Category:Letter
MONTHYEARIR 05000324/20253012024-10-17017 October 2024 Notification of Licensed Operator Initial Examination 05000325/2025301 and 05000324/2025301 IR 05000324/20244012024-10-15015 October 2024 Security Baseline Inspection Report 05000324/2024401 and 05000325/2024401 ML24297A6262024-10-11011 October 2024 PCA Letter to NRC Brunswick Potential Tropical Storm Eight IR 05000324/20240102024-09-10010 September 2024 Focused Engineering Inspection Commercial Grade Dedication Report 05000324-2024010 and 05000325-2024010 ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000324/20240052024-08-23023 August 2024 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2024005 and 05000325/2024005) IR 05000324/20240022024-08-0505 August 2024 Integrated Inspection Report 05000324/2024002 and 05000325/2024002 and 07200006/2024001 ML24206A1062024-07-30030 July 2024 2024 Brunswick Requal Inspection Corporate Notification Letter ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000324/20244202024-07-0202 July 2024 – Security Baseline Inspection Report 05000324/2024420 and 05000325/2024420 ML24108A0702024-06-0505 June 2024 – Issuance of License Amendments to Revise the 10 CFR 50.69 Categorization Process to Reflect an Alternative Seismic Approach IR 05000324/20244022024-05-17017 May 2024 Plan Material Control and Accounting Program Inspection Report 05000324/2024402 and 05000325/2024402 - Cover Letter IR 05000324/20240012024-05-0909 May 2024 Integrated Inspection Report 05000324/2024001 and 05000325/2024001 05000325/LER-2024-001, Primary Containment Penetration Local Leak Rate Testing Failure2024-04-10010 April 2024 Primary Containment Penetration Local Leak Rate Testing Failure 05000325/LER-2024-002, Re Automatic Start of Emergency Diesel Generator Due to Emergency Bus De-energization2024-04-10010 April 2024 Re Automatic Start of Emergency Diesel Generator Due to Emergency Bus De-energization IR 05000324/20243012024-04-0303 April 2024 NRC Operator License Examination Report 05000325/2024301 and 05000324/2024301 ML24066A0132024-03-0505 March 2024 Bru 2024-002 Radiation Safety Baseline Inspection Information Request ML24026A0982024-03-0101 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0057 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000324/20230062024-02-28028 February 2024 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 – NRC Inspection Reports 05000324/2023006 and 05000325/2023006 IR 05000324/20244032024-02-14014 February 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perm Inspection 05000325/2024403; 05000324/2024403 ML24032A1392024-02-12012 February 2024 Correction of Errors within Authorized Alternative Request RA-22-0308 IR 05000324/20230042024-02-0606 February 2024 Integrated Inspection Report 05000324/2023004 and 05000325/2023004 IR 05000324/20230112023-12-26026 December 2023 NRC Fire Protection Team Inspection - FPTI Report 05000324/2023011 and 05000325/2023011 IR 05000324/20234022023-12-14014 December 2023 Security Baseline Inspection Report 05000324-2023402 and 05000325-2023402 ML23297A0262023-11-27027 November 2023 Proposed Alternatives to ASME Code Section XI Subsection IWE Requirements for Torus Metallic Liner Inspections ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230032023-11-0101 November 2023 Integrated Inspection Report 05000324/2023003 and 05000325/2023003 IR 05000324/20230102023-10-17017 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000324/2023010 and 05000325/2023010 IR 05000325/20234012023-10-16016 October 2023 Security Baseline Inspection Report 05000324 and 05000325 2023401 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230052023-08-23023 August 2023 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2023005 and 