MONTHYEARML24295A3742024-10-23023 October 2024 Project Manager Assignment IR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 ML24291A0572024-10-17017 October 2024 License Amendment Request (LAR) – Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 1 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities 05000354/LER-2024-001-01, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement2024-09-0505 September 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24197A0552024-07-15015 July 2024 Requalification Program Inspection 05000354/LER-2024-001, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 LR-N24-0021, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums 05000354/LER-2023-003-01, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges 05000354/LER-2023-003, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-02-12012 February 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers 2024-09-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML22006A3212022-01-0606 January 2022 NRR E-mail Capture - Final RAI - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection ML21041A3972021-02-18018 February 2021 Request for Additional Information Revise Low Pressure Safety Limit to Address General Electric Part-21 Safety Communications (Non-Proprietary) ML20295A4922020-10-21021 October 2020 NRR E-mail Capture - Hope Creek - Final RAI Revise ECCS TS with Respect to HPCI System Inoperability (L-2020-LLA-0131) ML18263A1442018-09-12012 September 2018 NRR E-mail Capture - Final RAI from Apla: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18250A3142018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18150A6912018-05-30030 May 2018 NRR E-mail Capture - Hope Creek - Final RAI Revise TS to Adopt TSTF-542 ML18120A2482018-04-27027 April 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000354/2018403 ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML17349A0812017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Reactor Systems Branch (Srxb) - Hope Creek Mur ML17348A9972017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A6242017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Human Factors Associated with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A6282017-11-21021 November 2017 NRR E-mail Capture - Draft Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17331A0072017-11-21021 November 2017 E-mail Regarding Final Eicb Request for Additional Information - Hope Creek Power Uprate ML17324A2602017-11-17017 November 2017 NRR E-mail Capture - Final Request for Additional Information - Hope Creek Mur Electrical Instrumentation and Controls ML17320A2152017-11-16016 November 2017 NRR E-mail Capture - Hope Creek Measurement Uncertainty Recapture Application Review - Electrical Engineering (Eeob) Request for Additional Information (L-2017-LLS-0002) ML17290B0132017-10-17017 October 2017 NRR E-mail Capture - Hope Creek Mur Request for Additional Information for Apla and Snpb ML17222A1652017-08-10010 August 2017 NRR E-mail Capture - Hope Creek: Final Request for Information, Pressure-Temperature Limit Report Request (MF9502) ML17181A1352017-06-29029 June 2017 NRR E-mail Capture - Request for Additional Information Related to Hope Creek and Salem Emergency Action Level Scheme Change License Amendment Request (MF9268/69/70) ML17164A4062017-06-13013 June 2017 NRR E-mail Capture - Hope Creek - Final Request for Additional Information Concerning ILRT (MF8462) ML17027A3282017-02-27027 February 2017 Request for Additional Information Regarding License Amendment Request to Permanently Extend Type a and Type C Leak Rate Test Frequencies ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16277A5142016-11-0303 November 2016 Request for Additional Information Regarding License Amendment Request to Permit Operability of Low Pressure Coolant Injection While Aligned to Shutdown Cooling ML16271A2052016-11-0202 November 2016 Request for Additional Information Regarding Request to Delete Technical Specifications Action Statement 3.4.2.1.b Associated with Stuck Open Safety/Relief Valves ML16231A4272016-08-24024 August 2016 Request for Additional Information Regarding Relief Request VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16217A4302016-08-17017 August 2016 Request for Additional Information Regarding Digital Power Range Neutron Monitoring System Upgrade ML16007A1742016-05-31031 May 2016 Request for Additional Information Regarding Review of Post-EPU Steam Dryer Stress Calculation Acoustic Circuit Model Software Error ML16089A0792016-05-0505 May 2016 Request for Additional Information Regarding Relief Requests GR-01, PR-01, PR-02, VR-01, and VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16124A5802016-05-0303 May 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes ML15055A3772015-03-10010 March 2015 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 ML14197A6192014-07-24024 July 2014 and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) ML14168A2352014-07-0202 July 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation ML13309B5922013-11-22022 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13168A2762013-08-12012 August 2013 Peach Bottom, Units 2 and 3, Request for Additional Information Decommissioning Funding Status Report (TAC No. MF2202; MF2227; MF2228) ML13193A2912013-07-22022 July 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) TAC MF1031 ML13204A2532013-07-19019 July 2013 Draft RAIs - Decommissioning Funding Status Report for Hope Creek and Peach Bottom ML13190A2212013-07-0202 July 2013 RAIs for Hope Creek Regarding Response to Order EA-12-051 ML13154A4952013-06-0404 June 2013 Rai'S Following Ifib Analysis of Pseg'S 2013 Decommissioning Funding Status Report for Hope Creek Generating Station ML12334A3102012-12-0505 December 2012 Request for Additional Information Request to Correct Technical Specification and Facility Operating License Editorial Items ML12310A1672012-11-0101 November 2012 Draft RAI to License Amendment Request Regarding Average Power Range Monitoring Operability Requirements in Operational Condition 5 ML1227901012012-10-0505 October 2012 Clarifying Information for Question No. 4 (with Attachment) ML12212A1032012-08-0808 August 2012 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information ML12216A1792012-08-0303 August 2012 Draft RAI Related to Request for Exemption from Certain Requirements of the Fitness for Duty Rule ML12213A6162012-07-30030 July 2012 Draft Request for Additional Information Related to Request for Exemption from Certain Requirements of the Fitness for Duty Rule ML1209002372012-03-29029 March 2012 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Draft Request for Additional Information 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 27, 2017 Mr. Peter P. Sena, Ill President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P.O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
