Emergency Preparedness Biennial Exercise Inspection Report 05000461/2021501
ML22003A079
Person / Time
Site: Clinton Constellation icon.png
Issue date: 01/03/2022
From: Patricia Pelke
NRC/RGN-III/DRS/OLB
To: Rhoades D
Exelon Generation Co, Exelon Nuclear
Hansen G
References
IR 2021501
Download: ML22003A079 (8)


Text

SUBJECT:

CLINTON POWER STATION - EMERGENCY PREPAREDNESS BIENNIAL EXERCISE INSPECTION REPORT 05000461/2021501

Dear Mr. Rhoades:

On November 19, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Clinton Power Station. On November 18, 2021, the NRC inspectors discussed the results of this inspection with Mr. T. Chalmers and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Patricia J. Pelke, Chief Operations Branch Division of Reactor Safety Docket No. 05000461 License No. NPF-62

Enclosure:

As stated

Inspection Report

Docket Number:

05000461

License Number:

NPF-62

Report Number:

05000461/2021501

Enterprise Identifier:

I-2021-501-0013

Licensee:

Exelon Generation Company, LLC

Facility:

Clinton Power Station

Location:

Clinton, IL

Inspection Dates:

November 15, 2021 to November 18, 2021

Inspectors:

L. Cender, Health Physicist

E. Fernandez, Reactor Inspector

M. Garza, Emergency Preparedness Inspector

G. Hansen, Senior Emergency Preparedness Inspector

Approved By:

Patricia J. Pelke, Chief

Operations Branch

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an emergency preparedness biennial exercise inspection at Clinton Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01-02.11) (1 Sample)

(1) The inspectors evaluated the biennial emergency plan exercise on November 16, 2021. The exercise scenario simulated an event at the Clinton Power Station that initiated with the declaration and notification of an Alert in response to on-site gaseous release that impeded access to equipment necessary for normal plant operations, cooldown, or shutdown. The scenario conditions simulated the escalation of the significance of the event, requiring the declaration of a Site Area Emergency, and then a General Emergency, as well as the development of Protective Action Recommendations that were communicated to the required state and local government agencies.

71114.08 - Exercise Evaluation Scenario Review

Inspection Review (IP Section 02.01 - 02.04) (1 Sample)

(1) The inspectors reviewed and evaluated the proposed scenario for the biennial emergency plan exercise on October 13,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12)===

(1) July 01, 2020 through June 30, 2021 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) July 01, 2020 through June 30, 2021 EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) July 01, 2020 through June 30,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On November 18, 2021, the inspectors presented the emergency preparedness biennial exercise inspection results to Mr. T. Chalmers and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 04231567

EP ID 2019 NRC Graded Exercise - TSC Performance

03/21/2019

AR 04365598

EP Clinton 2020 Off Year Exercise - Sim/CR Issues

08/26/2020

AR 04365604

EP Clinton 2020 Off Year Exercise - TSC Issues

08/26/2020

AR 04365607

EP Clinton 2020 Off Year Exercise - OSC Issues

08/26/2020

AR 04365611

EP Clinton 2020 Off Year Exercise - Scenario/Control

08/26/2020

Corrective Action

Documents

AR 04365619

EP Clinton 2020 Off Year Exercise - Equipment Issues

08/26/2020

Emergency Preparedness Drill and Exercise Reports (Sample)

11/01/2019-

10/31/2021

Miscellaneous

Clinton Biennial Exercise - Exercise Evaluation

Results(PowerPoint Presentation)

11/18/2021

EP-AA-1000

Exelon Nuclear Standardized Radiological Emergency Plan

EP-AA-1003

Exelon Nuclear Radiological Emergency Plan Annex for

Clinton Station

EP-AA-1003,

Addendum

Clinton Station On-Shift Staffing Technical Basis

EP-AA-1003,

Addendum 3

Exelon Nuclear Emergency Action Levels for Clinton Station

EP-AA-110-200

Dose Assessment

EP-AA-110-301

Core Damage Assessment (BWR)

EP-AA-111

Emergency Classification and Protective Action

Recommendations

EP-AA-112

Emergency Response Organization (ERO) / Emergency

Response Facility Activation and Operation

EP-AA-112-200

TSC Activation and Operation

EP-AA-112-400

Emergency Operations Facility Activation and Operation

EP-AA-113

Personnel Protective Actions

71114.01

Procedures

EP-AA-114

Notifications

71114.08

Miscellaneous

RS-21-009

Clinton Station 2021 Emergency Preparedness Biennial

Exercise Scenario

09/16/2021

NEI 99-02

Regulatory Assessment Performance Indicator Guideline

71151

Miscellaneous

NRC

Performance

Alert Notification System Reliability

07/01/2021-

06/30/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Indicator Data

Sheets

NRC

Performance

Indicator Data

Sheets

Emergency Response Organization Readiness

07/01/2021-

06/30/2021

NRC

Performance

Indicator Data

Sheets

Drill/Exercise Performance

07/01/2021-

06/30/2021

NRC

Performance

Indicator Data

Sheets

Emergency Response Organization Drill Participation

07/01/2020-

06/31/2021