ML13141A748: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 14: Line 14:
| page count = 5
| page count = 5
| project = TAC:ME7708
| project = TAC:ME7708
| stage =
}}
}}



Revision as of 11:44, 30 March 2018

Schedule Revision for the Safety Review of the Callaway Plant, Unit 1, LRA (TAC No. ME7708)
ML13141A748
Person / Time
Site: Callaway Ameren icon.png
Issue date: 05/30/2013
From: Lubinski J W
Division of License Renewal
To: Heflin A C
Union Electric Co
CuadradoDeJesus S, 415-2946
References
TAC ME7708
Download: ML13141A748 (5)


Text

UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555"()001 May 30,2013 Mr. Adam C. Heflin, Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251 SCHEDULE REVISION FOR THE SAFETY REVIEW OF THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NO. ME7708) Dear Mr. Heflin: By letter dated December 15, 2011, Union Electric Company (Ameren Missouri) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-30 for the Callaway Plant, Unit 1 (Callaway), for review by the U.S. Nuclear Regulatory Commission (NRC). By letter dated April 23, 2013, the NRC issued its "Safety Evaluation Report (SER) with Open Items related to the License Renewal of Callaway Plant Unit 1," in support of an Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting scheduled for May 22,2013. By letter dated May 10, 2013, Ameren Missouri requested to postpone the ACRS subcommittee meeting to a later date due to delays in Callaway'S current refueling outage (RFO) No. 19 and its needs to focus on its completion. The NRC is aware of Ameren Missouri's activities to support the completion of Callaway's RFO No. 19. The NRC has monitored Ameren Missouri's activities in support of completing Callaway's RFO No. 19 to determine the necessary effort to support the review of additional information as a result of RFO No. 19 completion and will subsequently revise the current schedule to indicate the future milestone dates for the safety review. Enclosed is the staffs revised safety review schedule, with to be determined milestones, for the Callaway license renewal application (LRA). The NRC will continue to follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Parts 54 and 51.

A. Heflin -2 If you have any questions on the revised schedule, please contact Mr. Samuel Cuadrado de Jesus, project manager for the Callaway LRA safety review, by telephone at 301-415-2946 or bye-mail at Samuel.Cuadradode*esus Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-483 Enclosure: Revised safety review schedule cc w/encl: Listserv CALLAWAY PLANT, UNIT LICENSE RENEWAL UPDATED SAFETY REVIEW Milestone Scheduled Actual Receive license renewal application (LRA) 12/19/11 12/19/11 IPublish Federal Register Notice (FRN) -LRA availability 01/2012 01/03/12 Publish FRN -acceptance/rejection and opportunity for hearing 02/2012 02/14/12 Publish FRN -environmental scoping meeting 02/2012 02/24/12 Public Meeting -License Renewal Overview and Environmental Scoping meeting 03/14/12 03/14/12 Audit -Scoping & Screening Methodology 04/16/12 04/16/12 iAudit -Aging Management Programs 04/30/12 04/30/12 Deadline for filing hearing requests and petitions for intervention 2012 04/24/12 Environmental scoping period ends 04/2012 04/24/12 Audit -Environmental OS/22/12 05/22/12 Inspection -Regional 09/2012 09/2012 Issue safety evaluation report (SER) with open items 04/2013 04/23/2013 Issue draft supplemental environmental impact statement (SEIS) 08/2013 Publish FRN -draft SEIS available for comments 08/2013 Public Meeting -draft SEIS meeting 09/2013 End of draft SEIS comment period 09/2013 0*Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting Issue final SER TBD Issue final SEIS 04/2014 U.S. Environmental Protection Agency FRN Published -availability of final SEIS 04/2014 ACRS full committee meeting TBD Decision -Director, NRR TBD *To be determined (TBD)

A. Heflin -2 If you have any questions on the revised schedule, please contact Mr. Samuel Cuadrado de Jesus, project manager for the Callaway LRA safety review, by teleph()ne at 301-415-2946 or bye-mail at SamueI,Cuadradodejesus@nrc.gov. Sincerely, IRA! John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. Revised safety review cc w/encl: ADAMS Accession No'.. ML13141A748 *concurred via email OFFICE PM:DLR/RPB1 LA:DLR/RPB1* BC:DLR/RPB1 D:DLR NAME SCuadrado IKing YDiaz JLubinski DATE 5/29/13 5/22/13 5/30/13 5/30/13 OFFICIAL RECORD Letter to A. Heflin from J. Lubinski dated May 30, 2013 SCHEDULE REVISION FOR THE SAFETY REVIEW OF THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NO. IVIE7708) DISTRIBUTION: E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource SCuadrado FLyon THartman CFelis DMorey BMizuno (OGC) LSubin (OGC) DCylkowski (OGC) GPick