|
---|
Category:E-Mail
MONTHYEARML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24240A2092024-08-27027 August 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Relief Request VR-04, SSW Rupture Disc Replacement ML24197A1022024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise TS Lift Settings for Reactor Coolant System Safety Relief Valves ML24163A1632024-06-11011 June 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23129A7892023-05-0909 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise Trip and Standby Auto-Start Logic Associated with Safety Related HVAC Trains ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML22194A0522022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review - Hope Creek, Salem 1 and 2 - Relocate Staff Qualification Requirements to Licensee Quality Assurance Topical Report ML22038A1552022-02-0404 February 2022 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML22021A7012022-01-21021 January 2022 NRR E-mail Capture - Acceptance Review - Hope Creek -Relief Request HC-I4R-220 Regarding Partial Penetration Nozzle Repairs (L-2022-LLR-0003) ML22006A3212022-01-0606 January 2022 NRR E-mail Capture - Final RAI - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML21334A1182021-11-30030 November 2021 NRR E-mail Capture - Acceptance Review - Hope Creek -Revise SRs for Electric Power Monitor Channels for RPS and Power Range Neutron Monitoring System ML21154A0102021-05-28028 May 2021 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML20295A4922020-10-21021 October 2020 NRR E-mail Capture - Hope Creek - Final RAI Revise ECCS TS with Respect to HPCI System Inoperability (L-2020-LLA-0131) ML20293A1832020-10-19019 October 2020 NRR E-mail Capture - Acceptance Review - Hope Creek - Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20289A7062020-10-15015 October 2020 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise Low Pressure Safety Limit to Address GE Part-21 Safety Communication SC05-03 ML20246G5952020-09-0202 September 2020 Acceptance Review - Hope Creek - Adopt TSTF-427, Allowance for Non TS Barrier Degradation ML20191A0202020-07-0202 July 2020 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise ECCS TS with Respect to HPCI System Inoperability ML20153A3782020-06-0101 June 2020 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise TS Actions for Suppression Pool Cooling ML20006E2802020-01-0606 January 2020 NRR E-mail Capture - Acceptance Review - Hope Creek: LAR Regarding Proposed Adoption of 10 CFR 50.69, Risk- Informed Categorization and Treatment of SSCs for Nuclear Power Plants ML19280A0002019-10-0303 October 2019 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Final RAI Emergency Plan Staffing Requirements (L-2019-LLA-0145) ML19267A1622019-09-24024 September 2019 NRR E-mail Capture - Hope Creek - Acceptance Review: Alternative for Exam of ASME Section XI, Exam Category B-G-1, Item Number B6.40, Threads in Flange (L-2019-LLR-0090) ML19226A3932019-08-14014 August 2019 NRR E-mail Capture - Salem 1 & 2, Hope Creek - Acceptance Review: Delete License Conditions Related to Decommissioning Trust Provisions and License Transfer ML19198A0992019-07-17017 July 2019 NRR E-mail Capture - Salem 1 & 2, Hope Creek - Acceptance Review: Changes to Emergency Plan Staffing ML19186A3842019-07-0505 July 2019 NRR E-mail Capture - Acceptance Review - Hope Creek, Revise TS to Adopt TSTF-563, Revise Instrumentation Testing Definition ML19123A2172019-05-0303 May 2019 NRR E-mail Capture - Re Acceptance Review - Hope Creek, Revise TS to Adopt TSTF-564, Safety Limit MCPR ML19081A1532019-03-22022 March 2019 NRR E-mail Capture - Acceptance Review: Hope Creek - Revise TS to Adopt TSTF-546 (L-2019-LLA-0032) ML19046A2382019-02-15015 February 2019 NRR E-mail Capture - Acceptance Review Result: Hope Creek-Relief Request to Use ASME Code Case OMN-17 (L-2019-LLR-0010) ML18323A0252018-11-16016 November 2018 NRR E-mail Capture - Acceptance Review: Hope Creek - Remote Shutdown System I & C Amendment (L-2018-LLA-0295) ML18288A2512018-10-15015 October 2018 NRR E-mail Capture - Acceptance Review Result: Hope Creek-Relief Request Associated with Third 10-Year ISI Interval (L-2018-LLR-0124) ML18271A0342018-09-13013 September 2018 Receipt of Stephen Comley, We the People, September 6, 11 and 12 2018 Voicemail and Email ML18263A1442018-09-12012 September 2018 NRR E-mail Capture - Final RAI from Apla: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18250A3142018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18206A7302018-07-27027 July 2018 (50-272, 50-311, 50-354), Transmittal Email 26.717 Updates ML18201A1112018-07-20020 July 2018 NRR E-mail Capture - Acceptance Review Results: Hope Creek, Salem 1 & 2 Revise TS to Adopt TSTF-529 (L-2018-LLA-0185) ML18150A6912018-05-30030 May 2018 NRR E-mail Capture - Hope Creek - Final RAI Revise TS to Adopt TSTF-542 ML18128A3862018-05-0808 May 2018 NRR E-mail Capture - Acceptance Review Results: Hope Creek Revise Inverter AOT TS Actions (L-2018-LLA-0101) ML18122A2392018-05-0202 May 2018 NRR E-mail Capture - Acceptance Review Results: Revise