Letter Sequence Supplement |
|---|
TAC:MD3002, Control Room Habitability (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML0733004532003-11-27027 November 2003 Schedule and Response to PSEG Letter (LR-N07-0274) Dated October 23, 2007, Plans Related to Steam Dryer Evaluation Regarding Request for Extended Power Uprate Project stage: Other ML0626900642006-09-0101 September 2006 Attachment 26, C.D.I. Report No. 06-16NP, Rev 1, Estimating High Frequency Flow Induced Vibration in the Main Stream Lines at Hope Creek Unit 1: a Subscale Four Line Investigation of Standpipe Behavior Project stage: Request ML0626804512006-09-18018 September 2006 Request for License Amendment Extended Power Uprate Project stage: Request ML0626900442006-09-30030 September 2006 Attachment 21, C.D.I. Report No. 06-27, Rev 0, Stress Analysis of Hope Creek Unit 1 Steam Dryer at CLTP and EPU Conditions Using 1/8th Scale Model Pressure Measurement Data Project stage: Request ML0631101672006-09-30030 September 2006 Attachment 2 - CDI Technical Memo 06-23P (Non-Proprietary) Comparison of Hope Creek and Quad Cities Steam Dryer Loads at EPU Conditions, Revision 0, Dated September 2006 Project stage: Request LR-N06-0413, Supplement to License Amendment Request for Extended Power Uprate2006-10-10010 October 2006 Supplement to License Amendment Request for Extended Power Uprate Project stage: Supplement ML0628303692006-10-13013 October 2006 Supplement to Application for Extended Power Uprate Project stage: Other ML0629003222006-10-18018 October 2006 Extended Power Uprate Accpetance Review Results Project stage: Other LR-N06-0418, Supplement to License Amendment Request for Extended Power Uprate, to Increase the Maximum Authorized Power Level to 3840 Megawatts Thermal2006-10-20020 October 2006 Supplement to License Amendment Request for Extended Power Uprate, to Increase the Maximum Authorized Power Level to 3840 Megawatts Thermal Project stage: Supplement ML0628304722006-11-0808 November 2006 PSEG Nuclear LLC, Withholding from Public Disclosure, NEDC-33076P, Revision 2, Safety Analysis Report for Hope Creek Constant Pressure Power Uprate, Class III, MD3002 Project stage: Other ML0628304532006-11-21021 November 2006 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance ML0633301432006-12-15015 December 2006 11/13-14/2006 Summary of Category 1 Meeting with PSEG Nuclear LLC, Regarding Application for Extended Power Uprate for Hope Creek Project stage: Meeting LR-N07-0007, Response to the Request for Additional Information Regarding Resolution of NRC Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power.2007-01-26026 January 2007 Response to the Request for Additional Information Regarding Resolution of NRC Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power. Project stage: Request ML0703002772007-01-26026 January 2007 E-Mail Shea-NRR,to Duke, PSEG, Group1 Draft EPU RAI Project stage: Draft Other ML0716303072007-01-31031 January 2007 C.D.I. Technical Note No. 07-01NP, EPU Conditions in the Main Steam Lines at Hope Creek Unit 1: Additional Subscale Four Line Tests Project stage: Request LR-N07-0034, C.D.I. Technical Memorandum No. 06-23NP, Revision 1, Comparison of the Hope Creek and Quad Cities Steam Dryer Loads at EPU Conditions2007-01-31031 January 2007 C.D.I. Technical Memorandum No. 06-23NP, Revision 1, Comparison of the Hope Creek and Quad Cities Steam Dryer Loads at EPU Conditions Project stage: Request LR-N07-0026, Supplemental to License Amendment Request for Extended Power Uprate2007-02-14014 February 2007 Supplemental to License Amendment Request for Extended Power Uprate Project stage: Supplement 05000354/LER-2006-005, Drywell Hoist Breaker Not Open Prior to Operational Condition 2 Entry2007-02-16016 February 2007 Drywell Hoist Breaker Not Open Prior to Operational Condition 2 Entry Project stage: Request ML0703304152007-02-16016 February 2007 Request for Additional Information Regarding Request for Extended Power Uprate Project stage: RAI LR-N07-0029, Supplement to License Amendment Request for Extended Power Uprate2007-02-16016 February 2007 Supplement to License Amendment Request for Extended Power Uprate Project stage: Supplement ML0706606192007-02-20020 February 2007 Draft Request for Additional Information Hope Creek EPU Grp 5 Project stage: Draft RAI ML0706601992007-02-20020 February 2007 Draft Request for Additional Information Hope Creek EPU Grp 4 Project stage: Draft RAI ML0704602432007-02-23023 February 2007 Ltr Request for Additional Information Related to the Request for Extended Power Uprate Project stage: RAI ML0706606382007-02-23023 February 2007 Draft Request for Additional Information Hope Creek EPU Grp 6 Project stage: Draft RAI ML0706803142007-02-28028 February 2007 Supplement to License Amendment Request for Extended Power Uprate Project stage: Supplement ML0708103652007-02-28028 February 2007 C.D.I. Report No. 07-01NP, Rev. 0, Revised Hydrodynamic Loads on Hope Creek Unit 1 Steam Dryer to 