| ML071370700 OFFICE PDI-2/PM PDI-1/LA EEEB CVIB/BC SBWB/BC IOLB/BC SBPB/BC PD1-2/BC NAME JShea SLittle GWilson MMitchell GCranston NSalgado JSegala HChernoff DATE 5/17/07 5/17/07 5/4/07 5/3/07 5/3/07 5/3/07 5/4/07 5/17/07 | | ML071370700 OFFICE PDI-2/PM PDI-1/LA EEEB CVIB/BC SBWB/BC IOLB/BC SBPB/BC PD1-2/BC NAME JShea SLittle GWilson MMitchell GCranston NSalgado JSegala HChernoff DATE 5/17/07 5/17/07 5/4/07 5/3/07 5/3/07 5/3/07 5/4/07 5/17/07 Hope Creek Generating Station Mr. Michael Jesse Manager - Regulatory Assurance cc: P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Dennis Winchester Vice President - Nuclear Assessments Township Clerk PSEG Nuclear Lower Alloways Creek Township P.O. Box 236 Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. George P. Barnes Mr. Paul Bauldauf, P.E., Asst. Director Site Vice President - Hope Creek Radiation Protection Programs PSEG Nuclear NJ Department of Environmental P.O. Box 236 Protection and Energy Hancocks Bridge, NJ 08038 CN 415 Trenton, NJ 08625-0415 Mr. George H. Gellrich Plant Support Manager Mr. Brian Beam PSEG Nuclear Board of Public Utilities P.O. Box 236 2 Gateway Center, Tenth Floor Hancocks Bridge, NJ 08038 Newark, NJ 07102 Mr. Michael J. Massaro Regional Administrator, Region I Plant Manager - Hope Creek U.S. Nuclear Regulatory Commission PSEG Nuclear 475 Allendale Road P.O. Box 236 King of Prussia, PA 19406 Hancocks Bridge, NJ 08038 Senior Resident Inspector Mr. James Mallon Hope Creek Generating Station Manager - Licensing U.S. Nuclear Regulatory Commission 200 Exelon Way - KSA 3-E Drawer 0509 Kennett Square, PA 19348 Hancocks Bridge, NJ 08038 Jeffrie J. Keenan, Esquire PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038 |
|
| |
|
| Hope Creek Generating Station Mr. Michael Jesse Manager - Regulatory Assurance cc: P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Dennis Winchester Vice President - Nuclear Assessments Township Clerk PSEG Nuclear Lower Alloways Creek Township P.O. Box 236 Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. George P. Barnes Mr. Paul Bauldauf, P.E., Asst. Director Site Vice President - Hope Creek Radiation Protection Programs PSEG Nuclear NJ Department of Environmental P.O. Box 236 Protection and Energy Hancocks Bridge, NJ 08038 CN 415 Trenton, NJ 08625-0415 Mr. George H. Gellrich Plant Support Manager Mr. Brian Beam PSEG Nuclear Board of Public Utilities P.O. Box 236 2 Gateway Center, Tenth Floor Hancocks Bridge, NJ 08038 Newark, NJ 07102 Mr. Michael J. Massaro Regional Administrator, Region I Plant Manager - Hope Creek U.S. Nuclear Regulatory Commission PSEG Nuclear 475 Allendale Road P.O. Box 236 King of Prussia, PA 19406 Hancocks Bridge, NJ 08038 Senior Resident Inspector Mr. James Mallon Hope Creek Generating Station Manager - Licensing U.S. Nuclear Regulatory Commission 200 Exelon Way - KSA 3-E Drawer 0509 Kennett Square, PA 19348 Hancocks Bridge, NJ 08038 Jeffrie J. Keenan, Esquire PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038
| | REQUEST FOR ADDITIONAL INFORMATION REGARDING TECHNICAL SPECIFICATION CHANGES FOR EXTENDED POWER UPRATE HOPE CREEK GENERATING STATION DOCKET NO. 50-354 By letter dated September 18, 2006 (Agencywide Documents and Management System (ADAMS) Accession No. ML062680451), as supplemented on October 10, 2006 (Accession No. ML062920092), October 20, 2006 (Accession No. ML063110163), February 14, (Accession No. ML070530099), February 16, (Accession No. ML070590178), February 28, (Accession No. ML070680314), March 13 (Accession No. ML071140157), and April 18, 2007 (Accession No. ML071160121), PSEG Nuclear, LLC (PSEG or licensee) submitted an amendment request for an extended power uprate (EPU) for Hope Creek Nuclear Generating Station (Hope Creek). |
| | |
| REQUEST FOR ADDITIONAL INFORMATION REGARDING TECHNICAL SPECIFICATION CHANGES FOR EXTENDED POWER UPRATE HOPE CREEK GENERATING STATION DOCKET NO. 50-354 By letter dated September 18, 2006 (Agencywide Documents and Management System (ADAMS) Accession No. ML062680451), as supplemented on October 10, 2006 (Accession No. | |
| ML062920092), October 20, 2006 (Accession No. ML063110163), February 14, (Accession No. | |
| ML070530099), February 16, (Accession No. ML070590178), February 28, (Accession No. | |
| ML070680314), March 13 (Accession No. ML071140157), and April 18, 2007 (Accession No. | |
| ML071160121), PSEG Nuclear, LLC (PSEG or licensee) submitted an amendment request for an extended power uprate (EPU) for Hope Creek Nuclear Generating Station (Hope Creek). | |
| The proposed amendment would increase the authorized maximum power level by approximately 15%, from 3339 megawatts thermal (MWt) to 3840 MWt. | | The proposed amendment would increase the authorized maximum power level by approximately 15%, from 3339 megawatts thermal (MWt) to 3840 MWt. |
| The Nuclear Regulatory Commission (NRC) staff has been reviewing the submittal and has determined that additional information is needed to complete its review. | | The Nuclear Regulatory Commission (NRC) staff has been reviewing the submittal and has determined that additional information is needed to complete its review. |
Letter Sequence RAI |
---|
