|
|
Line 28: |
Line 28: |
| ^ | | ^ |
| * LOCAL LEAK RATE TESTIUG OF CONTAINMENT 9 8 ISOLATICN VALVES l | | * LOCAL LEAK RATE TESTIUG OF CONTAINMENT 9 8 ISOLATICN VALVES l |
| b Appendix J of 10CFR50, which specifies the integrated and local leakage rate testing requirements for containments, was published long af ter the construction of Sequoyah began and Sequoyah has not been required to conform to those requirements. The Seguoyah FSAR outlines TVA's present leak rate testing program for containment isolation valves. The test program permits the use of air er water as the test medium for local leak rate testing of isciation valves. Late this summer there were indications that the NRC may no longer accept water as a test medium for plants the vintage of Sequoyah. In october of this year TVA contacted the Eegulatory Staff and requested clarification on this issue | | b Appendix J of 10CFR50, which specifies the integrated and local leakage rate testing requirements for containments, was published long af ter the construction of Sequoyah began and Sequoyah has not been required to conform to those requirements. The Seguoyah FSAR outlines TVA's present leak rate testing program for containment isolation valves. The test program permits the use of air er water as the test medium for local leak rate testing of isciation valves. Late this summer there were indications that the NRC may no longer accept water as a test medium for plants the vintage of Sequoyah. In october of this year TVA contacted the Eegulatory Staff and requested clarification on this issue due to the potential impact on the Sequoyah startup date. The Staff verbally responded in telephone discussions that the use of air is required on all valves as specified in 10CFR50, Appendix J, except for cases of obvious hardship or justification i |
| ;
| |
| due to the potential impact on the Sequoyah startup date. The Staff verbally responded in telephone discussions that the use of air is required on all valves as specified in 10CFR50, Appendix J, except for cases of obvious hardship or justification i | |
| which would show that the potential for release of containment atmosphere is small. | | which would show that the potential for release of containment atmosphere is small. |
| TVA has reviewed the piping layouts at Sequoyah to determine the | | TVA has reviewed the piping layouts at Sequoyah to determine the |
Line 71: |
Line 69: |
|
| |
|
| D D 3: ' | | D D 3: ' |
| ;
| |
| penetration Svstem Eumber Rodifications Recuired Easis for a Natur Tent for First Fuel Cycle the primary containment. Any leakage across the isolation valves would he trapped in the system piping and not released to the atmosphere. The closed portions of this system are located in areas of the auxiliary building which are served by the ABGTS. The in-line block valve cannot he procured prior to fuel loading. The principal tests that could he delayed by requiring modification to this system are: | | penetration Svstem Eumber Rodifications Recuired Easis for a Natur Tent for First Fuel Cycle the primary containment. Any leakage across the isolation valves would he trapped in the system piping and not released to the atmosphere. The closed portions of this system are located in areas of the auxiliary building which are served by the ABGTS. The in-line block valve cannot he procured prior to fuel loading. The principal tests that could he delayed by requiring modification to this system are: |
| : 1) Containment Integrated Leak Bate Test | | : 1) Containment Integrated Leak Bate Test |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217M4461999-10-20020 October 1999 Forwards Rev 8 to Sequoyah Nuclear Plant Physical Security/ Contingency Plan, IAW 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 ML20217J4151999-10-15015 October 1999 Forwards Request for Addl Info Re Util 990624 Application for Amend of TSs That Would Revise TS for Weighing of Ice Condenser Ice Baskets 05000327/LER-1999-002, Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project1999-10-15015 October 1999 Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project ML20217G1141999-10-0707 October 1999 Responds to from P Salas,Providing Response to NRC Risk Determination Associated with 990630 Flooding Event at Sequoyah Facility.Meeting to Discuss Risk Determination Issues Scheduled for 991021 in Atlanta,Ga ML20217B2981999-10-0606 October 1999 Discusses Closeout of GL 92-01,rev 1,suppl 1, Reactor Vessel Integrity, for Sequoyah Nuclear Plant,Units 1 & 2. NRC Also Hereby Solicits Any Written Comments That TVA May Have on Current Rvid Data by 991101 ML20217B8431999-10-0505 October 1999 Requests NRC Review & Approval of ASME Code Relief Requests That Were Identified in Plant Second 10-yr ISI Interval for Both Units.Encl 3 Provides Util Procedure for Calculation of ASME Code Coverage for Section XI Nondestructive Exams IR 05000327/19990041999-10-0101 October 1999 Ack Receipt of Providing Comments on Insp Repts 50-327/99-04 & 50-328/99-04.NRC Considered Comments for Apparent Violation Involving 10CFR50.59 Issue ML20217C7101999-10-0101 October 1999 Forwards Response to NRC 990910 RAI Re Sequoyah Nuclear Plant,Units 1 & 2 URI 50-327/98-04-02 & 50-328/98-04-02 Re Ice Weight Representative Sample ML20212J5981999-10-0101 October 1999 Forwards SE Accepting Request for Relief from ASME Boiler & Pressure Vessel Code,Section Xi,Requirements for Certain Inservice Insp at Plnat,Unit 1 ML20212M1081999-09-29029 September 1999 Confirms Intent to Meet with Utils on 991025 in Atlanta,Ga to Discuss Pilot Plants,Shearon Harris & Sequoyah Any Observations & Lessons Learned & Recommendations Re Implementation of Pilot Program ML20217A9451999-09-27027 September 1999 Forwards Insp Repts 50-327/99-05 & 50-328/99-05 on 990718- 0828.One Violation Identified & Being Treated as Non-Cited Violation ML20216J9351999-09-27027 September 1999 Responds to NRC Re Violations Noted in Insp Repts 50-327/99-04 & 50-328/99-04.Corrective Actions:Risk Determination Evaluation Was Performed & Licensee