05000325/2023005) IR 05000324/20230022023-08-0404 August 2023 Integrated Inspection Report 05000324/2023002 and 05000325/2023002 ML23201A2042023-07-28028 July 2023 Summary of Regulatory Audit in Support of Alternative Request RA-22-0308 for Inservice Inspection of the Torus Metallic Liner ML23212B2682023-07-25025 July 2023 Notification of Licensed Operator Initial Examination 05000325/2024301 and 05000324/2024301 ML23212A9502023-05-24024 May 2023 Engine Systems, Inc., Part 21 Report Re Woodward EGB-35P Governor/Actuator with Foreign Material ML23146A0012023-05-24024 May 2023 EN 56538 - Engine Systems Inc and Brunswick ML23130A3902023-05-12012 May 2023 Regulatory Audit Plan in Support of Alternative Request RA 22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20230012023-05-10010 May 2023 Integrated Inspection Report 05000324 2023001 and 05000325 2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000324/20220042023-04-0404 April 2023 Reissue - Brunswick Steam Electric Plant - Integrated Inspection Report 05000324/2022004 and 05000325/022004 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000324/20220062023-03-0101 March 2023 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 NRC Inspection Reports 05000324/2022006 and 05000325/2022006 ML23033A5252023-02-0808 February 2023 Integrated Inspection Report 05000324/2022004 and 05000325/2022004 IR 05000324/20223012023-02-0303 February 2023 NRC Operator License Examination Report 05000325/2022301 and 05000324/2022301 ML22332A0132022-11-23023 November 2022 Operator Licensing Written Examination Approval 05000325/2022301 and 05000324/2022301 IR 05000324/20224022022-11-23023 November 2022 Security Baseline Inspection Report 05000324 2022402 and 05000325 2022402 ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 2024-09-04
[Table view] Category:Meeting Agenda
MONTHYEARPMNS20240492, Duke Sites Annual Assessment Meeting2024-04-10010 April 2024 Duke Sites Annual Assessment Meeting ML24100A8062024-04-0909 April 2024 Duke Energy Sites Annual Assessment Meeting Presentation Slides April 23, 2024 PMNS20230392, Annual Assessment Meeting2023-04-0707 April 2023 Annual Assessment Meeting PMNS20220350, Annual Assessment Meetingshearon Harris Nuclear Power Plant Annual Assessment Meeting2022-04-0404 April 2022 Annual Assessment Meetingshearon Harris Nuclear Power Plant Annual Assessment Meeting PMNS20210385, and Shearon Harris Nuclear Plant 2020 Annual Assessment Meeting2021-04-12012 April 2021 and Shearon Harris Nuclear Plant 2020 Annual Assessment Meeting ML21041A4532021-02-17017 February 2021 Brunswick/Nrc Pre-submittal Meeting: LAR to Adopt TSTF-505, Rev. 2 (Risk-Informed Completion Times) Presentation ML21041A4822021-02-10010 February 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Proposed License Amendment Request to Adopt TSTF-505 ML21022A2292021-01-22022 January 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Proposed Standby Liquid Control System License Amendment Request ML21011A1472021-01-11011 January 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Inservice Testing of Safety Relief Valves Relief Request ML21007A1942021-01-0707 January 2021 Closed Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Underground Service Water Pipe Coating Relief Valves Relief Request PMNS20201240, Closed Meeting with Duke Energy to Update the U.S. Nuclear Regulatory Commission Staff Security Plan Changes2020-10-22022 October 2020 Closed Meeting with Duke Energy to Update the U.S. Nuclear Regulatory Commission Staff Security Plan Changes ML20100G6342020-04-0909 April 2020 Revised- Bru 2019 Annual Assessment Meeting Slides ML18130A6942018-05-10010 May 2018 Agenda - Power Uprates Subcommittee Meeting - May 16, 2018 ML14140A2912014-05-20020 May 2014 EA-14-048 