TAC:MD3002, Control Room Habitability (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML0733004532003-11-27027 November 2003 Schedule and Response to PSEG Letter (LR-N07-0274) Dated October 23, 2007, Plans Related to Steam Dryer Evaluation Regarding Request for Extended Power Uprate Project stage: Other ML0626900642006-09-0101 September 2006 Attachment 26, C.D.I. Report No. 06-16NP, Rev 1, Estimating High Frequency Flow Induced Vibration in the Main Stream Lines at Hope Creek Unit 1: a Subscale Four Line Investigation of Standpipe Behavior. Project stage: Request LR-N06-0286, Request for License Amendment Extended Power Uprate2006-09-18018 September 2006 Request for License Amendment Extended Power Uprate Project stage: Request ML0626900442006-09-30030 September 2006 Attachment 21, C.D.I. Report No. 06-27, Rev 0, Stress Analysis of Hope Creek Unit 1 Steam Dryer at CLTP and EPU Conditions Using 1/8th Scale Model Pressure Measurement Data. Project stage: Request ML0631101672006-09-30030 September 2006 Attachment 2 - CDI Technical Memo 06-23P (Non-Proprietary) Comparison of Hope Creek and Quad Cities Steam Dryer Loads at EPU Conditions, Revision 0, Dated September 2006 Project stage: Request LR-N06-0413, Supplement to License Amendment Request for Extended Power Uprate2006-10-10010 October 2006 Supplement to License Amendment Request for Extended Power Uprate Project stage: Supplement ML0628303692006-10-13013 October 2006 Supplement to Application for Extended Power Uprate Project stage: Other ML0629003222006-10-18018 October 2006 Extended Power Uprate Accpetance Review Results Project stage: Other LR-N06-0418, Supplement to License Amendment Request for Extended Power Uprate, to Increase the Maximum Authorized Power Level to 3840 Megawatts Thermal2006-10-20020 October 2006 Supplement to License Amendment Request for Extended Power Uprate, to Increase the Maximum Authorized Power Level to 3840 Megawatts Thermal Project stage: Supplement ML0628304722006-11-0808 November 2006 PSEG Nuclear LLC, Withholding from Public Disclosure, NEDC-33076P, Revision 2, Safety Analysis Report for Hope Creek Constant Pressure Power Uprate, Class III, MD3002 Project stage: Other ML0628304532006-11-21021 November 2006 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance ML0633301432006-12-15015 December 2006 11/13-14/2006 Summary of Category 1 Meeting with PSEG Nuclear LLC, Regarding Application for Extended Power Uprate for Hope Creek Project stage: Meeting ML0703002772007-01-26026 January 2007 E-Mail Shea-NRR,to Duke, PSEG, Group1 Draft EPU RAI Project stage: Draft Other ML0716303072007-01-31031 January 2007 C.D.I. Technical Note No. 07-01NP, EPU Conditions in the Main Steam Lines at Hope Creek Unit 1: Additional Subscale Four Line Tests. Project stage: Request LR-N07-0034, C.D.I. Technical Memorandum No. 06-23NP, Revision 1, Comparison of the Hope Creek and Quad Cities Steam Dryer Loads at EPU Conditions.2007-01-31031 January 2007 C.D.I. Technical Memorandum No. 06-23NP, Revision 1, Comparison of the Hope Creek and Quad Cities Steam Dryer Loads at EPU Conditions. Project stage: Request LR-N07-0026, Supplemental to License Amendment Request for Extended Power Uprate2007-02-14014 February 2007 Supplemental to License Amendment Request for Extended Power Uprate Project stage: Supplement LR-N07-0029, Supplement to License Amendment Request for Extended Power Uprate2007-02-16016 February 2007 Supplement to License Amendment Request for Extended Power Uprate Project stage: Supplement ML0703304152007-02-16016 February 2007 Request for Additional Information Regarding Request for Extended Power Uprate Project stage: RAI ML0706606192007-02-20020 February 2007 Draft Request for Additional Information Hope Creek EPU Grp 5 Project stage: Draft RAI ML0706601992007-02-20020 February 2007 Draft Request for Additional Information Hope Creek EPU Grp 4 Project stage: Draft RAI ML0704602432007-02-23023 February 2007 Ltr Request for Additional Information Related to the Request for Extended Power Uprate Project stage: RAI ML0706606382007-02-23023 February 2007 Draft Request for Additional Information Hope Creek EPU Grp 6 Project stage: Draft RAI ML0706803142007-02-28028 February 2007 Hope Creek, Supplement to License Amendment Request for Extended Power Uprate Project stage: Supplement ML0708103652007-02-28028 February 2007 C.D.I. Report No. 07-01NP, Rev. 0, Revised Hydrodynamic Loads on Hope Creek Unit 1 Steam Dryer to 200 Hz. Project stage: Request ML0706006112007-03-0202 March 2007 Request for Additional Information Regarding Request for Extended Power Uprate Project stage: RAI ML0709200252007-03-0202 March 2007 Slides for Summary of March 2, 2007 Meeting with PSEG Nuclear LLC on an Application for Extended Power Uprate for Hope Creek Generating Station Regarding Steam Dryer Margin Project stage: Meeting ML0706803062007-03-13013 March 2007 Request for Additional Information Regarding Request for Extended Power Uprate Project stage: RAI LR-N07-0035, Response to Request for Additional Information Request for License Amendment - Extended Power Uprate2007-03-13013 March 2007 Response to Request for Additional Information Request for License Amendment - Extended Power Uprate Project stage: Response to RAI LR-N07-0055, Supplement to License Amendment Request for Extended Power Uprate2007-03-13013 March 2007 Supplement to License Amendment Request for Extended Power Uprate Project stage: Supplement ML0708004302007-03-29029 March 2007 Summary of March 2, 2007, Meeting with PSEG Nuclear, LLC, on an