IR 05000483/2012004: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 92: | Line 92: | ||
-significant systems: Inspection Scope August 11, 2012, high pressure safety injection train A August 28, 2012, emergency diesel generator train A September 8, 2012, containment spray train B September 18, 2012, component cooling water pump B The inspectors selected these systems based on their risk significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors attempted to identify any discrepancies that could affect the function of the system, and, therefore, potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, Final Safety Analysis Report, technical specification requirements, administrative technical specifications, outstanding work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have rendered the systems incapable of performing their intended functions. The inspectors also inspected accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program with the appropriate significance characterization. Specific documents reviewed during thi s inspection are listed in Attachment 1. | -significant systems: Inspection Scope August 11, 2012, high pressure safety injection train A August 28, 2012, emergency diesel generator train A September 8, 2012, containment spray train B September 18, 2012, component cooling water pump B The inspectors selected these systems based on their risk significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors attempted to identify any discrepancies that could affect the function of the system, and, therefore, potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, Final Safety Analysis Report, technical specification requirements, administrative technical specifications, outstanding work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have rendered the systems incapable of performing their intended functions. The inspectors also inspected accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program with the appropriate significance characterization. Specific documents reviewed during thi s inspection are listed in Attachment 1. | ||
These activities constitute completion of four partial system walkdown samples a s defined in Inspection Procedu re 71111.04-05. | These activities constitute completion of four partial system walkdown samples a s defined in Inspection Procedu re | ||
==71111.04 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
Line 102: | Line 104: | ||
Quarterly Fire Inspection Tours a. The inspectors conducted fire protection walkdowns that were focused on availability, accessibility, and the condition of firefighting equipment in the following risk | Quarterly Fire Inspection Tours a. The inspectors conducted fire protection walkdowns that were focused on availability, accessibility, and the condition of firefighting equipment in the following risk | ||
-significant plant areas: | -significant plant areas: | ||
Inspection Scope July 8, 2012, turbine building during fire loop outage, fire area T-2 July 20, 2012, emergency exhaust equipment rooms trains A and B, fire areas F-6 and F-7 July 23, 2012, fire pump house during announced fire drill, fire area S-8 September 1, 2012, south electrical penetration room, fire area September 8, 2012, containment spray pump room train B, fire area A-4 B The inspectors reviewed areas to assess if licensee personnel had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant; effectively maintained fire detection and suppression capability; maintained passive fire protection features in good material condition; and had implemented adequate compensatory measures for out of service, degraded or inoperable fire protection equipment, systems, or features, in accordance with the licensee's fire plan. The inspectors selected fire areas based on their overall contribution to internal fire risk as documented in the plant's Individual Plant Examination of External Events with later additional insights, their potential to affect equipment that could initiate or mitigate a plant transient, or their impact on the plant's ability to respond to a security event. Using the documents listed in Attachment 1, the inspectors verified that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed; that transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issues identified during the inspection were entered into the licensee's corrective action program. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five quarterly fire-protection inspection sampl es as defined in Inspection Procedure 71111.05-05. | Inspection Scope July 8, 2012, turbine building during fire loop outage, fire area T-2 July 20, 2012, emergency exhaust equipment rooms trains A and B, fire areas F-6 and F-7 July 23, 2012, fire pump house during announced fire drill, fire area S-8 September 1, 2012, south electrical penetration room, fire area September 8, 2012, containment spray pump room train B, fire area A-4 B The inspectors reviewed areas to assess if licensee personnel had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant; effectively maintained fire detection and suppression capability; maintained passive fire protection features in good material condition; and had implemented adequate compensatory measures for out of service, degraded or inoperable fire protection equipment, systems, or features, in accordance with the licensee's fire plan. The inspectors selected fire areas based on their overall contribution to internal fire risk as documented in the plant's Individual Plant Examination of External Events with later additional insights, their potential to affect equipment that could initiate or mitigate a plant transient, or their impact on the plant's ability to respond to a security event. Using the documents listed in Attachment 1, the inspectors verified that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed; that transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issues identified during the inspection were entered into the licensee's corrective action program. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five quarterly fire-protection inspection sampl es as defined in Inspection Procedure | ||
==71111.05 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
Line 137: | Line 141: | ||
Implementing appropriate work practices Scoping of systems in accordance with 10 CFR 50.65(b) Characterizing system reliability issues for performance monitoring Charging unavailability for performance monitoring Trending key parameters for condition monitoring Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or | Implementing appropriate work practices Scoping of systems in accordance with 10 CFR 50.65(b) Characterizing system reliability issues for performance monitoring Charging unavailability for performance monitoring Trending key parameters for condition monitoring Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or | ||
-(a)(2) Verifying appropriate performance criteria for structures, systems, and components classified as having an adequate demonstration of performance through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as requiring the establishment of appropriate and adequate goals and corrective actions for systems classified as not having adequate performance, as described in 10 CFR 50.65(a)(1) | -(a)(2) Verifying appropriate performance criteria for structures, systems, and components classified as having an adequate demonstration of performance through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as requiring the establishment of appropriate and adequate goals and corrective actions for systems classified as not having adequate performance, as described in 10 CFR 50.65(a)(1) | ||
The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of two quarterly maintenance effectiveness sampl es as defined in Inspection Procedure 71111.12-05. b. No findings were identified. | The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of two quarterly maintenance effectiveness sampl es as defined in Inspection Procedure | ||
==71111.12 - 05.== | |||
b. No findings were identified. | |||
Findings | Findings | ||
Line 149: | Line 156: | ||
-related inverter NN14 failure and troubleshooting, Job 12003827 The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4) and that the assessments were accurate and complete. When licensee personnel performed emergent work, the inspectors verified that the licensee personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed the technical specification requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid and applicable requirements were met. Specific documents reviewed during this inspection are listed in Attachment 1. | -related inverter NN14 failure and troubleshooting, Job 12003827 The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4) and that the assessments were accurate and complete. When licensee personnel performed emergent work, the inspectors verified that the licensee personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed the technical specification requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid and applicable requirements were met. Specific documents reviewed during this inspection are listed in Attachment 1. | ||
These activities constitute completion of four maintenance risk assessments and emergent work control inspection sampl es as defined in Inspection Procedure 71111.13-05. b. No findings were identified. | These activities constitute completion of four maintenance risk assessments and emergent work control inspection sampl es as defined in Inspection Procedure | ||
==71111.13 - 05.== | |||
b. No findings were identified. | |||
Findings | Findings | ||
Line 159: | Line 169: | ||
-driven auxiliary feedwater pump trip throttle valve seat material qualification issue, Callaway Action Request 201204847 July 30, 2012, containment normal sump level erratic indication, Callaway Action Request 201205304 August 6, 2012, containment cooler B inlet temperature instrument failure, Callaway Action Request 201204954 August 8, 2012, containment spray pump A room door seal leak, Callaway Action Request 201205597 August 30, 2012, diesel generator A governor oil leak, Callaway Action Request 201201117 The inspectors selected these operability and functionality assessments based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the evaluations to ensure technical specification operability was properly justified and to verify the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the technical specifications | -driven auxiliary feedwater pump trip throttle valve seat material qualification issue, Callaway Action Request 201204847 July 30, 2012, containment normal sump level erratic indication, Callaway Action Request 201205304 August 6, 2012, containment cooler B inlet temperature instrument failure, Callaway Action Request 201204954 August 8, 2012, containment spray pump A room door seal leak, Callaway Action Request 201205597 August 30, 2012, diesel generator A governor oil leak, Callaway Action Request 201201117 The inspectors selected these operability and functionality assessments based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the evaluations to ensure technical specification operability was properly justified and to verify the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the technical specifications | ||
and Final Safety Analysis Report to the licensee's evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. Additionally, the inspectors reviewed a sampling of corrective action documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five operabilit y evaluations inspection samples as defined in Inspection Procedure 71111.15-05. | and Final Safety Analysis Report to the licensee's evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. Additionally, the inspectors reviewed a sampling of corrective action documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five operabilit y evaluations inspection samples as defined in Inspection Procedure | ||
==71111.15 - 05.== | |||
====b. Findings==== | ====b. Findings==== | ||
Line 193: | Line 205: | ||
===1. These activities constitute completion of=== | ===1. These activities constitute completion of=== | ||
one sample for plant modifications as defined in Inspection Procedure 71111.18-05. | one sample for plant modifications as defined in Inspection Procedure | ||
==71111.18 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
Line 208: | Line 222: | ||
The inspectors evaluated these activities for the following: The effect of testing on the plant had been adequately addressed; testing was adequate for the maintenance performed Acceptance criteria were clear and demonstrated operational readiness; test instrumentation was appropriate The inspectors evaluated the activities against the technical specifications, the Final Safety Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various NRC generic communications to ensure that the test results adequately ensured that the equipment met the licensing basis and design requirements. In addition, the inspectors reviewed corrective action documents associated with post | The inspectors evaluated these activities for the following: The effect of testing on the plant had been adequately addressed; testing was adequate for the maintenance performed Acceptance criteria were clear and demonstrated operational readiness; test instrumentation was appropriate The inspectors evaluated the activities against the technical specifications, the Final Safety Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various NRC generic communications to ensure that the test results adequately ensured that the equipment met the licensing basis and design requirements. In addition, the inspectors reviewed corrective action documents associated with post | ||
-maintenance tests to determine whether the licensee was identifying problems and entering them in the corrective action program and that the problems were being corrected commensurate with their importance to safety. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five post-maintenance testing inspection sampl es as defined in Inspection Procedure 71111.19-05. | -maintenance tests to determine whether the licensee was identifying problems and entering them in the corrective action program and that the problems were being corrected commensurate with their importance to safety. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five post-maintenance testing inspection sampl es as defined in Inspection Procedure | ||
==71111.19 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
Line 221: | Line 237: | ||
July 5, 2012, emergency diesel generator B fast start routine test, Job 12500704 July 12, 2012, alternate emergency power system diesel routine surveillance test, Job 12506361 July 17, 2012, emergency exhaust fan A routine surveillance test, Job 12506838 July 18, 2012, emergency fuel oil pump A routine surveillance test, Job 12504725 August 20, 2012, 120 volt safety | July 5, 2012, emergency diesel generator B fast start routine test, Job 12500704 July 12, 2012, alternate emergency power system diesel routine surveillance test, Job 12506361 July 17, 2012, emergency exhaust fan A routine surveillance test, Job 12506838 July 18, 2012, emergency fuel oil pump A routine surveillance test, Job 12504725 August 20, 2012, 120 volt safety | ||
-related inverter NN14 outage test, Job 12004372 September 24, 2012, shutdown purge system containment isolation verification, Job 12509180 Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of a total of six surveillance testing inspection samples, including one containment isolation and five routine surveillances | -related inverter NN14 outage test, Job 12004372 September 24, 2012, shutdown purge system containment isolation verification, Job 12509180 Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of a total of six surveillance testing inspection samples, including one containment isolation and five routine surveillances | ||
, as defined in Inspection Procedure 71111.22 | , as defined in Inspection Procedure | ||
-05. b. No findings were identified. | |||
==71111.22 - 05.== | |||
b. No findings were identified. | |||
Findings Cornerstone: Emergency Preparedness | Findings Cornerstone: Emergency Preparedness | ||
Line 234: | Line 252: | ||
"; and the licensee | "; and the licensee | ||
's current FEMA-approved alert and notification system design report, "Callaway Plant Alert and Notification System Design Report," | 's current FEMA-approved alert and notification system design report, "Callaway Plant Alert and Notification System Design Report," | ||
dated April 2011. The specific documents reviewe d during this inspection are listed in Attachment 1. Inspection Scope These activities constitute completion of one sample as defined in Inspection Procedure 71114.02-05. b. No findings were identified. | dated April 2011. The specific documents reviewe d during this inspection are listed in Attachment 1. Inspection Scope These activities constitute completion of one sample as defined in Inspection Procedure | ||