Public Meeting Summary - Regulatory Conference and Predecision Enforcement Conference for Brunswick Steam Electric Plant ML14106A2622014-04-16016 April 2014 Notice of Category 3 Public Meeting Regarding Brunswick Steam Electric Plant to Discuss NRC Reactor Oversight Process Annual Assessment ML13295A3062013-10-22022 October 2013 Meeting Notice with Duke Energy Carolinas, LLC Discuss the Planned Modifications Related to the Fukushima Flood Hazard Reevaluations for the Sites Operated by Duke Energy Carolinas, LLC ML13221A5122013-08-12012 August 2013 8/20/2013 - Closed Notice of Forthcoming Meeting with Duke Energy Regarding Mella Brunswick Steam Electric Plant, Units 1 and 2 ML13106A3372013-04-17017 April 2013 Notice of Forthcoming Meeting with Duke Energy, Inc. Concerning the Relocation of the Emergency Operating Facilities ML12346A2842012-12-18018 December 2012 Forthcoming Public Conference Call Meeting with Duke Energy Carolinas Re Mellla+ for Brunswick Steam Electric Plant, Units 1 and 2, to Discuss the Maximum Extended Load Limit Analysis Plus (Mellla+) Implementation ML12300A4032012-10-26026 October 2012 11/8/2012 Meeting Notice with Duke Energy to Discuss NRC Order on Mitigation Strategies for Beyond-design-Basis External Events ML12160A5732012-06-11011 June 2012 Meeting Notice - Forthcoming Pre-Application Conference Call with Carolina Power and Light Company Regarding National Fire Protection Association Standard 805 for Brunswick Steam Electric Plant, Units 1 and 2 ML12144A2802012-05-23023 May 2012 Notice of Forthcoming Pre-Application Meeting with Carolina Power and Light Company Regarding Emergency Diesel Generator Completion Time Extension for Brunswick Steam Electric Plant, Units 1 and 2 ML12128A3462012-05-10010 May 2012 Meeting Notice - Forthcoming Notice of Pre-application Meeting with Carolina Power & Light Company Regarding NFPA805 ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML11126A0962011-05-12012 May 2011 Notice of Meeting with Petitioner Requesting Action Under 10CFR2.206 Regarding Immediate Suspension of Operating Licenses of General Electric Mark 1 Boiling Water Reactors ML1108406312011-03-29029 March 2011 Notice of Forthcoming Pre-Application Meeting with Carolina Power & Light Co. and Florida Power Corp., Brunswick Units 1 & 2, Crystal River Unit 3, and H.B. Robinson Unit 2, to Discuss Transition to the Requirements of National Fire.. ML0921609632009-08-0404 August 2009 Meeting Summary - Public Meeting Category 1 - Preliminary White Finding - Brunswick Steam Electric Plant ML0830800052008-10-31031 October 2008 Meeting Slides, Progress Energy Public Meeting, NRC Region II Visit ML0733711662007-12-0303 December 2007 Notice of Meeting with Progress Energy & Duke Energy Regarding Fire Probabilistic Risk Assessment for the Pilot Plants Transitioning to the National Fire Protection Association Standard NFPA 805 BSEP 07-0108, Areva Presentation Slides for Brunswick Fuel Transition License Amendment Request2007-07-31031 July 2007 Areva Presentation Slides for Brunswick Fuel Transition License Amendment Request ML0715503752007-06-0404 June 2007 Notice of Meeting with Brunswick Steam Electric Plant Regarding Security-Based Event Emergency Preparedness Drill Scenario Review ML0711503272007-04-23023 April 2007 Brunswick, EOC Slides, Cy 2006 ML0710804062007-04-0505 April 2007 Emergency Diesel Generator No. 1 Trip and Failure of Engine Crankshaft Bearing ML0707502252007-03-16016 March 2007 Notice of Meeting with Carolina Power and Light Company to Discuss the Trip of Emergency Diesel Generator (EDG) #1 and Failure of Engine Crankshaft Bearing on 11/02/2006, & to Discuss Brunswick Site and EDG Improvements ML0605503872006-02-24024 February 2006 Meeting to Discuss Fuel