MONTHYEARIR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 ML24295A3742024-10-23023 October 2024 Project Manager Assignment IR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 ML24291A0572024-10-17017 October 2024 License Amendment Request (LAR) – Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 1 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24281A1012024-10-0707 October 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities ML24221A2582024-09-0606 September 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification 05000277/LER-2024-003, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum2024-09-0505 September 2024 Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum 05000354/LER-2024-001-01, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement2024-09-0505 September 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 ML24235A0342024-08-23023 August 2024 U.S. Nuclear Regulatory Commission’S Analysis of Constellation Energy Generation’S Decommissioning Funding Status Report IR 05000277/20240022024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24225A1692024-08-12012 August 2024 10 CFR 50.46 Annual Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 ML24214A3232024-08-0101 August 2024 Response to Request for Additional Information - Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24197A0552024-07-15015 July 2024 Requalification Program Inspection ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report 05000354/LER-2024-001, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML24166A1172024-06-20020 June 2024 Regulatory Audit Summary Regarding Proposed Alternative Schedule to Complete Decommissioning Beyond 60 Years RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities 2024-09-06
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24185A1772024-07-0303 July 2024 Request for Additional Information IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML22118A3312022-04-28028 April 2022 NRR E-mail Capture - Peach Bottom - Formal RAI for Proposed Alternative I5R-14, Revision 1 ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 IR 05000277/20224032022-01-21021 January 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000277/2022403 and 05000278/2022403 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML22006A3212022-01-0606 January 2022 NRR E-mail Capture - Final RAI - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21041A3972021-02-18018 February 2021 Request for Additional Information Revise Low Pressure Safety Limit to Address General Electric Part-21 Safety Communications (Non-Proprietary) ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21035A2222021-02-0404 February 2021 Notification of Conduct of a Fire Protection Team Inspection ML21091A1782021-02-0202 February 2021 Ti 2515/194 Inspection Documentation Request ML21012A1302021-01-12012 January 2021 Request for Additional Information - TSTF-505 ML20357A0972020-12-21021 December 2020 Request for Additional Information - TSTF-505 ML20295A4922020-10-21021 October 2020 NRR E-mail Capture - Hope Creek - Final RAI Revise ECCS TS with Respect to HPCI System Inoperability (L-2020-LLA-0131) ML20296A3342020-10-21021 October 2020 ISI Remote Inspection - Supplemental Request for Information ML20239A7982020-08-25025 August 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet License Amendment Request to Adopt TSTF-568, Revision 2 ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20070R2282020-03-10010 March 2020 Request for Additional Information - RR ML19303D1662019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- RAIs ML19232A1752019-08-20020 August 2019 Request for Additional Information - TSTF-500 Implementation LAR ML19140A2832019-05-15015 May 2019 Email - Peach Bottom Atomic Power Station, Units 2 and 3 Second Round RAI Request - Set 1 ML19140A2822019-05-15015 May 2019 027 Pb FU RAI Subsequent to Clarification Call - Cu Greater than 15 Zn Holston (Jg) ML19253D2932019-05-0707 May 2019 002 Attachment 4D Confirmation Water Chemistry Chereskin Revised (002) ML19249C7252019-05-0303 May 2019 SLRA Requests for Additional Information - Set 2 May 3, 2019 ML19108A4282019-04-10010 April 2019 RAIs SLRA Set 1_ERO(Rev 1) ML19079A0232019-03-19019 March 2019 Licensed Operator Positive Fitness-For-Duty Test ML19058A2902019-02-27027 February 2019 Request for Additional Information - High Pressure Service Water One Time TS Change ML19037A4832019-02-0606 February 2019 NRR E-mail Capture - Clarification Questions Associated with Staff Assessment of Peach Bottom Seismic Probabilistic Risk Assessment Report Dated August 28, 2018 ML19028A0062019-01-25025 January 2019 Secondary Containment LAR Requests for Additional Information ML19017A0472019-01-16016 January 2019 Request for Additional Information - High Pressure Service Water One Time TS Change ML18348B0292018-12-13013 December 2018 Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information ML19010A3832018-12-0707 December 2018 Additional Documents Needed for Peach Bottom SLR Environmental Review ML18324A6742018-11-15015 November 2018 Request for Additional Information (FINAL)- LAR to Allow 2SRV/SVs OOS at High Pressure ML18312A4072018-11-0808 November 2018 Request for Additional Information (Public) - LAR to Allow 2SRV/SVs OOS at High Pressure ML18276A0202018-10-0202 October 2018 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Amendment Request to Revise Emergency Plan for Limerick and Peach Bottom ML18263A1442018-09-12012 September 2018 NRR E-mail Capture - Final RAI from Apla: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18250A3142018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18240A1742018-08-28028 August 2018 Request for Additional Information (Final) - Adopt TSTF-500 Battery TS Changes LAR ML18239A1322018-08-27027 August 2018 Request for Additional Information Final - Relief Request I5R-04 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 12. 2013 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236, N09 Hancocks Bridge, NJ 08038
SUBJECT:
HOPE CREEK GENERATING STATION AND PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION REGARDING DECOMMISSIONING FUNDING STATUS REPORT (TAC NOS. MF2202, MF2227 AND MF2228)
Dear Mr. Joyce:
By letter dated March 26, 2013,1 PSEG Nuclear LLC (the licensee), submitted to the Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status report for Hope Creek Generating Station, and Peach Bottom Atomic Power Station, Units 2 and 3, as required under Title 10 of the Code of Federal Regulations, paragraph 50. 75(f)(1). The NRC staff has reviewed the submittal by the licensee and has determined that additional information is required, as provided in the enclosure, in order to complete its review.
