|
---|
Category:E-Mail
MONTHYEARML24277A0812024-10-0303 October 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon Collected on 10/02/2024 ML24269A0362024-09-24024 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/24/2024 ML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24248A0452024-09-0303 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/3/2024 ML24240A2092024-08-27027 August 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Relief Request VR-04, SSW Rupture Disc Replacement ML24229A0422024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Implement Optimized ZIRLO Fuel Rod Cladding ML24229A0432024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Exemption from 10 CFR 50.46 and 10 CFR 50 Appendix K to Allow the Use of Optimized ZIRLO Fuel Rod Cladding ML24227A5092024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 8/13/2024 ML24228A1942024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form for a Live - Atlantic Sturgeon 8/14/2024 ML24197A1022024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise TS Lift Settings for Reactor Coolant System Safety Relief Valves ML24250A0562024-07-11011 July 2024 PSEG to NMFS, Regarding Processing of Fin Clips ML24219A2472024-07-0909 July 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Shortnose Sturgeon 7/9/2024 ML24163A1632024-06-11011 June 2024 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle ML24123A0522024-05-0101 May 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - One Deceased Sturgeon 4/30/2024 ML24106A0542024-04-12012 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Alive Atlantic Sturgeon 4/12/2024 ML24101A2192024-04-0909 April 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 4/8/24 ML24093A1222024-04-0101 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Atlantic Sturgeon 4/1/2024 ML24075A1862024-03-14014 March 2024 NRR E-mail Capture - (External_Sender) Biological Opinion Gar 2020-02842 - PSEG Salem and Hope Creek Generating Station Annual Incidental Take Report - 2023 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML24030A8432024-01-30030 January 2024 NRR E-mail Capture - (External_Sender) 2023 PSEG Sturgeon Pit Tag Data ML24016A1612024-01-10010 January 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms - Two Atlantic Sturgeon 1/9/2024 ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML24002A7242023-12-28028 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - Sturgeon 12/28/2023 ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML24002A7252023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Shortnose Sturgeon 12/21/23 ML23346A0962023-12-0606 December 2023 NRR E-mail Capture - Reminder - Final Report - Completion of Required Additional Protocol (AP) Information in Accordance with the U.S. - IAEA Treaty Obligations ML23311A0792023-11-0101 November 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Atlantic Sturgeon Collected on 10/31/2023 ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23226A0702023-08-11011 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Sturgeon Collected on 8/10/2023 ML23226A0732023-08-10010 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Submittal of Necropsy Reports Regarding Sea Turtles Collected on 06/12/2022 ML23201A0132023-07-20020 July 2023 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML23172A0982023-06-21021 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/20/2022 ML23164A2062023-06-13013 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/12/2023 ML24250A0572023-06-0606 June 2023 PSEG to NMFS, Request for Sturgeon Fin Clip Analysis Facilities ML23163A0442023-06-0606 June 2023 NRR E-mail Capture - (External_Sender) Biological Opinion GAR-2020-02842; FIN Clip Analysis Facilities ML23153A1552023-06-0202 June 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 6/1/2023 ML23151A6582023-05-31031 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/30/2023 ML23137A2632023-05-17017 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/16/2023 ML23135A0102023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 5/11/2023 ML23129A7892023-05-0909 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise Trip and Standby Auto-Start Logic Associated with Safety Related HVAC Trains ML23136B2832023-05-0404 May 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 5/3/2023 ML23122A1982023-05-0202 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeon 5/1/2023 ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23117A2722023-04-17017 April 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 04/14/2023 ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML23033A0302023-02-0808 February 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 1/24/2023 ML23010A2882023-01-10010 January 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 01/09/2023 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22318A1062022-11-14014 November 2022 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000272/2023011 and 05000311/2023011 ML22290A2202022-10-17017 October 2022 NRR E-mail Capture - Final RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22055A0702022-02-22022 February 2022 NRR E-mail Capture - Final RAI - Salem 1-Relief Request Associated with Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2021-LLR-0085) ML22006A3212022-01-0606 January 2022 NRR E-mail Capture - Final RAI - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21068A4142021-03-0909 March 2021 NRR E-mail Capture - Final RAI for Salem Unit 1 LAR to Revise and Relocate Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report