200 Hz Project stage: Request ML0706006112007-03-0202 March 2007 Request for Additional Information Regarding Request for Extended Power Uprate Project stage: RAI ML0709200252007-03-0202 March 2007 Slides for Summary of March 2, 2007 Meeting with PSEG Nuclear LLC on an Application for Extended Power Uprate for Hope Creek Generating Station Regarding Steam Dryer Margin Project stage: Meeting ML0706803062007-03-13013 March 2007 Request for Additional Information Regarding Request for Extended Power Uprate Project stage: RAI LR-N07-0055, Supplement to License Amendment Request for Extended Power Uprate2007-03-13013 March 2007 Supplement to License Amendment Request for Extended Power Uprate Project stage: Supplement LR-N07-0035, Response to Request for Additional Information Request for License Amendment - Extended Power Uprate2007-03-13013 March 2007 Response to Request for Additional Information Request for License Amendment - Extended Power Uprate Project stage: Response to RAI ML0708004302007-03-29029 March 2007 Summary of March 2, 2007, Meeting with PSEG Nuclear, LLC, on an Application for Extended Power Uprate for Hope Creek Generating Station Regarding Steam Dryer Margin Project stage: Meeting LR-N07-0060, Response to Request for Additional Information Request for License Amendment - Extended Power Uprate2007-03-30030 March 2007 Response to Request for Additional Information Request for License Amendment - Extended Power Uprate Project stage: Response to RAI LR-N07-0069, Response to Request for Additional Information Request for License Amendment - Extended Power Uprate2007-03-30030 March 2007 Response to Request for Additional Information Request for License Amendment - Extended Power Uprate Project stage: Response to RAI LR-N07-0070, Response to Request for Additional Information on Request for License Amendment - Extended Power Uprate2007-04-13013 April 2007 Response to Request for Additional Information on Request for License Amendment - Extended Power Uprate Project stage: Response to RAI LR-N07-0084, Supplement to License Amendment Request for Extended Power Uprate, Revised No Significant Hazards Consideration2007-04-18018 April 2007 Supplement to License Amendment Request for Extended Power Uprate, Revised No Significant Hazards Consideration Project stage: Supplement ML0711400912007-04-20020 April 2007 Request for Additional Information Regarding Request for Extended Power Uprate (TAC MD3002) - NON-PROPRIETARY Project stage: RAI LR-N07-0076, 2007 Annual Report - Guarantees of Payment of Deferred Premiums2007-04-30030 April 2007 2007 Annual Report - Guarantees of Payment of Deferred Premiums Project stage: Request ML0713603772007-04-30030 April 2007 C.D.I. Report No. 06-16NP, Rev. 2, Estimating High Frequency Flow Induced Vibration in the Main Steam Lines at Hope Creek, Unit 1: a Subscale Four Line Investigation of Standpipe Behavior Project stage: Request LR-N07-0099, Response to Request for Additional Information Request for License Amendment, Extended Power Uprate2007-04-30030 April 2007 Response to Request for Additional Information Request for License Amendment, Extended Power Uprate Project stage: Response to RAI ML0710104492007-05-0303 May 2007 Explanation of Hope Creek Nuclear Generating Station Extended Power Uprate and Conclusion of Informal Consultation Project stage: Other ML0712404872007-05-0909 May 2007 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance LR-N07-0102, Response to Request for Additional Information Request for License Amendment - Extended Power Uprate2007-05-10010 May 2007 Response to Request for Additional Information Request for License Amendment - Extended Power Uprate Project stage: Response to RAI ML0712404112007-05-14014 May 2007 RAI, Request for Additional Information Regarding Request for Extended Power Uprate Project stage: RAI ML0712405052007-05-15015 May 2007 Summary of Meeting with PSEG Nuclear LLC, Regarding Technical Aspects of the Licensees Application for an Extended Power Uprate (EPU) at the Hope Creek Generating Station (Hope Creek) Project stage: Meeting ML0713707002007-05-17017 May 2007 Request for Additional Information (RAI) Regarding Request for Extended Power Uprate Project stage: RAI ML0712404612007-05-17017 May 2007 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance ML0712405102007-05-17017 May 2007 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance ML0628605302007-05-17017 May 2007 Nuclear LLC, Request for Withholding Information from Public Disclosure for Hope Creek Generating Station Project stage: Withholding Request Acceptance LR-N07-0123, Response to Request for Additional Information, Request for License Amendment - Extended Power Uprate2007-05-18018 May 2007 Response to Request for Additional Information, Request for License Amendment - Extended Power Uprate Project stage: Response to RAI 2007-02-23
[Table View] |
Text
PSEG Nuclear LLC P.O. Box 236,, Hancocks Bridge, NJ 08038-0236 0 PSEG Nuclear L.L. C.