Application for Extended Power Uprate for Hope Creek Generating Station Regarding Steam Dryer Margin Project stage: Meeting LR-N07-0060, Response to Request for Additional Information Request for License Amendment - Extended Power Uprate2007-03-30030 March 2007 Response to Request for Additional Information Request for License Amendment - Extended Power Uprate Project stage: Response to RAI LR-N07-0069, Response to Request for Additional Information Request for License Amendment - Extended Power Uprate2007-03-30030 March 2007 Response to Request for Additional Information Request for License Amendment - Extended Power Uprate Project stage: Response to RAI LR-N07-0070, Response to Request for Additional Information on Request for License Amendment - Extended Power Uprate2007-04-13013 April 2007 Response to Request for Additional Information on Request for License Amendment - Extended Power Uprate Project stage: Response to RAI LR-N07-0084, Supplement to License Amendment Request for Extended Power Uprate, Revised No Significant Hazards Consideration2007-04-18018 April 2007 Supplement to License Amendment Request for Extended Power Uprate, Revised No Significant Hazards Consideration Project stage: Supplement ML0711400912007-04-20020 April 2007 Request for Additional Information Regarding Request for Extended Power Uprate (TAC MD3002) - NON-PROPRIETARY Project stage: RAI ML0713603772007-04-30030 April 2007 C.D.I. Report No. 06-16NP, Rev. 2, Estimating High Frequency Flow Induced Vibration in the Main Steam Lines at Hope Creek, Unit 1: a Subscale Four Line Investigation of Standpipe Behavior. Project stage: Request LR-N07-0099, Response to Request for Additional Information Request for License Amendment, Extended Power Uprate2007-04-30030 April 2007 Response to Request for Additional Information Request for License Amendment, Extended Power Uprate Project stage: Response to RAI ML0710104492007-05-0303 May 2007 Explanation of Hope Creek Nuclear Generating Station Extended Power Uprate and Conclusion of Informal Consultation Project stage: Other ML0712404872007-05-0909 May 2007 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance LR-N07-0102, Response to Request for Additional Information Request for License Amendment - Extended Power Uprate2007-05-10010 May 2007 Response to Request for Additional Information Request for License Amendment - Extended Power Uprate Project stage: Response to RAI ML0712404112007-05-14014 May 2007 RAI, Request for Additional Information Regarding Request for Extended Power Uprate Project stage: RAI ML0712405052007-05-15015 May 2007 Summary of Meeting with PSEG Nuclear LLC, Regarding Technical Aspects of the Licensee'S Application for an Extended Power Uprate (EPU) at the Hope Creek Generating Station (Hope Creek) Project stage: Meeting ML0712404612007-05-17017 May 2007 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance ML0628605302007-05-17017 May 2007 Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance ML0713707002007-05-17017 May 2007 Request for Additional Information (RAI) Regarding Request for Extended Power Uprate Project stage: RAI ML0712405102007-05-17017 May 2007 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance LR-N07-0123, Response to Request for Additional Information, Request for License Amendment - Extended Power Uprate2007-05-18018 May 2007 Response to Request for Additional Information, Request for License Amendment - Extended Power Uprate Project stage: Response to RAI LR-N07-0113, Supplement to Request for License Amendment Extended Power Uprate Steam Dryer Limit Curves2007-05-18018 May 2007 Supplement to Request for License Amendment Extended Power Uprate Steam Dryer Limit Curves Project stage: Supplement LR-N07-0122, Supplement to Request for License Amendment Re Extended Power Uprate & C.D.I. Technical Note No. 07-012007-05-24024 May 2007 Supplement to Request for License Amendment Re Extended Power Uprate & C.D.I. Technical Note No. 07-01 Project stage: Supplement ML0717203702007-05-31031 May 2007 Attachment 2, C.D.I. Technical Note No. 07-19NP, Revision 0, Hope Creek, Unit 1, Extended Power Uprate Limit Curve Analysis for Dryer Stress Prediction During Power Ascension Project stage: Request 2007-02-28
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers ML23307A1532023-12-15015 December 2023 NRC Investigation Report No. 1-2023-001 ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000354/20230032023-11-0707 November 2023 Integrated Inspection Report 05000354/2023003 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0065, Submittal of 2023 Annual 10 CFR 50.46 Report2023-10-0202 October 2023 Submittal of 2023 Annual 10 CFR 50.46 Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 IR 05000354/20230102023-08-0303 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000354/2023010 LR-N23-0052, Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.12023-07-31031 July 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.1 LR-N23-0042, Spent Fuel Cask Registration2023-07-12012 July 2023 Spent Fuel Cask Registration LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 IR 05000354/20230112023-05-0101 May 2023 Commercial Grade Dedication Report 05000354/2023011 ML23121A1412023-05-0101 May 2023 Senior Reactor and Reactor Operator Initial License Examinations LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) IR 