009 Nuclear Generating Plant, RAI, License Renewal Application Project stage: RAI ML0923308312009-08-31031 August 2009 Request for Additional Information Regarding License Renewal Application Project stage: RAI ML0923309042009-09-0202 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0925800952009-09-11011 September 2009 Response to Requests for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC No. ME0274) and Amendment #2 Project stage: Response to RAI ML0921602132009-09-11011 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0926008882009-09-11011 September 2009 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML0926008892009-09-11011 September 2009 Areva Np, Inc., 51-9057252-001, Rev. 1, CR3 Reconciliation of 60-Year Fluence Projections Used in Reactor Vessel Beltline Embrittlement Calculations for License Renewal, Enclosure Attachment 3 Project stage: Other ML0926502722009-09-18018 September 2009 Response to Requests for Additional Information for the Review of the License Renewal Application and Amendment #3 Project stage: Response to RAI ML0923706692009-09-22022 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Unit Plant, License Renewal Application Project stage: RAI ML0926103092009-09-29029 September 2009 Scoping and Screening Audit Report Regarding the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: Other ML0927901502009-09-30030 September 2009 Response to Requests for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC ME0274) and Amendment #4 Project stage: Response to RAI ML0927901542009-10-0202 October 2009 Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application (TAC No. ME0274) - Sections B.2.37-1, 3.3.2.2, and XI.S8 Project stage: Response to RAI 3F1009-03, Response to Request for Additional Information Regarding Severe Accident Mitigation Alternatives2009-10-0909 October 2009 Response to Request for Additional Information Regarding Severe Accident Mitigation Alternatives Project stage: Response to RAI ML0928901552009-10-13013 October 2009 Response to Request for Additional Information for the Review of Unit 3 Nuclear Generating Plant License Renewal Application and Amendment #5 Project stage: Response to RAI ML0926405542009-10-15015 October 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0930005052009-10-22022 October 2009 Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application (TAC No. ME0274) - and Amendment #6 Project stage: Response to RAI ML0929606602009-10-27027 October 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0929403222009-11-0303 November 2009 Request for Additional Information for the Review of the Crystal River, Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML1009805172009-11-0505 November 2009 License Renewal Revised Environmental Site Audit Needs List Hydrology (Additional Reference 8 Through 16) Project stage: Other ML1009805192009-11-0505 November 2009 Nuclear Generating Plant License Renewal, Revised Environmental Site Audit Needs List, Air, Meteorology, Climate Project stage: Other ML1009805282009-11-0505 November 2009 License Renewal Revised Environmental Site Audit Needs List, Non-Radiological Waste Radiation Protection, Socioeconomics Terrestrial Ecology Project stage: Other ML0931704872009-11-0505 November 2009 Response to Request for Additional Information Re Review of License Renewal Application for Environmental Review Project stage: Response to RAI ML1009805202009-11-0505 November 2009 License Renewal Environmental Site Audit Needs List, Aquatic Ecology (Except AQ-3), Archaeology Project stage: Other ML1009805232009-11-0505 November 2009 License Renewal Environmental Site Audit Needs List, Aquatic Ecology, Additional References, Through AR-3, Page 7 Project stage: Other ML1009805242009-11-0505 November 2009 License Renewal Revised Environmental Site Audit Needs List, Aquatic Ecology AQ-3 Project stage: Other ML1009805182009-11-0505 November 2009 Response to Request for Additional Information Regarding the Review of the License Renewal Application - Revised Environmental Site Audit Needs List Project stage: Response to RAI ML1009805252009-11-0505 November 2009 Plant Operating Manual AI-571, Sea Turtle Rescue and Handling Guidance Project stage: Other ML1009805262009-11-0505 November 2009 License Renewal Revised Environmental Site Audit Needs List, Hydrology (Through Additional Reference 6) Project stage: Other ML1011102352009-11-0505 November 2009 License Renewal Environmental Site Audit Needs List, Aquatic Ecology, AR-3 Page 8 Through AR-6 Project stage: Other 2009-06-10
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commissions Analysis of ADP CR3, LLCs Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan 2024-09-23
[Table view] Category:Schedule and Calendars