Emergency Diesel Generator Technical Specifications Action to Remove Salem Unit 3 Gas Turbine Generator (L-2018-LLA-0079) ML17348A6242017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Human Factors Associated with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A9972017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17349A0812017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Reactor Systems Branch (Srxb) - Hope Creek Mur ML17340B2682017-12-0606 December 2017 NRR E-mail Capture - Notification to State of New Jersey of Impending License Amendment Issuance for Hope Creek (MF9501; EPID L-2017-LLA-0183) ML17338A2742017-12-0404 December 2017 NRR E-mail Capture - State of New Jersey: Notification of Impending Amendment Issuance for Hope Creek - Relocate Pressure-Temperature Limits Curves to the Pressure-Temperature Limits Report 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML22006A3212022-01-0606 January 2022 NRR E-mail Capture - Final RAI - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection ML21041A3972021-02-18018 February 2021 Request for Additional Information Revise Low Pressure Safety Limit to Address General Electric Part-21 Safety Communications (Non-Proprietary) ML20295A4922020-10-21021 October 2020 NRR E-mail Capture - Hope Creek - Final RAI Revise ECCS TS with Respect to HPCI System Inoperability (L-2020-LLA-0131) ML18263A1442018-09-12012 September 2018 NRR E-mail Capture - Final RAI from Apla: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18250A3142018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18150A6912018-05-30030 May 2018 NRR E-mail Capture - Hope Creek - Final RAI Revise TS to Adopt TSTF-542 ML18120A2482018-04-27027 April 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000354/2018403 ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML17349A0812017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Reactor Systems Branch (Srxb) - Hope Creek Mur ML17348A9972017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A6242017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Human Factors Associated with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A6282017-11-21021 November 2017 NRR E-mail Capture - Draft Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17331A0072017-11-21021 November 2017 E-mail Regarding Final Eicb Request for Additional Information - Hope Creek Power Uprate ML17324A2602017-11-17017 November 2017 NRR E-mail Capture - Final Request for Additional Information - Hope Creek Mur Electrical Instrumentation and Controls ML17320A2152017-11-16016 November 2017 NRR E-mail Capture - Hope Creek Measurement Uncertainty Recapture Application Review - Electrical Engineering (Eeob) Request for Additional Information (L-2017-LLS-0002) ML17290B0132017-10-17017 October 2017 NRR E-mail Capture - Hope Creek Mur Request for Additional Information for Apla and Snpb ML17222A1652017-08-10010 August 2017 NRR E-mail Capture - Hope Creek: Final Request for Information, Pressure-Temperature Limit Report Request (MF9502) ML17181A1352017-06-29029 June 2017 NRR E-mail Capture - Request for Additional Information Related to Hope Creek and Salem Emergency Action Level Scheme Change License Amendment Request (MF9268/69/70) ML17164A4062017-06-13013 June 2017 NRR E-mail Capture - Hope Creek - Final Request for Additional Information Concerning ILRT (MF8462) ML17027A3282017-02-27027 February 2017 Request for Additional Information Regarding License Amendment Request to Permanently Extend Type a and Type C Leak Rate Test Frequencies ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16277A5142016-11-0303 November 2016 Request for Additional Information Regarding License Amendment Request to Permit Operability of Low Pressure Coolant Injection While Aligned to Shutdown Cooling ML16271A2052016-11-0202 November 2016 Request for Additional Information Regarding Request to Delete Technical Specifications Action Statement 3.4.2.1.b Associated with Stuck Open Safety/Relief Valves ML16231A4272016-08-24024 August 2016 Request for Additional Information Regarding Relief Request VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16217A4302016-08-17017 August 2016 Request for Additional Information Regarding Digital Power Range Neutron Monitoring System Upgrade ML16007A1742016-05-31031 May 2016 Request for Additional Information Regarding Review of Post-EPU Steam Dryer Stress Calculation Acoustic Circuit Model Software Error ML16089A0792016-05-0505 May 2016 Request for Additional Information Regarding Relief Requests GR-01, PR-01, PR-02, VR-01, and VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16124A5802016-05-0303 May 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes ML15055A3772015-03-10010 March 2015 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 ML14197A6192014-07-24024 July 2014 and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) ML14168A2352014-07-0202 July 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation ML13309B5922013-11-22022 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13168A2762013-08-12012 August 2013 Peach