==71114.02 - 05.== | |||
b. No findings were identified. | |||
Findings | Findings | ||
Line 241: | Line 262: | ||
{{IP sample|IP=IP 71114.03}} | {{IP sample|IP=IP 71114.03}} | ||
a. The inspector s discussed with licensee staff the operability of primary and backup systems for augmenting the on | a. The inspector s discussed with licensee staff the operability of primary and backup systems for augmenting the on | ||
-shift emergency response staff to determine the adequacy of licensee methods for staffing emergency response facilities in accordance with their emergency plan and the requirements of 10 CFR Part 50, Appendix E. The inspector s also reviewed the licensee's methods to notify the emergency response organization to staff alternative response facilities as necessary, and licensee training on the primary and backup notification methods. The specific documents reviewed during this inspection are listed in Attachment 1. Inspection Scope These activities constitute completion of one sample as defined in Inspection Procedure 71114.03-05. b. No findings were identified. | -shift emergency response staff to determine the adequacy of licensee methods for staffing emergency response facilities in accordance with their emergency plan and the requirements of 10 CFR Part 50, Appendix E. The inspector s also reviewed the licensee's methods to notify the emergency response organization to staff alternative response facilities as necessary, and licensee training on the primary and backup notification methods. The specific documents reviewed during this inspection are listed in Attachment 1. Inspection Scope These activities constitute completion of one sample as defined in Inspection Procedure | ||
==71114.03 - 05.== | |||
b. No findings were identified. | |||
Findings | Findings | ||
Line 255: | Line 279: | ||
-site alternate Technical Support Center and Operations Support Center to determine the licensee's compliance with Appendix E to Part 50, Section IV.E(8)(c). | -site alternate Technical Support Center and Operations Support Center to determine the licensee's compliance with Appendix E to Part 50, Section IV.E(8)(c). | ||
The specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one sample as defined in Inspection Procedure 71114.05-05. | The specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one sample as defined in Inspection Procedure | ||
==71114.05 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
Line 264: | Line 290: | ||
===Cornerstone:=== | ===Cornerstone:=== | ||
Occupational and Public Radiation Safety 2RS 1 Radiological Hazard Assessment and Exposure Controls (71124.01)a. This area was inspected to: (1) review and assess licensee's performance in assessing the radiological hazards in the workplace associated with licensed activities and the implementation of appropriate radiation monitoring and exposure control measures for both individual and collective exposures, (2)verify the licensee is properly identifying and reporting Occupational Radiation Safety Cornerstone performance indicators, and (3) identify those performance deficiencies that were reportable under a performance indicator and which may have represented a substantial potential for overexposure of the worker. | Occupational and Public Radiation Safety 2RS 1 Radiological Hazard Assessment and Exposure Controls (71124.01)a. This area was inspected to: | ||
: (1) review and assess licensee's performance in assessing the radiological hazards in the workplace associated with licensed activities and the implementation of appropriate radiation monitoring and exposure control measures for both individual and collective exposures, (2)verify the licensee is properly identifying and reporting Occupational Radiation Safety Cornerstone performance indicators, and | |||
: (3) identify those performance deficiencies that were reportable under a performance indicator and which may have represented a substantial potential for overexposure of the worker. | |||
Inspection Scope The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed the radiation protection manager, radiation protection supervisors, and radiation workers. The inspectors performed walkdowns of various portions of the plant, performed independent radiation dose rate measurements and reviewed the following items: | Inspection Scope The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed the radiation protection manager, radiation protection supervisors, and radiation workers. The inspectors performed walkdowns of various portions of the plant, performed independent radiation dose rate measurements and reviewed the following items: | ||
Performance indicator events and associated documentation reported by the licensee in the Occupational Radiation Safety Cornerstone The hazard assessment program, including a review of the licensee's evaluations of changes in plant operations and radiological surveys to detect dose rates, airborne radioactivity, and surface contamination levels Instructions and notices to workers, including labeling or marking containers of radioactive material, radiation work permits, actions for electronic dosimeter alarms, and changes to radiological conditions Programs and processes for control of sealed sources and release of potentially contaminated material from the radiologically controlled area, including survey performance, instrument sensitivity, release criteria, procedural guidance, and sealed source accountability Radiological hazards control and work coverage, including the adequacy of surveys, radiation protection job coverage, and contamination controls; the use of electronic dosimeters in high noise areas; dosimetry placement; airborne radioactivity monitoring; controls for highly activated or contaminated materials (non-fuel) stored within spent fuel and other storage pools; and posting and physical controls for high radiation areas and very high radiation areas Radiation worker and radiation protection technician performance with respect to radiation protection work requirements Audits, self | Performance indicator events and associated documentation reported by the licensee in the Occupational Radiation Safety Cornerstone The hazard assessment program, including a review of the licensee's evaluations of changes in plant operations and radiological surveys to detect dose rates, airborne radioactivity, and surface contamination levels Instructions and notices to workers, including labeling or marking containers of radioactive material, radiation work permits, actions for electronic dosimeter alarms, and changes to radiological conditions Programs and processes for control of sealed sources and release of potentially contaminated material from the radiologically controlled area, including survey performance, instrument sensitivity, release criteria, procedural guidance, and sealed source accountability Radiological hazards control and work coverage, including the adequacy of surveys, radiation protection job coverage, and contamination controls; the use of electronic dosimeters in high noise areas; dosimetry placement; airborne radioactivity monitoring; controls for highly activated or contaminated materials (non-fuel) stored within spent fuel and other storage pools; and posting and physical controls for high radiation areas and very high radiation areas Radiation worker and radiation protection technician performance with respect to radiation protection work requirements Audits, self | ||
-assessments, and corrective action documents related to radiological hazard assessment and exposure controls since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspecti on Procedure 71124.01-05. b. | -assessments, and corrective action documents related to radiological hazard assessment and exposure controls since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspecti on Procedure | ||
==71124.01 - 05.== | |||
b. | |||
=====Introduction.===== | =====Introduction.===== | ||
Line 284: | Line 315: | ||
=====Analysis.===== | =====Analysis.===== | ||
The failure to follow radiation work permit instructions is a performance deficiency. The performance deficiency was more than minor because, if left uncorrected, the performance deficiency had the potential to lead to a more significant safety concern. Using the Occupational Radiation Safety Significance Determination Process, the inspectors determined the finding had very low safety significance because: | The failure to follow radiation work permit instructions is a performance deficiency. The performance deficiency was more than minor because, if left uncorrected, the performance deficiency had the potential to lead to a more significant safety concern. Using the Occupational Radiation Safety Significance Determination Process, the inspectors determined the finding had very low safety significance because: | ||
: (1) it was not an as low as is reasonably achievable finding, (2)there was no overexposure, (3)there was no substantial potential for an overexposure, and (4)the ability to assess dose was not compromised. This finding had a crosscutting aspect in the human performance area, work practices component, in that the worker failed to use error prevention techniques, such as self | |||
-checking. [H.4(a)]. | -checking. [H.4(a)]. | ||
Line 299: | Line 331: | ||
-specific trends in collective exposures, and source-term measurements ALARA work activity evaluations/postjob reviews, exposure estimates, and exposure mitigation requirements The methodology for estimating work activity exposures, the intended dose outcome, the accuracy of dose rate and man | -specific trends in collective exposures, and source-term measurements ALARA work activity evaluations/postjob reviews, exposure estimates, and exposure mitigation requirements The methodology for estimating work activity exposures, the intended dose outcome, the accuracy of dose rate and man | ||
-hour estimates, and intended versus actual work activity doses and the reasons for any inconsistencies Records detailing the historical trends and current status of tracked plant source terms and contingency plans for expected changes in the source term due to changes in plant fuel performance issues or changes in plant primary chemistry Radiation worker and radiation protection technician performance during work activities in radiation areas, airborne radioactivity areas, or high radiation areas Audits, self | -hour estimates, and intended versus actual work activity doses and the reasons for any inconsistencies Records detailing the historical trends and current status of tracked plant source terms and contingency plans for expected changes in the source term due to changes in plant fuel performance issues or changes in plant primary chemistry Radiation worker and radiation protection technician performance during work activities in radiation areas, airborne radioactivity areas, or high radiation areas Audits, self | ||
-assessments, and corrective action documents related to ALARA planning and controls since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspection Procedure 71124.02-05. b. No findings were identified. | -assessments, and corrective action documents related to ALARA planning and controls since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspection Procedure | ||
==71124.02 - 05.== | |||
b. No findings were identified. | |||
Findings 2RS 3 In-plant Airborne Radioactivity Control and Mitigation (71124.03)a. This area was inspected to verify in | Findings 2RS 3 In-plant Airborne Radioactivity Control and Mitigation (71124.03)a. This area was inspected to verify in | ||
Line 308: | Line 343: | ||
-assessments, and corrective action documents related to in-plant airborne radioactivity control and mitigation since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. | -assessments, and corrective action documents related to in-plant airborne radioactivity control and mitigation since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. | ||
These activities constitute completion of one sample as defined in Inspection Procedure 71124.03-05. b. No findings were identified. | These activities constitute completion of one sample as defined in Inspection Procedure | ||
==71124.03 - 05.== | |||
b. No findings were identified. | |||
Findings 2RS 4 Occupational Dose Assessment (71124.04) | Findings 2RS 4 Occupational Dose Assessment (71124.04) | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
This area was inspected to: | This area was inspected to: | ||
: (1) determine the accuracy and operability of personal monitoring equipment; (2)determine the accuracy and effectiveness of the licensee's methods for determining total effective dose equivalent; and (3)ensure occupational dose is appropriately monitored. The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items: | |||
External dosimetry accreditation, storage, issue, use, and processing of active and passive dosimeters The technical competency and adequacy of the licensee's internal dosimetry program Adequacy of the dosimetry program for special dosimetry situations such as declared pregnant workers, multiple dosimetry placement, and neutron dose assessment Audits, self | External dosimetry accreditation, storage, issue, use, and processing of active and passive dosimeters The technical competency and adequacy of the licensee's internal dosimetry program Adequacy of the dosimetry program for special dosimetry situations such as declared pregnant workers, multiple dosimetry placement, and neutron dose assessment Audits, self | ||
-assessments, and corrective action documents related to dose assessment since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspection Procedure 71124.04-05. b. No findings were identified. | -assessments, and corrective action documents related to dose assessment since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspection Procedure | ||
==71124.04 - 05.== | |||
b. No findings were identified. | |||
Findings | Findings | ||
Line 437: | Line 479: | ||
-up Inspection a. During a review of items entered in the licensee's corrective action program, the inspectors recognized a corrective action item documenting | -up Inspection a. During a review of items entered in the licensee's corrective action program, the inspectors recognized a corrective action item documenting | ||
: Inspection Scope alternate emergency power system diesel generator 1 inadvertent isolation, Callaway Action Request 201205208 conflicting guidance in the procedures directing the response to an abnormal condition of the safety | : Inspection Scope alternate emergency power system diesel generator 1 inadvertent isolation, Callaway Action Request 201205208 conflicting guidance in the procedures directing the response to an abnormal condition of the safety | ||
-related 120 volt inverters, Callaway Action Request 201205681 Th e s e activities constitute completion of two in-depth problem identification and resolution sample s as defined in Inspection Procedure 71152-05. b. No findings were identified. | -related 120 volt inverters, Callaway Action Request 201205681 Th e s e activities constitute completion of two in-depth problem identification and resolution sample s as defined in Inspection Procedure | ||
==71152 - 05.== | |||
b. No findings were identified. | |||
Findings | Findings | ||
Line 449: | Line 494: | ||
This activity constitutes completion of one operator workaround inspection sample as part of the annual in | This activity constitutes completion of one operator workaround inspection sample as part of the annual in | ||
-depth problem identification and resolution samples defined in Inspection Procedure 71152-05. b. No findings were identified. | -depth problem identification and resolution samples defined in Inspection Procedure | ||
==71152 - 05.== | |||
b. No findings were identified. | |||
Findings | Findings |
Revision as of 23:45, 17 September 2018
ML12311A097 | |
Person / Time | |
---|---|
Site: | Callaway |
Issue date: | 11/05/2012 |
From: | O'Keefe N F NRC/RGN-IV/DRP/RPB-B |
To: | Heflin A C Union Electric Co |
O'Keefe N F | |
References | |
IR-12-004 | |
Download: ML12311A097 (60) | |
Text
November 5, 2012
Mr. Adam C. Heflin, Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251
SUBJECT: CALLAWAY PLANT
- NRC INTEGRATED INSPECTION REPORT 05000483/2012004
Dear Mr. Heflin:
On September 25, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Callaway Plant.
The enclosed inspection report documents the inspection results which were discussed on September 27, 2012, with Mr. F. Diya, Vice President Nuclear Operations
, and other members of your staff.