05000354/20230012023-04-26026 April 2023 Integrated Inspection Report 05000354/2023001 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0009, License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains2023-04-18018 April 2023 License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains ML23087A1492023-04-17017 April 2023 NRC to PSEG Salem, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23089A0942023-04-17017 April 2023 NRC to PSEG Hope Creek, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23103A3232023-04-13013 April 2023 Submittal of Updated Final Safety Analysis Report, Rev. 26, Summary of Revised Regulatory Commitments for Hope Creek, Summary of Changes to PSEG Nuclear LLC, Quality Assurance Topical Report, NO-AA-10, Rev. 89 ML23095A3682023-04-12012 April 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Threshold Determination for Proposed Transfer of Land Ownership LR-N23-0024, Submittal of Hope Creek Generating Station Technical Specification Bases Changes2023-03-29029 March 2023 Submittal of Hope Creek Generating Station Technical Specification Bases Changes LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23086A0912023-03-24024 March 2023 NMFS to NRC, Transmittal of Biological Opinion for Continued Operations of Salem and Hope Creek Nuclear Generating Stations LR-N23-0019, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML23037A9712023-03-0909 March 2023 and Salem Nuclear, Unit Nos. 1 and 2 Issuance of Amendment Nos. 233, 344, and 325 Relocate Technical Specification Staff Qualification Requirements to the PSEG Quality Assurance Topical Report IR 05000354/20220062023-03-0101 March 2023 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2022006) LR-N23-0016, and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0018, Technical Specification 6.9.1.5.b - 2022 Annual Report of SRV Challenges2023-02-27027 February 2023 Technical Specification 6.9.1.5.b - 2022 Annual Report of SRV Challenges LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 IR 05000354/20220042023-01-24024 January 2023 Integrated Inspection Report 05000354/2022004 LR-N23-0011, In-Service Inspection Activities - 90 Day Report: Twenty-Fourth Refueling Outage2023-01-19019 January 2023 In-Service Inspection Activities - 90 Day Report: Twenty-Fourth Refueling Outage LR-N22-0096, and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination2023-01-0505 January 2023 and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination LR-N22-0094, Emergency Plan Document Revisions Implemented November 21, 20222022-12-14014 December 2022 Emergency Plan Document Revisions Implemented November 21, 2022 LR-N22-0091, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2022-12-0202 December 2022 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments ML22335A0412022-12-0101 December 2022 Notification of Commercial Grade Dedication Inspection (05000354/2023011) and Request for Information IR 05000354/20220032022-11-0303 November 2022 Integrated Inspection Report 05000354/2022003 2024-02-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML22006A3212022-01-0606 January 2022 NRR E-mail Capture - Final RAI - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection ML21041A3972021-02-18018 February 2021 Request for Additional Information Revise Low Pressure Safety Limit to Address General Electric Part-21 Safety Communications (Non-Proprietary) ML20295A4922020-10-21021 October 2020 NRR E-mail Capture - Hope Creek - Final RAI Revise ECCS TS with Respect to HPCI System Inoperability (L-2020-LLA-0131) ML18263A1442018-09-12012 September 2018 NRR E-mail Capture - Final RAI from Apla: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18250A3142018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18150A6912018-05-30030 May 2018 NRR E-mail Capture - Hope Creek - Final RAI Revise TS to Adopt TSTF-542 ML18120A2482018-04-27027 April 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000354/2018403 ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML17349A0812017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Reactor Systems Branch (Srxb) - Hope Creek Mur ML17348A9972017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A6242017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Human Factors Associated with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17331A0072017-11-21021 November 2017 E-mail Regarding Final Eicb Request for Additional Information - Hope Creek Power Uprate ML17348A6282017-11-21021 November 2017 NRR E-mail Capture - Draft Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17324A2602017-11-17017 November 2017 NRR E-mail Capture - Final Request for Additional Information - Hope Creek Mur Electrical Instrumentation and Controls ML17320A2152017-11-16016 November 2017 NRR E-mail Capture - Hope Creek Measurement Uncertainty Recapture Application Review - Electrical Engineering (Eeob) Request for Additional Information (L-2017-LLS-0002) ML17290B0132017-10-17017 October 2017 NRR E-mail Capture - Hope Creek Mur Request for Additional Information for Apla and Snpb ML17222A1652017-08-10010 August 2017 NRR E-mail Capture - Hope Creek: Final Request for Information, Pressure-Temperature Limit Report Request (MF9502) ML17181A1352017-06-29029 June 2017 NRR E-mail Capture - Request for Additional Information Related to Hope Creek and Salem Emergency Action Level Scheme