Transition to Framatome Anf with Carolina Power & Light Company ML0526503162005-09-23023 September 2005 Notice of Category 1 Meeting with Carolina Power and Light Co., Brunswick Units 1 and 2 MSIV TS Revisions ML0432703752004-11-22022 November 2004 Progress Energy, Meeting Notice to Communicate the Current Status and Results to Date of Progress Energy'S Initiatives in the Area of Fire Protection ML0335605522003-12-22022 December 2003 Forthcoming Meeting with Carolina Power Co. to Discuss Details of Ongoing Work ML0304400702003-02-13013 February 2003 Meeting with Carolina Power & Light Co., to Discuss Plans for Corrective Actions & Modifications for Brunswick Sprinkler Heads Under Heat Collectors in Cable Spreading Room ML17252A1551977-09-19019 September 1977 Summary of Meeting with Representatives of the Mark I Owner'S Group and GE to Discuss the Structural Acceptance Criteria for the Mark I Containment Ltp ML17252A1571977-09-14014 September 1977 Summary of Meeting Held with Representatives of the Mark I Owner'S Group to Discuss the Structural Acceptance Criteria for the Mark I Containment Long Term Program 2024-04-09
[Table view] Category:Meeting Notice
MONTHYEARPMNS20240492, Duke Sites Annual Assessment Meeting2024-04-10010 April 2024 Duke Sites Annual Assessment Meeting PMNS20230392, Annual Assessment Meeting2023-04-0707 April 2023 Annual Assessment Meeting PMNS20220350, Annual Assessment Meetingshearon Harris Nuclear Power Plant Annual Assessment Meeting2022-04-0404 April 2022 Annual Assessment Meetingshearon Harris Nuclear Power Plant Annual Assessment Meeting PMNS20210385, and Shearon Harris Nuclear Plant 2020 Annual Assessment Meeting2021-04-12012 April 2021 and Shearon Harris Nuclear Plant 2020 Annual Assessment Meeting ML21041A4822021-02-10010 February 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Proposed License Amendment Request to Adopt TSTF-505 ML21022A2292021-01-22022 January 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Proposed Standby Liquid Control System License Amendment Request ML21011A1472021-01-11011 January 2021 Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Inservice Testing of Safety Relief Valves Relief Request ML21007A1942021-01-0707 January 2021 Closed Pre-Submittal Teleconference with Duke Energy Progress, LLC Regarding Brunswick Steam Electric Plant, Units 1 and 2 - Underground Service Water Pipe Coating Relief Valves Relief Request PMNS20201240, Closed Meeting with Duke Energy to Update the U.S. Nuclear Regulatory Commission Staff Security Plan Changes2020-10-22022 October 2020 Closed Meeting with Duke Energy to Update the U.S. Nuclear Regulatory Commission Staff Security Plan Changes ML14106A2622014-04-16016 April 2014 Notice of Category 3 Public Meeting Regarding Brunswick Steam Electric Plant to Discuss NRC Reactor Oversight Process Annual Assessment ML13295A3062013-10-22022 October 2013 Meeting Notice with Duke Energy Carolinas, LLC Discuss the Planned Modifications Related to the Fukushima Flood Hazard Reevaluations for the Sites Operated by Duke Energy Carolinas, LLC ML13221A5122013-08-12012 August 2013 8/20/2013 - Closed Notice of Forthcoming Meeting with Duke Energy Regarding Mella Brunswick Steam Electric Plant, Units 1 and 2 ML13136A0562013-05-16016 May 2013 7/23-24/2013 Notice of Public Meeting Announcement with All Region II Licensees, Initial Examination Writers' Workshop ML13106A3372013-04-17017 April 2013 Notice of Forthcoming Meeting with Duke Energy, Inc. Concerning the Relocation of the Emergency Operating Facilities ML13093A2202013-04-0303 April 2013 Meeting Announcement - Category 3 Public Meeting - Annual Assessment of Brunswick Steam Electric Plant, Docket Nos. 50-325, 50-324 ML12346A2842012-12-18018 December 2012 Forthcoming