Bottom, Units 2 and 3, Request for Additional Information Decommissioning Funding Status Report (TAC No. MF2202; MF2227; MF2228) ML13193A2912013-07-22022 July 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) TAC MF1031 ML13204A2532013-07-19019 July 2013 Draft RAIs - Decommissioning Funding Status Report for Hope Creek and Peach Bottom ML13190A2212013-07-0202 July 2013 RAIs for Hope Creek Regarding Response to Order EA-12-051 ML13154A4952013-06-0404 June 2013 Rai'S Following Ifib Analysis of Pseg'S 2013 Decommissioning Funding Status Report for Hope Creek Generating Station ML12334A3102012-12-0505 December 2012 Request for Additional Information Request to Correct Technical Specification and Facility Operating License Editorial Items ML12310A1672012-11-0101 November 2012 Draft RAI to License Amendment Request Regarding Average Power Range Monitoring Operability Requirements in Operational Condition 5 ML1227901012012-10-0505 October 2012 Clarifying Information for Question No. 4 (with Attachment) ML12212A1032012-08-0808 August 2012 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information ML12216A1792012-08-0303 August 2012 Draft RAI Related to Request for Exemption from Certain Requirements of the Fitness for Duty Rule ML12213A6162012-07-30030 July 2012 Draft Request for Additional Information Related to Request for Exemption from Certain Requirements of the Fitness for Duty Rule ML1209002372012-03-29029 March 2012 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Draft Request for Additional Information ML12056A0482012-03-12012 March 2012 Enclosure 2 - Recommendation 2.1: Flooding 2024-09-09
[Table view] |
Text
NRR-DMPSPEm Resource From: Kim, James Sent: Wednesday, May 30, 2018 1:40 PM To: Duke, Paul R.; Thomas, Brian J.
Subject:
Hope Creek - Final RAI RE: Revise TS to Adopt TSTF-542 Attachments: Final RAI_Hope Creek_542.docx By letter dated September 21, 2017 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML17265A847, PSEG Nuclear LLC, (PSEG or the licensee), requested to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2, which changes the Technical Specifications (TSs) for Hope Creek Generating Station.
Hope Creek TS Section 2.0, Safety Limits and Limiting Safety System Settings, 2.1.4 states; the reactor vessel water level shall be above the top of the active irradiated fuel for Operational Conditions 3, 4 and 5.
With the reactor vessel water level at or below the top of the active irradiated fuel, manually initiate the Emergency Core Cooling System to restore the water level, after depressurizing the reactor vessel, if required.
Safety Limit 2.1.4 is maintained through the TS Limited Condition of Operation (LCO), applicability, actions, and notes. The Hope Creek TSs require certain safety systems to be OPERABLE during operations with a potential for draining the reactor vessel (OPDRVs). The proposed changes would replace existing TS requirements associated to OPDRVs with revised TSs providing an alternative requirement for Reactor Pressure Vessel (RPV) Water Inventory Control. These alternative requirements would protect Safety Limit 2.1.4.
The NRC staff has determined that the additional information is required for the staff to complete its review. On March 30, 2018, the NRC staff sent PSEG the draft Request for Additional Information (RAI). This RAI relates to the licensees request to adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2.
On May 30, 2018, the NRC staff and the licensee held a conference call to clarify the request. A publicly available version of this final RAI (attached) will be placed in the NRCs ADAMS. Subsequently, the licensee agreed to respond to this request within 30 days of the date of this email (i.e., by June 29, 2018).
Jim Kim Project Manager - Hope Creek Generating Station NRR/DORL/LPL1 301-415-4125 1
Hearing Identifier: NRR_DMPS Email Number: 393 Mail Envelope Properties (James.Kim@nrc.gov20180530134000)
Subject:
Hope Creek - Final RAI RE: Revise TS to Adopt TSTF-542 Sent Date: 5/30/2018 1:40:00 PM Received Date: 5/30/2018 1:40:00 PM From: Kim, James Created By: James.Kim@nrc.gov Recipients:
"Duke, Paul R." <Paul.Duke@pseg.com>
Tracking Status: None "Thomas, Brian J." <Brian.Thomas@pseg.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2107 5/30/2018 1:40:00 PM Final RAI_Hope Creek_542.docx 25499 Options Priority: Standard Return Notification: Yes Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
REQUEST FOR ADDITIONAL INFORMATION APPLICATION TO REVISE TECHNICAL SPECIFICATION TO ADOPT TSTF-542, REVISION 2, REACTOR PRESSURE VESSEL WATER INVENTORY CONTROL PGES NUCLEAR LLC HOPE CREEK GENERATIONG STATION EPID: L-2017-LLA-0352 By application dated September 21, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17265A847, PSEG Nuclear LLC, (PSEG), (the licensee),
requested to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2, which changes the Technical Specifications (TSs) for Hope Creek Generating Station. Traveler TSTF-542, Revision 2, was approved by the U.S. Nuclear Regulatory Commission (NRC) on December 20, 2016 (ADAMS Accession No. ML16343B008).