Concluded That Event Is in Green Regulatory Response Band ML20212F0751999-09-23023 September 1999 Forwards SER Granting Util 981021 Request for Relief from ASME Code,Section XI Requirements from Certain Inservice Insp at Sequoyah Nuclear Power Plant,Units 1 & 2 Pursuant to 10CFR50.55a(a)(3)(ii) ML20212F4501999-09-23023 September 1999 Forwards Amends 246 & 237 to Licenses DPR-77 & DPR-79, Respectively & Ser.Amends Approve Request to Revise TSs to Allow Use of Fully Qualified & Tested Spare Inverter in Place of Any of Eight Required Inverters ML20212M1911999-09-21021 September 1999 Discusses Exercise of Enforcement Discretion Re Apparent Violation Noted in Insp Repts 50-327/99-04 & 50-328/99-04 Associated with Implementation of Procedural Changes Which Resulted in Three Containment Penetrations Being Left Open ML20211Q0311999-09-10010 September 1999 Requests Written Documentation from TVA to Provide Technical Assistance to Region II Re TS Compliance & Ice Condenser Maint Practices at Plant ML20216F5441999-09-0707 September 1999 Provides Results of Risk Evaluation of 990630,flooding Event at Sequoyah 1 & 2 Reactor Facilities.Event Was Documented in Insp Rept 50-327/99-04 & 50-328/99-04 & Transmitted in Ltr, ML20211N5681999-09-0101 September 1999 Submits Clarification of Two Issues Raised in Insp Repts 50-327/99-04 & 50-328/99-04,dtd 990813,which Was First Insp Rept Issued for Plant Under NRC Power Reactor Oversight Process Pilot Plant Study ML20211G5881999-08-27027 August 1999 Submits Summary of 990820 Management Meeting Re Plant Performance.List of Attendees & Matl Used in Presentation Enclosed ML20211F8891999-08-25025 August 1999 Forwards Sequoyah Nuclear Plant Unit 1 Cycle 9 Refueling Outage, Re Completed SG Activities,Per TSs 4.4.5.5.b & 4.4.5.5.c ML20211A1851999-08-16016 August 1999 Forwards Proprietary TR WCAP-15128 & non-proprietary Rept WCAP-15129 for NRC Review.Repts Are Provided in Advance of TS Change That Is Being Prepared to Support Cycle 10 Rfo. Proprietary TR Withheld,Per 10CFR2.790 ML20210V1471999-08-13013 August 1999 Forwards Insp Repts 50-327/99-04 & 50-328/99-04 on 990601- 0717.One Potentially Safety Significant Issue Identified.On 990630,inadequate Performance of Storm Drain Sys Caused Water from Heavy Rainfall to Backup & Flood Turbine Bldg ML20211A1921999-08-12012 August 1999 Requests Proprietary TR WCAP-15128, Depth-Based SG Tube Repair Criteria for Axial PWSCC at Dented TSP Intersections, Be Withheld from Public Disclosure Per 10CFR2.790 ML20210Q5011999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006 at Sequoyah Nuclear Plant. Sample Registration Ltr Encl ML20210L4291999-08-0202 August 1999 Forwards Sequoyah Nuclear Plant Unit 2 Cycle 9 12-Month SG Insp Rept & SG-99-07-009, Sequoyah Unit-2 Cycle 10 Voltage-Based Repair Criteria 90-Day Rept. Repts Submitted IAW TS 4.4.5.5.b & TS 4.4.5.5.c ML20210L1611999-07-30030 July 1999 Forwards Request for Relief RV-4 Re ASME Class 1,2 & 3 Prvs, Per First ten-year Inservice Test Time Interval.Review & Approval of RV-4 Is Requested to Support Unit 1 Cycle 10 Refueling Outage,Scheduled to Start 000213 ML20210G5301999-07-28028 July 1999 Forwards Sequoyah Nuclear Plant Unit 2 ISI Summary Rept That Contains Historical Record of Repairs,Replacement & ISI & Augmented Examinations That Were Performed on ASME Code Class 1 & 2 Components from 971104-990511 ML20211B9661999-07-26026 July 1999 Informs That Sequoyah Nuclear Plant Sewage Treatment Plant, NPDES 0026450 Outfall 112,is in Standby Status.Flow Has Been Diverted from Sys Since Jan 1998 ML20210B2521999-07-14014 July 1999 Confirms 990712 Telcon Between J Smith of Licensee Staff & M Shannon of NRC Re semi-annual Mgt Meeting Schedule for 990820 in Atlanta,Ga to Discuss Recent Sequoyah Nuclear Plant Performance ML20210J1091999-07-10010 July 1999 Submits Suggestions & Concerns Re Y2K & Nuclear Power Plants ML20196K0381999-06-30030 June 1999 Provides Written Confirmation of Completed Commitment for Final Implementation of Thermo-Lag 330-1 Fire Barrier Corrective Actions at Snp,Per GL 92-08 ML20209E4071999-06-30030 June 1999 Forwards Insp Repts 50-327/99-03 & 50-328/99-03 on 990328- 0531.Violations Being Treated as Noncited Violations ML20196J8261999-06-28028 June 1999 Forwards Safety Evaluation Authorizing Request for Relief from ASME Boiler & Pressure Vessel Code,Section XI Requirements for Certain Inservice Inspections at Sequoyah Nuclear Plant,Units 1 & 2 ML20196G7881999-06-22022 June 1999 Informs NRC of Changes That Util Incorporated Into TS Bases Sections & Trm.Encl Provides Revised TS Bases Pages & TRM Affected by Listed Revs ML20196G1801999-06-21021 June 1999 Requests Termination of SRO License SOP-20751-1,for Lf Hardin,Effective 990611.Subject Individual Resigned from Position at TVA ML20195G1821999-06-0808 June 1999 Requests NRC Review & Approval of ASME Code Relief for ISI Program.Encl 1 Provides Relief Request 1-ISI-14 That Includes Two Attachments.Encl 2 Provides Copy of Related ASME Code Page ML20195E9521999-06-0707 June 1999 Requests Relief from Specific Requirements of ASME Section Xi,Subsection IWE of 1992 Edition,1992 Addenda.Util Has Determined That Proposed Alternatives Would Provide Acceptable Level of Quality & Safety ML20195E9311999-05-28028 May 1999 Informs of Planned Insp Activities for Licensee to Have Opportunity to Prepare for Insps & Provide NRC with Feedback on Any Planned Insps Which May Conflict with Plant Activities ML20195B3631999-05-21021 May 1999 Requests Termination of SRO License for Tj Van Huis,Per 10CFR50.74(a).TJ Van Huis Retired from Util,Effective 990514 ML20207A5721999-05-20020 May 1999 Forwards Correction to Previously Issued Amend 163 to License DPR-79 Re SR 4.1.1.1.1.d Inadvertently Omitted from Pp 3/4 1-1 of Unit 2 TS ML20206Q8791999-05-13013 May 1999 Forwards L36 9990415 802, COLR for Sequoyah Nuclear Plant Unit 2,Cycle 10, IAW Plant TS 6.9.1.14.c 05000327/LER-1999-001, Forwards LER 99-001-00 Re Condition That Resulted in Granting of Enforcement Discretion,Per Failure of Centrifugal Charging Pump.Condition Being