ML21041A3972021-02-18018 February 2021 Request for Additional Information Revise Low Pressure Safety Limit to Address General Electric Part-21 Safety Communications (Non-Proprietary) ML21043A1442021-02-11011 February 2021 NRR E-mail Capture - Salem - Final RAI Alternative for Examination of ASME Section XI, Category B-B, Item Number B2.11and B2.12 (L-2020-LRR-0103) ML21021A2592021-01-21021 January 2021 NRR E-mail Capture - Final RAI - Salem 1 - Steam Generator Tube Inspection Report ML20295A4922020-10-21021 October 2020 NRR E-mail Capture - Hope Creek - Final RAI Revise ECCS TS with Respect to HPCI System Inoperability (L-2020-LLA-0131) ML20281A5172020-10-13013 October 2020 Notification of Conduct of a Fire Protection Team Inspection ML18267A1712018-09-21021 September 2018 NRR E-mail Capture - Final RAI from PRA Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18264A0122018-09-20020 September 2018 NRR E-mail Capture - Final RAI from I&C Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18263A1442018-09-12012 September 2018 NRR E-mail Capture - Final RAI from Apla: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18250A3132018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18250A3142018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18171A3212018-06-20020 June 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Adopt TSTF-411 and 418 (L-2017-LLA-0442) ML18150A6912018-05-30030 May 2018 NRR E-mail Capture - Hope Creek - Final RAI Revise TS to Adopt TSTF-542 ML18120A2482018-04-27027 April 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000354/2018403 ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17348A6242017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Human Factors Associated with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A9972017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17349A0812017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Reactor Systems Branch (Srxb) - Hope Creek Mur ML17331A0072017-11-21021 November 2017 E-mail Regarding Final Eicb Request for Additional Information - Hope Creek Power Uprate ML17348A6282017-11-21021 November 2017 NRR E-mail Capture - Draft Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17324A2602017-11-17017 November 2017 NRR E-mail Capture - Final Request for Additional Information - Hope Creek Mur Electrical Instrumentation and Controls ML17320A2152017-11-16016 November 2017 NRR E-mail Capture - Hope Creek Measurement Uncertainty Recapture Application Review - Electrical Engineering (Eeob) Request for Additional Information (L-2017-LLS-0002) ML17290B0132017-10-17017 October 2017 NRR E-mail Capture - Hope Creek Mur Request for Additional Information for Apla and Snpb ML17222A1652017-08-10010 August 2017 NRR E-mail Capture - Hope Creek: Final Request for Information, Pressure-Temperature Limit Report Request (MF9502) ML17212B1152017-07-31031 July 2017 Request for Additional Information - Salem Units 1 and 2 - Containment Fan Coil Unit Allowed Outage Time Amendment Request (CACs MF9364 and MF9365) ML17199A1122017-07-18018 July 2017 Request for Additional Information - Salem Units 1 and 2 - Accident Monitoring Instrumentation License Amendment Request (CAC Nos. MF8859 & MF8860) ML17192A1672017-07-11011 July 2017 Request for Additional Information - Salem Unit 1 - Steam Generator Tube Inspection Report ML17181A1352017-06-29029 June 2017 NRR E-mail Capture - Request for Additional Information Related to Hope Creek and Salem Emergency Action Level Scheme Change License Amendment Request (MF9268/69/70) ML17164A4062017-06-13013 June 2017 NRR E-mail Capture - Hope Creek - Final Request for Additional Information Concerning ILRT (MF8462) ML17115A4032017-05-0909 May 2017 Request for Additional Information Regarding Relief Request SC-14R-171 - Use of Code Cases N-695-1 and N-696-1 ML17027A3282017-02-27027 February 2017 Request for Additional Information Regarding License Amendment Request to Permanently Extend Type a and Type C Leak Rate Test Frequencies ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16277A5142016-11-0303 November 2016 Request for Additional Information Regarding License Amendment Request to Permit Operability of Low Pressure Coolant Injection While Aligned to Shutdown Cooling ML16271A2052016-11-0202 November 2016 Request for Additional Information Regarding Request to Delete Technical Specifications Action Statement 3.4.2.1.b Associated with Stuck Open Safety/Relief Valves ML16231A4272016-08-24024 August 2016 Request for Additional Information Regarding Relief Request VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16217A4302016-08-17017 August 2016 Request for Additional Information Regarding Digital Power Range Neutron Monitoring System Upgrade ML16218A0052016-08-11011 August 2016 Request for Additional Information Concerning Request for an Extension to Enforcement Guidance Memorandum 12-001 2024-09-09
[Table view] |
Text
From: Hughey, John Sent: Friday, October 05, 2012 10:27 AM To: Hughey, John; 'michelle.patti@pseg.com' Cc: 'Duke, Paul R.'; Khanna, Meena
Subject:
Clarifying Information for Question No. 4 (with attachment)
Attachments: Salem and Hope Creek Generating Stations - Request for Additional Information Regarding August 1, 2012, Security Plan Submittal
- Michelle, As discussed on yesterdays teleconference call, NSIR has provided clarifying information below regarding Question #4 in the attached RAI request. Please contact me at 301-415-3204, or by reply e-mail, to discuss the need for an additional teleconference and the originally requested response due date of October 19, 2012.