Hope Creek TS Section 2.0, Safety Limits and Limiting Safety System Settings, 2.1.4 states; the reactor vessel water level shall be above the top of the active irradiated fuel for Operational Conditions 3, 4 and 5. With the reactor vessel water level at or below the top of the active irradiated fuel, manually initiate the Emergency Core Cooling System to restore the water level, after depressurizing the reactor vessel, if required. Safety Limit 2.1.4 is maintained through the TS Limited Condition of Operation (LCO), applicability, actions, and notes. The Hope Creek TSs require certain safety systems to be OPERABLE during operations with a potential for draining the reactor vessel (OPDRVs).
The proposed changes would replace existing TS requirements associated to OPDRVs with revised TSs providing an alternative requirement for Reactor Pressure Vessel (RPV) Water Inventory Control. These alternative requirements would protect Safety Limit 2.1.4.
The Nuclear Regulatory Commission (NRC) staff has reviewed the information the licensee provided that supports the proposed amendment and is requesting for the licensee to address the following issues to be resolved and supplement the submittal:
Question 1 (HC-RAI-1)
Background:
LAR Attachment 1, page 7, item D.1 describes a variation related to Core Alterations. The variation states:
In alignment with TSTF-542, Rev. 2, Proposed Safety Basis (Section 3.1.2), the existing Hope Creek TS 3.5.2 requirement to suspend core alterations as an action for ECCS inoperability is no longer warranted since there are no postulated events associated with core alterations that are prevented or mitigated by the proposed RPV water inventory control requirements. In addition, loss of RPV inventory events are not initiated by core alteration operations. Refueling Limiting Conditions for Operation (LCOs) 3.9.1, Reactor Mode Switch, 3.9.2, Instrumentation, 3.9.3, Control Rod Position, and 3.9.8, Water Level
- Reactor Vessel, provide requirements to ensure safe operation during core alterations, including required water level above the RPV flange. Therefore, PSEG proposes to delete TS 3.5.2, Action 'b' in its entirety, including the action relating to core alterations.
Traveler 542 does not specifically address that existing TS that have in place requirement for CORE ALTERATION, can be deleted.
Question:
Re-instate the TS requirement for CORE ALTERATION as describe in the following sections; LCO 3.5.2, Action b, LCO 3.5.3, Action b, or provide stronger justification that these actions can be deleted.
Question 2 (HC-RAI-2)
Background:
In LAR Attachment 2, proposed TS Table 3.3.12-2, RPV Water Inventory Control Instrumentation Setpoints (TS Page 3/4 3-114), Function 1.a, Core Spray System, Reactor Vessel Pressure - Low (Permissive) has a trip setpoint of 461 psig and Function 2.a, Low Pressure Coolant Injection Mode of RHR System, Reactor Vessel Pressure - Low (Permissive), has a trip setpoint of 450 psig. The proposed change varies from the origin of these TS requirements, existing Table 3.3.3-2, Emergency Core Cooling System Actuation Instrumentation Setpoints, Functions 1.c with trip setpoint 461 psig and Function 2.a, with trip setpoint 450 psig.
Question:
Please provide technical justification for the proposed trip setpoints for TS Table 3.3.12-2 Functions 1.a and 2.a.
Question 3 (HC-RAI-3)
Background:
In LAR Attachment 2, Table 3.3.12-1, RPV Water Inventory Control Instrumentation (TS Page 3/4 3-112), Function 3.a, RHR System Shutdown Cooling Mode of RHR System, Reactor Vessel Water Level - Low, Level 3, and Function 4.a, Reactor Water Cleanup System Isolation, Reactor Vessel Water Level - Low Low, Level 2 each has a value of 2 for their minimum operable channels per trip function. The proposed change varies from the origin of these TS requirements, existing Table 3.3.2-1, Isolation Actuation Instrumentation, Functions 7.a and 4.f, respectively. Each function currently has a value of 2/Valve minimum operable channels per trip system. Additionally, in the existing Table 3.3.2-1, both functions contain footnote (e), which states, Sensors arranged per valve group, not per trip system.
Question:
Please provide technical justification for the proposed minimum operable channels per trip function for TS Table 3.3.12-1 Functions 3.a and 4.a.