Reported IAW 10CFR50.73(a)(2)(i)(B) & (a)(2)(iv)1999-05-11011 May 1999 Forwards LER 99-001-00 Re Condition That Resulted in Granting of Enforcement Discretion,Per Failure of Centrifugal Charging Pump.Condition Being Reported IAW 10CFR50.73(a)(2)(i)(B) & (a)(2)(iv) ML20206M9341999-05-10010 May 1999 Forwards Rept of SG Tube Plugging During Unit 2 Cycle 9 Refueling Outage,As Required by TS 4.4.5.5.a.ISI of Unit 2 SG Tubes Was Completed on 990503 ML20206K6271999-05-0606 May 1999 Requests Termination of SRO License for MR Taggart,License SOP-21336 Due to Resignation on 990430 ML20206J2061999-05-0404 May 1999 Requests Relief from Specified ISI Requirements in Section XI of ASME B&PV Code.Tva Requests Approval to Use Wire Type Penetrameters in Lieu of Plaque Type Penetrameters for Performing Radiographic Insps.Specific Relief Request,Encl ML20209J0391999-04-27027 April 1999 Forwards Annual Radioactive Effluent Release Rept, Radiological Impact Assessment Rept & Rev 41 to ODCM, for Period of Jan-Dec 1998 ML20206C6541999-04-23023 April 1999 Forwards Response to NRC 990127 RAI Re GL 96-05 for Sequoyah Nuclear Plant,Units 1 & 2 ML20206C0841999-04-23023 April 1999 Forwards Insp Repts 50-327/99-02 & 50-328/99-02 on 990214-0327.No Violations Noted ML20206B9591999-04-20020 April 1999 Responds to 990417 Request That NRC Exercise Discretion Not to Enforce Compliance with Actions Required in Unit 1 TS 3.1.2.2,3.1.2.4 & 3.5.2 & Documents 990417 Telephone Conversation When NRC Orally Issued NOED ML20205S5891999-04-17017 April 1999 Documents Request for Discretionary Enforcement for Unit 1 TS LCOs 3.1.2.2,3.1.2.4 & 3.5.2 to Support Completion of Repairs & Testing for 1B-B Centrifugal Charging Pump (CCP) 1999-09-07
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217M4461999-10-20020 October 1999 Forwards Rev 8 to Sequoyah Nuclear Plant Physical Security/ Contingency Plan, IAW 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 05000327/LER-1999-002, Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project1999-10-15015 October 1999 Forwards LER 99-002-00 Re Start of Units 1 & 2 EDGs as Result of Cable Being Damaged During Installation of Thermo- Lag for Kaowool Upgrade Project ML20217B8431999-10-0505 October 1999 Requests NRC Review & Approval of ASME Code Relief Requests That Were Identified in Plant Second 10-yr ISI Interval for Both Units.Encl 3 Provides Util Procedure for Calculation of ASME Code Coverage for Section XI Nondestructive Exams ML20217C7101999-10-0101 October 1999 Forwards Response to NRC 990910 RAI Re Sequoyah Nuclear Plant,Units 1 & 2 URI 50-327/98-04-02 & 50-328/98-04-02 Re Ice Weight Representative Sample ML20216J9351999-09-27027 September 1999 Responds to NRC Re Violations Noted in Insp Repts 50-327/99-04 & 50-328/99-04.Corrective Actions:Risk Determination Evaluation Was Performed & Licensee Concluded That Event Is in Green Regulatory Response Band ML20211N5681999-09-0101 September 1999 Submits Clarification of Two Issues Raised in Insp Repts 50-327/99-04 & 50-328/99-04,dtd 990813,which Was First Insp Rept Issued for Plant Under NRC Power Reactor Oversight Process Pilot Plant Study ML20211F8891999-08-25025 August 1999 Forwards Sequoyah Nuclear Plant Unit 1 Cycle 9 Refueling Outage, Re Completed SG Activities,Per TSs 4.4.5.5.b & 4.4.5.5.c ML20211A1851999-08-16016 August 1999 Forwards Proprietary TR WCAP-15128 & non-proprietary Rept WCAP-15129 for NRC Review.Repts Are Provided in Advance of TS Change That Is Being Prepared to Support Cycle 10 Rfo. Proprietary TR Withheld,Per 10CFR2.790 ML20211A1921999-08-12012 August 1999 Requests Proprietary TR WCAP-15128, Depth-Based SG Tube Repair Criteria for Axial PWSCC at Dented TSP Intersections, Be Withheld from Public Disclosure Per 10CFR2.790 ML20210L4291999-08-0202 August 1999 Forwards Sequoyah Nuclear Plant Unit 2 Cycle 9 12-Month SG Insp Rept & SG-99-07-009, Sequoyah Unit-2 Cycle 10 Voltage-Based Repair Criteria 90-Day Rept. Repts Submitted IAW TS 4.4.5.5.b & TS 4.4.5.5.c ML20210L1611999-07-30030 July 1999 Forwards Request for Relief RV-4 Re ASME Class 1,2 & 3 Prvs, Per First ten-year Inservice Test Time Interval.Review & Approval of RV-4 Is Requested to Support Unit 1 Cycle 10 Refueling Outage,Scheduled to Start 000213 ML20210G5301999-07-28028 July 1999 Forwards Sequoyah Nuclear Plant Unit 2 ISI Summary Rept That Contains Historical Record of Repairs,Replacement & ISI & Augmented Examinations That Were Performed on ASME Code Class 1 & 2 Components from 971104-990511 ML20210J1091999-07-10010 July 1999 Submits Suggestions & Concerns Re Y2K & Nuclear Power Plants ML20196K0381999-06-30030 June 1999 Provides Written Confirmation of Completed Commitment for Final Implementation of Thermo-Lag 330-1 Fire Barrier Corrective Actions at Snp,Per GL 92-08 ML20196G7881999-06-22022 June 1999 Informs NRC of Changes That Util Incorporated Into TS Bases Sections & Trm.Encl Provides Revised TS Bases Pages & TRM Affected by Listed Revs ML20196G1801999-06-21021 June 1999 Requests Termination of SRO License SOP-20751-1,for Lf Hardin,Effective 990611.Subject Individual Resigned from Position at TVA ML20195G1821999-06-0808 June 1999 Requests NRC Review & Approval of ASME Code Relief for ISI Program.Encl 1 Provides Relief Request 1-ISI-14 That Includes Two Attachments.Encl 2 Provides Copy of Related ASME Code Page ML20195E9521999-06-0707 June 1999 Requests Relief from Specific Requirements of ASME Section Xi,Subsection IWE of 1992 Edition,1992 Addenda.Util Has Determined That Proposed Alternatives Would Provide Acceptable Level of Quality & Safety ML20195B3631999-05-21021 May 1999 Requests Termination of SRO License for Tj Van Huis,Per 10CFR50.74(a).TJ Van Huis Retired from Util,Effective 990514 ML20206Q8791999-05-13013 May 1999 Forwards L36 9990415 802, COLR for Sequoyah Nuclear Plant Unit 2,Cycle 10, IAW Plant TS 6.9.1.14.c 05000327/LER-1999-001, Forwards LER 99-001-00 Re Condition That Resulted in Granting of Enforcement Discretion,Per Failure of Centrifugal Charging Pump.Condition Being Reported IAW 