The draft questions were sent via electronic transmission on July 19, 2013, to Mr. Paul Duke, of your staff. The draft questions were sent to ensure that the questions were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. On July 24, 2013, Mr. Duke indicated that the licensee will submit a response within 30 days of the date of this letter.
If you have any questions, please contact me at (301) 415-3204 or via e-mail at John.Hughey@nrc.gov.
Si~D~
John D. Hughey, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-354, 50-277 and 50-278
Enclosure:
Request for Additional Information cc: Distribution via ListServ 1 Agencywide Documents Access and Management System Accession No. ML13085A284.
REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR REACTOR REGULATION 2013 DECOMMISSIONING FUNDING STATUS REPORT PSEG NUCLEAR. LLC HOPE CREEK GENERATING STATION PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 DOCKET NUMBERS 50-354, 50-277 AND 50-278 By tetter dated March 26,2013, (Agencywide Documents Access and Management System Accession No. ML13085A284) PSEG Nuclear, LLC, (PSEG) submitted to the Nuclear Regulatory Commission (!\IRC) the 2013 Decommissioning Funding Status report for Hope Creek Generating Station (Hope Creek), and Peach Bottom Atomic Power Station (PBAPS),
Units 2 and 3, as required under Title 10 of the Code of Federal Regulations (10 CFR) paragraph 50. 75(f)(1). The NRC staff has reviewed the information provided in the submittal and determined that the following additional information is required in order to complete its review.
Reporting Requirements RAI 1 Indicate what portion of the accumulated fund balances are for radiological decommissioning activities only. Specify if any of the $448,673,976 for Hope Creek, the
$246,506,792 for PBAPS Unit 2, and the $249,543,711 for PBAPS Unit 3, is for non radiological decommissioning costs such as spent fuel management or other non radiological decommissioning activities.
On March 26, 2013, PSEG provided the amount accumulated in the decommissioning trust fund at the end of the calendar year preceding the date of the report for items included in 10 CFR 50.75 (b) and (c). Confirm that the dollar amounts identified above are exclusively for radiological decommissioning.
Per 10 CFR 50.75(f)(1), licensees must identify "the amount accumulated to the end of the calendar year preceding the date of the report." This actual amount is dedicated for NRC decommissioning activities as defined in 10 CFR 50.2.
Amounts accumulated RAI2 Indicate if the amount of decommissioning funds identified in the March 26, 2013, submittal are for the after-tax amounts of decommissioning funds accumulated through December 31, 2012. If not, please provide the after-tax amounts of decommissioning funds accumulated through December 31,2012, for Hope Creek, PBAPS Unit 2, and PBAPS Unit 3.
Enclosure
-2 On March 26, 2013, PSEG reported the amount of decommissioning funds accumulated as of December 31,2012, for Hope Creek, PBAPS Unit 2, and PBAPS Unit 3, but did not indicate if the amount stated was the before or after-tax balance.
The provisions of 10 CFR 50.75(f)(1) and (2) require the licensee to report the amount of funds accumulated to the end of the calendar year preceding the report.
August 12, 2013 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236, N09 Hancocks Bridge, NJ 08038
SUBJECT:
HOPE CREEK GENERATING STATION AND PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION REGARDING DECOMMISSIONING FUNDING STATUS REPORT (TAC NOS. MF2202, MF2227 AND MF2228)
Dear Mr. Joyce:
By letter dated March 26, 2013,1 PSEG Nuclear LLC (the licensee), submitted to the Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status report for Hope Creek Generating Station, and Peach Bottom Atomic Power Station, Units 2 and 3, as required under Title 10 of the Code of Federal Regulations, paragraph 50.75(f)(1). The NRC staff has reviewed the submittal by the licensee and has determined that additional information is required, as provided in the enclosure, in order to complete its review.
The draft questions were sent via electronic transmission on July 19, 2013, to Mr. Paul Duke, of your staff. The draft questions were sent to ensure that the questions were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. On July 24, 2013, Mr. Duke indicated that the licensee will submit a response within 30 days of the date of this letter.
If you have any questions, please contact me at (301) 415-3204 or via e-mail at John.Hughey@nrc.gov.
Sincerely, Ira!
John D. Hughey, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-354, 50-277 and 50-278
Enclosure:
Request for Additional Information cc: Distribution via ListServ 1 Agencywide Documents Access and Management System Accession No. ML13085A284.
DISTRIBUTION:
RidsNrrPMHopeCreek Resource RidsNrrLAABaxter Resource RidsNrrDorlDpr Resource RidsRgn1 MailCenter Resource RidsNrrDorlLpl1-2 Resource LPLI-2 R/F RidsNrrDirslfib Resource RidsAcrsAcnw MailCTR Resource PUBLIC R. Tu rtil , NRR RidsNrrPMPeachBottom Resource ADAMS Accession No' ML13168A276 *via memo dated OFFICE LPL 1-2/PM LPL 1-2/LA IFIB/BC* LPL 1-2/BC LPL 1-2/PM NAME JHughey ABaxter CRegan VRodriguez JHughey DATE 07/31/2013 07/31/2013 6/4/13 & 7/10/13 08/07/2013 08/12/2013 OFFICIAL RECORD COPY 1 Agencywide Documents Access and Management System Accession No. IVIL13085A284.