The inspecti on examined activities conducted under your license as they relate to safety and compliance with the Commission
's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
One NRC-identified finding and one self-revealing finding of very low safety significance (Green) were identified during this inspection
. Both of these findings were determined to involve violations of NRC requirements. The NRC is treating these violation s as non-cited violation s (NCV s) consistent with Section 2.3.2 of the Enforcement Policy. If you disagree with a cross
-cutting aspect assignment in this report, or if you contest these non-cited violations , you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555
-0001; with copies to the Regional Administrator, Region I V , the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555
-0001; and the NRC Resident Inspector at the Callaway Plant.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is U N I T E D S T A T E S N U C L E A R R E G U L A T O R Y C O M M I S S I O N R E G I O N I V1600 EAST LAMAR BLVD A R L I N G T O N , T E X A S 7 6 0 1 1-4511 accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Sincerely,/RA/
Neil O'Keefe , Chief Project Branch B Division of Reactor Projects Docket No.: 50-483 License No: NPF-30
Enclosure:
Inspection Report 05000483 w/ Attachment 1: Supplemental Information Attachment 2: Request for Information for Occupational Radiation Safety Inspection
cc w/ encl: Electronic Distribution
SUMMARY OF FINDINGS
IR 05000483/2012004; 06/27 - 09/25/2012, Callaway Plant, Integrated
Resident and Regional Report; Operability Evaluations and Functionality Assessments and Radiological Hazard Assessment and Exposure Controls The report covered a 3
-month period of inspection by resident inspectors and announced baseline inspectio ns by region-based inspecto rs. Two Green non-cited violations of significance were identified. The significance of most findings is indicated by their color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, "Significance Determination Process." The cross-cutting aspect is determined using Inspection Manual Chapter 0310, "Components Within the Cross-Cutting Areas." Findings for which the significance determination process does not apply may be Green or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG
-1649, "Reactor Oversight Process," Revision 4, dated December 2006.
A. NRC-Identified Findings and Self-Revealing Findings
Cornerstone: Mitigating Systems
- Green.
The inspectors identified a non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Action," involving the licensee's failure to correct an adverse condition on a safety related system. Specifically, when a low oil condition was identified on an emergency diesel generator governor, the licensee fixed the symptom by adding oil, but failed to correct the condition by stopping the leak. This issue was entered into the licensee's corrective action program as Callaway Action Request 201206798. Failure to correct an adverse condition on a safety related system was a performance deficiency.
This finding was more than minor because it adversely affected the equipment performance attribute of the Mitigating Systems Cornerstone, and affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.
Using Manual Chapter 0609, Appendix A, Exhibit 2, "Mitigating Systems Screening Questions," the finding was determined to be of very low safety concern because it affected the qualification of a mitigating system, but the affected train was still able to meet its PRA mission time. This finding has a cross-cutting aspect in the area of Problem Identification and Resolution associated with the Corrective Action Program component because the licensee failed to thoroughly evaluate the problem such that the resolutions address causes including properly classifying, prioritizing, and evaluating for operability and reportability conditions adverse to quality
P.1(c). (Section 1R15)
Cornerstone: Occupational Radiation Safety
- Green.
The inspectors reviewed a self-revealing non-cited violation of Technical Specification 5.4.1.a, because a worker did not follow radiation work permit instructions. Specifically, an individual entered an area with radiation dose rates significantly higher than the areas on which he was briefed. As corrective action, the licensee coached the individual on the radiation work permit instructions and the licensee's expected radiation worker behavior. This was documented in the licensee's corrective action program as Callaway Action Request 201108483. The failure to follow radiation work permit instructions is a performance deficiency. The performance deficiency was more than minor because, if left uncorrected, the performance deficiency had the potential to lead to a more significant safety concern. Using the Occupational Radiation Safety Significanc e Determination Process, the inspectors determined the finding had very low safety significance because: (1)it was not an as low as is reasonably achievable finding, (2)there was no overexposure, (3)there was no substantial potential for an overexposure, and (4)the ability to assess dose was not compromised. This finding had a crosscutting aspect in the human performance area, work practices component, in that the worker failed to use error prevention techniques, such as self-checking H.4(a). (Section 2RS 1)
B. Licensee-Identified Violations
None
REPORT DETAILS
Summary of Plant Status
Callaway operated at 100 percent power for the duration of the inspection period with the exception of planned power reductions for routine surveillance testing.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R04 Equipment Alignment
Partial Walkdown a. The inspectors performed partial system walkdowns of the following risk
-significant systems: Inspection Scope August 11, 2012, high pressure safety injection train A August 28, 2012, emergency diesel generator train A September 8, 2012, containment spray train B September 18, 2012, component cooling water pump B The inspectors selected these systems based on their risk significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors attempted to identify any discrepancies that could affect the function of the system, and, therefore, potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, Final Safety Analysis Report, technical specification requirements, administrative technical specifications, outstanding work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have rendered the systems incapable of performing their intended functions. The inspectors also inspected accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program with the appropriate significance characterization. Specific documents reviewed during thi s inspection are listed in Attachment 1.
These activities constitute completion of four partial system walkdown samples a s defined in Inspection Procedu re
71111.04 - 05.
b. No findings were identified.
Findings
1R05 Fire Protection
Quarterly Fire Inspection Tours a. The inspectors conducted fire protection walkdowns that were focused on availability, accessibility, and the condition of firefighting equipment in the following risk
-significant plant areas:
Inspection Scope July 8, 2012, turbine building during fire loop outage, fire area T-2 July 20, 2012, emergency exhaust equipment rooms trains A and B, fire areas F-6 and F-7 July 23, 2012, fire pump house during announced fire drill, fire area S-8 September 1, 2012, south electrical penetration room, fire area September 8, 2012, containment spray pump room train B, fire area A-4 B The inspectors reviewed areas to assess if licensee personnel had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant; effectively maintained fire detection and suppression capability; maintained passive fire protection features in good material condition; and had implemented adequate compensatory measures for out of service, degraded or inoperable fire protection equipment, systems, or features, in accordance with the licensee's fire plan. The inspectors selected fire areas based on their overall contribution to internal fire risk as documented in the plant's Individual Plant Examination of External Events with later additional insights, their potential to affect equipment that could initiate or mitigate a plant transient, or their impact on the plant's ability to respond to a security event. Using the documents listed in Attachment 1, the inspectors verified that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed; that transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issues identified during the inspection were entered into the licensee's corrective action program. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five quarterly fire-protection inspection sampl es as defined in Inspection Procedure
71111.05 - 05.
b. No findings were identified.
Findings
1R11 Licensed Operator Requalification Program and Licensed Operator Performance
.1 a. Quarterly Review of Licensed Operator Requalification Program
On August 14, 2012, the inspectors observed a crew of licensed operators in the plant's simulator during requalification testing. The inspectors assessed the following areas:
Inspection Scope Licensed operator performance The ability of the licensee to administer the evaluations The modeling and performance of the control room simulator The quality of post
-scenario critiques Follow-up actions taken by the licensee for identified discrepancies Specific documents reviewed during this inspection are listed in Attachme nt 1. These activities constitute completion of one quarterly licensed operator requalification program sample as defined in Inspection Procedure 71111.11. b. No findings were identified.
Findings
.2 a. Quarterly Observation of Licensed Operator Performance
On August 8 and 11, 2012, the inspectors observed the performance of on
-shift licensed operators in the plant's main control room. At the time of the observations, the plant was in a period of heightened activity due to the evolutions listed below. The inspectors observed the operators' performance of the following activities:
Inspection Scope August 8, 2012, high pressure coolant injection system train A valve strokes, reactor coolant system subcooling monitor train A troubleshooting
, and alternate emergency power system testing August 11, 2012, reactor coolant system dilution and response to loss of interlock annunciator P-9 In addition, the inspectors assessed the operators' adherence to plant procedures, including Procedure ODP-ZZ-00001 , "Operations Department
- Code of Conduct
," and other operations department policies
. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one quarterly licensed
-operator performance sample as defined in Inspection Procedure 71111.11. b. No findings were identified.
Findings
1R12 Maintenance Effectiveness
a. The inspectors evaluated degraded performance issues involving the following risk significant systems:
Inspection Scope August 1, 2012, containment ventilation system August 9, 2012, review of periodic evaluation per 10 CFR 50.65a(3) The inspectors reviewed events such as where ineffective equipment maintenance has resulted in valid or invalid automatic actuations of engineered safeguards systems and independently verified the licensee's actions to address system performance or condition problems in terms of the following:
Implementing appropriate work practices Scoping of systems in accordance with 10 CFR 50.65(b) Characterizing system reliability issues for performance monitoring Charging unavailability for performance monitoring Trending key parameters for condition monitoring Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or
-(a)(2) Verifying appropriate performance criteria for structures, systems, and components classified as having an adequate demonstration of performance through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as requiring the establishment of appropriate and adequate goals and corrective actions for systems classified as not having adequate performance, as described in 10 CFR 50.65(a)(1)
The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of two quarterly maintenance effectiveness sampl es as defined in Inspection Procedure
71111.12 - 05.
b. No findings were identified.
Findings
1R13 Maintenance Risk Assessments and Emergent Work Control
a. The inspectors reviewed licensee personnel's evaluation and management of plant risk for the maintenance and emergent work activities affecting risk
-significant and safety
-related equipment listed below to verify that the appropriate risk assessments were performed prior to removing equipment for work:
Inspection Scope July 16, 2012, 120 volt non-safety inverter PN09 failure and troubleshooting, Job 12003592 July 17, 2012, work on train B reactor vessel level indication system (protected train work), Job 12003350 July 23, 2012, Yellow risk during train B pressurizer power operated relief valve block valve breaker maintenance, Job 07507305 August 13, 2012, 120 volt safety
-related inverter NN14 failure and troubleshooting, Job 12003827 The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4) and that the assessments were accurate and complete. When licensee personnel performed emergent work, the inspectors verified that the licensee personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed the technical specification requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid and applicable requirements were met. Specific documents reviewed during this inspection are listed in Attachment 1.
These activities constitute completion of four maintenance risk assessments and emergent work control inspection sampl es as defined in Inspection Procedure
71111.13 - 05.
b. No findings were identified.
Findings
1R15 Operability Evaluations and Functionality Assessments
a. The inspectors reviewed the following assessments:
Inspection Scope July 11, 2012, turbine
-driven auxiliary feedwater pump trip throttle valve seat material qualification issue, Callaway Action Request 201204847 July 30, 2012, containment normal sump level erratic indication, Callaway Action Request 201205304 August 6, 2012, containment cooler B inlet temperature instrument failure, Callaway Action Request 201204954 August 8, 2012, containment spray pump A room door seal leak, Callaway Action Request 201205597 August 30, 2012, diesel generator A governor oil leak, Callaway Action Request 201201117 The inspectors selected these operability and functionality assessments based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the evaluations to ensure technical specification operability was properly justified and to verify the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the technical specifications
and Final Safety Analysis Report to the licensee's evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. Additionally, the inspectors reviewed a sampling of corrective action documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five operabilit y evaluations inspection samples as defined in Inspection Procedure
71111.15 - 05.
b. Findings
Introduction
. The inspectors identified a Green non
-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Action," involving the licensee's failure to correct an adverse condition on a safety related system. Specifically, when a low oil condition was identified on an emergency diesel generator governor, the licensee fixed the symptom by adding oil, but failed to correct the condition by stopping the leak. Description . On February 3, 2012, while performing plant rounds, an operations technician identified a low oil level condition in the governor for emergency diesel generator A. The technician initiated Job 12000746 to add oil to the governor. Later that day, oil was added to the governor. On February 12, 2012, an operations technician again identified a low oil condition in the governor for emergency diesel generator A. The technician initiated Job 12000905 to add oil to the governor. Upon hearing that th e governor needed oil again within the short time frame, the system engineer initiated Callaway Action Request 201201117, performed a walkdown of the governor, and identified an oil leak coming from the drain of the governor. The oil leak was approximately one drop every five minutes. Job 12000924 was initiated to investigate and correct the leak. On February 14, 2012, the drain petcock valve was found to be slightly open.
The drain petcock valve was tightened closed and oil was again added to the governor. Subsequent observation noted no additional leakage or oil loss.
A review of the oil leak identified, at the rate of loss with the oil level at the bottom of the sight glass, the diesel generator would operate normally for 3.4 days with an additional 2.9 days of degraded operation. After 6.3 days, the governor would no longer support diesel operation. The mission time for the emergency diesel generator is 7 days.