10CFR50.73(a)(2)(i)(B) & (a)(2)(iv)1999-05-11011 May 1999 Forwards LER 99-001-00 Re Condition That Resulted in Granting of Enforcement Discretion,Per Failure of Centrifugal Charging Pump.Condition Being Reported IAW 10CFR50.73(a)(2)(i)(B) & (a)(2)(iv) ML20206M9341999-05-10010 May 1999 Forwards Rept of SG Tube Plugging During Unit 2 Cycle 9 Refueling Outage,As Required by TS 4.4.5.5.a.ISI of Unit 2 SG Tubes Was Completed on 990503 ML20206K6271999-05-0606 May 1999 Requests Termination of SRO License for MR Taggart,License SOP-21336 Due to Resignation on 990430 ML20206J2061999-05-0404 May 1999 Requests Relief from Specified ISI Requirements in Section XI of ASME B&PV Code.Tva Requests Approval to Use Wire Type Penetrameters in Lieu of Plaque Type Penetrameters for Performing Radiographic Insps.Specific Relief Request,Encl ML20209J0391999-04-27027 April 1999 Forwards Annual Radioactive Effluent Release Rept, Radiological Impact Assessment Rept & Rev 41 to ODCM, for Period of Jan-Dec 1998 ML20206C6541999-04-23023 April 1999 Forwards Response to NRC 990127 RAI Re GL 96-05 for Sequoyah Nuclear Plant,Units 1 & 2 ML20205S5891999-04-17017 April 1999 Documents Request for Discretionary Enforcement for Unit 1 TS LCOs 3.1.2.2,3.1.2.4 & 3.5.2 to Support Completion of Repairs & Testing for 1B-B Centrifugal Charging Pump (CCP) ML20205B1091999-03-19019 March 1999 Submits Response to NRC Questions Concerning Lead Test Assembly Matl History,Per Request ML20204H0161999-03-19019 March 1999 Resubmits Util 990302 Response to Violations Noted in Insp Repts 50-327/98-11 & 50-328/98-11.Corrective Actions:Lessons Learned from Event Have Been Provided to Operating Crews ML20204E8251999-03-0505 March 1999 Forwards Sequoyah Nuclear Plant,Four Yr Simulator Test Rept for Period Ending 990321, in Accordance with Requirements of 10CFR55.45 ML20207E6851999-03-0202 March 1999 Responds to NRC Re Violations Noted in Insp Repts 50-327/98-11 & 50-328/98-11.Corrective Actions:Lessons Learned from Event Have Been Provided to Operating Crews ML20207J1171999-01-29029 January 1999 Forwards Copy of Final Exercise Rept for Full Participation Ingestion Pathway Exercise of Offsite Radiological Emergency Response Plans site-specific to Sequoyah NPP ML20202A7141999-01-20020 January 1999 Provides Request for Relief for Delaying Repair on Section of ASME Code Class 3 Piping within Essential Raw Cooling Water Sys ML20198S7141998-12-29029 December 1998 Forwards Cycle 10 Voltage-Based Repair Criteria 90-Day Rept, Per GL 95-05.Rept Is Submitted IAW License Condition 2.C.(9)(d) 05000327/LER-1998-004, Forwards LER 98-004-00,providing Details Concerning Inability to Complete Surveillance within Required Time Interval1998-12-21021 December 1998 Forwards LER 98-004-00,providing Details Concerning Inability to Complete Surveillance within Required Time Interval ML20198D5471998-12-14014 December 1998 Requests That License OP-20313-2 for Je Wright,Be Terminated IAW 10CFR50.74(a).Individual Retiring ML20197J5541998-12-10010 December 1998 Forwards Unit 1 Cycle 9 90-Day ISI Summary Rept IAW IWA-6220 & IWA-6230 of ASME Code,Section Xi.Request for Relief Will Be Submitted to NRC Timeframe to Support Second 10-year Insp Interval,Per 10CFR50.55a 05000327/LER-1998-003, Forwards LER 98-003-00 Re Automatic Reactor Trip with FW Isolation & Auxiliary FW Start as Result of Failure of Vital Inverter & Second Inverter Failure.Event Is Being Reported IAW 10CFR50.73(a)(2)(iv)1998-12-0909 December 1998 Forwards LER 98-003-00 Re Automatic Reactor Trip with FW Isolation & Auxiliary FW Start as Result of Failure of Vital Inverter & Second Inverter Failure.Event Is Being Reported IAW 10CFR50.73(a)(2)(iv) ML20196F9841998-11-25025 November 1998 Provides Changes to Calculated Peak Fuel Cladding Temp, Resulting from Recent Changes to Plant ECCS Evaluation Model ML20195H7891998-11-17017 November 1998 Requests NRC Review & Approval of Five ASME Code Relief Requests Identified in Snp Second ten-year ISI Interval for Units 1 & 2 ML20195E4991998-11-12012 November 1998 Forwards Rev 7 to Physical Security/Contingency Plan.Rev Adds Requirement That Security Personnel Will Assess Search Equipment Alarms & Add Definition of Major Maint.Rev Withheld (Ref 10CFR2.790(d)(1)) 05000328/LER-1998-002, Forwards LER 98-002-00 Re Automatic Turbine & Reactor Trip, Resulting from Failure of Sudden Pressure Relay on 'B' Phase Main Transformer1998-11-10010 November 1998 Forwards LER 98-002-00 Re Automatic Turbine & Reactor Trip, Resulting from Failure of Sudden Pressure Relay on 'B' Phase Main Transformer ML20195G5701998-11-10010 November 1998 Documents Util Basis for 981110 Telcon Request for Discretionary Enforcement for Plant TS 3.8.2.1,Action B,For 120-VAC Vital Instrument Power Board 1-IV.Licensee Determined That Inverter Failed Due to Component Failure ML20155J4031998-11-0505 November 1998 Provides Clarification of Topical Rept Associated with Insertion of Limited Number of Lead Test Assemblies Beginning with Unit 2 Operating Cycle 10 Core ML20154R9581998-10-21021 October 1998 Requests Approval of Encl Request for Relief ISI-3 from ASME Code Requirements Re Integrally Welded Attachments of Supports & Restraints for AFW Piping ML20155B1481998-10-21021 October 1998 Informs That as Result of Discussion of Issues Re Recent Events in Ice Condenser Industry,Ice Condenser Mini-Group (Icmg),Decided to Focus Efforts on Review & Potential Rev of Ice condenser-related TS in Order to Clarify Issues ML20154K1581998-10-13013 October 1998 Forwards Rept Re SG Tube Plugging Which Occurred During Unit 1 Cycle 9 Refueling Outage,Per TS 4.4.5.5.a.ISI of Unit 1 SG Was Completed on 980930 ML20154H6191998-10-0808 October 1998 Forwards Rev 0 to Sequoyah Nuclear Plant Unit 1 Cycle 10 COLR, IAW TS 6.9.1.14.c 05000328/LER-1998-001, Forwards LER 98-001-00 Providing Details Re Automatic Turbine & Reactor Trip Due to Failure of Sudden Pressure Relay on 'B' Phase Main Transformer1998-09-28028 September 1998 Forwards LER 98-001-00 Providing Details Re Automatic Turbine & Reactor Trip Due to Failure of Sudden Pressure Relay on 'B' Phase Main Transformer ML20151W4901998-09-0303 September 1998 Responds to NRC Re Violations Noted in Insp Repts 50-327/98-07 & 50-328/98-07.Corrective Actions:Revised Per SQ971279PER to Address Hardware Issues of Hysteresis, Pressure Shift & Abnormal Popping Noise 1999-09-27