HOPE CREEK GENERATING STATION - REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO PERMANENTLY EXTEND TYPE A AND TYPE C LEAK RATE TEST FREQUENCIES (CAC NO. MF8462)
Dear Mr. Sena:
By letter dated October 7, 2016, 1 PSEG Nuclear LLC (PSEG or the licensee) submitted a license amendment request to revise the Hope Creek Generating Station (Hope Creek)
Technical Specifications by incorporating Nuclear Energy Institute (NEI) topical report 94-01, Revision 3-A, and the conditions and limitations specified in NEI topical report 94-01, Revision 2-A, as the implementation document for the Hope Creek performance based containment leakage rate testing program. Based on guidance in NEI 94-01, Revision 3-A, the proposed change would allow the Hope Creek Type A Test (Integrated Leak Rate Test, or ILRT) frequency to be extended from 10 to 15 years, and the Type C Tests (Local Leak Rate Tests, or LLRTs} frequency to be extended from 60 to 75 months. In addition, the amendment would delete a one-time extension of the test frequencies previously granted in License Amendment No. 147 (dated April 16, 2003).
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (1 O CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The U.S. Nuclear Regulatory Commission staff has reviewed the licensee's application and, based upon this review, determined that additional information is needed to complete our review. On January 25, 2017, a draft of these questions were sent to Mr. Paul Duke of your staff to ensure that the questions were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. On February 14, 2017, and Feburary 21, 2017, teleconferences were held to clarify the questions. On Feburary 24, 2017, Mr. Duke indicated that PSEG will submit a response within 30 days of the date of this letter.
1 Agencywide Documents Access and Management System Accession No. ML16281A139.
P. Sena, Ill If you have any questions, please contact me at (301) 415-1603 or by e-mail at Carleen.Parker@nrc.gov.
Sincerely,
{\
I\ \~
C~en . arker, Project Manager Plant Lie sing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-354
Enclosure:
Request for Additional Information cc w/enclosure: Distribution via Listserv
P. Sena, Ill
SUBJECT:
HOPE CREEK GENERATING STATION - REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO PERMANENTLY EXTEND TYPE A AND TYPE C LEAK RA TE TEST FREQUENCIES (CAC NO. MF8462) DATED FEBRUARY 27, 2017 DISTRIBUTION:
PUBLIC LPL 1 R/F RidsNrrDorlLpl1 Resource RidsNrrLALRonewicz Resource RidsNrrPMHopeCreek Resource RidsACRS_MailCTR Resource RidsRgn1 MailCenter Resource RidsNrrDraApla Resource DHoang, NRR RidsNrrDssStsb Resource RidsNrrDssSbpb Resource RidsNrrDeEmcb Resource SVasavada, NRR CTilton, NRR JBettle, NRR RidsNrDorl Resource ADAMS A ccess1on N o.: ML17027A328 *b,Y e-ma1*1 dae t d OFFICE DORL/LPL 1/PM DORL/LPL 1/LA DRA/APLA/BC* DORL/LPL 1/BC(A) DORL/LPL 1/PM NAME CParker LRonewicz SRosenberg SKoenick CParker DATE 02/15/17 01 /31/17 01/09/17 02/15/17 02/27/17 OFFICIAL RECORD COPY
REQUEST FOR ADDITIONAL INFORMATION REGARDING AMENDMENT REQUEST TO PERMANENTLY EXTEND TYPE A AND TYPE C LEAK RATE TEST FREQUENCIES PSEG NUCLEAR LLC HOPE CREEK GENERATING STATION DOCKET NO. 50-354 By letter dated October 7, 2016, 1 PSEG Nuclear LLC (PSEG or the licensee) submitted a license amendment request (LAR) to revise the Hope Creek Generating Station (Hope Creek or HCGS) Technical Specifications by incorporating Nuclear Energy Institute (NEI) topical report 94-01, Revision 3-A, and the conditions and limitations specified in NEI topical report 94-01, Revision 2-A, as the implementation document for the Hope Creek performance based containment leakage rate testing program. Based on guidance in NEI 94-01, Revision 3-A, the proposed change would allow the Hope Creek Type A Test (Integrated Leak Rate Test, or ILRT) frequency to be extended from 10 to 15 years, and the Type C Tests (Local Leak Rate Tests, or LLRTs) frequency to be extended from 60 to 75 months. In addition, the amendment would delete a one-time extension of the test frequencies previously granted in License Amendment No. 147 (dated April 16, 2003). 2 The U.S. Nuclear Regulatory Commission (NRC or the Commission) staff has reviewed the application and, based upon this review, determined that the following additional information is needed to complete our review:
- 1. LAR Attachment 3, Section 5.7.3, "Other External Events Discussion," states that other external hazards, including high winds and tornadoes, external floods, transportation accidents, and nearby facility accidents, were assumed to not impact the results and conclusion of the risk assessment. These hazards were determined to be negligible contributors to overall plant risk based on the individual plant examination for external events (IPEEE) analysis. Since the IPEEE studies are outdated (one-time review completed in 1997), discuss, in the context of the current plant and its environs, the applicability of the IPEEE conclusions for the current LAR. Also, discuss the impact of any updated risk studies, such as the reevaluated external hazards for Hope Creek arising from the Near-Term Task Force (NTTF) 3 recommendation.