Public Conference Call Meeting with Duke Energy Carolinas Re Mellla+ for Brunswick Steam Electric Plant, Units 1 and 2, to Discuss the Maximum Extended Load Limit Analysis Plus (Mellla+) Implementation ML12300A4032012-10-26026 October 2012 11/8/2012 Meeting Notice with Duke Energy to Discuss NRC Order on Mitigation Strategies for Beyond-design-Basis External Events ML12284A4612012-10-12012 October 2012 Forthcoming Meeting Notice with Duke Energy to Discuss NRC Order on Mitigation Strategies for Beyond-Design-Basis External Events ML12221A2612012-08-0707 August 2012 09/25-26/2012 Noticeo of Meeting Announcement - 2012 U.S. Nuclear Regulatory Commission (NRC) Initial Examination Writers' Workshop ML12160A5732012-06-11011 June 2012 Meeting Notice - Forthcoming Pre-Application Conference Call with Carolina Power and Light Company Regarding National Fire Protection Association Standard 805 for Brunswick Steam Electric Plant, Units 1 and 2 ML12153A1592012-06-0101 June 2012 Notice of Category 1 Public Meeting - Annual Assessment of Brunswick ML12144A2802012-05-23023 May 2012 Notice of Forthcoming Pre-Application Meeting with Carolina Power and Light Company Regarding Emergency Diesel Generator Completion Time Extension for Brunswick Steam Electric Plant, Units 1 and 2 ML12128A3462012-05-10010 May 2012 Meeting Notice - Forthcoming Notice of Pre-application Meeting with Carolina Power & Light Company Regarding NFPA805 ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML1115403882011-06-0202 June 2011 08/02-03/2011 Meeting Announcement - 2011 U.S. Nuclear Regulatory Commission (NRC) Initial Examination Writers Workshop ML11126A0962011-05-12012 May 2011 Notice of Meeting with Petitioner Requesting Action Under 10CFR2.206 Regarding Immediate Suspension of Operating Licenses of General Electric Mark 1 Boiling Water Reactors ML1112200802011-05-0202 May 2011 Notice of Category 1 Public Meeting to Discuss Nrc'S Reactor Oversight Process Annual Assessment of Brunswick Steam Electric Plant ML1108406312011-03-29029 March 2011 Notice of Forthcoming Pre-Application Meeting with Carolina Power & Light Co. and Florida Power Corp., Brunswick Units 1 & 2, Crystal River Unit 3, and H.B. Robinson Unit 2, to Discuss Transition to the Requirements of National Fire.. ML1015501432010-06-0404 June 2010 08/17-18/2010 Meeting Announcement - 2010 NRC Initial Exam Writers Workshop ML1014400462010-05-21021 May 2010 Notice of Public Meeting to Discuss Fire Protection Screening Criteria Identified at Browns Ferry and Their Implications to Brunswick Steam Electric Plant - Docket Nos. 05000325 and 05000324 ML1013105942010-05-11011 May 2010 Notice of Public Meeting with Carolina Power and Light to Discuss NRC Reactor Oversight Process Annual Assessment of Brunswick Steam Electric Plant ML0936404762009-12-30030 December 2009 Notice of Public Meeting Announcement Category 1, with Brunswick Regarding Human Performance Improvement Plan ML0927903892009-10-0606 October 2009 Notice of Category 1 Public Meeting with Brunswick to Discuss Issues Regarding Emergency Diesel Generators and Corrective Actions ML0919501722009-07-13013 July 2009 Notice of Meeting with Brunswick Steam Electric Plant to Discuss a Preliminary White Finding Involving Failure to Correctly Translate Design Basis Into an Engineering Change to Replace Control Relays on All Four Emergency Diesel Generators ML0918004532009-06-29029 June 2009 Meeting Announcement - Category 2 Public Meeting, 2009 U.S. Nuclear Regulatory Commission (NRC) Initial Examination Development Workshop ML0912708612009-05-0707 May 2009 Notice of Category 1 Public Meeting with Carolina Power & Light and Florida Power Corp., Regarding Brunswick Performance and Organizational Alignment within the Company