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059K6661990-09-17017 September 1990 Forwards Evaluation That Provides Details of Plug Cracks & Justification for Continued Operation Until 1993 ML20059H4031990-09-10010 September 1990 Discusses Plant Design Baseline & Verification Program Deficiency D.4.3-3 Noted in Insp Repts 50-327/86-27 & 50-328/86-27.Evaluation Concluded That pre-restart Walkdown Data,Loops 1 & 2 Yielded Adequate Design Input ML20059E1851990-08-31031 August 1990 Responds to NRC Re Violations Noted in Insp Repts 50-327/90-22 & 50-328/90-22.Corrective Actions:Extensive Mgt Focus Being Applied to Improve Overtime Use Controls ML20059E2881990-08-31031 August 1990 Forwards Addl Info Re Alternate Testing of Reactor Vessel Head & Internals Lifting Rigs,Per NUREG-0612.Based on Listed Hardships,Util Did Not Choose 150% Load Test Option ML20059H1831990-08-31031 August 1990 Forwards Nonproprietary PFE-F26NP & Proprietary PFE-F26, Sequoyah Nuclear Plan Unit 1,Cycle 5 Restart Physics Test Summary, Re Testing Following Vantage 5H Fuel Assembly installation.PFE-F26 Withheld (Ref 10CFR2.790(b)(4)) ML18033B5031990-08-31031 August 1990 Forwards Financial Info Required to Assure Retrospective Premiums,Per 10CFR140 & 771209 Ltr ML20028G8341990-08-28028 August 1990 Forwards Calculation SCG1S361, Foundation Investigation of ERCW Pumping Station Foundation Cells. ML20063Q2471990-08-20020 August 1990 Submits Implementation Schedule for Cable Tray Support Program.Util Proposes Deferral of Portion of Remaining Activities Until After Current Unit 2 Cycle 4 Refueling Outage,Per 900817 Meeting.Tva Presentation Matl Encl ML20056B5181990-08-20020 August 1990 Responds to NRC Re Order Imposing Civil Monetary Penalty & Violations Noted in Insp Repts 50-327/90-01 & 50-328/90-01.Corrective Actions:Organizational Capabilities Reviewed.Payment of Civil Penalty Wired to NRC ML20063Q2461990-08-17017 August 1990 Forwards Cable Test Program Resolution Plan to Resolve Issues Re Pullbys,Jamming & Vertical Supported Cable & TVA- Identified Cable Damage.Tva Commits to Take Actions Prior to Startup to Verify Integrity of safety-related Cables ML20059A5121990-08-15015 August 1990 Provides Clarification of Implementation of Replacement Items Project at Plant for Previously Procured Warehouse Inventory.Util Committed to 100% Dedication of Commercial Grade,Qa,Level Ii,Previous Procurement Warehouse Spare ML20058M2321990-08-0707 August 1990 Forwards Rept of 900709 Fishkill,Per Requirements in App B, Environ Tech Spec,Subsections 4.1.1 & 5.4.2.Sudden Water Temp Increase Killed Approximately 150 Fish in Plant Diffuser Pond ML20058N2361990-08-0707 August 1990 Confirms That Requalification Program Evaluation Ref Matl Delivered to Rd Mcwhorter on 900801.Ref Matl Needed to Support NRC Preparation for Administering Licensed Operator Requalification Exams in Sept 1990 ML20058M4471990-07-27027 July 1990 Responds to Unresolved Items Which Remain Open from Insp Repts 50-327/90-18 & 50-328/90-18.TVA in Agreement W/Nrc on Scope of Work Required to Address Concerns W/Exception of Design Basis Accident & Zero Period Accelaration Effects ML20058M0111990-07-27027 July 1990 Forwards Addl Info Re Plant Condition Adverse to Quality Rept Concerning Operability Determination.Probability of Cable Damage During Installation Low.No Programmatic Cable Installation Problems Exist ML20055J3531990-07-27027 July 1990 Forwards Revised Commitment to Resolve EOP Step Deviation Document Review Comments ML20055J0771990-07-26026 July 1990 Requests Termination of Senior Reactor Operator License SOP-20830 for Jh Sullivan Due to Resignation from Util ML20055G6611990-07-17017 July 1990 Forwards Justification for Continued Operation for safety- Related Cables Installed at Plant,Per 900717 Telcon.No Operability Concern Exists at Plant & No Programmatic Problems Have Been Identified.Summary of Commitments Encl ML20058L7001990-07-16016 July 1990 Forwards Response to SALP Repts 50-327/90-09 & 50-328/90-09 for 890204 - 900305,including Corrective Actions & Improvements Being Implemented ML20055F6151990-07-13013 July 1990 Provides Addl Bases for Util 900320 Proposal to Discontinue Review to Identify Maint Direct Charge molded-case Circuit Breakers Procured Between Aug 1983 & Dec 1984,per NRC Bulletin 88-010.No Significant Assurance Would Be Expected ML20044B2211990-07-12012 July 1990 Forwards Addl Info Clarifying Certain Conclusions & Recommendation in SER Re First 10-yr Interval Inservice Insp Program ML20055D2531990-07-0202 July 1990 Provides Status of Q-list Development at Plant & Revises Completion Date for Effort.Implementation of Q-list Would Cause Unnecessary & Costly Delays in Replanning Maint,Mod, outage-related Activities & Associated Procedure Revs ML20043H9061990-06-21021 June 1990 Responds to Generic Ltr 90-04, Request for Info on Status of Licensee Implementaion of Generic Safety Issues Resolved W/Imposition or Requirements or Corrective Actions. No Commitments Contained in Submittal ML20043H2281990-06-18018 June 1990 Informs of Issue Recently Identified During Startup of Facility from Cycle 4 Refueling Outage & How Issue Addressed to Support Continued Escalation to 100% Power,Per 900613 & 14 Telcons ML20043G4901990-06-14014 June 1990 Forwards Tabs for Apps a & B to Be Inserted Into Util Consolidated Nuclear Power Radiological Emergency Plan ML20043F9261990-06-13013 June 1990 Responds to NRC Bulletin 89-002, Stress Corrosion Cracking of High-Hardness Type 410 Stainless Steel Internal Preloaded Bolting in Anchor/Darling Model S3502 Swing Check Valves or Valves of Similar Design. ML20043F9301990-06-13013 June 1990 Responds to NRC 900516 Ltr Re Violations Noted in Insp Repts 50-327/90-17 & 50-328/90-17.Corrective Action:Test Director & Supervisor