The inspectors noted that when the licensee first identified the low oil condition, the diesel generator would not have been able to support the full mission time and should have been considered inoperable. Once oil was added, the diesel was able to operate for its designed mission time. However, since the adverse condition was not corrected, the oil level lowered again rendering the diesel generator inoperable a second time.
Analysis . The inspectors determined that the failure to correct an adverse condition on a safety related component was a performance deficiency. Specifically, when a low oil condition was identified on an emergency diesel generator, the licensee fixed the symptom by adding oil, but failed to correct the condition by stopping the leak. This finding is more than minor because it adversely affected the equipment performance attribute of the Mitigating Systems Cornerstone, and affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.
The inspectors evaluated the finding in accordance with Manual Chapter 0609, Appendix A, Exhibit 2 , "Mitigating Systems Screening Questions." The inspectors determined the finding was of very low safety significance (Green) because it affect ed the qualification of a mitigating system, but the affected train was still able to meet its PRA mission time. This finding has a cross
-cutting aspect in the area of Problem Identification and Resolution associated with the corrective action program component because the licensee failed to thoroughly evaluate the problem such that the resolutions address causes and extent of conditions, as necessary including properly classifying, prioritizing, and evaluating for operability and reportability conditions adverse to quality
P.1(c). Enforcement
. Title 10 of the Code of Federal Regulations Part 50, Appendix B, Criterion XVI, "Corrective Action," requires, in part, that measures shall be established to assure that conditions adverse to quality are promptly identified and corrected. Contrary to this, on February 3, 2012, the licensee did not correct an adverse condition on a safety related system. Specifically, when a low oil condition was identified on an emergency diesel generator, the licensee fixed the symptom by adding oil, but failed to correct the condition by stopping the leak. This caused the emergency diesel generator to become inoperable again due to inability to support the full mission time.
Because this violation was of very low safety significance and was entered into the licensee's corrective action program as Callaway Action Request 201206798, this violation is being treated as a non
-cited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy: NCV 05000483/2012004
-01, "Failure to Correct an Adverse Condition on an Emergency Diesel Generator
."
1R18 Plant Modifications
a. Permanent Modifications The inspectors reviewed key parameters associated with, materials, replacement components, timing, equipment protection from hazards, operations, flow paths, pressure boundary, ventilation boundary, process medium properties, licensing basis, and failure modes for the permanent modification identified as MP 12-0019, "I nstall Isolation Valves for the Circulation and Service Hydraulic Pump C ," associated with the circulating water isolation valve hydraulic system
. Inspection Scope
The inspectors verified that modification preparation, staging, and implementation did not impair emergency/abnormal operating procedure actions, key safety functions, or operator response to loss of key safety functions; post modification testing will maintain the plant in a safe configuration during testing by verifying that unintended system interactions will not occur; systems, structures and components' performance characteristics still meet the design basis; the modification design assumptions were appropriate; the modification test acceptance criteria will be met; and licensee personnel identified and implemented appropriate corrective actions associated with permanent plant modifications. Specific documents reviewed during this inspection are listed in
1. These activities constitute completion of
one sample for plant modifications as defined in Inspection Procedure
71111.18 - 05.
b. No findings were identified.
Findings
1R19 Post-Maintenance Testing
a. The inspectors reviewed the following post
-maintenance activities to verify that procedures and test activities were adequate to ensure system operability and functional capability:
Inspection Scope July 11, 2012, safety injection pump train A post-maintenance test, Job 1051509 August 1, 2012, ultimate heat sink electrical room lighting breaker change, Job 07509139 August 13, 2012, 120 volt safety
-related inverter NN14 logic card replacement, Job 12003827 August 20, 2012, 120 volt safety
-related inverter NN14 component replacement, Job 12004372 August 24, 2012, reactor vessel level indication system train B, Job 12003350 The inspectors selected these activities based upon the structure, system, or component's ability to affect risk.
The inspectors evaluated these activities for the following: The effect of testing on the plant had been adequately addressed; testing was adequate for the maintenance performed Acceptance criteria were clear and demonstrated operational readiness; test instrumentation was appropriate The inspectors evaluated the activities against the technical specifications, the Final Safety Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various NRC generic communications to ensure that the test results adequately ensured that the equipment met the licensing basis and design requirements. In addition, the inspectors reviewed corrective action documents associated with post
-maintenance tests to determine whether the licensee was identifying problems and entering them in the corrective action program and that the problems were being corrected commensurate with their importance to safety. Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of five post-maintenance testing inspection sampl es as defined in Inspection Procedure
71111.19 - 05.
b. No findings were identified.
Findings
1R22 Surveillance Testing
a. The inspectors reviewed the Final Safety Analysis Report, procedure requirements, and technical specifications to ensure that the surveillance activities listed below demonstrated that the systems, structures, and/or components tested were capable of performing their intended safety functions. The inspectors either witnessed or reviewed test data to verify that the significant surveillance test attributes were adequate to address the following:
Inspection Scope Preconditioning Evaluation of testing impact on the plant Acceptance criteria Test equipment Procedures Test data Testing frequency and method demonstrated technical specification operability Test equipment removal Restoration of plant systems Fulfillment of ASME Code requirements Reference setting data Annunciators and alarms setpoints The inspectors also verified that licensee personnel identified and implemented any needed corrective actions associated with the surveillance testing.
July 5, 2012, emergency diesel generator B fast start routine test, Job 12500704 July 12, 2012, alternate emergency power system diesel routine surveillance test, Job 12506361 July 17, 2012, emergency exhaust fan A routine surveillance test, Job 12506838 July 18, 2012, emergency fuel oil pump A routine surveillance test, Job 12504725 August 20, 2012, 120 volt safety
-related inverter NN14 outage test, Job 12004372 September 24, 2012, shutdown purge system containment isolation verification, Job 12509180 Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of a total of six surveillance testing inspection samples, including one containment isolation and five routine surveillances
, as defined in Inspection Procedure
71111.22 - 05.
b. No findings were identified.
Findings Cornerstone: Emergency Preparedness
1EP2 Alert and Notification System Evaluation
a. The inspectors discussed with licensee staff the operability of offsite siren emergency warning systems , tone alert radio systems, and backup notification and alerting methods, to determine the adequacy of licensee methods for testing the alert and notification system in accordance with 10 CFR Part 50, Appendix E. The licensee
's alert and notification system testing program was compared with criteria in NUREG
-0654, "Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants," Revision 1; Federal Emergency Management Agency (FEMA) Report REP
-10, "Guide for the Evaluation of Alert and Notification Systems for Nuclear Power Plants
"; and the licensee
's current FEMA-approved alert and notification system design report, "Callaway Plant Alert and Notification System Design Report,"
dated April 2011. The specific documents reviewe d during this inspection are listed in Attachment 1. Inspection Scope These activities constitute completion of one sample as defined in Inspection Procedure
71114.02 - 05.
b. No findings were identified.
Findings
1EP3 Emergency Response Organization Staffing and Augmentation System
a. The inspector s discussed with licensee staff the operability of primary and backup systems for augmenting the on
-shift emergency response staff to determine the adequacy of licensee methods for staffing emergency response facilities in accordance with their emergency plan and the requirements of 10 CFR Part 50, Appendix E. The inspector s also reviewed the licensee's methods to notify the emergency response organization to staff alternative response facilities as necessary, and licensee training on the primary and backup notification methods. The specific documents reviewed during this inspection are listed in Attachment 1. Inspection Scope These activities constitute completion of one sample as defined in Inspection Procedure
71114.03 - 05.
b. No findings were identified.
Findings
1EP5 Maintenance of Emergency Preparedness
a. The inspector s reviewed the following documents originated between June 2010 and September 2012: Inspection Scope The licensee's corrective action program requirements described in Procedure APA-ZZ-00500 , "Corrective Action Program," Revision 54 The licensee's program requirements for preparing event after
-action reports described in Procedure EIP-ZZ-00260, "Event Closeout/Plant Recovery ," Revision 23 The licensee's program requirements for making changes to the site emergency plan and implementing procedures as described in Procedure KDP-ZZ-00400 , "RERP Impact Evaluations and Changes," Revisi on 19 The licensee's program requirements for the protection of onsite workers during hostile actions as described in Procedures OTO-SK-00002 "Plant Security Event, Aircraft Threat," Revision 15, and EIP
-ZZ-SK001, "Response to Security Events," Revision 8 The licensee's program requirements for maintaining emergency preparedness facilities and equipment as described in Procedure KDP-ZZ-00013, "Emergency Response Facility and Equipment Evaluation," Revision Summaries of 164 corrective action program entries assigned to the emergency preparedness department and emergency response organization After-a ction reports for events on April 13, 2010, and September 18, 2011 Quality Assurance reports, assessments, and audits Program assessments Dril l evaluation reports The inspector s evaluated response s to the corrective action program requests, audits, and assessments, to determine the licensee
's ability to identify, evaluate, and correct problems in accordance with the licensee program requirements, planning standard 10 CFR 50.47(b)(14), and 10 CFR Part 50, Appendix E. The inspector s selected 26 corrective action program entries for detailed review against the program requirements.
The inspector s also toured the near
-site alternate Technical Support Center and Operations Support Center to determine the licensee's compliance with Appendix E to Part 50,Section IV.E(8)(c).
The specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one sample as defined in Inspection Procedure
71114.05 - 05.
b. No findings were identified.
Findings
RADIATION SAFETY
Cornerstone:
Occupational and Public Radiation Safety 2RS 1 Radiological Hazard Assessment and Exposure Controls (71124.01)a. This area was inspected to:
- (1) review and assess licensee's performance in assessing the radiological hazards in the workplace associated with licensed activities and the implementation of appropriate radiation monitoring and exposure control measures for both individual and collective exposures, (2)verify the licensee is properly identifying and reporting Occupational Radiation Safety Cornerstone performance indicators, and
- (3) identify those performance deficiencies that were reportable under a performance indicator and which may have represented a substantial potential for overexposure of the worker.
Inspection Scope The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed the radiation protection manager, radiation protection supervisors, and radiation workers. The inspectors performed walkdowns of various portions of the plant, performed independent radiation dose rate measurements and reviewed the following items:
Performance indicator events and associated documentation reported by the licensee in the Occupational Radiation Safety Cornerstone The hazard assessment program, including a review of the licensee's evaluations of changes in plant operations and radiological surveys to detect dose rates, airborne radioactivity, and surface contamination levels Instructions and notices to workers, including labeling or marking containers of radioactive material, radiation work permits, actions for electronic dosimeter alarms, and changes to radiological conditions Programs and processes for control of sealed sources and release of potentially contaminated material from the radiologically controlled area, including survey performance, instrument sensitivity, release criteria, procedural guidance, and sealed source accountability Radiological hazards control and work coverage, including the adequacy of surveys, radiation protection job coverage, and contamination controls; the use of electronic dosimeters in high noise areas; dosimetry placement; airborne radioactivity monitoring; controls for highly activated or contaminated materials (non-fuel) stored within spent fuel and other storage pools; and posting and physical controls for high radiation areas and very high radiation areas Radiation worker and radiation protection technician performance with respect to radiation protection work requirements Audits, self
-assessments, and corrective action documents related to radiological hazard assessment and exposure controls since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspecti on Procedure
71124.01 - 05.
b.
Introduction.
The inspectors reviewed a Green, self
-revealing non
-cited violation of Technical Specification 5.4.1.a because a worker did not follow radiation work permit instructions.
Findings Description
. On October 17, 2011, the licensee was alerted by an electronic dosimeter dose rate alarm to a situation that involved an instrumentation and controls technician installing cameras that would be used during valve work, inside the bioshield. The individual worked in accor dance with Radiation Work Permit 191001HRA and was briefed on work area dose rates up to, but not exceeding, the dose rate alarm setpoint o f his electronic dosimeter (150 millirem/hour). Without contacting radiation protection personnel as required by the radiation work permit, the instrumentation and controls technician climbed to areas higher than 8 feet above the floor level and entered into an area with a dose rate of 263 millirem/hour, which was significantly greater than that on which the technician was briefed.
The licensee investigated the circumstances that led to the individual receiving the dose rate alarm. They determined the individual had fo c used on locating the valve on which work was to be done.
However, the individual did not perform an adequate "two
-minute drill" to help himself assess the surroundings and recall the requirements of the radiation work permit. The individual was coached on the radiation work permit instructions and the licensee's expected behavior.