MONTHYEARRA-14-0005, Redacted Version of License Amendment Request - Cyber Security Plan Implementation Schedule Milestone 82014-03-31031 March 2014 Redacted Version of License Amendment Request - Cyber Security Plan Implementation Schedule Milestone 8 RA-12-031, Carolina Power & Light Company and Florida Power Corporation'S License Amendment Request - Cyber Security Plan Implementation Schedule Milestones2012-09-12012 September 2012 Carolina Power & Light Company and Florida Power Corporation'S License Amendment Request - Cyber Security Plan Implementation Schedule Milestones ML1103200902011-02-17017 February 2011 Schedule Revision for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application ML1014605772010-08-12012 August 2010 Revised Review Schedule Regarding the Application from Florida Power Corporation for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant ML1020903962010-01-26026 January 2010 Email from Saba, Farideh to Khanna, Meena; Lupold, Timothy; Farzam, Farhad; Thomas, George; Rezai, Aii; Orf, Tracy; Kuntz, Robert; Bernardo, Robert; Subject: OUO - CR3 Concrete Delamination Repair Schedule - OUO ML1029205122010-01-18018 January 2010 Cr3 Npc Outage Containment Repair Project - Level 3 Schedule ML1028710442010-01-0404 January 2010 CR3 Outage Containment Repair Project - Level 3 Schedule ML1028710432010-01-0404 January 2010 Email - Subject: Schedule ML1029105822009-12-28028 December 2009 12-28-09 Level 3 Rev D -11 x17.pdf ML1029106282009-12-21021 December 2009 Email-Subject: FW: CR3 Containment Repair Project Level 1 Schedule Attachments: 12-16-09 Level 1 Rev C - 11x17.pdf ML1029106502009-12-17017 December 2009 Email - from: Lake, Louis (Louis. Lake@Pgnmail.Com) to: Lake Louis Dated Thursday, December 17, 2009 12:05 PM Subject: FW: CR3 Containment Repair Project Level 1 Schedule Attachments: 12-16-09 Level 1 Rev C - 11x17.pdf ML1029106592009-12-16016 December 2009 Email - from: Fagan, Paul (Paul.Fagan@Pgnmail.Com) to Lake, Louis Dated Wednesday, December 16, 2009 6:10 PM Subject: FW: 12-16-09 Containment Repair Project Level 3 Schedule Attachments: 12-16-09 Level 3 Rev B - 11x17.pdf ML1027208432009-10-30030 October 2009 Williams Q&A - Request #32 - 2009-OCT28 Containment Schedule 3F0807-01, Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations.2007-08-15015 August 2007 Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations. 3F0906-02, Response to NRC Regulatory Issue Summary 2006-15, Preparation and Scheduling of Operator Licensing Examinations.2006-09-11011 September 2006 Response to NRC Regulatory Issue Summary 2006-15, Preparation and Scheduling of Operator Licensing Examinations. 2014-03-31
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON. D.C. 20555-0001 August 12. 2010 Mr. Jon Franke, Vice President Crystal River Nuclear Plant (NA 1B)
ATTN: Supervisor, Licensing & Regulatory Programs 15760 W. Power Line Street Crystal River, FL 34428-6708
SUBJECT:
REVISED REVIEW SCHEDULE REGARDING THE APPLICATION FROM FLORIDA POWER CORPORATION FOR RENEWAL OF THE OPERATING LICENSE FOR CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT (TAC NO. ME0278)
Dear Mr. Franke:
By letter dated December 16, 2008, the U.S. Nuclear Regulatory Commission (NRC or the staff) received the Florida Power Corporation application for renewal of Operating License No.
DPR-72 for Crystal River Unit 3 Nuclear Generating Plant (CR-3), in accordance with Title 10 of the Code of Federal Regulations Section 54.17. By letter dated May 22. 2009 (ADAMS Accession No. ML091200415), the staff issued a proposed schedule for the review of the CR-3 license renewal application.
By letter dated January 25, 2010, the NRC issued a revised schedule for the CR-3 license renewal application due to the ongoing analysis of the gap in the containment structure. The January 25,2010, letter noted that "The enclosed schedule may be modified if the resolution of the containment issue does not support the proposed schedule." Because the repair of the containment is ongoing, the staff is again revising the license renewal schedule. The enclosed schedule contains the revised milestone dates.
J. Franke -2 If you have any questions. contact Ms. Elaine Keegan by telephone at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov, or Robert Kuntz at 301-415-3733 or bye-mail at Robert.Kuntz@nrc.gov for the review of the CR-3 license renewal application.
Sincerely, OJ9 V_
David J. Wrona, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302
Enclosure:
As stated cc w/encl: Distribution via Listserv
Crystal River Unit 3 Nuclear Generating Plant LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestones Schedule Actual Draft Supplemental Environmental Impact Statement (SEIS) 11/05/2010 Issued EPA FRN Published - Availability 1 Comment on draft SEIS 11/19/2010 Public Meeting - draft SEIS 12/2010 Safety Evaluation Report (SER) with Open Items - Issued 12/10/2010 End of draft SEIS Comment Period 01/19/2011 ACRS Subcommittee Meeting on SER with Open Items 01/12/2011 Final SEIS - Issued 03/04/2011 EPA FRN Published - Availability of Final SEIS 03/18/2011 SER-Issued 04/11/2011 ACRS Full Committee Meeting on SER 05/12/2011 Decision Director NRR - Approval (if no hearing) 07/15/2011 ENCLOSURE
J. Franke - 2 If you have any questions, contact Ms. Elaine Keegan by telephone at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov, or Robert Kuntz at 301-415-3733 or bye-mail at Robert.Kuntz@nrc.gov for the review of the CR-3 license renewal application.
Sincerely, IRA!
David J. Wrona, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302
Enclosure:
As stated cc w/encl: Distribution via Listserv DISTRIBUTION:
See next page ADAMS Accession No'.. ML101460577 OFFICE PM:RPB2:DLR LA:DLR BC:RPB2:DLR NAME EKeegan IKing DWrona DATE 07/28/10 06/04/10 08/12110 OFFICIAL RECORD COpy
Letter to J. Franke from D. Wrona dated August 12,2010
SUBJECT:
REVISED REVIEW SCHEDULE REGARDING THE APPLICATION FROM FLORIDA POWER CORPORATION FOR RENEWAL OF THE OPERATING LICENSE FOR CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT (TAC NO. ME0278)