Thank you, John John Hughey Salem & Hope Creek Project Manager NRR / Division of Operating Reactor Licensing Phone: 301-415-3204 e-mail: John.Hughey@nrc.gov Clarifying Information for Question No. 4 In section 15.3 of the PSP, the licensee describes intrusion detection equipment at the site. The last paragraph of this section includes a description of an early warning system (EWS). Describe how the EWS barrier and associated intrusion detection and assessment equipment that are identified in Section 15.3 of the PSP meets the requirements of 10 CFR 73.55. Specifically:
- a. Describe the function of the EWS barrier by identifying how it and the associated intrusion detection and assessment capabilities are integrated within the physical protection program and protective strategy and how these capabilities are used to support the initiation of the protective strategy. Describe how the detection and assessment capability at the EWS barrier facilitates the initiation of operator actions that are credited as target elements within target sets. Describe how the implementation of the EWS barrier and associated intrusion detection and assessment equipment have been included in the drills and exercises of the sites protective strategy that have been conducted to meet the Performance Evaluation Program requirements of 10 CFR Part 73, Appendix B VI, C.3.
Describe the percentage of drills and exercises, conducted since implementation of the EWS barrier and associated intrusion detection and assessment equipment, in which initiation of the protective strategy resulted from adversary detection at the EWS barrier.
Regulatory Basis:
Consistent with 10 CFR 73.55(c)(3), the licensee shall establish, maintain, and implement a PSP which describes how the performance objective and requirements set forth in this section will be implemented.
Consistent with 10 CFR 73.55(e)(1)(ii), the licensee shall describe in the security plan, physical barriers, barrier systems, and their functions within the physical protection program.
- b. Describe how the openings in the EWS barrier are secured and monitored to prevent exploitation of the openings.
Regulatory Basis:
In accordance with 10 CFR 73.55(e)(4), consistent with the stated function to be performed, openings in any barrier or barrier system established to meet the requirements of this section must be secured and monitored to prevent exploitation of the opening.
- c. Describe how vehicle and material access through the EWS barrier is controlled.
Regulatory Basis:
In accordance with 10 CFR 73.55(g)(1), consistent with the function of each barrier or barrier system, the licensee shall control personnel, vehicle, and material access, as applicable, at each access control point in accordance with the physical protection program design requirements of 10 CFR 73.55, and 10 CFR 73.55(b).
- d. Describe the personnel, vehicle and material access control portals of the EWS barrier, specifically whether they are located outside of, or co-located with, the EWS barrier.
Regulatory Basis:
Consistent with 10 CFR 73.55(g)(1)(i)(A), access control portals must be located outside of, or concurrent with, the physical barrier system through which it controls access.
- e. Describe how the locking devices, intrusion detection equipment, and surveillance equipment implemented at the EWS personnel, vehicle, and material access control portals meet regulatory requirements.
Regulatory Basis:
Consistent with 10 CFR 73.55(g)(1)(i)(B), access control portals must be equipped with locking devices, intrusion detection equipment, and surveillance equipment consistent with the intended function.
- f. Describe the search procedures that have been implemented at EWS access control portals.
Regulatory Basis:
Consistent with 10 CFR 73.55(h)(2)(i), where the licensee has established physical barriers in the owner controlled area, the licensee shall implement search procedures for access control points in the barrier.
- g. Describe how the intrusion detection and assessment equipment at the EWS provides, at all times, the capability to detect and assess unauthorized persons and facilitate the effective implementation of the protective strategy.
Regulatory Basis:
Consistent with 10 CFR 73.55(i)(1), the licensee shall establish and maintain intrusion detection and assessment systems that satisfy the design requirements of 10 CFR 73.55(b) and provide, at all times, the capability to detect and assess unauthorized persons and facilitate the effective implementation of the licensees protective strategy.