Analysis.
The failure to follow radiation work permit instructions is a performance deficiency. The performance deficiency was more than minor because, if left uncorrected, the performance deficiency had the potential to lead to a more significant safety concern. Using the Occupational Radiation Safety Significance Determination Process, the inspectors determined the finding had very low safety significance because:
- (1) it was not an as low as is reasonably achievable finding, (2)there was no overexposure, (3)there was no substantial potential for an overexposure, and (4)the ability to assess dose was not compromised. This finding had a crosscutting aspect in the human performance area, work practices component, in that the worker failed to use error prevention techniques, such as self
-checking. H.4(a).
Enforcement.
Technical Specification 5.4.1.a required procedures be established, implemented, and maintained covering activities specified in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Section 7.e.(1) of the regulatory guide required procedures for access control to radiation areas including a radiation work permit system. Procedure APA-ZZ-01004, "Radiological Work Standards," Revision 21, Step, 4.3.1.a.3 require d individuals working in the radiological controlled area ensure they adhere to the instructions on radiation work permits. Radiation Work Permit 191001HRA instructed workers to contact radiation protection personnel prior to accessing areas greater than 8 feet above floors or work platforms. Contrary to this, on October 17, 2011, the licensee failed to implement a procedure required by Technical Specification 5.4.1.a and Regulatory Guide 1.33 when a licensee worker did not adhere to the instructions on a radiation work permit. Specifically, an instrumentation and controls technician did not contact radiation protection personnel prior to accessing areas greater than 8 feet above the floor and entering into a dose rate of 263 millirem/hour. As corrective action, the licensee coached the individual on the radiation work permit instructions and the licensee's expected radiation worker behavior.
Because this violation is of very low safety significance and has been entered into the licensee's corrective action program as Callaway Action Request 2 01108483, it is being treated as a non
-cited violation, consistent with Section 2.3.2 of the NRC Enforcement Policy: NCV 5000483/2012004
-02 , "Failure to Follow Radiation Work Permit Instructions.
"
2RS 2 Occupational ALARA Planning and Controls (71124.02)a. This area was inspected to assess performance with respect to maintaining occupational individual and collective radiation exposures as low as is reasonably achievable (ALARA). The inspectors used the requirements in 10 CFR Part 20, th e technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed licensee personnel and reviewed the following items:
Inspection Scope Site-specific ALARA procedures and collective exposure history, including the current 3-year rolling average, site
-specific trends in collective exposures, and source-term measurements ALARA work activity evaluations/postjob reviews, exposure estimates, and exposure mitigation requirements The methodology for estimating work activity exposures, the intended dose outcome, the accuracy of dose rate and man
-hour estimates, and intended versus actual work activity doses and the reasons for any inconsistencies Records detailing the historical trends and current status of tracked plant source terms and contingency plans for expected changes in the source term due to changes in plant fuel performance issues or changes in plant primary chemistry Radiation worker and radiation protection technician performance during work activities in radiation areas, airborne radioactivity areas, or high radiation areas Audits, self
-assessments, and corrective action documents related to ALARA planning and controls since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspection Procedure
71124.02 - 05.
b. No findings were identified.
Findings 2RS 3 In-plant Airborne Radioactivity Control and Mitigation (71124.03)a. This area was inspected to verify in
-plant airborne concentrations are being controlled consistent with ALARA principles and the use of respiratory protection devices on
-site do es not pose an undue risk to the wearer. The inspectors used the requirements in Inspection Scope 10 CFR Part 20, the technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items:
The licensee's use, when applicable, of ventilation systems as part of its engineering controls The licensee's respiratory protection program for use, storage, maintenance, and quality assurance of National Institute for Occupational Safety and Health certified equipment, qualification and training of personnel, and user performance The licensee
's capability for refilling and transporting self-contained breathing apparatus air bottles to and from the control room and operations support center during emergency conditions, status of self-contained breathing apparatus staged and ready for use in the plant and associated surveillance records, and personnel qualification and training Audits, self
-assessments, and corrective action documents related to in-plant airborne radioactivity control and mitigation since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1.
These activities constitute completion of one sample as defined in Inspection Procedure
71124.03 - 05.
b. No findings were identified.
Findings 2RS 4 Occupational Dose Assessment (71124.04)
a. Inspection Scope
This area was inspected to:
- (1) determine the accuracy and operability of personal monitoring equipment; (2)determine the accuracy and effectiveness of the licensee's methods for determining total effective dose equivalent; and (3)ensure occupational dose is appropriately monitored. The inspectors used the requirements in 10 CFR Part 20, the technical specifications, and the licensee's procedures required by technical specifications as criteria for determining compliance. During the inspection, the inspectors interviewed licensee personnel, performed walkdowns of various portions of the plant, and reviewed the following items:
External dosimetry accreditation, storage, issue, use, and processing of active and passive dosimeters The technical competency and adequacy of the licensee's internal dosimetry program Adequacy of the dosimetry program for special dosimetry situations such as declared pregnant workers, multiple dosimetry placement, and neutron dose assessment Audits, self
-assessments, and corrective action documents related to dose assessment since the last inspection Specific documents reviewed during this inspection are listed in Attachment 1. These activities constitute completion of one required sample as defined in Inspection Procedure
71124.04 - 05.
b. No findings were identified.
Findings
OTHER ACTIVITIES
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Occupational Radiation Safety, Public Radiation Safety, and Security
4OA1 Performance Indicator Verification
.1 Data Submission Issue
a. The inspectors performed a review of the performance indicator data submitted by the licensee for the second quarter 20 12 performance indicators for any obvious inconsistencies prior to its public release in accordance with Inspection Manual Chapter 0608, "Performance Indicator Program."
Inspection Scope This review was performed as part of the inspectors' normal plant status activities and, as such, did not constitute a separate inspection sample.
b. No findings were identified.
Findings
.2 Unplanned Scrams per 7000 Critical Hours (IE01)
a. The inspectors sampled licensee submittals for the unplanned scrams per 7000 critical hours performance for the period from the third quarter 20 11 through the second quarter 20 12. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in Nuclear Energy Institute (NEI) Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6. The inspectors reviewed the licensee's operator narrative logs, issue reports, event reports, and NRC integrated inspection reports for the period of July 2011 through June 2012 to validate the accuracy of the submittals. The inspectors also reviewed the licensee's issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in
1. Inspection Scope
These activities constitute completion of one unplanned scrams per 7000 critical hours sample as defined in Inspection Procedure 71151-05. b. No findings were identified.
Findings
.3 Unplanned Power Changes per 7000 Critical Hours (IE03)
a. The inspectors sampled licensee submittals for the unplanned power changes per 7000 critical hours performance for the period from third quarter 2011 through the second quarter 2012. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6. The inspectors reviewed the licensee's operator narrative logs, issue reports, maintenance rule records, event reports, and NRC integrated inspection reports for the period of July 2011 through June 2012 to validate the accuracy of the submittals. The inspectors also reviewed the licensee's issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified
. Specific documents reviewed are described in Attachment 1. Inspection Scope These activities constitute completion of one unplann ed power changes per 7 000 critical hours sample as defined in Inspection Procedure 71151-05.
b. No findings were identified.
Findings
.4 Unplanned Scrams with Complications (IE04)
a. The inspectors sampled licensee submittals for the unplanned scrams with complications performance indicator for the period from the third quarter 2011 through the second quarter 2012. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6. The inspectors reviewed the licensee's operator narrative logs, issue reports, event reports, and NRC integrated inspection reports for the period July 2011 through June 2012 to validate the accuracy of the submittals. The inspectors also reviewed the licensee's issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in Attachment 1. Inspection Scope These activities constitute completion of one unplanned scrams with complications sample as defined in Inspection Procedure 71151-05.
b. No findings were identified.
Findings
.5 Drill/Exercise Performance (EP01)
a. The inspector s sampled licensee submittals for the Drill and Exercise Performance, performance indicator for the period April 2011 through June 2012. The performance indicator definitions and guidance in NEI Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, were used determine the accuracy of the reported performance indicator data. The inspector s reviewed the licensee's records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance and site Procedure KDP-ZZ-02000, "NRC Performance Indicator Data Collection," Revision 14. The inspector s reviewed licensee records of performance indicator opportunities during predesignated control room simulator training sessions, the 2011 biennial exercise, and other drills. The specific documents reviewed are described in Attachment 1. Inspection Scope These activities constitute completion of one drill/exercise performance sample as defined in Inspection Procedure 71151-05. b. No findings were identified.
Findings
.6 Emergency Response Organization Drill Participation (EP02)
a. The inspector s sampled licensee submittals for the Drill and Exercise Performance, performance indicator for the period April 2011 through June 2012. The performance indicator definitions and guidance in Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, were used determine the accuracy of the reported performance indicator data. The inspector s reviewed the licensee's records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance and site Procedure KDP-ZZ-02000, "NRC Performance Indicator Data Collection," Revision 14. The inspector s reviewed licensee records of drill and exercise participation opportunities for key emergency response organization personnel, organization rosters, and exercise participation records. The specific documents reviewed are described in Attachment 1. Inspection Scope
These activities constitute completion of one emergency response organization drill participation sample as defined in Inspection Procedure 71151-05. b. No findings were identified.
Findings
.7 Alert and Notification System (EP03)
a. The inspector s sampled licensee submittals for the Drill and Exercise Performance, performance indicator for the period April 2011 through June 2012. The performance indicator definitions and guidance in Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, were used determine the accuracy of the reported performance indicator data. The inspector s reviewed the licensee's records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the Nuclear Energy Institute guidance and site Procedure KDP-ZZ-02000, "NRC Performance Indicator Data Collection," Revision 14. Specifically, the inspector s reviewed licensee records and processes
, including procedural guidance for assessing opportunities for the performance indicator
, and the results of periodic alert notification system operability tests. The specific documents reviewed are described in
1. Inspection Scope
These activities constitute completion of one alert and notification system sample as defined in Inspection Procedure 71151-05. b. No findings were identified.
Findings
.8 Occupational Exposure Control Effectiveness (OR01)
a. The inspectors reviewed performance indicator data for the fourth quarter 2011 through the second quarter 2012. The objective of the inspection was to determine the accuracy and completeness of the performance indicator data reported during these periods. The inspectors used the definitions and clarifying notes contained in NEI Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, as criteria for determining whether the licensee was in compliance.
Inspection Scope The inspectors reviewed corrective action program records associated with high radiation area (greater than 1 rem/hr) and very high radiation area non
-conformances. The inspectors reviewed radiological, controlled area exit transactions greater than 100 mrem. The inspectors also conducted walkdowns of high radiation areas (greater than 1 rem/hr) and very high radiation area entrances to determine the adequacy of the controls of these areas.
These activities constitute completion of one occupational exposure control effectiveness sample as defined in Inspection Procedure 71151-05.
b. No findings were identified.
Findings
.9 Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (PR01)
a. The inspectors reviewed performance indicator data for the fourth quarter 2011 through the second quarter 2012. The objective of the inspection was to determine the accuracy and completeness of the performance indicator data reported during these periods. The inspectors used the definitions and clarifying notes contained in NEI Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, as criteria for determining whether the licensee was in compliance.
Inspection Scope The inspectors reviewed the licensee's corrective action program records and selected individual annual or special reports to identify potential occurrences such as unmonitored, uncontrolled, or improperly calculated effluent releases that may have impacted offsite dose.
These activities constitute completion of one radiological effluent technical specifications/offsite dose calculation manual radiological effluent occurrences sample as defined in Inspection Procedure 71151-05.
b. No findings were identified.
Findings
4OA2 Problem Identification and Resolution
.1 Routine Review of Identification and Resolution of Problems
a. As part of the various baseline inspection procedures discussed in previous sections of this report, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that they were being entered into the licensee's corrective action program at an appropriate threshold, that adequate attention was being given to timely corrective actions, and that adverse trends were identified and addressed. The inspectors reviewed attributes that included the complete and accurate identification of the problem; the timely correction, commensurate with the safety significance; the evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent of condition reviews, and previous occurrences reviews; and the classification, prioritization, focus, and timeliness of corrective actions. Minor issues entered into the licensee's corrective action program because of the inspectors' observations are included in the list of documents reviewed in Attachment 1. Inspection Scope These routine reviews for the identification and resolution of problems did not constitute any additional inspection samples. Instead, by procedure, they were considered an integral part of the inspections performed during the quarter and documented in Section 1 of this report.
b. No findings were identified.