ML0912708402009-05-0707 May 2009 Notice of Meeting with Carolina Power and Light to Discuss the NRC Reactor Oversight Process Annual Assessment of Brunswick Steam Electric Plant Units 1 and 2 ML0825209362008-09-0808 September 2008 Notice of Public Category 1 Meeting with Carolina Power & Light and Florida Power Corporation Organizational Alignment within the Company ML0819600282008-07-11011 July 2008 08/05-06/2008-Notice of Meeting - 2008 Us Nuclear Regulatory Commission Initial Examination Development Workshop ML0810704112008-04-16016 April 2008 Notice of Meeting with Carolina Power and Light to Discuss Their Corrective Actions Regarding the White Mitigating Systems Performance Indicators for Emergency AC Power Systems and Cooling Water Systems, and the White Inspection Finding... ML0733711662007-12-0303 December 2007 Notice of Meeting with Progress Energy & Duke Energy Regarding Fire Probabilistic Risk Assessment for the Pilot Plants Transitioning to the National Fire Protection Association Standard NFPA 805 ML0713706072007-05-17017 May 2007 Notice of Meeting for NRC Training Managers' Conference Hosting by Rgn II ML0712803242007-05-0808 May 2007 Notice of Meeting with Progress Energy Regarding the Licensee'S Plans for Providing Further Information to Support the Transition to Areva Fuel at Brunswick Nuclear Generating Station ML0709601712007-04-0606 April 2007 Notice of Meeting with Carolina Power & Light Company to Discuss the NRC Reactor Oversight Process Annual Assessment of Brunswick Steam Electric Plant Units 1 and 2 ML0707502252007-03-16016 March 2007 Notice of Meeting with Carolina Power and Light Company to Discuss the Trip of Emergency Diesel Generator (EDG) #1 and Failure of Engine Crankshaft Bearing on 11/02/2006, & to Discuss Brunswick Site and EDG Improvements ML0618700742006-07-0505 July 2006 and 07/20/2006 Meeting Announcement 2006 NRC Initial Exam Development Workshop to Clarify the Exam Development Process and Question Development for Both the Written and Operating Portion of the Initial Examination ML0616400032006-06-12012 June 2006 Meeting Announcement - Public Meeting - Brunswick ML0607903442006-03-20020 March 2006 Public Meeting Notice with Brunswick Media Center, to Discuss the NRC Reactor Oversight Process Annual Assessment for Brunswick Steam Electric Plant ML0605503872006-02-24024 February 2006 Meeting to Discuss Fuel Transition to Framatome Anf with Carolina Power & Light Company ML0526503162005-09-23023 September 2005 Notice of Category 1 Meeting with Carolina Power and Light Co., Brunswick Units 1 and 2 MSIV TS Revisions 2024-04-10
[Table view] |
Text
March 16, 2007 EA-07-024 Carolina Power and Light Company ATTN: Mr. James Scarola Vice President Brunswick Steam Electric Plant P. O. Box 10429 Southport, NC 28461
SUBJECT:
MEETING ANNOUNCEMENT- REGULATORY CONFERENCE AND MANAGEMENT MEETINGS - BRUNSWICK STEAM ELECTRIC PLANT -
DOCKET NO. 05000325 AND 05000324
Dear Mr. Scarola:
This letter confirms the telephone conversation between Ms. Annette Pope of your staff and myself of this office on March 8, 2007, concerning a Regulatory Meeting (Category One) which has been scheduled for April 5, 2007, from 10:00 a.m. to 12:00 p.m. and a Management Meeting (Category One) which has been scheduled for April 5, 2007, from 1:00 p.m. to 2:00 p.m. The meeting notices, which provide additional details, are enclosed. The purposes of the meetings are to discuss the trip of emergency diesel generator (EDG) #1 and failure of engine crankshaft bearing on November 2, 2006, and to discuss Brunswick site and EDG improvements. These meetings are being conducted at your request.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/NRC/ADAMS/index.html (the Public Electronic Reading Room).