Change License Amendment Request (MF9268/69/70) ML17164A4062017-06-13013 June 2017 NRR E-mail Capture - Hope Creek - Final Request for Additional Information Concerning ILRT (MF8462) ML17027A3282017-02-27027 February 2017 Request for Additional Information Regarding License Amendment Request to Permanently Extend Type a and Type C Leak Rate Test Frequencies ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16277A5142016-11-0303 November 2016 Request for Additional Information Regarding License Amendment Request to Permit Operability of Low Pressure Coolant Injection While Aligned to Shutdown Cooling ML16271A2052016-11-0202 November 2016 Request for Additional Information Regarding Request to Delete Technical Specifications Action Statement 3.4.2.1.b Associated with Stuck Open Safety/Relief Valves ML16231A4272016-08-24024 August 2016 Request for Additional Information Regarding Relief Request VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16217A4302016-08-17017 August 2016 Request for Additional Information Regarding Digital Power Range Neutron Monitoring System Upgrade ML16007A1742016-05-31031 May 2016 Request for Additional Information Regarding Review of Post-EPU Steam Dryer Stress Calculation Acoustic Circuit Model Software Error ML16089A0792016-05-0505 May 2016 Request for Additional Information Regarding Relief Requests GR-01, PR-01, PR-02, VR-01, and VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16124A5802016-05-0303 May 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes ML15055A3772015-03-10010 March 2015 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 ML14197A6192014-07-24024 July 2014 and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) ML14168A2352014-07-0202 July 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation ML13309B5922013-11-22022 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13168A2762013-08-12012 August 2013 Peach Bottom, Units 2 and 3, Request for Additional Information Decommissioning Funding Status Report (TAC No. MF2202; MF2227; MF2228) ML13193A2912013-07-22022 July 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) TAC MF1031 ML13204A2532013-07-19019 July 2013 Draft RAIs - Decommissioning Funding Status Report for Hope Creek and Peach Bottom ML13190A2212013-07-0202 July 2013 RAIs for Hope Creek Regarding Response to Order EA-12-051 ML13154A4952013-06-0404 June 2013 Rai'S Following Ifib Analysis of Pseg'S 2013 Decommissioning Funding Status Report for Hope Creek Generating Station ML12334A3102012-12-0505 December 2012 Request for Additional Information Request to Correct Technical Specification and Facility Operating License Editorial Items ML12310A1672012-11-0101 November 2012 Draft RAI to License Amendment Request Regarding Average Power Range Monitoring Operability Requirements in Operational Condition 5 ML1227901012012-10-0505 October 2012 Clarifying Information for Question No. 4 (with Attachment) ML12212A1032012-08-0808 August 2012 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information ML12216A1792012-08-0303 August 2012 Draft RAI Related to Request for Exemption from Certain Requirements of the Fitness for Duty Rule ML12213A6162012-07-30030 July 2012 Draft Request for Additional Information Related to Request for Exemption from Certain Requirements of the Fitness for Duty Rule ML1209002372012-03-29029 March 2012 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Draft Request for Additional Information ML12056A0512012-03-12012 March 2012 Enclosure 5 - Recommendation 9.3: Emergency Preparedness ML12056A0482012-03-12012 March 2012 Enclosure 2 - Recommendation 2.1: Flooding ML12056A0492012-03-12012 March 2012 Enclosure 3 - Recommendation 2.3: Seismic ML12056A0472012-03-12012 March 2012 Enclosure 1 - Recommendation 2.1: Seismic 2022-01-06
[Table view] |
Text
May 17, 2007 Mr. William Levis Senior Vice President & Chief Nuclear Officer PSEG Nuclear LLC-X04 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
HOPE CREEK GENERATING STATION - REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING REQUEST FOR EXTENDED POWER UPRATE (TAC NO. MD3002)
Dear Mr. Levis:
By letter dated September 18, 2006, as supplemented by letters dated October 10, 2006, October 20, 2006, February 14, February 16, February 28, March 13, and April 18, 2007, PSEG Nuclear, LLC (PSEG or licensee) submitted an amendment request for an extended power uprate (EPU) for Hope Creek Nuclear Generating Station (Hope Creek). The proposed amendment would increase the authorized maximum power level by approximately 15%, from 3339 megawatts thermal (MWt) to 3840 MWt.
The Nuclear Regulatory Commission (NRC) staff had requested additional information in a May 14, 2007, letter (ML071240411) in order to complete our review. In this letter, your staff noticed that question 1.6 was not the latest version as provided in draft form and that question 8.21 was inadvertently omitted. Enclosed is a corrected version of the complete set of RAI's that supercedes the May 14, 2007, letter. In subsequent discussions with Ms. Pam Cowan, it was indicated to Mr. Harold Chernoff, that you would respond to the enclosed questions by May 18, 2007.
Please note that if you cannot respond to all questions by May 18, 2007, as the NRC staff requested, then the schedule may be adversely impacted. If you have any questions, I can be reached at (301) 415-1388.