Findings
.2 Daily Corrective Action Program Reviews
a. In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow
-up, the inspectors performed a daily screening of items entered into the licensee's corrective action program. The inspectors accomplished this through review of the station's daily corrective action documents.
Inspection Scope The inspectors performed these daily reviews as part of their daily plant status monitoring activities and, as such, did not constitute any separate inspection samples.
b. No findings were identified.
Findings
.3 Selected Issue Follow
-up Inspection a. During a review of items entered in the licensee's corrective action program, the inspectors recognized a corrective action item documenting
- Inspection Scope alternate emergency power system diesel generator 1 inadvertent isolation, Callaway Action Request 201205208 conflicting guidance in the procedures directing the response to an abnormal condition of the safety
-related 120 volt inverters, Callaway Action Request 201205681 Th e s e activities constitute completion of two in-depth problem identification and resolution sample s as defined in Inspection Procedure
71152 - 05.
b. No findings were identified.
Findings
.4 In-depth Review of Operator Workarounds
a. The inspectors evaluated the licensee's implementation of their process used to identify, document, track, and resolve operational challenges. Inspection activities included, but were not limited to, a review of the cumulative effects of the operator workarounds on system availability and the potential for improper operation of the system, for potential impacts on multiple systems, and on the ability of operators to respond to plant transients or accidents.
Inspection Scope The inspectors performed a review of the cumulative effects of operator workarounds. The documents listed in A ttachment 1 were reviewed to accomplish the objectives of the inspection procedure. The inspectors reviewed both current and historical operational challenge records to determine whether the licensee was identifying operator challenges at an appropriate threshold, had entered them into their corrective action program, and proposed or implemented appropriate and timely corrective actions that addressed each issue. Reviews were conducted to determine if any operator challenge could increase the possibility of an initiating event, if the challenge was contrary to training, required a change from long
-standing operational practices, or created the potential for inappropriate compensatory actions. Additionally, all temporary modifications were reviewed to identify any potential effect on the functionality of mitigating systems, impaired access to equipment, or required equipment uses for which the equipment was not designed. Daily plant and equipment status logs, degraded instrument logs, and operator aids or tools being used to compensate for material deficiencies were also assessed to identify any potential sources of unidentified operator workarounds.
This activity constitutes completion of one operator workaround inspection sample as part of the annual in
-depth problem identification and resolution samples defined in Inspection Procedure
71152 - 05.
b. No findings were identified.
Findings
4OA3 Follow-up of Events and Notices of Enforcement Discretion
Inverter NN14 Notice of Enforcement Discretion Introduction
. On August 19, 2012, safety
-related inverter NN14 failed. After determining the cause of the failure, the length of time to repair, test, and return to service; the licensee requested enforcement discretion since activities would extend beyond the allowed outage time specified in technical specifications. An unresolved item was identified to assess whether the cause for the noncompliance
, for which a Notice of Enforcement Discretion was granted
, involved a violation.
Description
. On July 27 and August 13, 2012 , safety relat ed inverter NN14 auto-transferred to the backup source. The licensee entered Technical Specification 3.8.7, Action A.1, which required returning the inverter to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or place the plant in Mode 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and Mode 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Troubleshooting effort s concluded that the most likely cause for the inadvertent auto
-transfer was a degraded card associated with the automatic static transfer switch.
This card was replaced along with successful completion of post
-maintenance testing.
On August 19, 2012, inverter NN14 failed again. The licensee entered Technical Specification 3.8.7, Action A.1. Troubleshooting revealed that the constant-voltage transformer phase B secondary windings were shorted to ground.
The most probable cause of the short was determined to be degradation of the transformer windings/insulation.
In consultation with the vendor, the licensee determined that following replacement of the transformer, post
-maintenance testing and temperature/voltage stabilization would exceed the time allowed by technical specifications.
Therefore, the licensee contacted the NRC on August 20, 2012, to request enforcement discretion to extend the allowed outage time of Technical Specificati on 3.8.7, Action A.1 , for an additional 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> (a total of 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br />). The NRC staff evaluated the information provided by the licensee and granted Notice of Enforcement Discretion 12-4-002 (ADAMS ML12237A010)
. An unresolved item was identified to assess whether the cause for the noncompliance
, for which a Notice of Enforcement Discretion was granted
, involved a violation URI 05000483/2012004-03, "Review Cause of the Failure of Inverter NN14."
4OA5 Other Activities
(Closed) Temporary Instruction 2515/185, Follow-up on the Industry's Ground Water Protection Initiative
a. Inspection Scope
An NRC follow-up assessment of the licensee's ground water protection program was performed the week of August 27, 2012. This review was to determine whether the licensee had implemented program elements that were identified as incomplete during the NRC's inspection of Temporary Instruction on Groundwater Protection, TI
-2515/173, "Industry Groundwater Protection Initiative," on June 22, 2009. Inspectors interviewed personnel, performed walkdowns of selected areas, and reviewed the implementation of the program elements listed below.
b. Findings
The following elements had been implemented since the previous review:
Element 1.1a
- Perform hydrogeologic studies to determine predominant ground water flow characteristics and gradients
.
Element 1.1 b
- Review existing hydrogeologic and geologic studies, historical environmental studies and permit or license
-related reports
.
Element 1.1 c
- Identify potential pathways for ground water migration from on
-site locations to off
-site locations through ground water
.
Element 1.1d
- Establish the frequency for periodic reviews of site hydrogeologic studies.
Element 1.2.c
- Identify potential enhancements to leak detection systems or programs.
These may include additional or increased frequency of rounds or walkdowns or inspections, or integrity testing.
Element 1.2d
- Identify potential enhancements to prevent spills or leaks from reaching ground water.
Element 1.2f
- Establish long
-term programs to perform preventative maintenance or surveillance activities to minimize the potential for inadvertent releases of licensed materials due to equipment failure.
Element 1.2g
- Establish the frequency for periodic reviews of systems, structures, and components and work practices.
Element 1.3.b
- Consider, as appropriate, placing sentinel wells closer to structures, systems
, and components that have the highest potential for inadvertent releases that could reach ground water or structures, systems, and components where leak detection capability is limited.
Element 1.3d
- Establish a formal, written program for long
-term ground water monitoring. For those ground water monitoring locations that are included in the REMP, revise the site's Offsite Dose Calculation Manual.
Element 1.3f
- Establish a long
-term program for preventative maintenance of ground water wells.
Element 1.4a
- Establish written procedures outlining the decision making process for remediation of leaks and spills or other instances of inadvertent releases.
Element 1.4b
- Evaluate the potential for detectible levels of licensed material resulting from planned releases of liquids and/or airborne materials.
Element 1.4c
- Evaluate and document, as appropriate, decommissioning impacts resulting from remediation activities or the absence thereof
.
All elements were verified as complete.
No findings were identified.
4OA6 Meetings, Including Exit
Exit Meeting Summary
On August 30, 2012, the inspectors presented the results of the radiation safety inspections to Mr. L. Graessle, Director of Plant Support, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
On September 14, 2012, the inspector presented the results of the onsite inspection of the licensee's emergency preparedness program to Mr. C. Reasoner, Vice President, Engineering , and other members of the licensee's staff. The licensee acknowledged the issues presented. The inspector asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
On September 27, 2012, the inspectors presented the inspection results to Mr. F. Diya, Vice President Nuclear Operations
, and other members of the licensee staff.
On October 9, 2012, the inspectors conducted a follow
-up exit and presented updated inspection results to Mr. S. Maglio, Regulatory Affairs Manager. The licensee acknowledged the issues presented. The inspector s asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was retain ed.
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- F. Bianco, Assistant Operations Manager, Support
- K. Blair, Engineer, Engineering Technical Support and Programs
- L. Bodenschatz, Engineer, Maintenance Rule
- B. Cox, Manager, Planning/Scheduling
/Outages
- W. Cravens, Medical Review Officer
- L. Eitel, Supervising Engineer Systems, Balance of Plant
- T. Elwood, Supervising Engineer, Licensing/Regulatory Affairs
- G. Gary, Consulting Chemist, Ameren
- K. Gilliam, ALARA Supervisor, Radiation Protection
- L. Graessle, Director, Operations
Support
- C. Graham, Health Physicist, Radiation Protection
- A. Heflin, Senior Vice President and Chief Nuclear Officer
- G. Hurla, Supervisor, Radiation Protection
- A. King, Senior Health Physicist, Radiation Protection
- J. Little, Supervising Engineer
Systems , Reactor/Safety Analysis
- S. Maglio, Manager, Regulatory Affairs
- P. McKenna, Manager, Emergency Preparedness
- D. Neterer, Plant Director
- H. Osborn, Regulatory Affairs Specialist
- T. Pettus, Supervisor of Major Projects, Engineering
- S. Petzel, Engineer, Regulatory Affairs
- C. Reasoner, Vice President Engineering
- C. Smith, Manager, Radiation Protection
- F. Stuckey, Senior Health Physicist, Radiation Protection
- D. Thompson, Senior Health Physicist, Radiation Protection
LIST OF ITEMS
OPENED AND CLOSED
Opened
-03 URI Review the Cause of the Failure of Inverter NN14 (Section 4OA3)
Opened and Closed
-01 NCV Failure to Correct an Adverse Condition
o n an Emergency Diesel Generator (Section 1R15)
-02 NCV Failure to Follow Radiation Work Permit Instructions
(Section 2RS 1)
LIST OF DOCUMENTS REVIEWED
Section 1R04
- Equipment Alignment
- PROCEDURES
- NUMBER TITLE REVISION
- ODP-ZZ-0016E, Appendix 1 Operations Technician General Inspection Guide
- ODP-ZZ-0016E, Appendix 1 Operations Technician General Inspection Guide
- OSP-BG-P005A Centrifugal Charging Pump A Inservice Test
- Group B 42
- DRAWING S NUMBER TITLE REVISION / DATE M-22EJ01 (Q)
- Piping and Instrumentation Diagram
- Residual Heat Removal System
- M-33EG01 Piping and Instrumentation Diagram
- Component Cooling Water System
- CALLAWAY ACTION REQUESTS
- 201205668
- 201007538
- 201102434
- 201102435
- JOB S
- 12004240
- Section 1R05
- Fire Protection
- PROCEDURES
- NUMBER TITLE REVISION / DATE
- Fire Preplan Manual
- 21592 Fire Protection Impairment Permit July 8, 2012
- APA-ZZ-00703
- Fire Protection Operability Criteria and Surveillance Requirements
- Auxiliary Building Prefire Strategies
- CALLAWAY ACTION REQUESTS
- 199903704
- Section 1R11
- Licensed Operator Requalification Program
- PROCEDURES
- NUMBER TITLE REVISION
- CDP-ZZ-01100 Atmospheric Hazard Control Program
- ODP-ZZ-00001 Operations Department
- Code of Conduct
- ODP-ZZ-00001, Addendum 1 Annunciator Response
- ODP-ZZ-00017 Annunciator Status and Tracking
- OTN-BG-00002 Reactor Makeup Control and Boron Thermal Regeneration System 41
- OTO-SB-00069 SB069 Contingency Monitoring Actions
- MISCELLANEOU
- S NUMBER TITLE DATE
- Cycle 12-5 As Found Scenario July 13, 2012
Section 1R12: Maintenance Effectiveness
- PROCEDURES
- NUMBER TITLE REVISION
- EDP-ZZ-01128 Maintenance Rule Program 17
- EDP-ZZ-01128 , Appendix 1 Systems, Structures, and Components in the Scope of the Maintenance Rule at Callaway
- EDP-ZZ-01128 , Appendix 2 Summary of System Structure and Component Performance Criteria
- EDP-ZZ-01128 , Appendix 4 Maintenance Rule System Functions
- OTO-GN-00002 Control Rod Drive Mechanism Cooling Fan Malfunctions
- CALLAWAY ACTION REQUESTS
- 201004315
- 201205258
- 201205298
- 201205357
- 201205384
- 201205391
- 201200166
- 201000663
- 201010303
- 201110202
- CALLAWAY ACTION REQUESTS
- 201100199
- MISCELLANEOU
- S NUMBER TITLE DATE
- FSA 201200166-21 Maintenance Rule Periodic Assessment for Cycle 18 (6/13/10 through 11/25/11
) May 15, 20 12
- Section 1R13
- Maintenance Risk Assessment and Emergent Work Controls
- PROCEDURES
- NUMBER TITLE REVISION
- APA-ZZ-00152 Emergent Issue Response
- ODP-ZZ-00002 Equipment Status Control
- ODP-ZZ-00002 , Appendix 1 Protected Equipment Program
- ODP-ZZ-00002 , Appendix 2 Risk Management Actions for Planned Risk Significant Activities
- CALLAWAY ACTION REQUESTS
- 201204962
- 201205680
- JOB S
- 12003592
- 12003350
- 07507305
- 12003827
- MISCELLANEOU
- S NUMBER TITLE REVISION/ DATE CA2980 Protected Equipment Work Approval Form July 17, 2012
- Callaway Control Room Logs July 23, 2012
- WCAP-16673-P 7300 Process Protection and Control System Life Cycle Sourcebook (PA
-SEE-0176) 0
- Section 1R15
- Operability Evaluations
- PROCEDURES
- NUMBER TITLE REVISIO N
- APA-ZZ-00500 Corrective Action Program
- APA-ZZ-00500 Appendix 1
- Operability and Functionality Determinations
- APA-ZZ-00500 Appendix 3
- Past Operability & Reportability Evaluations (REPO)
- APA-ZZ-00500 Appendix 17
- Screening Process Guidelines
- APA-ZZ-0500 Appendix 22
- Corrective Action Program Definitions
- APA-ZZ-00322 Integrated Work Management Process Description
- PDP-ZZ-00023 Work Screening and Processing
- KDP-ZZ-00013 Emergency Response Facility and Equipment Evaluation
- ODP-ZZ-00001, Addendum 15
- Operability and Functionality Determinations
- APA-ZZ-00500 Appendix 1
- Operability and Functionality Determinations
- CALLAWAY ACTION REQUESTS
- 201204847 2012 0 4973
- 201205304
- 201201117
- 201204954
- 199400595
- 199400609
- 201005797
- 201205597
- JOB S
- 12003602
- 12000746
- 12000905
- 12000924
- MISCELLANEOU
- S NUMBER TITLE REVISION / DATE 00138 Parts Q List August 13, 1997
- 332566 Certificate of Conformance/Compliance for Order No.