- 2. Based on the individual contributors to the total large early release frequency (LEAF) reported in LAR Attachment 3, Table 5.7-7, "Impact of 15-YR ILRT Extension on LERF 1
Agencywide Documents Access and Management System (ADAMS) Accession No. ML16281A139.
2 ADAMS Accession No. ML030660099.
3 The NTTF was established in response to Commission direction to conduct a systematic and methodical review of NRG processes and regulations to determine whether the agency should make additional improvements to its regulatory system and to make recommendations to the Commission for its policy direction, in light of the accident at the Fukushima Dai-ichi Nuclear Power Plant (ADAMS Accession No. ML111861807).
Enclosure
for HCGS," it appears that the total LEAF would be 4.82E-6 per year, instead of the reported value of 8.17E-6 per year. In addition, the values for delta LEAF in LAR Attachment 3, Table 5.6-1, "HCGS ILRT Cases: Base, 3 to 10, and 3 to 15 YR Extensions (Including Age Adjusted Steel Liner Corrosion Likelihood)," and Table 5.6-2, "HCGS ILRT Extension Results Comparison to Acceptance Criteria, are inconsistent.
Address the cited discrepancies in total LEAF and delta LEAF.
- 3. In LAR Attachment 3, Appendix A, Section A.2.4, "Consistency with Applicable PRA Standards, the licensee provided a summary of peer reviews and self-assessments for the internal events probabilistic risk assessment (PRA) model.
- a. Confirm that the 2009 peer review was a full-scope peer review of the internal events and internal flooding PRA model.
- b. Describe all changes, including any new analyses or incorporation of new methodology, performed in the internal events and internal flooding PRA model after the peer review, and justify whether any of the changes fit the definition and criteria of 2009 American Society of Mechanical Engineers (ASME)/American Nuclear Society (ANS) PRA Standard (ASME/ANS RA-Sa-2009) for a PRA upgrade.
- c. If a focused-scope peer review is deemed necessary based on the response to item b above, provide the results of such a review addressing the associated facts and observations (F&Os) and their disposition.
- 4. The following requests for information apply to the internal events F&Os and their corresponding resolutions as reported in Table A-1, "Resolution of Peer Review F&Os,
of Appendix A, Attachment 3, to the LAR:
- a. F&O LE-G1-01, Level 2 Analysis roadmap detail enhancement, states that the Hope Creek Level 2 analysis notebook was not "written in a manner conducive to demonstrating the requirements of the standard were met" and that it "limited the ability of the Peer-Review team to perform an adequate review." The corresponding resolution compares the Hope Creek Level 2 analysis notebook to those used and peer-reviewed elsewhere. However, the F&O statements appear to imply that the peer review team, due to the limitations cited in the F&O, did not review, or only partially reviewed, the Level 2 analysis against the LEAF analysis (LE) supporting requirements of the 2005 ASME PRA standard. Since LEAF is a key metric in the risk assessment supporting the LAR, justify, in the context of the cited F&O and the foregoing discussion, why a focused-scope peer review of the Level 2 PRA model is not required.