10 CFR 50.90 LR-N08-0102 LCR H05-01, Rev. 1 May 02, 2008 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Hope Creek Generating Station Facility Operating License No. NPF-57 NRC Docket No. 50-354
Subject:
Supplement to License Amendment Request for Extended Power Uprate
Reference:
- 1) Letter from George P. Barnes (PSEG Nuclear LLC) to USNRC, September 18, 2006.
In Reference 1, PSEG Nuclear LLC (PSEG) requested an amendment to Facility Operating License NPF-57 and the Technical Specifications (TS) for the Hope Creek Generating Station to increase the maximum authorized power level to 3840 megawatts thermal (MWt).
Reference 1 proposed a new License Condition to allow leak rate tests required by Surveillance Requirement (SR) 4.6.1.2.a to be considered to be performed per SR 4.0.1, upon implementation of the license amendment approving the proposed extended power uprate, until the next scheduled performance.
The attachment to this letter modifies the proposed License Condition to also include hydrostatic leak rate testing required by SR 4.6.1.2.h.
PSEG has determined that the information contained in this letter and attachment does not alter the conclusions reached in the 10CFR50.92 no significant hazards analysis previously submitted.
A6017-
LR-N08-0102 LCR H05-01, Rev. 1 May 02, 2008 Page 2 There are no regulatory commitments contained within this letter.
Should you have any questions regarding this submittal, please contact Mr. Paul Duke at 856-339-1466.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on: May 2, 2008 George P. Barnes Site Vice President Hope Creek Generating Station
Attachment:
Supplement to Request for License Amendment cc:
S. Collins, Regional Administrator - NRC Region I J. Lamb, Project Manager - USNRC NRC Senior Resident Inspector - Hope Creek P. Mulligan, Manager IV, NJBNE
ATTACHMENT 1 Hope Creek Generating Station Facility Operating License NPF-57 Docket No. 50-354 Extended Power Uprate Supplement to License Amendment Request In Reference 1, PSEG Nuclear LLC (PSEG) requested an amendment to Facility Operating License NPF-57 and the Technical Specifications (TS) for the Hope Creek Generating Station (HCGS) to increase the maximum authorized power level to 3840 megawatts thermal (MWt).
Reference 1 proposed a new License Condition to allow leak rate tests required by Surveillance Requirement (SR) 4.6.1.2.a to be considered to be performed per SR 4.0.1, upon implementation of the license amendment approving the proposed extended power uprate (EPU), until the next scheduled performance.
This attachment modifies the proposed License Condition to also include hydrostatic leak rate testing required by SR 4.6.1.2.h.
Modified Proposed License Condition Leak rate tests required by Surveillance Requirement 4.6.1.2.a and 4.6.1.2.h to be performed in accordance with the Primary Containment Leakage Rate Testing Program are not required to be performed until their next scheduled performance, which is due at the end of the first test interval that begins on the date the test was last performed prior to implementation of Amendment No.
[XXX].
Primary Containment Leakage Rate Testing Program Surveillance Requirement 4.6.1.2.a requires that primary containment leakage rates be demonstrated in accordance with the Primary Containment Leakage Rate Testing Program. The testing program is required by 10 CFR 50.54(o) and 10 CFR 50 Appendix J and is described in Technical Specification 6.8.4.f. Test intervals are established on a performance basis in accordance with 10 CFR 50 Appendix J, Option B. Surveillance Requirement 4.6.1.2.h requires that all containment isolation valves in hydrostatically tested lines which penetrate the primary containment be leak tested at least once per 18 months. The combined leakage rate is limited to less than or equal to 10 gpm when tested at 1.10 times Pa, the calculated peak containment pressure (Pa).
The Type A integrated leak rate test and the Type B and C local leak rate tests are performed at the calculated peak containment pressure (Pa). Pa increases to 50.6
LR-N08-0102 Page 2 psig for the EPU; and Technical Specification 6.8.4.f is being revised to reflect the change. The hydrostatic leak testing required by SR 4.6.1.2.h is performed at 1.10 times Pa. The required hydrostatic test pressure increases from 52.9 psig to 55.7 psig for the EPU. However, with substantial margin to the leakage rate acceptance limits based upon current leak rate test results, it is not necessary to reperform all of the leak rate tests at the higher pressures before implementation of the EPU.
The proposed License Condition would allow leak rate tests required by Surveillance Requirements 4.6.1.2.a and 4.6.1.2.h to be considered to be performed per SR 4.0.1, upon implementation of the license amendment approving the proposed EPU, until the next scheduled performance. This would preclude having to perform the affected leak rate tests before their next scheduled performance solely for the purpose of documenting compliance. The allowance provided in the proposed License Condition would not supercede that aspect of SR 4.0.1 that governs cases where it is believed that, if the SR were performed, it would not be met.
Performance of the leak rate tests merely to document compliance would unnecessarily divert resources, interfere with plant operations, potentially incur additional personnel dose, and would not improve plant safety.
Reference
- 1)
Letter from George P. Barnes (PSEG Nuclear LLC) to USNRC, September 18, 2006