- 332566
- 1
- Control Room Logs July 31, 2012
- MISCELLANEOU
- S NUMBER TITLE REVISION / DATE O120.0015 Night Order: Containment Temperature Monitoring August 4, 2012
- M-FL-02 Flooding of Auxiliary Building Rooms 1107
- 1114 0
- SK-06 Auxiliary & Control Building Flood Analysis
- M-FL-06 Auxiliary Building Flooding Due to Pipe Break (No Seismic Event)
- Section 1R18
- Plant Modifications
- DRAWING S NUMBER TITLE REVISION 8600-X-89620 Piping & Instrumentation Diagram Hydraulic Unit SDA2101 Circulating and Service Water Pumphouse
- CALLAWAY ACTION REQUESTS
- 201205084
- JOB S
- 11007194
- MISCELLANEOU
- S NUMBER TITLE DATE
- MP 12-0019 Engineering Change Notice July 19, 2012
- O120.0015 Night Order: Discharge Isolation Valves to Circulating and Service Hydraulic Pumps July 19, 2012
- Section 1R19
- Post-Maintenance Testing
- PROCEDURES
- NUMBER TITLE REVISION / DATE
- ESP-UB-03012 FUB7001 In
-Place Bypass Leakage Test
- OSP-EM-P001A Safety Injection Train A Inservice Test
- Group B 45
- OTO-ZZ-00001 Control Room Inaccessibility
- PROCEDURES
- NUMBER TITLE REVISION / DATE
- ISL-BB-T443A Reactor Coolant System Hot Leg Wide Range Temperature Loop 4 13
- ISL-BB-0P403 Reactor Coolant System Pressure (Wide Range) Loop Calibration
- ISL-BB-L1321 Instrumentation & Control Loop Calibration Surveillance
- Reactor Vessel Level Train B
- CALLAWAY ACTION REQUESTS
- 201205011
- JOB S
- 1051509
- 12004372
- 07509139
- 12003350
- 12003827
- Section 1R22
- Surveillance Testing
- PROCEDURES
- NUMBER TITLE REVISION
- OSP-GG-0001A A Train Emergency Exhaust System Operability Test
- OSP-JE-P001A Emergency Fuel Oil Pump A Inservice Test
- OSP-NE-0001B Standby Diesel Generator B Periodic Tests 51
- OTS-PA-00001 Operation and Testing of the Alternate Emergency Power Source 8
- OSP-GT-00001 Shutdown Purge System Lineup Verification
- OTS-NN-00014 NN14 Inverter Outage
- IPTE 19
- DRAWING S NUMBER TITLE REVISION 8600-X-90988 Single Line Diagram Alternate Emergency Power System
- CALLAWAY ACTION REQUESTS
- 201204759
- JOB S
- 12504725
- 12506838
- 12500704
- 12506361
- 12509180 12004372
Section 1EP2: Alert and Notification System Evaluation
- MISCELLANEOUS
- NUMBER TITLE REVISION / DATE
- KSP-ZZ-00008 Tone Alert Radios
- KSP-ZZ-00008 Appendix 1, Electric Utility Providers in the EPZ and other Information Providers
- KSP-ZZ-00008 Appendix 2, Microsoft Access Tone Alert Radio Database Fields 1
- KSP-ZZ-00110 Siren Alerting System Testing Tone Alert Radio Database Audit January 2010
- Tone Alert Radio Database Audit January 2011
- Tone Alert Radio Database Audit January 2012
Section 1EP3: Emergency Response Organization Staffing and Augmentation System
- MISCELLANEOUS
- NUMBER TITLE REVISION
- EIP-ZZ-00200 Augmentation of the Emergency Callout System
- EIP-ZZ-A0001 Emergency Response Organization
- KSP-ZZ-00102 Monthly Emergency Communications System Testing
- KSP-ZZ-00201 Emergency Augmentation Drill/Test
- KSP-ZZ-00202 Emergency Response Notification System Weekly Testing Evaluation Report for the Augmentation Test conducted September 28, 2010
- Evaluation Report for the Augmentation Test conducted December 14, 2010
- Evaluation Report for the Augmentation Test conducted March 23, 2011
- Evaluation Report for the Augmentation Test conducted June 15, 2011
- MISCELLANEOUS
- NUMBER TITLE REVISION
- Evaluation Report for the Augmentation Test conducted September 14, 2011
- Evaluation Report for the Augmentation Test conducted November 30, 2011
- Evaluation Report for the Augmentation Test conducted March 19, 2012
- Evaluation Report for the Augmentation Test conducted June 19, 2012
Section 1EP5: Maintenance of Emergency Preparedness
- MISCELLANEOUS
- NUMBER TITLE REVISION / DATE
- APA-ZZ-00004 Emergency Preparedness Department Responsibilities
- ZZ-00500 Appendix 12, Significant Adverse Condition
- Significance Level 1 15 APA
- ZZ-00500 Appendix 13, Adverse Condition
- Significance Level 2
- ZZ-00500 Appendix 14, Adverse Condition
- Significance Level 3
- ZZ-00500 Appendix 15, Adverse Condition
- Significance Level 4
- ZZ-00500 Appendix 16, Adverse Condition
- Significance Level 5
- ZZ-00500 Appendix 17, Screening Process Guidelines
- ZZ-00500 Appendix 21, Other Issues - Significance Level 6
- EIP-ZZ-A0001 Emergency Response Organization
- EIP-ZZ-A0020 Maintaining Emergency Preparedness
- EIP-ZZ-A0066 RERP Training Program Form CA2783
- Emergency Response Facility Functionality Evaluation Form CA3100
- Emergency Response Equipment Functionality Evaluation
- GDP-ZZ-01810 Nuclear Oversight Assessment Coverage
- KDP-ZZ-00013 Emergency Response Facility and Equipment Evaluation
- KDP-ZZ-00300 Maintaining Emergency Preparedness, Supplemental Documents 15
- MISCELLANEOUS
- NUMBER TITLE REVISION / DATE
- KDP-ZZ-02001 Drill and Exercise Program
- KSP-ZZ-00007 Offsite Effectiveness of the Emergency Preparedness Program 9
- PDP-ZZ-00023 Work Screening and Processing After Action Report for the April 13, 2010, Notification of Unusual Event April 27, 2010
- After Action Report for the September 18, 2011, Alert March 13, 2012
- AP10-006 Nuclear Oversight Audit: Emergency Preparedness July 29, 2010
- AP11-008 Nuclear Oversight Audit: Emergency Preparedness August 15, 2011
- AP12-008 Nuclear Oversight Audit: Emergency Preparedness August 2012
- SA10-EP-C01 Benchmark: NEI Form and RUG4 Meeting June 23, 2010
- SA10-EP-S01 Assessment: Validate Drill and Exercise Performance August 19, 2010
- 201100569-15 NRC EP Performance Indicators Self
-Assessment April 26, 2011
- 201201081-6.3 Readiness for September 2012 NRC Program Inspection, Self Assessment July 16, 2012
- 01077217 Emergency Response Facility Functionality Evaluation October 4, 2010
- 01132026 Emergency Response Facility Functionality Evaluation October 17, 2010
- 01077256 Emergency Response Facility Functionality Evaluation December 16, 2010
- 01077272 Emergency Response Facility Functionality Evaluation March 28, 2011
- 17914 Emergency Response Facility Functionality Evaluation May 16, 2011
- 01077302 Emergency Response Facility Functionality Evaluation June 15, 2011
- 01077325 Emergency Response Facility Functionality Evaluation September 20, 2011
- 01119507 Emergency Response Facility Functionality Evaluation February 2, 2012
- 01077356 Emergency Response Facility Functionality Evaluation April 9, 2012
- 01077372 Emergency Response Facility Functionality Evaluation May 9, 2012
- MISCELLANEOUS
- NUMBER TITLE REVISION / DATE
- 01077383 Emergency Response Facility Functionality Evaluation July 10, 2012
- 01077390 Emergency Response Facility Functionality Evaluation August 7, 2012
- Emergency Response Equipment Functionality Evaluation: SJRE0002 Steam Generator Blowdown Radiation Monitor August 28, 2012
- Emergency Response Equipment Functionality Evaluation: GTRE0031 Containment Atmosphere Radiation Monitor August 28, 2012
- Emergency Management Director Meeting Minutes, Fourth Quarter 2010
- Emergency Management Director Meeting Minutes March 21, 2011
- Emergency Management Director Meeting Minutes June 20, 2011
- Emergency Management Director Meeting Minutes September 19, 2011
- Emergency Management Director Meeting Minutes December 12, 2011
- Emergency Management Director Meeting Minutes June 11, 2012
- Evaluation Report for the Drill conducted September 9, 2010
- Evaluation Report for the Drill conducted September 15, 2010
- Evaluation Report for the Drill conducted September 22, 2010
- Evaluation Report for the Drill conducted September 29, 2010
- Evaluation Report for the Drill conducted October 6, 2010
- Evaluation Report for the Drill conducted October 13, 2010
- Evaluation Report for the Drill conducted December 1, 2010
- Evaluation Report for the Drill conducted January 12, 2011
- Evaluation Report for the Drill conducted January 19, 2011
- MISCELLANEOUS
- NUMBER TITLE REVISION / DATE
- Evaluation Report for the Drill conducted January 26, 2011
- Evaluation Report for the Drill conducted March 30, 2011
- Evaluation Report for the Drill conducted May 11, 2011
- Evaluation Report for the Drill conducted June 22, 2011
- Evaluation Report for the Drill conducted June 29, 2011
- Evaluation Report for the Drill conducted September 7, 2011
- Evaluation Report for the Drill conducted September 11, 2011
- Evaluation Report for the Drill conducted July 20, 2011
- Evaluation Report for the Drill conducted July 27, 2011
- Evaluation Report for the Drill conducted August 3, 2011
- Evaluation Report for the Drill conducted August 10, 2011
- Evaluation Report for the Drill conducted August 17, 2011
- Evaluation Report for the Drill conducted August 24, 2011
- Evaluation Report for the Drill conducted December 7, 2011
- Evaluation Report for the Drill conducted December 29, 2011
- Evaluation Report for the Drill conducted July 9, 2012
- Evaluation Report for the Drill conducted July 24, 2012
- Evaluation Report for the Drill conducted August 21, 2012
- Evaluation Report for the Drill conducted September 12, 2012
- CALLAWAY ACTION REQUESTS
- 201009834
- 201011526
- 201100128
- 201100323
- 201101266
- 201101687
- 201101783
- 201103935
- 201104179
- 201104442
- 201105543
- 201105927
- 201105980
- 201106204
- 201106251
- 201106882
- 201107465
- 201107484
- 201107528
- 201202166
- CALLAWAY ACTION REQUESTS