- b. F&O QU-E4-01, Uncertainty analysis structured sensitivity evaluations, identified that the evaluation of uncertainties did not identify or address any plant specific sources of uncertainty. In the F&O resolution the licensee stated that this issue has not yet been resolved, because there was no published guidance on the treatment of uncertainties at the time the resolution was documented. This
resolution appears to no longer be valid since NUREG-1855, Volume 1, "Guidance on the Treatment of Uncertainties Associated with PRAs in Risk-Informed Decision Making,4 and supplemental Electric Power Research Institute (EPRI) guidance, such as EPRI Technical Report (TR)-1016737 and EPRI TR-1026511, on the treatment of uncertainties in PRA have been issued.
Further, contrary to the F&O resolution stating that the PRA standard does not require evaluation of sources of model uncertainty, such an evaluation is required per the 2009 ASME/ANS PRA Standard (ASME/ANS RA-Sa-2009) endorsed by Regulatory Guide (RG) 1.200, Revision 2, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities." 5 The F&O resolution contradicts the results of the self-assessment, which concluded that supporting requirement QU-E4 of ASME/ANS RA-Sa-2009 is met.
- i. Describe how the uncertainty evaluation mentioned in F&O QU-E4-01 was performed, given that relevant guidance on the treatment of uncertainties is available. Discuss the impact of the results of the uncertainty evaluation on the LAR.
ii. If the uncertainty evaluation mentioned in the F&O has not been performed, justify the conclusion that the lack of the uncertainty analysis would have no impact on the current application.
- c. F&O SY-814-01, Missing Common Piping Failure Modeling, found that, "it cannot be demonstrated that components/failure modes which fail multiple systems have been included," as required, and provided an example that failure of common piping between the high pressure core injection(HPCl)/feedwater (FW)/core spray (CS) and reactor core isolation cooling (RCIC)/FW systems was not modeled. The resolution provides an explanation of how the example cited in the F&O was addressed. The resolution states that the model modification resulting from the F&O's concerns "has been evaluated and assessed as a negligible impact on PRA risk metrics." However, the resolution also states that, "it has been included as the highest priority model change in 2009."
- i. Confirm that the failure of common piping between HPCl/FW/CS and RCIC/FW systems has been included in the internal events PRA model used for the LAR or, alternatively, if not included in the model, provide the basis for concluding that there is "negligible impact."
ii. Discuss how it was ensured that other than the example identified by the peer review team, no other possible instances of common piping that could fail multiple systems are left unaddressed in the internal events PRA model.
4 ADAMS Accession No. ML090970525.
5 ADAMS Accession No. ML090410014.
- d. F&O AS-82-01 identified that the operation of the automatic depressurization system (ADS), under conditions of a stuck open relief valve (SORV) with failure of the high pressure makeup, appears to be modeled as always successful. The resolution of this F&O states that this is a documentation issue only. However, it appears that the issue may point to a flaw in the PRA model that precludes a dependent failure that is logically possible. Explain whether or not the F&O identified a flaw in the PRA model logic. Further, if a flaw exists, either correct it and reevaluate the model to determine the effect on the current submittal, or justify why it does not adversely impact the current submittal.
- e. F&O SC-A6-01, Basis for the fire pump flow rate, questioned the basis for crediting the diesel-driven firewater pump as a low pressure source of makeup to the reactor vessel after depressurization, stating that the pump flow curve has not been rigorously analyzed. In the resolution to this F&O, the licensee performed a detailed deterministic calculation of the fire pump flow curve and identified that additional equipment, such as a fire pumper truck" to boost pressure, is required for the success of the diesel-driven firewater pump.
Confirm that given the changes to the PRA model described in the F&O resolution, human failure events associated with the changes, such as the need to stage and operate the fire pumper truck, have been considered and incorporated into the PRA model.
- 5. The resolutions of the Hope Creek fire PRA (FPRA) peer review F&Os are presented in LAR Attachment 3, Appendix A, Table A-4, "Resolution of FPRA Peer Review F&Os."
Some of the modeling choices made during the resulting FPRA model modifications appear to be non-conservative. Examples of such choices include, but are not limited to, the use of point estimates due to unquantified uncertainties (F&Os 1-11, 5-27, 5-40, 5-52, and 6-4), possible use of a probability of failure of alternate shutdown capability deemed to be non-conservative by the peer reviewers (F&Os 4-9 and 5-32), and the use of a potentially non-conservative value for the fraction of cable length participating in cable tray fires (F&Os 5-33 and 5-35). In addition, the resolution of F&O 4-14 appears to indicate the non-suppression probability in the Hope Creek FPRA are based on NUREG/CR-6850, "EPRl/NRC-RES Fire PRA Methodology for Nuclear Power Facilities, instead of the updated values in NUREG-2169, "Nuclear Power Plant Fire Ignition Frequency and Non-Suppression Probability Estimation Using the Updated Fire Events Database."6 Identify all potential non-conservatisms in the Hope Creek FPRA and justify, preferably quantitatively, why the FPRA does not result in an under-prediction of the fire risk for the current LAR.
6 ADAMS Accession No. ML15016A069.