IR 05000461/2020010

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000461/2020010
ML21071A077
Person / Time
Site: Clinton Constellation icon.png
Issue date: 03/11/2021
From: Richard Skokowski
Division of Reactor Safety III
To: Rhoades D
Exelon Generation Co, Exelon Nuclear
References
IR 2020010
Download: ML21071A077 (9)


Text

March 11, 2021

SUBJECT:

CLINTON POWER STATION - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000461/2020010

Dear Mr. Rhoades:

On February 11, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Clinton Power Station and discussed the results of this inspection with Mr. G. Olson, Maintenance Director and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Richard A. Skokowski, Chief Engineering Branch 3 Division of Reactor Safety

Docket No. 05000461 License No. NPF-62

Enclosure:

As stated

Inspection Report

Docket Number:

05000461

License Number:

NPF-62

Report Number:

05000461/2020010

Enterprise Identifier: I-2020-010-0058

Licensee:

Exelon Generation Company, LLC

Facility:

Clinton Power Station

Location:

Clinton, IL

Inspection Dates:

September 21, 2020 to February 11, 2021

Inspectors:

K. Barclay, Reactor Inspector

J. Beavers, Senior Resident Inspector

A. Dahbur, Senior Reactor Inspector (Lead)

B. Daley, Senior Reactor Inspector

D. Sargis, Resident Inspector

D. Szwarc, Senior Reactor Analyst

Approved By:

Richard A. Skokowski, Chief

Engineering Branch 3

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Clinton Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease (COVID-19), regional inspectors were directed to begin telework. During this time regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. In some cases, portions of an IP were completed remotely and on-site.

The inspection documented below was determined that the objectives and requirements stated in the IP could be completed remotely.

REACTOR SAFETY

===71111.21N.05 - Fire Protection Team Inspection (FPTI)

Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===

The inspectors verified that the following systems credited in the approved fire protection program could perform their licensing basis function:

(1) Safe Shutdown Method 2 which credited Automatic Depressurization System (ADS),

Low Pressure Core Injection (LPCI) and Residual Heat Removal (RHR) "B" Pump for suppression pool cooling

(2) Suppression System in Emergency Diesel Generator (EDG) Room (CO2)
(3) Suppression System in Auxiliary Building (Sprinklers System)

Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the following fire protection program administrative controls were implemented in accordance with the current licensing basis:

(1) Control of Transient Combustible Material

Fire Protection Program Changes/Modifications (IP Section 03.03) (2 Samples)

The inspectors reviewed the following changes to ensure that they did not constitute an adverse effect on the ability to safely shutdown post-fire and to verify that fire protection program documents and procedures affected by the changes were updated.

(1) Generic Letter 86-10 Evaluation for MSO Scenario 2-NEW-6 RCIC [Reactor Core Isolation Cooling], HPCS [High Pressure Core Spray] or RHR Operating with No Flowpath (EC-389773)
(2) Generic Letter 86-10 Evaluation for Loss of Breaker Control (EC-383787)

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On February 11, 2021, the inspectors presented the triennial fire protection inspection results to Mr. G. Olson, Maintenance Director and other members of the licensee staff.
  • On October 9, 2020, the inspectors presented the Interim Exit Meeting inspection results to Mr. T. Chalmers, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.05 Calculations

19-AI-78

Evaluate Circuits Routed Through Various Fire Areas to

Determine If an Appendix R Fire in That Area Could

Cause Loss of Offsite Power

19-AI-81

CPS Appendix R Safe Shutdown Component Circuit

Analysis87-802

Hydraulic Calculations for Fire Protection Water Supply

System Fire Flow Testing

Corrective Action

Documents

04162045

EOID: 0FP01PA, Fire Pump A, Failed to Start for

Operability

08/06/2018

1668436

9071.04C002 Failed Acceptance Criteria

06/05/2014

4171931

Leak on A Fire Pump 1FP013

09/11/2018

4353266

Analyze Data Per 9071.02, Section 8.5 for 0FP01PB8.5

Analyzing Recorded Data 8.5.1

07/15/2020

Corrective Action

Documents

Resulting from

Inspection

AR 4373987

Revise and Correct UFSAR Appendix E Cable Tray

Drawings

10/02/2020

AR 4375388

Revise and Correct Drawing E28-1001-05A-EI

10/08/2020

Drawings

CE-CLT6-51.0

Sheet 001

One-Line Single Line Diagram

A

E02-1RH99

Residual Heat Removal Sys (RH) Shutdown Clg. Suction

Valves 1E12-F006A & 1E12-F006B

N

E02-1RH99

Residual Heat Removal Sys (RH) RHR B to Feedwater

Keep Fill Valve 1E12-F496

M

E02-1RH99

Schematic Diagram Residual Heat Removal System (RH)

