ML18153B575

From kanterella
Revision as of 09:17, 23 January 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Forwards Summary Rept Main Control Room & Emergency Switchgear Room Air Conditioning Sys, Confirming Commitments Made in 881019 Ltr & During 881026 Meeting Re Items Requiring Corrective Action Prior to Restart
ML18153B575
Person / Time
Site: Surry  Dominion icon.png
Issue date: 01/06/1989
From: CARTWRIGHT W R
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
Shared Package
ML18153B576 List:
References
88-689A, NUDOCS 8901200420
Download: ML18153B575 (2)


Text

( e e VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 W. R. C.A.RTWR:COHT VICE PRESIDENT NucLEAR January 6, 1989 United States Nuclear Regulatory Commission Attention:

Document Control Desk Washington, D. C. 20555 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 CONFIRMATION OF ACTION LETTER MAIN CONTROL ROOM.AND EMERGENCY SWITCHGEAR ROOM AIR CONDITIONING SYSTEM -

SUMMARY

REPORT Serial No. NO/DAS:vlh Docket Nos. License Nos. 88-689A 50-280 50-281 DPR-32 DPR-37 Our letter (Serial No.88-689) of October 19, 1988, in conjunction with commitments made during a meeting on October 26, 1988, identified several items which required investigation and appropriate corrective action prior to plant restart. One of those items addresses the adequacy of the main control room and emergency switchgear room air conditioning system. This letter forwards for your information and review the summary report of this issue which includes test findings, corrective actions, and interim operating restrictions.

Should you have any questions concerning the summary report, please do not hesitate to contact us. W. R. Cartwright Attachment


Summary Report -Main Control Room and Emergency Switchgear Room Air Conditioning System 8901200420 890106 PDR ADOCK 05000280 P PDC

.. cc: U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, N. W. Suite 2900 Atlanta, Georgia 30323 Mr. W. E. Holland NRG Senior Resident Inspector Surry Power Station Mr. B. C. Buckley NRG Surry Project Manager Project Directorate II-2 Division of Reactor Projects -I/II