2 Should you have any questions concerning this conference, please contact me at 404-562-4603 Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects
Enclosures:
As Stated Docket Nos.: 50-325, 50-324 License Nos.: DPR-71, DPR-62
OFFICE RII/DRP RII/DRP SIGNATURE SON NAME SNinh DATE 03/16/2007 03/ /2007 3/ /2007 3/ /2007 3/ /2007 3/ /2007 3/ /2007 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO 3
Benjamin C. Waldrep Beverly Hall, Chief, Radiation Plant Manager Protection Section Brunswick Steam Electric Plant N. C. Department of Environment Carolina Power & Light Company and Natural Resources Electronic Mail Distribution Electronic Mail Distribution James W. Holt, Manager Peggy Force Performance Evaluation and Assistant Attorney General Regulatory Affairs PEB 7 State of North Carolina Carolina Power & Light Company Electronic Mail Distribution Electronic Mail Distribution Chairman of the North Carolina Edward T. O'Neil, Manager Utilities Commission Training c/o Sam Watson, Staff Attorney Carolina Power & Light Company Electronic Mail Distribution Brunswick Steam Electric Plant Electronic Mail Distribution Robert P. Gruber Executive Director Randy C. Ivey, Manager Public Staff NCUC Support Services 4326 Mail Service Center Carolina Power & Light Company Raleigh, NC 27699-4326 Brunswick Steam Electric Plant Electric Mail Distribution Public Service Commission State of South Carolina Garry D. Miller, Manager P. O. Box 11649 License Renewal Columbia, SC 29211 Progress Energy Electronic Mail Distribution David R. Sandifer Brunswick County Board of Annette H. Pope, Supervisor Commissioners Licensing/Regulatory Programs P. O. Box 249 Carolina Power and Light Company Bolivia, NC 28422 Electronic Mail Distribution Warren Lee David T. Conley Emergency Management Director Associate General Counsel - Legal Dept. New Hanover County Department of Progress Energy Service Company, LLC Emergency Management Electronic Mail Distribution P. O. Box 1525 Wilmington, NC 28402-1525 James Ross Nuclear Energy Institute Electronic Mail Distribution John H. O'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128
4 Letter to James Scarola from Randall A. Musser dated March 16, 2007.
SUBJECT:
MEETING ANNOUNCEMENT- REGULATORY CONFERENCE AND MANAGEMENT MEETINGS - BRUNSWICK STEAM ELECTRIC PLANT -
DOCKET NO. 05000325 AND 05000324 Distribution w/encl:
Region II Administrator's Secretary Region II DRP Division Secretary Region II Division Directors and Deputies Region II Counsel Region II State Liaison Officer Region II Public Affairs Officer Region II Resource Management Branch Region II Receptionist Region II Regional Coordinator OEDO Headquarters Operation Officer PMNS S. Bailey, NRR R. Franovich, NRR (Regulatory Conferences Only)
L. Slack, RII EICS RIDSNRRDIRS RIDSNRRDIRSIPAB OE Mail (email address if applicable)
PUBLIC
SUBJECT:
REGULATORY CONFERENCE WITH THE PROGRESS ENERGY-CAROLINA POWER AND LIGHT COMPANY FACILITY: Brunswick Steam Electric Plant, Unit 1 DOCKET: 50-325 DATE & TIME: Thursday, April 5, 2007 10:00 a.m. to 12:00 p.m.