- h. Describe how the intrusion detection and assessment equipment at the EWS is designed to annunciate and display concurrently in two continuously staffed onsite alarm stations.
Regulatory Basis:
Consistent with 10 CFR 73.55(i)(2), intrusion detection equipment must annunciate and assessment equipment shall display concurrently, in at least two continuously staffed onsite alarm stations, at least one of which must be protected in accordance with the requirements of the central alarm station within this section.
- i. Describe how the EWS intrusion detection and assessment systems are designed to: 1) provide visual and audible annunciation of an alarm; 2) provide a visual display from which assessment of the detected activity can be made;
- 3) ensure that the annunciation of an alarm indicates the type and location of the alarm; 4) ensure that alarm devices to include transmission lines to annunciators are tamper indicating and self-checking; 5) provide an automatic indication when the alarm system or a component of the alarm system fails, or when the system is operating on the back-up power supply; and 6) support the initiation of a timely response in accordance with the security plans, protective strategy, and associated implementing procedures.
Regulatory Basis:
Consistent with 10 CFR 73.55(i)(3)(i) through (i)(3)(vi), the licensees intrusion detection and assessment systems must be designed to: (i) provide visual and audible annunciation of the alarm; (ii) provide a visual display from which assessment of the detected activity can be made; (iii) ensure that annunciation of an alarm indicates the type and location of the alarm; (iv) ensure that alarm devices to include transmission lines to annunciators are tamper indicating and self-checking; (v) provide an automatic indication when the alarm system or a component of the alarm system fails, or when the system is operating on the back-up power supply; and (vi) support the initiation of a timely response in accordance with the security plans, protective strategy, and associated implementing procedures.
- j. Describe how unattended openings that intersect the EWS barrier have been addressed to detect exploitation by surreptitious bypass.
Regulatory Basis:
Consistent with 10 CFR 73.55(i)(5)(iii), unattended openings that intersect a security boundary such as underground pathways must be protected by a physical barrier and monitored by intrusion detection equipment or observed by security personnel at a frequency sufficient to detect exploitation.
- k. Describe the type of illumination assets that are implemented to ensure the area of the EWS is provided with the illumination necessary to satisfy the design requirements of 10 CFR 73.55(b) and implement the protective strategy.
Regulatory Basis:
Consistent with 10 CFR 73.55(i)(6)(i), the licensee shall ensure that all areas of the facility are provided with illumination necessary to satisfy the design requirements of 10 CFR 73.55(b) and implement the protective strategy.
- l. Describe how the implementation of the EWS barrier and associated intrusion detection and assessment equipment is included in security program reviews.
Regulatory Basis:
Consistent with 10 CFR 73.55(m)(1), as a minimum the licensee shall review each element of the physical protection program at least every 24 months.
- m. Describe how the EWS barrier and associated intrusion detection and assessment equipment is included in the site maintenance, testing, and calibration program and the intervals that the security equipment (intrusion detection and assessment, access control, and if applicable search equipment) at the EWS are tested for operability and performance.
Regulatory Basis:
Consistent with 10 CFR 73.55(n)(1)(i), the licensee shall establish, maintain, and implement a maintenance, testing and calibration program to ensure that security systems and equipment, including secondary power supplies and uninterruptible power supplies, are tested for operability and performance at predetermined intervals, maintained in an operable condition, and are capable of performing their intended function.
- n. Describe the compensatory measures that are implemented when the EWS barrier, intrusion detection, assessment, access control, and if applicable search equipment fails or becomes degraded.
Regulatory Basis:
Consistent with 10 CFR 73.55(n)(1)(v), licensees shall implement compensatory measures that ensure the effectiveness of the onsite physical protection program when there is a failure or degraded operation of security-related component or equipment.
Additionally, appropriate changes should be made during the next revision of the sites security plans to ensure the language clearly describes the intended function of
this EWS barrier as it pertains to the implementation of certain aspects of the physical protection program (e.g., access control, initiation of the protective strategy, etc.) in accordance with 10 CFR 73.55(e)(1)(ii).
Regulatory Basis:
Consistent with 10 CFR 73.55(c)(3), the licensee shall establish, maintain, and implement a PSP which describes how the performance objective and requirements set forth in this section will be implemented.
Consistent with 10 CFR 73.55(e)(1)(ii), the licensee shall describe in the security plan, physical barriers, barrier systems, and their functions within the physical protection program.