Sincerely,
/ra/
James J. Shea, Project Manager Project Directorate I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-354
Enclosure:
As stated cc w/encl: See next page
ML071370700 OFFICE PDI-2/PM PDI-1/LA EEEB CVIB/BC SBWB/BC IOLB/BC SBPB/BC PD1-2/BC NAME JShea SLittle GWilson MMitchell GCranston NSalgado JSegala HChernoff DATE 5/17/07 5/17/07 5/4/07 5/3/07 5/3/07 5/3/07 5/4/07 5/17/07 Hope Creek Generating Station Mr. Michael Jesse Manager - Regulatory Assurance cc: P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Dennis Winchester Vice President - Nuclear Assessments Township Clerk PSEG Nuclear Lower Alloways Creek Township P.O. Box 236 Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. George P. Barnes Mr. Paul Bauldauf, P.E., Asst. Director Site Vice President - Hope Creek Radiation Protection Programs PSEG Nuclear NJ Department of Environmental P.O. Box 236 Protection and Energy Hancocks Bridge, NJ 08038 CN 415 Trenton, NJ 08625-0415 Mr. George H. Gellrich Plant Support Manager Mr. Brian Beam PSEG Nuclear Board of Public Utilities P.O. Box 236 2 Gateway Center, Tenth Floor Hancocks Bridge, NJ 08038 Newark, NJ 07102 Mr. Michael J. Massaro Regional Administrator, Region I Plant Manager - Hope Creek U.S. Nuclear Regulatory Commission PSEG Nuclear 475 Allendale Road P.O. Box 236 King of Prussia, PA 19406 Hancocks Bridge, NJ 08038 Senior Resident Inspector Mr. James Mallon Hope Creek Generating Station Manager - Licensing U.S. Nuclear Regulatory Commission 200 Exelon Way - KSA 3-E Drawer 0509 Kennett Square, PA 19348 Hancocks Bridge, NJ 08038 Jeffrie J. Keenan, Esquire PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038
REQUEST FOR ADDITIONAL INFORMATION REGARDING TECHNICAL SPECIFICATION CHANGES FOR EXTENDED POWER UPRATE HOPE CREEK GENERATING STATION DOCKET NO. 50-354 By letter dated September 18, 2006 (Agencywide Documents and Management System (ADAMS) Accession No. ML062680451), as supplemented on October 10, 2006 (Accession No. ML062920092), October 20, 2006 (Accession No. ML063110163), February 14, (Accession No. ML070530099), February 16, (Accession No. ML070590178), February 28, (Accession No. ML070680314), March 13 (Accession No. ML071140157), and April 18, 2007 (Accession No. ML071160121), PSEG Nuclear, LLC (PSEG or licensee) submitted an amendment request for an extended power uprate (EPU) for Hope Creek Nuclear Generating Station (Hope Creek).
The proposed amendment would increase the authorized maximum power level by approximately 15%, from 3339 megawatts thermal (MWt) to 3840 MWt.
The Nuclear Regulatory Commission (NRC) staff has been reviewing the submittal and has determined that additional information is needed to complete its review.
- 1) Vessels & Internals Integrity Branch (CVIB) (additional question) 1.6 In response to RAI CVIB 1.4(b), the licensee in its letter dated March 13, 2007, stated that for the top guide whose fluence exceeds the irradiated assisted stress corrosion cracking (IASCC) threshold (5 x1020 n/cm2) (E > 1 MeV), the grid beams are not required to be inspected. The licensee further states that this is based on the Boiling Water Reactor Vessel Inspection Program (BWRVIP)-26-A, which states that there is no safety consequences resulting from a failure at a single beam intersection, and that a large number of complete separations would need to occur before control rod insertion would be affected. In other words, BWRVIP-26 acknowledges that while there is no safety concern from a single beam failure, multiple beam failures would be a safety concern, as it would compromise the safe shutdown of the reactor.
The NRC notes that multiple failures of the top guide beams are possible when the threshold fluence for IASCC is exceeded. For example, according to BWRVIP-26-A, multiple cracks have been observed in the top guide beams at Oyster Creek. In addition, multiple failures have occurred in other components that have exceeded the threshold fluence for IASCC, such as baffle-former bolts in pressurized-water reactors (PWRs).
The NRC also notes that the BWRVIP has been informed of this issue by NRC letter dated June 10, 2003. This letter recommended that the BWRVIP conduct a comprehensive evaluation of the impact of IASCC and multiple failures of the top guide beams, and that an inspection program for top guide beams that exceed the IASCC threshold fluence for all BWRs should be developed by the BWRVIP to ensure that all BWRs can meet the requirements of 10 CFR Part 54 (continue to perform their intended function under the current licensing basis for the extended period of operation). At the time, the NRC believed that the IASCC would be exceeded during the extended period of
operation. However, the NRC now has information that some plants, such as Hope Creek, have already exceeded the IASCC fluence threshold during the current operating period. Therefore, since this degradation mechanism is based on exceeding the IASCC fluence threshold, this issue may also apply to the current operating period. The BWRVIP is working on resolving this issue generically, but until then, a site-specific inspection program is necessary to manage the effects of IASCC in the top guide.