Residual Heat Removal Pump 1B

H

E02-1RH99,

Sheet 503

RHR Suction Valve 1E12-F006B

N

E03-1RH00

Internal - External Wiring Diagram Residual Heat Removal

System (RH) Motor Operated Valves Limit Switches

S

E29-1001-01A-EI

Diesel Generator and HVAC Building Ground Floor Plan

El. 737'-0" Area 1

AH

E29-1001-04A-EI

Electrical Installation Diesel Generator and HVAC Building

Y

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Ground Floor Plan El. 737'-0" Area 4

M05-1075

Sheet 1

P&ID Residual Heat Removal (RH)

AZ

M05-1075

Sheet 2

P&ID Residual Heat Removal (RH)

AO

M05-1075

Sheet 3

P&ID Residual Heat Removal (RH)

AI

M05-1075

Sheet 4

P&ID Residual Heat Removal (RH)

AG

Engineering

Changes

EC 380723

GL86-10 Evaluation in Support of Revision to CPS

1893.06, for Min Acceptable Voltage for the Fire

Protection Diesel Engine

EC 383787

MSO Scenario 7D - Loss of Breaker Control / Initiating

Loss of Bus Coordination and GL 86-10-2011-09001 Fire

Protection Evaluation / Qualitative Fire Modeling for Fire

Zone F-1A

EC 383788

MSO Scenario 2l - Spurious RHR Min Flow Closure with

Spurious Pump Start

EC 389773

MSO Scenario 2-new-6 - RCIC, HPCS, or RHR Operating

with No Flowpath Historical GL-86-10-2012-10-001

Engineering

Evaluations

EPU-T0611

Extended Power Uprate Task T0611 Appendix R Fire

Protection

Miscellaneous

SSD Cables Routing for a Component: 1E12-C002B RHR

Pump 1-B A-3A

10/06/2020

SSD Cables Routing for a Component: 1E12-C002C RHR

Pump 1-C A-3B

10/06/2020

XTP-FP/CO-14

Diesel Generator Carbon Dioxide Fire Protection System

Test

03/08/1986

Procedures

4401.01 EOP-1

RPV Control

CPS 1893.06

Fire Protection Maintenance and Testing Program

CPS 3312.01

Residual Heat Removal (RHR)

47d

CPS

3312.01H001

LPCI Initiation and Shutdown Hard Card

CPS 3312.02

Alternate Shutdown Cooling (A-SDC) Methods

9e

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CPS 3312.03

RHR - Shutdown Cooling (SDC) & Fuel Pool Cooling and

Assist (FPC&A)

11f

CPS

4003.01C006

RSP - DIV 1 LPCI Operation

CPS

4003.01C007

RSP - DIV 1 Suppression Pool Cooling Operation

0a

CPS

4003.01C008

RSP - DIV 1 Shutdown Cooling Operation

1c

CPS

4003.01H001

MCR - "A" CRO Hard Card

CPS

4003.01H002

MCR - "B" CRO Hard Card

0a

CPS

4003.01H003

RSP - Hard Card 'A'

0c

CPS 4411.03

Injection/Flooding Sources

10d

CPS 4411.04

Throttling ECCS Flow

5d

OP-AA-201-009

Control of Transient Combustible Material

Work Orders

21410

9601.10A20 Visual Inspection Spray/Sprinkler System

(C00l)

08/21/2018

1858700

9071.09, FP CO2 System Auto Actuation (DIV I DG)

Detector Functional

03/19/2020

4987766

9071.19A20 OP Fire Protection Valve Lineup

(Safety-Related C00l)

07/03/2020