| issue date = 02/14/2008
| issue date = 02/14/2008
| title = IR 05000461-07-501 & 404, on 12/31/2007, 01/01/2007, Clinton Power Station - NRC Emergency Preparedness Annual and Security Annual Inspection
| title = IR 05000461-07-501 & 404, on 12/31/2007, 01/01/2007, Clinton Power Station - NRC Emergency Preparedness Annual and Security Annual Inspection
| author name = Duncan E R
| author name = Duncan E
| author affiliation = NRC/RGN-III/DRS/PSB
| author affiliation = NRC/RGN-III/DRS/PSB
| addressee name = Pardee C G
| addressee name = Pardee C
| addressee affiliation = Exelon Generation Co, LLC
| addressee affiliation = Exelon Generation Co, LLC
| docket = 05000461
| docket = 05000461
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:ary 14, 2008
[[Issue date::February 14, 2008]]


Mr. Charles Chief Nuclear Officer and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville IL 60555
==SUBJECT:==
 
CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404
SUBJECT: CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404


==Dear Mr. Pardee:==
==Dear Mr. Pardee:==
Line 30: Line 28:
Issuance of this letter closes Inspection Report Number 2007501. On December 31, 2007, the NRC staff also completed its annual inspection of the Security Program at the Clinton Power Station. This inspection began on January 1, 2007. Issuance of this letter closes Inspection Report Number 2007404. Some of the time NRC expended during routine Emergency Preparedness and Security Program reviews was charged to these report numbers. Any observations and findings in these areas were provided to you via separate correspondence.
Issuance of this letter closes Inspection Report Number 2007501. On December 31, 2007, the NRC staff also completed its annual inspection of the Security Program at the Clinton Power Station. This inspection began on January 1, 2007. Issuance of this letter closes Inspection Report Number 2007404. Some of the time NRC expended during routine Emergency Preparedness and Security Program reviews was charged to these report numbers. Any observations and findings in these areas were provided to you via separate correspondence.


In accordance with 10 CFR 2.390 of the NRC
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter, and your response, if any, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). Inspection reports are posted on the Reactor Oversight Process (ROP) Web page. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
=s ARules of Practice,@ a copy of this letter, and your response, if any, will be available electronically for pub lic inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). Inspection reports are posted on the Reactor Oversight Process (ROP) Web page. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
Sincerely,/RA/
Eric Duncan, Chief Plant Support Branch Division of Reactor Safety
 
Docket No. 50-461 License No. NPF-62
 
DISTRIBUTION See next page
 
Mr. Charles Chief Nuclear Officer and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville IL 60555


SUBJECT: CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404
Sincerely,
/RA/
Eric Duncan, Chief Plant Support Branch
==SUBJECT:==
CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404


==Dear Mr. Pardee:==
==Dear Mr. Pardee:==
Line 49: Line 41:
Issuance of this letter closes Inspection Report Number 2007501. On December 31, 2007, the NRC staff also completed its annual inspection of the Security Program at the Clinton Power Station. This inspection began on January 1, 2007. Issuance of this letter closes Inspection Report Number 2007404. Some of the time NRC expended during routine Emergency Preparedness and Security Program reviews was charged to these report numbers. Any observations and findings in these areas were provided to you via separate correspondence.
Issuance of this letter closes Inspection Report Number 2007501. On December 31, 2007, the NRC staff also completed its annual inspection of the Security Program at the Clinton Power Station. This inspection began on January 1, 2007. Issuance of this letter closes Inspection Report Number 2007404. Some of the time NRC expended during routine Emergency Preparedness and Security Program reviews was charged to these report numbers. Any observations and findings in these areas were provided to you via separate correspondence.


In accordance with 10 CFR 2.390 of the NRC
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter, and your response, if any, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). Inspection reports are posted on the Reactor Oversight Process (ROP) Web page. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
=s ARules of Practice,@ a copy of this letter, and your response, if any, will be available electronically for pub lic inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). Inspection reports are posted on the Reactor Oversight Process (ROP) Web page. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
Sincerely,/RA/
Eric Duncan, Chief Plant Support Branch Division of Reactor Safety
 
Docket No. 50-461 License No. NPF-62
 
DISTRIBUTION See next page
 
DOCUMENT NAME: G:\Security & EP Ltrs\CLI Security & EP Ltr.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl; "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII NAME RJickling:co DF for DFunk EDuncan DATE 02/14/08 02/14/08 02/14/08 OFFICIAL RECORD COPY Letter to Charles from Eric Duncan dated February 14, 2008.
 