Involved Given Appropriate Level of Disciplinary Action ML20043H0361990-06-11011 June 1990 Forwards Supplemental Info Re Unresolved Item 88-12-04 Addressing Concern W/Double Differentiation Technique Used to Generate Containment Design Basis Accident Spectra,Per 900412 Request ML20043D9921990-06-0505 June 1990 Responds to NRC 900507 Ltr Re Violations Noted in Insp Repts 50-327/90-14 & 50-328/90-14.Corrective Actions:Util Reviewed Issue & Determined That Trains a & B Demonstrated Operable in Jan & Apr,Respectively of 1989 ML20043C2821990-05-29029 May 1990 Requests Relief from ASME Section XI Re Hydrostatic Pressure Test Requirements Involving RCS & Small Section of Connected ECCS Piping for Plant.Replacement & Testing of Check Valve 1-VLV-63-551 Presently Scheduled for Completion on 900530 ML20043C0581990-05-29029 May 1990 Forwards Response to NRC 900426 Ltr Re Violations Noted in Insp Repts 50-327/90-15 & 50-328/90-15.Response Withheld (Ref 10CFR73.21) ML20043B3051990-05-22022 May 1990 Forwards Detailed Scenario for 900711 Radiological Emergency Plan Exercise.W/O Encl ML20043B1201990-05-18018 May 1990 Forwards, Diesel Generator Voltage Response Improvement Rept. Combined Effect of Resetting Exciter Current Transformers to Achieve flat-compounding & Installing Electronic Load Sequence Timers Produced Acceptable Voltage ML20043A6101990-05-15015 May 1990 Forwards Rev 16 to Security Personnel Training & Qualification Plan.Rev Withheld (Ref 10CFR2.790) ML20043A2391990-05-15015 May 1990 Forwards Revised Tech Spec Pages to Support Tech Spec Change 89-27 Re Steam Generator Water Level Adverse Trip Setpoints for Reactor Trip Sys Instrumentation & Esfas. Encl Reflects Ref Leg Heatup Environ Allowance ML20043A0581990-05-11011 May 1990 Forwards Cycle 5 Redesign Peaking Factor Limit Rept for Facility.Unit Redesigned During Refueling Outage Due to Removal & Replacement of Several Fuel Assemblies Found to Contain Leaking Fuel Rods ML20043A0571990-05-10010 May 1990 Forwards List of Commitments to Support NRC Review of Eagle 21 Reactor Protection Sys Function Upgrade,Per 900510 Telcon ML20042G9771990-05-0909 May 1990 Responds to NRC 900412 Ltr Re Violations Noted in Insp Repts 50-327/90-01 & 50-328/90-01 & Proposed Imposition of Civil Penalty.Corrective Actions:Rhr Pump 1B-B Handswitch in pull- to-lock Position to Ensure One Train of ECCS Operable ML20042G4651990-05-0909 May 1990 Provides Addl Info Re Plant Steam Generator Low Water Level Trip Time Delay & Function of P-8 Reactor Trip Interlock,Per 900430 Telcon.Trip Time Delay Does Not Utilize P-8 Interlock in Any Manner ML20042G4541990-05-0909 May 1990 Provides Notification of Steam Generator Tube Plugging During Unit 1 Cycle 4 Refueling Outage,Per Tech Specs 4.4.5.5.a.Rept of Results of Inservice Insp to Be Submitted by 910427.Summary of Tubes Plugged in Unit 1 Encl ML20042G0441990-05-0808 May 1990 Forwards Nonproprietary WCAP-11896 & WCAP-8587,Suppl 1 & Proprietary WCAP-8687,Suppls 2-E69A & 2-E69B & WCAP-11733 Re Westinghouse Eagle 21 Process Protection Sys Components Equipment Qualification Test Rept.Proprietary Rept Withheld ML20042G1431990-05-0808 May 1990 Forwards WCAP-12588, Sequoyah Eagle 21 Process Protection Sys Replacement Hardware Verification & Validation Final Rept. Info Submitted in Support of Tech Spec Change 89-27 Dtd 900124 ML20042G1001990-05-0808 May 1990 Forwards Proprietary WCAP 12504 & Nonproprietary WCAP 12548, Summary Rept Process Protection Sys Eagle 21 Upgrade,Rtd Bypass Elimination,New Steam Line Break Sys,Medical Signal Selector .... Proprietary Rept Withheld (Ref 10CFR2.790) ML20042G1701990-05-0808 May 1990 Provides Addl Info Re Eagle 21 Upgrade to Plant Reactor Protection Sys,Per 900418-20 Audit Meeting.Partial Trip Output Board Design & Operation Proven by Noise,Fault,Surge & Radio Frequency Interference Testing Noted in WCAP-11733 ML20042G1231990-05-0707 May 1990 Forwards Detailed Discussion of Util Program & Methodology Used at Plant to Satisfy Intent of Reg Guide 1.97,Rev 2 Re Licensing Position on post-accident Monitoring ML20042F7741990-05-0404 May 1990 Informs of Completion of Eagle 21 Verification & Validation Activities Re Plant Process Protection Sys Upgrade.No Significant Disturbances Noted from NRC Completion Date of 900420 ML20042F1691990-05-0303 May 1990 Responds to NRC Bulletin 88-009, Thimble Tube Thinning in Westinghouse Electric Corporation Reactors. Wear Acceptance Criteria Established & Appropriate Corrective Actions Noted. Criteria & Corresponding Disposition Listed ML20042G1381990-04-26026 April 1990 Forwards Westinghouse 900426 Ltr to Util Providing Supplemental Info to Address Questions Raised by NRC Re Eagle-21 Process Protection Channels Required for Mode 5 Operation at Facilities ML20042E9641990-04-26026 April 1990 Forwards Rev 24 to Physical Security/Contingency Plan.Rev Withheld (Ref 10CFR73.21) ML20012E6181990-03-28028 March 1990 Discusses Reevaluation of Cable Pullby Issue at Plant in Light of Damage Discovered at Watts Bar Nuclear Plant. Previous Conclusions Drawn Re Integrity of Class 1E Cable Sys Continue to Be Valid.Details of Reevaluation Encl 1990-09-17
[Table view] |
Text
h 4-
. 4 TENNESSEE VALLEY AUTHORITY CHATTANOOGA. TENNESSEE 37401 500C Chestnut Street Tower II JAN 181979 Director of Nuclear Reactor Regulation Attention: Mr. S. A. Varga, Chief Light Water Reac' ors Branch No. 4 Division of Project bbnagement U.S. Nuclear Regulatory Commission Washington, DC 20555
Dear Mr. Varga:
In the Matter of the Application of ) Docket Nos. 50-327 Tennessee Valley Authority ) 50-328 Enclosed is the additional information concerning local leak rate testing at the Sequoyah '..uclear Plant requested by the Nuclear Regulatory Commission (NRC) Containment Systems Branch reviewer i.
a telephone converse'. ion on January 10, 1979. The material specifies the basis for local leak rate testing of some containment isolation valves with water as the test medium. Amendment 60 to the Sequoyah Nuclear Plant Final Safety Analysis Report will incorporate the enclosed material.
Very truly yours, o,t J. E. Gillelan'd Assistant Manager of Power Enclosure (10) 790124 0/9?
An Equal Opportunity Employer
^
- LOCAL LEAK RATE TESTIUG OF CONTAINMENT 9 8 ISOLATICN VALVES l
b Appendix J of 10CFR50, which specifies the integrated and local leakage rate testing requirements for containments, was published long af ter the construction of Sequoyah began and Sequoyah has not been required to conform to those requirements. The Seguoyah FSAR outlines TVA's present leak rate testing program for containment isolation valves. The test program permits the use of air er water as the test medium for local leak rate testing of isciation valves. Late this summer there were indications that the NRC may no longer accept water as a test medium for plants the vintage of Sequoyah. In october of this year TVA contacted the Eegulatory Staff and requested clarification on this issue due to the potential impact on the Sequoyah startup date. The Staff verbally responded in telephone discussions that the use of air is required on all valves as specified in 10CFR50, Appendix J, except for cases of obvious hardship or justification i
which would show that the potential for release of containment atmosphere is small.
TVA has reviewed the piping layouts at Sequoyah to determine the
, specific plant design features and such modifications to the plant as would be required to permit local valve testing in conformance with Appendix J. The local valve test program considers 75 penetrations. Forty-four penetrations were scheduled to be tested with water instead of air. The remaining 31 penetrations would be tested with air as required by Appendix J. We determined from the system-by-system review of the 4 4 water test penetrations that 17 penetrations could and will be tested as required by Appendix J prior to initial plant operation. The remaining 27 water test penetrations were found to require hardware modifications which cannot be inplemented without delaying the fuel load date of April 1979.
TVA therefore requests that leak rate testing with water of the isolation valves associated with these 27 penetrations he permitted for plant operation during the first fuel cycle. TVA will, during the first refueling outage, modify the plant so that all future local leak rate testing will b.. done in full compliance with Appendix J.
The problem with any modilications at this time is that plant preoperational testing (such as hot functional testing scheduled from January, 1979 through February) requires the proper function of many systems simultaneously to support any particular test.
Some tests (such as the~ Type A containment leak test scheduled in February) preclude physical access to areas required to perform modifications. There are few time periodo left between now and scheduled fuel loading when we have both physical access to certain equipment and freedom from its functional tie to cther testing. These periods are already scheduled for intense testing .
activity that can only be done during such pericds. Our every effort at this time is to direct our construction and testing I program towards minimizing any further delays in the critical path schedule for fuel loading and plant operation. To alter the
^
ID p, M @d u d@W
- s w
MM A a
o
lor mo Ifications at this time is certain to cause additicnal delay.
The attached table lists each of the systems and penetrations for which an exemption is requested. A brief discussion is provided f~' f or each system giving a basis for permitting the one-time-only water test. Factors discussed are procurement delays, system status, and design features which, in addition to the containment isolation provisions, would limit the release of radioactive material from the containment. TVA believes that plant and public safety are nct compromised by permitting these few one-time water tests.
A cne time exemption from the draining requirements of Appendix J for the Type A test is also requested for the penetrations provided in the attached table. These lines will he vented in accordance with the Type A procedures in Appendix J, however, the modificaticns required to perform the Type C test with air'are also required in order to properly drain these lines for the Type A test.
q a r
e 9
s Fenetration Modifications Easis for a Wal.er: Teut System Number Recuired for First Fuel Cycle Ice Condenser X-47A In-Line Block Ice loading is presently underway.
Valve & Drain Modifications would require the syster valve to be removed from service which would delay ice loading. Ice loading is a X-47B In-Line Block critical path item and any delays are Valve & Drain translated directly to the fuel load valve date. Additionally, the in-line blcck X-114 Drain Valve valves cannot be procured prior to X-115 Drain valvc start-up of the plant.
UHI X-110 2 Blind Preoperational testing is presently Flanges S underway on this system. The system
'agg 2 Vent valves would have to be removed from service ggg=,;'= ) to make modifications. This line has,
--d in addition to the containment iso-laticn valves, a manual normally closed
$35d Class E glche valve located outside containment in each branch of the line.
6 9- Any leakage from this system would be 2359 treated by the Auxiliary Building Gas Treatment System (AEGTS) prior to bd cd release to the outdoors. The principal tests that could be delayed by requiring N?2d modification to this system are:
553D 1) Containment Integrated Leak Bate Test b 2) Hot Functional Tests Domineralized X-77 2 Drain Valves S stem tests (non-critical) are Water scheduled for January 1979. The required modifications would delay putting this system in Service.
Portions of this system are located in the Auxiliary Building where any leakage across the isolation valves
~
Penetration hodifications Easis for a Wal.or Tunt System Nur.ber Reauired for First Fuel Cvele would he treated by the AEGTS. The principal tests that could he delayed by by requiring modification to this system are:
- 1) Containment Integrated Leak Rate Test
- 2) Hot Functional Tests Component X-29 Drain Valve Freoperational testing has been com-Cooling pleted for this system. The system Water X-52 Drain valve would haye to be removed from service to make modifications. This would TEN X-35 Drain valve & delay the performance of other pre-QZZ3 Cross Connect operational tests and thereby delay
@==9- fuel loading. The Component Cooling gggg X-53 Drain valve & Kater System is a Class C, seismic Cross Connect Category I closed loop piping system q g outside cf containment. Any leakage 51E0 across the isolaticn valves would be contained in the system piping and gg g . not released to the atmosphere. The principal tests that could be delayed by pand requiring modification to this system are:
g 1) Containment Integrated Leak Bate Test b 2) Hot Functional Tests
- 3) CVCS Tests
- 4) Onsite Power Distribution Load Tests
- 5) ECP Tests CVCS X-15 In-Line Block Preoperaticnal testing is presently Valve C 2 underway on this system: The system Drain valves would have to to removed from service to make modifications. Additionally, X-44 Drain Valve the CVCS is a Class E, seismic Category I closed system outside of
D D 3: '
penetration Svstem Eumber Rodifications Recuired Easis for a Natur Tent for First Fuel Cycle the primary containment. Any leakage across the isolation valves would he trapped in the system piping and not released to the atmosphere. The closed portions of this system are located in areas of the auxiliary building which are served by the ABGTS. The in-line block valve cannot he procured prior to fuel loading. The principal tests that could he delayed by requiring modification to this system are:
- 1) Containment Integrated Leak Bate Test
- 2) Hot Functional Tests
- 3) Oncite Power Distribution Load Tests
- 4) Full Flow Tests A/C Chilled X-64 Drain Valve System testing (non-critical) is Water presently scheduled for late January X-65 Crain Valve 1979. Mcdification would delay testing and putting the system in X-66 Drain Valve service. This is a closed system F75d
(< 9 X-67 Drain Valve incide ccntainment located in the instrument room. The piping is f~3 ANSI E31.1 and seismic category I, gggg therefore it is unlikely that a release of radicactivity wculd occur g following a LOCA due to this system.
