ML17324A260

From kanterella
Jump to navigation Jump to search

NRR E-mail Capture - Final Request for Additional Information - Hope Creek Mur Electrical Instrumentation and Controls
ML17324A260
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 11/17/2017
From: Lisa Regner
Plant Licensing Branch IV
To: Duke P
Public Service Enterprise Group
References
L-2017-LLA-0002, MF9930
Download: ML17324A260 (2)


Text

NRR-PMDAPEm Resource From: Regner, Lisa Sent: Friday, November 17, 2017 1:01 PM To: Paul.Duke@pseg.com; Thomas, Brian J.

Subject:

HCGS MUR - Final Request for Additional Information Electrical Instrumentation and Controls (EICB)

Attachments: Draft RAI for Hope Creek MUR Final Request for Additional Information (L-2017-LLS-0002)

On November 9, 2017, the U.S. Nuclear Regulatory Commission (NRC) staff sent PSEG (the licensee) a draft Request for Additional Information (RAI) as provided in the attached document. These RAI questions relate to a license amendment request (LAR) that proposes to increase the rated thermal power level from 3840 megawatts thermal to 3902 megawatts thermal, and make technical specification changes as necessary to support operation at the uprated power level. This is referred to as a measurement uncertainty recapture (MUR) uprate.

PSEG informed the NRC staff that a clarification call was needed, and this call was held on November 15, 2017. Subsequently. PSEG informed the NRC staff that the questions were understood and Mr. Brian Thomas agreed to provide a response to this final RAI on or before December 22, 2017. If PSEG does not respond by this date, the requested completion date for the MUR decision may not be met by the NRC.

The NRC staff also informed the licensee that a publicly available version of this final RAI would be placed in the NRCs Agencywide Documents Access and Management System (ADAMS).

By letter dated July 7, 2017, (ADAMS package Accession No. ML17188A259), the licensee requested an amendment to the Operating License for Hope Creek Generating Station. The proposed amendment requests a MUR uprate for Hope Creek. The NRC staff requires additional information to complete its review of this request as detailed in the attached document.

Lisa Regner Sr. Project Manager NRR/DORL/LPL4 301-415-1906 O9D14 1

Hearing Identifier: NRR_PMDA Email Number: 3841 Mail Envelope Properties (0e2b3493ec8946c086372b856478206b)

Subject:

HCGS MUR - Final Request for Additional Information Electrical Instrumentation and Controls (EICB)

Sent Date: 11/17/2017 1:01:27 PM Received Date: 11/17/2017 1:01:28 PM From: Regner, Lisa Created By: Lisa.Regner@nrc.gov Recipients:

"Paul.Duke@pseg.com" <Paul.Duke@pseg.com>

Tracking Status: None "Thomas, Brian J." <Brian.Thomas@pseg.com>

Tracking Status: None Post Office: HQPWMSMRS05.nrc.gov Files Size Date & Time MESSAGE 1664 11/17/2017 1:01:28 PM Draft RAI for Hope Creek MUR 19962 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: