MONTHYEARML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24185A1772024-07-0303 July 2024 Request for Additional Information IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML22118A3312022-04-28028 April 2022 NRR E-mail Capture - Peach Bottom - Formal RAI for Proposed Alternative I5R-14, Revision 1 ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 IR 05000277/20224032022-01-21021 January 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000277/2022403 and 05000278/2022403 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML22006A3212022-01-0606 January 2022 NRR E-mail Capture - Final RAI - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21041A3972021-02-18018 February 2021 Request for Additional Information Revise Low Pressure Safety Limit to Address General Electric Part-21 Safety Communications (Non-Proprietary) ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21035A2222021-02-0404 February 2021 Notification of Conduct of a Fire Protection Team Inspection ML21091A1782021-02-0202 February 2021 Ti 2515/194 Inspection Documentation Request ML21012A1302021-01-12012 January 2021 Request for Additional Information - TSTF-505 ML20357A0972020-12-21021 December 2020 Request for Additional Information - TSTF-505 ML20295A4922020-10-21021 October 2020 NRR E-mail Capture - Hope Creek - Final RAI Revise ECCS TS with Respect to HPCI System Inoperability (L-2020-LLA-0131) ML20296A3342020-10-21021 October 2020 ISI Remote Inspection - Supplemental Request for Information ML20239A7982020-08-25025 August 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet License Amendment Request to Adopt TSTF-568, Revision 2 ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20070R2282020-03-10010 March 2020 Request for Additional Information - RR ML19303D1662019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- RAIs ML19232A1752019-08-20020 August 2019 Request for Additional Information - TSTF-500 Implementation LAR ML19140A2832019-05-15015 May 2019 Email - Peach Bottom Atomic Power Station, Units 2 and 3 Second Round RAI Request - Set 1 ML19140A2822019-05-15015 May 2019 027 Pb FU RAI Subsequent to Clarification Call - Cu Greater than 15 Zn Holston (Jg) ML19253D2932019-05-0707 May 2019 002 Attachment 4D Confirmation Water Chemistry Chereskin Revised (002) ML19249C7252019-05-0303 May 2019 SLRA Requests for Additional Information - Set 2 May 3, 2019 ML19108A4282019-04-10010 April 2019 RAIs SLRA Set 1_ERO(Rev 1) ML19079A0232019-03-19019 March 2019 Licensed Operator Positive Fitness-For-Duty Test ML19058A2902019-02-27027 February 2019 Request for Additional Information - High Pressure Service Water One Time TS Change ML19037A4832019-02-0606 February 2019 NRR E-mail Capture - Clarification Questions Associated with Staff Assessment of Peach Bottom Seismic Probabilistic Risk Assessment Report Dated August 28, 2018 ML19028A0062019-01-25025 January 2019 Secondary Containment LAR Requests for Additional Information ML19017A0472019-01-16016 January 2019 Request for Additional Information - High Pressure Service Water One Time TS Change ML18348B0292018-12-13013 December 2018 Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information ML19010A3832018-12-0707 December 2018 Additional Documents Needed for Peach Bottom SLR Environmental Review ML18324A6742018-11-15015 November 2018 Request for Additional Information (FINAL)- LAR to Allow 2SRV/SVs OOS at High Pressure ML18312A4072018-11-0808 November 2018 Request for Additional Information (Public) - LAR to Allow 2SRV/SVs OOS at High Pressure ML18276A0202018-10-0202 October 2018 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Amendment Request to Revise Emergency Plan for Limerick and Peach Bottom ML18263A1442018-09-12012 September 2018 NRR E-mail Capture - Final RAI from Apla: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18250A3142018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18240A1742018-08-28028 August 2018 Request for Additional Information (Final) - Adopt TSTF-500 Battery TS Changes LAR ML18239A1322018-08-27027 August 2018 Request for Additional Information Final - Relief Request I5R-04 ML18226A2012018-08-14014 August 2018 Request for Additional Information - Relief Request I5R-05 ML18228A6762018-08-14014 August 2018 Request for Additional Information - Adopt TSTF-500 Battery TS Changes LAR 2024-09-09
[Table view] |
Text
DRAFT REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR REACTOR REGULATION 2013 DECOMMISSIONING FUNDING STATUS REPORT PSEG NUCLEAR, LLC HOPE CREEK GENERATING STATION PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 DOCKET NUMBERS 50-277, 50-278 AND 50-354 By letter dated March 26, 2013, (Agencywide Documents Access and Management System Accession No. ML13085A284) PSEG Nuclear, LLC, (PSEG) submitted to the Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for Hope Creek Generating Station (Hope Creek), and Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3, as required under 10 CFR 50.75(f)(1). The NRC staff has reviewed the information provided in the submittal and determined that the following additional information is required in order to complete its review.
Reporting Requirements RAI 1 Indicate what portion of the accumulated fund balances are for radiological decommissioning activities only. Specify if any of the $448,673,976 for Hope Creek, the
$246,506,792 for PBAPS Unit2, and the $249,543,711 for PBAPS Unit 3, is for non-radiological decommissioning costs such as spent fuel management or other non-radiological decommissioning activities.
On March 26, 2013, PSEG provided the amount accumulated in the decommissioning trust fund at the end of the calendar year preceding the date of the report for items included in 10 CFR 50.75 (b) and (c). Confirm that the dollar amounts identified above are exclusively for radiological decommissioning.
Per 10 CFR 50.75(f)(1), licensees must identify the amount accumulated to the end of the calendar year preceding the date of the report. This actual amount is dedicated for NRC decommissioning activities as defined in 10 CFR 50.2.
Amounts accumulated RAI 2 Indicate if the amount of decommissioning funds identified in the March 26, 2013, submittal are for the after-tax amounts of decommissioning funds accumulated through December 31, 2012. If not, please provide the after-tax amounts of decommissioning funds accumulated through December 31, 2012, for Hope Creek, PBAPS Unit 2 and PBAPS Unit 3.
DRAFT
On March 26, 2013, APS reported the amount of decommissioning funds accumulated as of December 31, 2012, for Hope Creek, PBAPS Unit 2 and PBAPS Unit 3, but did not indicate if the amount stated was the before or after-tax balance.
The provisions of 10 CFR 50.75(f)(1) and (2) require the licensee to report the amount of funds accumulated to the end of the calendar year preceding the report.
DRAFT