$350 The principal tests that could he delayed by requiring modification to this syster b5IO are:
- 1) Containment Integrated Leak Fate Test pggg 2) Hot Functional Tests p .
b
7 7 7- .
Fenetration Modifications Easis for a Gal.er Tent Svstem ?;umbe r Recuired for First Fuel Cvcle Floors & Equip- X-41 Drain Valve The preoperational test for this ment Drains system is presently underway. Modifica-tions would delay putting the system in service. This system is located in the Auxiliary Euilding and any leakage across the isolation valves would be treated by the AEGTS. The principal tests that could be delayed by requiring modification to this system are:
- 1) Containment Integrated Leak Rate Test
- 2) Eat Functional Tests Primary Water X-42 Drain Valve Prooperational testing on this syster is scheduled for December 1978.
35b
- This test is a prerequisite to other CSEEd tests required prior to startup.
6__3 Modification of this system at this
$399 time wculd delay the performance of this test and therefore delay fuel
(< >) loading. The principal tests that cculd gggg he delayed by requiring modificaticn to this system are:
[]2) 1) Centainment Integrated Leak Fate Test
- 2) Hot Functional Tests
- 3) CVCS Tests gj5D 4) Eoron Recycle Test y 5) Boric Acid Test
~ Fuel Poc1 Cooling X-82 In-Line Block Freoperational testing on tb.is Valve system has been ccmpleted. The in-line block valve cannot he procured pricr to fuel loading.
Fenetration Modifications Easis for a Watm; Test Svste.? Number Roauired for First Fuel Cyclo ERC% Supply X-56 Drain Valve Freoperational testing on this system is underway at the present time.
X-58 Dr L1 valve Modifications would require that the system he removed from service. A X-60 Drain Valve functional ERCW system is a pre-requisite for the performance cf many X-62 Drain valve remaining preoperational and system tests. Fuel loading will incur a X-68 Crain Valve minimum of a day to day delay for
' time the ERCW is out of service.
X-69 Drain Valve The ERCU is a seismic Category I Class C system. There is a X-74 Drain Valve sufficient elevation difference in the piping outside of containment tc X-75 Drain Valve maintain a 10 psig water leg seal in the supply lines after an accident.
This water leg seal would limit the release of radioactive material which leaks past the isolation valves to a very small amcunt. The ERCh "Tgg discharge lines are scaled with a y g seal system which meets the g g requirements of 10CFR50, Appendix J.
The principal tests that could he bEEO delayed by requiring mcdificaticn to this system are:
6=rb 1) Containment Integrated Leak Bate Test 555d
- 2) Hot Functional Tests
- 3) HVAC Tests fh 74gp
- 4) CVCS Tests
- 5) RI!R Tests
- 6) Containment Spray Tests 5533 7) SIS Tests b 8) Onsite Power Distributicn Load Tests S) Ccmponent Cooling Water Tests 10)Ccntrcl Eay HVAC Tests
WATER .EAKAGE TO AIR LEAKAGE COtiVERSION In order to support our request for a o.'c time water test on f certain fluid lines a t the Sequoyah Iluclear Plant, TVA is supplying wa ter to air leakage conversion data. The data was developed for use at Unit 2 of the Browns Ferry Plant.
As part of our evaluation of converting isolation valve water leakage to gas equivalent, TVA empirically measured both air and water leakage through several typical valves. The purpoco of this program was twofold. The first purpose was to reproduce the data presented in a technical report by Maine Yankee Atomic vouer Ccrpany entitled " Water Leakage to Air Leakage Correlation." The sec nd purpose of the program was to extend the Maine Yankee tests to cover a larger range of leakagcc and valve types. The range of leakages was to cover those typically oncountered in a type C test program.
A comparison of the water and air leakage for those valves tested in the TVA program is depicted in Figure 1. Data from Maine Yankee is included for reference. There is reasonable agreement betwoon the Maine Yankee and the data collected by TVA for the range of water leakage considered in the Maine Yankee report.
Figure 2 depicts the conversion curve presented in the 14aine Yankee report and that obtained in these tests. The larger degree of scatter from the fit line for the 1/A tests is attributable in part to the larger range of valve sizes tested.
The TVA curve presented in Figure 2 uns used at Browns Ferry.
This curve was based on tests conducted at 50 psig. Tne Sequoyah Type C test is performed at 12 psig. Therefore the curve should be corrected for the pressure difference. We intend to use the TVA curve (Figure 2) modified by multiplying the air leakage values by the square root of the pressure ratio between Sequoyah and Brouns Ferry (i.e., $/i2/5 0' ) at Sequoyah. Appendix J uses this method of ratioing pressure to evaluate the leak rate for the' Type A reduced pressure test. This water to air conversion method uould be used only for the preoperational test.
D h hhh m Ju a u b e D
.p - . .
<C -
g.
<C O N
-G Lt! 2 -
>-1-- ~
4 '5 , . <C i
3 un -
Mjg - Z .
I x.. H< g x
.n fp 2 -
X x 7; l} -
~
oX X ><"< ---
1 X -
I h, : : ~
'C I
X lt-O I'. - _ Z X <bP -
~
I-I X -
I~ X X X - LtJ X X X - G l X -*
<C gl-.
- g -
--> X #U O X --
LLI -
X i1-1 >: X , _ _j
.w "
x x >t. i x yg - e m x 2 - 113
- X x OX __
i-4
. >t'.,X -
3 X ~
X X X Xo s 3
X X -
N
> < l
)
g J '
I G
,-. X -
~~
C xo X
~
)
.) ,
~
CO I
lirlTITT IIITT n i IIITITI I H1TITI-- I ,
Ilfl I I I I CD v co u o - -
O O O ~ I
- - - G
~ N -
~
.d 2
. D D 1)']1
% w o
4 10 -
= .
N
~'
l
- TV,(
A /
i0 3
.L - , -
= i R .-j 1
L l .
' l.
A 5n2 K
E /
A 3 G
. E T 10 YANKEE N R .
S ]
to) .
- p) C I
/ .
a-3 L5'Pe>
- H F q q
77 c 9 _
m -.
-1 Lcre 3 i i i iiiij 1 iitisi i i i i ii, , s i l iiti 1 i
-3 -2 , e i iiii) t 10 2
10 10 10- 1 10 3 -
b WATER LEAKAGE IN CFH
.