Matrix 1 of RS-001, Revision 0, Review Standard for Extended Power Uprates (December 2003) specifies that the NRCs acceptance criteria for reactor internal and core support materials are based on GDC-1 of Appendix A to 10 CFR Part 50. GDC-1 specifies, where generally recognized codes and standards are used, they shall be identified and evaluated to determine their applicability, adequacy, and sufficiency and shall be supplemented or modified as necessary to assure a quality product in keeping with the required safety function. Therefore, since the current inspection plan of excluding inspections of the top guide beam is not adequate to address the safety concern of multiple grid beam failures impacting the safe shutdown of the reactor, the inspection plan is required by GDC-1 to be supplemented. This modification can be accomplished by providing, for NRC approval, an inspection program to manage this aging effect to preclude loss of the component intended function. An example of an acceptable inspection program is as follows:
Enhanced visual testing (EVT-1) of the top guide grid beams will be performed in accordance with GE SIL 554 following the sample selection and inspection frequency of BWRVIP-47 for CRD guide tubes. That is, inspections will be performed on 10% of the total population of cells within twelve years, and 5% of the population within six years. The sample locations selected for examination will be in areas that are exposed to the highest fluence. This inspection plan will be implemented beginning with the refueling outage following EPU operation.
Therefore, the licensee is requested to provide an inspection program to manage the IASCC degradation mechanism of the top guide to preclude the loss of component intended function, as required by GDC-1.
- 2) Electrical Engineering Branch (EEEB) (additional questions) 2.6 Please provide the existing and the proposed Hope Creek EPU, expected uprated power level in MWe.
2.7 Please provide the existing and uprated ratings for the main generator (MVA and power factor and include any effect of the power uprate).
2.8 Was the delta portion of the iso-phase bus duct modified for the EPU? Povide the existing and, if necessary, uprated rating (in Amperes).
2.9 Were any modifications made to the unit auxiliary (UAT)/start-up transformers (SAT)?
Provide the existing MVA ratings for the UAT/SAT. Is the total calculated loading on the UAT/SAT within the design ratings?
- 3) Reactor Systems Branch (SRXB) (additional question) 3.66 Please provide the evaluation models (computer codes and version) used for each transient and accident analyzed in the Hope Creek EPU application according to the order of Review Standard for EPU (RS001) Section 2.8.5. If multiple codes were used, please specify all the codes and version used for each event.
3.67 Provide a demonstration analysis using the Statistical Method for Analysis of Anticipated Operational Occurrences (TRACG) to determine the Delta CPR/Initial CPR Vs.
Oscillation Magnitude (DIVOM) slope based on a limiting SVEA 96+ legacy fuel bundle in order to demonstrate that any uncertainties in the void reactivity feedback for these legacy bundles would not impact the DIVOM curve determination for fuel Cycle 15.
- 4) Operator Lic & Human Perf. Br (IOLB) (additional questions) 4.6 Please Clarify that the available times credited in the Hope Creek Updated Final Safety Analysis Report (UFSAR) for manual actions remains the same. In your response to RAI 4.1.C, you stated that the times remain the same for manual actions but did not explicitly state that the available times remain unchanged as well.
4.7 In the response to RAI 4.2.c, you stated that "The greater amount of decay heat due to EPU will affect the operator time associated with decay heat removal results only."
Please provide further clarification on how the operator times will be affected.
4.8 PSEG has committed to training licensed operators prior to the EPU implementation, however there were no statements concerning the training of non-licensed personnel.
Pleas describe your training plans and commitments for the Hope Creek non-licensed personnel.
4.9 Is the verification of successful completion of operator training required as a part of the Hope Creek Design Change Process?
- 7) Balance-of-Plant Branch (SBPB) (additional questions) 7.11 Section 10.3.2 of the Hope Creek UFSAR states that the main steam insolation valves (MSIV) and main turbine stop valves (MSVs) can close against maximum steam flow.
This licensing basis is partially addressed in of the Hope Creek Power Uprate Safety analysis Report (PUSAR), Attachment 4 of the Hope Creek EPU submittal, Section 3.8 which states that an increase in flow rate assists MSIV closure. However, the PUSAR does not address the capability of the MSVs to close against the new maximum steam flow of CPPU.
Evaluate the effect of the increased steam flow conditions of the proposed Constant Pressure Power Uprate (CPPU) upon the MSVs to close against maximum steam flow.
7.12 Section 7.4.2 of the PUSAR states that two independent hydraulic analyses were performed to account for feedwater demand transients in a 3 primary condensate pump (PCP), 3 secondary condensate pump (SCP), 3 reactor feedwater pump (RFP) lineup.
The purpose of the analyses is to ensure that adequate margin above the CPPU FW flow is available. The PUSAR stated that the predicted operating parameters from the two hydraulic analyses were acceptable.
a) For the two independent analyses, please state in more specific terms what transients were analyzed, what were the results, and what are the conclusions.
b) Describe the impact of the loss of a PCP and/or SCP upon the RFPs at CPPU.
How are the margins to RFP trips affected? Are any changes required to achieve acceptable performance?
c) Describe the impact of the loss of a RFP upon the remaining RFPs at CPPU.
How are the margins to RFP trips affected? Are any changes required to achieve acceptable performance?
7.13 Section 10.4.7.2 of the Hope Creek UFSAR for the Condensate and Feedwater Systems describes each primary condensate pump (PCP), secondary condensate pump (SCP),
and reactor feedwater pump (RFP) as one-third capacity pumps for operation at the current licensed power level.
Section 10.4.7.1 of the UFSAR states that:
The condensate and feedwater systems are designed to permit continued operation of the plant at reduced power without reactor trip on loss of one of the three primary condensate pumps, one of the three secondary condensate pumps, one of the three reactor feed pumps, or one of the three strings of feedwater heaters.