LOCATION: NRC Region II Office Sam Nunn Atlanta Federal Center (Suite 24T25) 61 Forsyth Street, S.W.
Atlanta, GA 30303-3415 PURPOSE: To discuss the trip of emergency diesel generator (EDG) #1 and failure of engine crankshaft bearing on November 2, 2006 The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov , and contains information regarding conduct of NRC meetings.
CATEGORY: This is a Category 1 meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
NRC OFFICE(S)
PARTICIPATING: Region II, NRR and OE OTHER ORGANIZATIONS PARTICIPATING: None PARTICIPANTS: NRC (partial list)
W. Travers, Regional Administrator, Region II (RII)
C. Casto, Director, Division of Reactor Projects (DRP), RII J. Shea, Director, Division of Reactor Safety (DRS)
R. Musser, Chief, Division of Reactor Projects Branch 4, RII R. Bernhardt, Senior Reactor Analyst, DRS, RII C. Evans, Regional Counsel and Enforcement Officer, RII S. Sparks, Enforcement Specialist, RII M. Franovich, Chief, PRA Licensing Branch, Office of Nuclear Reactor Regulation (NRR)
S. Wong, Senior Reactor Analyst, NRR L. Trocine, Senior Enforcement Specialist, Office of Enforcement (OE)
Enclosure
2 LICENSEE J. Scarola, Site Vice President B. Waldrep, Plant General Manager S. Howard, Operations Manager T. Trask, Engineering Manager S. Rogers, Maintenance Manager R. Ivey, Support Services Manager R. Rishel, PRA Supervisor MEETING CONTACT: R. Musser. NRC, RII (404)562-4603 RXM1@NRC.GOV AUDIO TELE-CONFERENCE: Interested members of the public can participate in this meeting via a toll-free audio teleconference. Please contact the NRC meeting contact in advance of the meeting, indicating your intent to attend and to obtain teleconferencing information by no later than April 2, 2007.
VIDEO TELE -
CONFERENCE: Not available
SUBJECT:
MANAGEMENT MEETING WITH THE PROGRESS ENERGY- CAROLINA POWER AND LIGHT COMPANY FACILITY: Brunswick Steam Electric Plant DOCKETS: 50-325 and 50-324 DATE & TIME: Thursday, April 5, 2007 1:00 p.m. to 2:00 p.m.
LOCATION: NRC Region II Office Sam Nunn Atlanta Federal Center (Suite 24T25) 61 Forsyth Street, S.W.
Atlanta, GA 30303-3415 PURPOSE: To discuss Brunswick site and EDG improvements. The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov , and contains information regarding conduct of NRC meetings.
CATEGORY: This is a Category 1 meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
NRC OFFICE(S)
PARTICIPATING: Region II OTHER ORGANIZATIONS PARTICIPATING: None PARTICIPANTS: NRC (partial list)
W. Travers, Regional Administrator, Region II (RII)
C. Casto, Director, Division of Reactor Projects (DRP), RII J. Shea, Director, Division of Reactor Safety (DRS)
R. Musser, Chief, Division of Reactor Projects Branch 4, RII R. Bernhardt, Senior Reactor Analyst, DRS, RII LICENSEE J. Scarola, Site Vice President B. Waldrep, Plant General Manager S. Howard, Operations Manager T. Trask, Engineering Manager Enclosure
2 S. Rogers, Maintenance Manager R. Ivey, Support Services Manager R. Rishel, PRA Supervisor MEETING CONTACT: R. Musser. NRC, RII (404)562-4603 RXM1@NRC.GOV AUDIO TELE-CONFERENCE: Interested members of the public can participate in this meeting via a toll-free audio teleconference. Please contact the NRC meeting contact in advance of the meeting, indicating your intent to attend and to obtain teleconferencing information by no later than April 2, 2007.
VIDEO TELE -
CONFERENCE: Not available