SUBJECT: CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404


cc: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General State Liaison Officer Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Illinois Emergency Management Agency Letter to Charles from Eric Duncan dated February 14, 2008.
Sincerely,
/RA/
Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 DISTRIBUTION See next page DOCUMENT NAME: G:\Security & EP Ltrs\CLI Security & EP Ltr.doc 9 Publicly Available 9 Non-Publicly Available  9 Sensitive  9 Non-Sensitive To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy OFFICE  RIII  RIII  RIII NAME  RJickling:co DF for  DFunk  EDuncan DATE  02/14/08  02/14/08  02/14/08 OFFICIAL RECORD COPY


SUBJECT: CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404
Letter to Charles from Eric Duncan dated February 14, 2008.


cc: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General State Liaison Officer Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Illinois Emergency Management Agency  
SUBJECT: CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404 cc: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General State Liaison Officer Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Illinois Emergency Management Agency


DISTRIBUTION
Letter to Charles from Eric Duncan dated February 14, 2008.
: TEB RAG1 SPS1 MMT RidsNrrDirsIrib MAS KGO JKH3 RML2 SRI Clinton


CAA1 DRSIII DRPIII PLB1 TXN
SUBJECT: CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404 cc: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General State Liaison Officer Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Illinois Emergency Management Agency DISTRIBUTION:
TEB RAG1 SPS1 MMT RidsNrrDirsIrib MAS KGO JKH3 RML2 SRI Clinton CAA1 DRSIII DRPIII PLB1 TXN
}}
}}

Latest revision as of 19:19, 14 November 2019

IR 05000461-07-501 & 404, on 12/31/2007, 01/01/2007, Clinton Power Station - NRC Emergency Preparedness Annual and Security Annual Inspection
ML080510561
Person / Time
Site: Clinton Constellation icon.png
Issue date: 02/14/2008
From: Eric Duncan
Plant Support Branch II
To: Pardee C
Exelon Generation Co
References
IR-07-404, IR-07-501
Download: ML080510561 (4)


Text

ary 14, 2008

SUBJECT:

CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404

Dear Mr. Pardee:

On December 31, 2007, the NRC staff completed its annual inspection of the Emergency Preparedness Program at the Clinton Power Station. This inspection began on January 1, 2007.

Issuance of this letter closes Inspection Report Number 2007501. On December 31, 2007, the NRC staff also completed its annual inspection of the Security Program at the Clinton Power Station. This inspection began on January 1, 2007. Issuance of this letter closes Inspection Report Number 2007404. Some of the time NRC expended during routine Emergency Preparedness and Security Program reviews was charged to these report numbers. Any observations and findings in these areas were provided to you via separate correspondence.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter, and your response, if any, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). Inspection reports are posted on the Reactor Oversight Process (ROP) Web page. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch

SUBJECT:

CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404

Dear Mr. Pardee:

On December 31, 2007, the NRC staff completed its annual inspection of the Emergency Preparedness Program at the Clinton Power Station. This inspection began on January 1, 2007.

Issuance of this letter closes Inspection Report Number 2007501. On December 31, 2007, the NRC staff also completed its annual inspection of the Security Program at the Clinton Power Station. This inspection began on January 1, 2007. Issuance of this letter closes Inspection Report Number 2007404. Some of the time NRC expended during routine Emergency Preparedness and Security Program reviews was charged to these report numbers. Any observations and findings in these areas were provided to you via separate correspondence.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter, and your response, if any, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). Inspection reports are posted on the Reactor Oversight Process (ROP) Web page. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 DISTRIBUTION See next page DOCUMENT NAME: G:\Security & EP Ltrs\CLI Security & EP Ltr.doc 9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy OFFICE RIII RIII RIII NAME RJickling:co DF for DFunk EDuncan DATE 02/14/08 02/14/08 02/14/08 OFFICIAL RECORD COPY

Letter to Charles from Eric Duncan dated February 14, 2008.

SUBJECT: CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404 cc: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General State Liaison Officer Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Illinois Emergency Management Agency

Letter to Charles from Eric Duncan dated February 14, 2008.

SUBJECT: CLINTON POWER STATION - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT NO. 05000461/2007501; NRC SECURITY ANNUAL INSPECTION REPORT NO. 05000461/2007404 cc: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General State Liaison Officer Illinois Emergency Management Agency Chairman, Illinois Commerce Commission Illinois Emergency Management Agency DISTRIBUTION:

TEB RAG1 SPS1 MMT RidsNrrDirsIrib MAS KGO JKH3 RML2 SRI Clinton CAA1 DRSIII DRPIII PLB1 TXN