Section 7.4 of the PUSAR does not describe any modifications to these pumps for CPPU that would suggest a decrease in the marginal performance for EPU operation.
a) For EPU operating conditions, describe how the PCP, SCP, and RFP normal operating parameters will change as compared to plant operation at the current licensed power level, including a comparison of pump suction pressures, discharge pressures, and margin to pump run out. Also, identify what the minimum allowable pump suction pressures are, what the pump suction pressure trip set points are, and how these trip set points will change for EPU operation.
b) Describe in detail the modeling that was used, analytical methods, assumptions, and analyses that have been completed (including results) that conclusively demonstrate that the plant design basis as described in Section 10.4.7.1 of the UFSAR will continue to be satisfied for the transient plant response that will occur following EPU implementation, including a bounding estimate of the total amount of uncertainty that exists and specifically what the uncertainties are and how they were determined. Also, describe how the accuracy of this analytical approach was validated for use at the uprated power level, along with the results of an analysis that examines the sensitivity of parameters to scaling effects when extrapolating the analytical methods for use at the uprated power level.
c) For a postulated trip of a PCP, SCP, and RFP (each taken individually), provide the following information for each of the pump trip scenarios:
- 1. a description of the most limiting case scenario that will result in the lowest RFP suction pressure, either as a direct consequence of the postulated pump trip or as a consequence of other PCP or SCP trips that occur as a result of the transient, and identify what minimum RCP suction pressure will be reached (corrected to account for the total amount of uncertainty that exists);
- 2. compare the minimum transient RFP suction pressure to the RFP suction pressure trip set point (corrected to compensate for allowable tolerances) and determine the minimum margin that will exist to RFP trip for the transient, and compare this margin to the minimum margin that exists for the current licensed power level.
d) Describe any transient testing that will be completed to confirm that the analytical results are sufficiently conservative and representative of transient EPU operation.
Note that as an alternative to the information referred to above, transient testing that adequately demonstrates that the plant design basis as described in UFSAR Section 10.4.7.1 will be maintained for EPU operation, similar to the pump trip testing that was specified for the Browns Ferry EPU (Accession No: ML062360160) and for the Vermont Yankee EPU (Accession No: ML060050028), is considered to be acceptable.
7.14 UFSAR Section 10.2.6.6., "Overspeed Protection," states that the turbine has two electrical trips, specifically : 1) A primary electrical overspeed trip that is initiated if the turbine speed reaches approximately 8 percent above rated speed, and 2) An emergency electrical overspeed trip that serves as a backup to the primary trip that is initiated at approximately 10 percent above rated speed.
UFSAR Table 10.2-1 states that the overspeed trip is 110% and the backup is 112% of rated speed. The table refers to the overspeed trip as a mechanical trip. The description of the overspeed trip devices in Table 10.2-1 does not appear to be consistent with the description of the overspeed devices in UFSAR Section 10.2.6.6.
Additionally, Attachment 10 of the CPPU submittal, in the notes of Matrix 5, refers only to a mechanical trip that is set at 109.9% - 110.4% with a "normal overspeed" of 109.2% and an "emergency overspeed" value of 119.35%.
Please explain these apparent inconsistencies, and describe how the main turbines will be protected from overspeed conditions following CPPU implementation such that design limitations will not be exceeded. Also, please describe testing that will be completed to assure acceptable performance of the main turbine overspeed protective features.
7.15 Please clarify your RAI response to RAI 7.5 regarding Post EPU spent fuel pool (SFP)
Heat Load. The values in the table of your respose specify a normal fuel off load.
Whereas, the PUSAR on page 6-7, bottom paragragh, says the Safety Auxiliaries Cooling System Loss of Coolant Accident heat load calculation used a full fuel offload. Should you be considering the full off load condition?
- 8) SG Tube Integrity & Chem. Eng Br (CSGB) 8.21 Please provide the Pre-EPU flow accelerated corrosion (FAC) rates for comparison purposes as an additional column to the After Up-rate table provided in your response to RAI 8.18.
- 13) Containment and Ventilation Branch (SCVB) (additional question) 13.17 Pleased provide a reference to NRC staff approval of hydrodynamic loads issues for Hope Creek.
13.18 Explain why the drywell head region have to be reanalyzed for subcompartment analyses?
13.19 Explain why the MELLA 66% power/40% flow is the most limiting point on the power flow map for subcompartment analysis.
13.20 The Hope Creek response to GL 97-04 shows that although adequate available net positive suction head (NPSH) existed, the NPSH margin was less than 1 foot for both the core spray and the residual heat removal (RHR) pumps (December 30, 1997 letter to NRC Page 4/5). Was there any change to the NPSH methods described in the Hope Creek response to GL 97-04 for the EPU? If not, how was the increase in suppression pool temperature accommodated?
13.21 Please confirm: The peak bulk pool temperature in Table 4-1 of the PUSAR of 201 0F is calculated at 2% above 3339 MWt. The peak bulk pool temperature of 212.3 0F is calculated at 2% above 3840 MWt. The peak wetwell air space pressure of 27.6 psig is calculated at 2% above 3339 MWt and the peak wetwell airspace pressure of 27.7 psig is calculated at 2% above 3840 psig.
13.22 The response to RAI 13.9 listed the maximum temperatures for various systems attached to the torus. It is not clear from the response what the temperature limit is for the attached piping to demonstrate that the calculated temperatures at EPU conditions are acceptable, please clarify this temperature limit.