- 201203349
- 201203749
- 201204367
- 201204516
- 201205145
- 201205183
- 201206544
- 201206551
- 201206553
- 201206554
- 201206555
- 201206556
- 201206561
- 201206562
- 201206563
- 201206564
- 201206567 201206569
Section 2RS1: Radiological Hazard Assessment and Exposure Controls
- PROCEDURES
- NUMBER TITLE REVISION
- APA-ZZ-00014 Conduct of Operations
- Radiation Protection
- APA-ZZ-01004 Radiological Work Standards
- HDP-ZZ-1500 Radiological Postings
- HDP-ZZ-03000 Radiological Survey Program
- HDP-ZZ-6100 Radioactive Sealed Source Leak Check Surveillance
- HTP-ZZ-01203 Radiological Area Access Control
- HTP-ZZ-02004 Control of Radioactive Sources
- HTP-ZZ-06001 High Radiation/Locked High Radiation/Very High Radiation Area Access
- CALLAWAY ACTION REQUESTS
- 201108483
- 201108946
- 201108871
- 201200372
- 201200482
- RADIATION WORK PERMITS
- NUMBER TITLE REVISION
- 200120LHRA
Miscellaneous
- Minor Work
- 082912RBENTRY
- Reactor Building Entry
- 200320ALPSRESIN
- Resin Sluicing
- 201401VALVETEAM
- Valve Work
- RADIOLOGICAL SURVEYS
- MAP NUMBER
- TITLE DATE 1322 South Piping Penetration Room August 14, 2012
- 1323 North Piping Penetration Room August 14, 2012
- 25 Low Level Drum Storage Area August 3, 2012
- 1306C Valve Compartments October 26, 2011
- RB-2000-AI Reactor Building Inside Bioshield 2000' Loop "A" October 17, 2011
- RB-20231 Reactor Building S/G Sludge Lancing Platforms 2023
- October 17, 2011
- MISCELLANEOUS DOCUMENTS
- TITLE DATE Radioactive Sources Requiring Leak Tests August 27, 2012
- Accountable Radioactive Source Inventory August 27, 2012
Section 2RS2: Occupational
- ALARA Planning and Controls
- PROCEDURES
- NUMBER TITLE REVISION / DATE 54-ISI-400-020 AREVA NP Inc. Multi
-Frequency Eddy Current Examination of Tubing July 27, 2011
- APA-ZZ-01001 Callaway Plant ALARA Program
- CTP-BB-06300 RCS Optimized Shutdown Chemistry
- ETP-ZZ-01300 Multi-Frequency Eddy Current Examination of Tubing
- ETP-BB-01309 Steam Generator Eddy Current Testing Acquisition and Analysis Guidelines
- ETP-ZZ-01310 TYPE W-9 Steam Generator Nozzle Dam Installation and Removal, Test, Operation and Maintenance Manual
- HDP-ZZ-01100 ALARA Planning and Review
- HDP-ZZ-01100 ALARA Planning and Review
- HDP-ZZ-01200 Radiation Work Permits
- HTP-ZZ-01101 Administrative Controls for Radioactivity
- AUDITS, SELF
-ASSESSMENTS, AND SURVEILLANCES
- NUMBER TITLE DATE
- UO 12-0002
- IER 11-1, Level 2 Self
-Assessment of INPO Inadequate CRE Performance Improvements for Callaway Energy Center January 24, 2012
- UO 12-0007
- IER 11-41, Level 2 Unplanned Personnel Exposure from Highly Radioactive In
-Core Components Response for Callaway March 27, 2012
- CALLAWAY ACTION REQUESTS
- 201105450
- 201108869
- 201108911
- 201109057
- 201109132
- 201109111
- 201109174
- 201109257
- 201109394
- 201109405
- RADIATION WORK PERMITS
- NUMBER TITLE REVISION 180917004EC
- Steam Generator Tube Eddy Current Testing in all Four Steam Generators
- Area and Equipment Setup
- 0, 3, 4
- 180813187 Detension Reactor Vessel Studs, Removal, Clean Stud Holes, Lubricate Stud Holes
- 180813206 Install Reactor Vessel Studs, Tension, Remove
- 180917004MAN
- Steam Generator Manway Cover Removal, Re-installation, and Bolt Hole Work
- 180917004PLUG
- Steam Generator Tube Plugging and Stabilizing, Including Setup
- MISCELLANEOUS DOCUMENTS
- NUMBER TITLE REVISION / DATE
- Callaway Energy Center Long Range Dose and Source Term Reduction Plan
- RB-SGJP-AD Steam Generator A&D Jump Platform Survey Sheets October 25
- 30, 2011
- RB-SGJP-BC Steam Generator B&C Jump Platform Survey Sheets October 25
- November 2, 2011
Section 2RS3: In-plant Airborne Radioactivity Control and Mitigation
- PROCEDURES
- NUMBER TITLE REVISION
- HDP-ZZ-08000 Respiratory Protection Program
- HTP-ZZ-08002 Respiratory Protection Issue and Use
- AUDITS, SELF
-ASSESSMENTS, AND SURVEILLANCES
- NUMBER TITLE DATE CAR 201200069
- Simple Self
-Assessment Report
- Callaway Respiratory Protection Program April 23, 2012
- 10501126.510
- Flow Test SJ
-143 Fume Hoods at Primary Sample Sinks February 1, 2012
- CALIBRATION DOCUMENTS
- SERIAL NUMBER TITLE DATE 42863 PortaCount Plus 8020
- October 10, 2011
- 2868 PortaCount Plus 8020
- January 11, 2012 L01925 PosiChek3 (Model 54
-20-1110) September 14, 2011 L01923 PosiChek3 (Model 54
-20-1110) March 13, 2012
- SAMPLE ANALYSES
- NUMBER TITLE DATE
- 227123 Air Quality Analysis July 22, 2012
- 21976 Air Quality Analysis April 16, 2012
- 216986 Air Quality Analysis January 18, 2012
- 213282 Air Quality Analysis November 7, 2011
- 208279 Air Quality Analysis August 10, 2011
- MAINTENANCE RECORDS
- NUMBER TITLE DATE
- APR-0003-HP Respiratory Protection Maintenance Record March 7, 2012
- MAINTENANCE RECORDS
- NUMBER TITLE DATE
- SPR-0027-HP Respiratory Protection Maintenance Record May 18, 2012
- SPR-0031-HP Respiratory Protection Maintenance Record May 14, 2012
- SPR-0008-HP Respiratory Protection Maintenance Record May 16, 2012
- SPR-0014-HP Respiratory Protection Maintenance Record May 16, 2012
- SPR-0012-HP Respiratory Protection Maintenance Record May 16, 2012
- CALLAWAY ACTION REQUESTS
- 201005544
- 201004639
- 201104745
- 201006317
- 201202999
- 201203105
- MISCELLANEOUS DOCUMENTS
- NUMBER TITLE DATE
- Callaway Plant, Unit 1
- Use of Delta Protection Respiratory Protection Equipment September 14, 2005
- Callaway Plant, Unit 1
- Use of Delta Protection Mururoa BLU Single
-Use Respiratory Protection Suit December 18, 2006
Section 2RS4: Occupational Dose Assessment
- PROCEDURES
- NUMBER TITLE REVISION
- HDP-ZZ-01200 Radiation Work Permits
- HTP-ZZ-01203 Radiological Area Access Control
- HDP-ZZ-01300 Internal Dosimetry Program
- HDP-ZZ-01480 External Radiation Dose Evaluation
- AUDITS, SELF
-ASSESSMENTS, AND SURVEILLANCES
- NUMBER TITLE DATE SA10-RP-S03 Offsite Vendors Assessment Report (CAR#201000191)
- January 11, 2010
- CP-201100841 Notification of Results from the 2010 NVLAP On
-site Assessment at Landauer June 9, 2011
- RADIATION SURVEYS
- NUMBER TITLE DATE
- RB-2047 Reactor Building 2047 General Area August 30, 2012
- RB-2026 Reactor Building 2026 General Area August 30, 2012
- RB-2000 Reactor Building 2000 General Area August 29, 2012
- RB-2068 Reactor Building 2068 General Area August 29, 2012
- RADIATION WORK PERMIT
- NUMBER TITLE REVISION 209999NEUTRON
- Radiation Work Permit (for Neutron Dose Tracking)
- CALLAWAY ACTION REQUESTS
- 201201243
- 201103578
- 201011556
- 201103254
- 201109110
- 201107140
- 201201535
- 201204303
- MISCELLANEOUS DOCUMENTS
- NUMBER TITLE DATE
- Waste Stream Report May 24, 2012 082912RBENTRY
- RWP Review Summary August 30, 2012
- 210120RBSAFETY
- RWP Review Summary August 30, 2012
- 209999NEUTRON
- RWP Review Summary August 30, 2012
- FS-5300-HP Whole Body Counter MDA Report August 29, 2012
- HPCI-02-02 Callaway Plant Health Physics Department Calculation for Electronic Dosimeter Calibration Factor April 5, 2006
Section 4OA1: Performance Indicator Verification
- PROCEDURES
- NUMBER TITLE REVISION S
- EIP-ZZ-00101 Classification of Emergencies
- EIP-ZZ-00101 Addendum 2, Emergency Action Level Technical Bases Document 5, 6
- EIP-ZZ-00102 Emergency Implementing Actions
- PROCEDURES
- NUMBER TITLE REVISION S
- EIP-ZZ-00201 Notifications
- EIP-ZZ-00201 Addendum A, Control Room Notification Flowchart
- EIP-ZZ-00201 Addendum C, EOF Notification Package
- EIP-ZZ-00202 Protective Action Recommendations
- CALLAWAY ACTION REQUESTS
- 201006794
- 201107259
- MISCELLANEOU
- S NUMBER TITLE REVISION / DATE G215.0001.001
- NRC Performance Indicator Transmittal Report
- Third Quarter 2011
- October 11, 2011 G215.0001.001
- NRC Performance Indicator Transmittal Report
- Fourth Quarter 2011
- January 5, 2012 G215.0001.001
- NRC Performance Indicator Transmittal Report
- First Quarter 2012
- April 3, 2012
- G215.0001.001
- NRC Performance Indicator Transmittal Report
- Second Quarter 2012
- July 11, 2012
- Callaway Control Room Logs September 9, 2011
- Callaway Control Room Logs September 16, 2011
Section 4OA2: Identification and Resolution of Problems
- PROCEDURES
- NUMBER TITLE REVISION
- ODP-ZZ-00001 Addendum 12
- Operator Burdens and Workarounds
- DRAWING S NUMBER TITLE REVISION 8600-X-90988 Single Line Diagram
- Alternate Emergency Power System
- CALLAWAY ACTION REQUESTS
- 201205655
- 201205681
- 201205208
- MISCELLANEOU
- S NUMBER TITLE REVISION / DATE
- Callaway Narrative Logs August 13, 2012
- EOSL# 18868
- NF039A and NF039B Channel 4 Undervoltage and Degr August 13, 2012
- List of Operator Burdens and Workarounds for previous months August 14, 2012
- Shift Manager Operation Focus Items July 24, 2012
Section 4OA3: Event Follow-Up
- MISCELLANEOU
- S TITLE DATE Letter; Union Electric Co to NRC Docket 50-483, Callaway Plant Unit
- 1; Request for NRC Enforcement Discretion Regarding Requirements of Technical Specification
- 3.8.7, 'Inverter-Operating,' ULNRC
-05901 (ML12235A531)
- August 22, 2012
- Section 4OA5
- Other Activities
- PROCEDURES
- NUMBER TITLE REVISION H190.0010 Response to Spills or Leaks of Radioactive Material into
- Groundwater
- HTP-ZZ-07101 REMP Sample Locations and Analysis Schedule
- CALLAWAY ACTION REQU
- EST 200812093
- 200812146
- 200812148
- 200903671
- MISCELLANEOUS DOCUMENTS
- TITLE REVISION / DATE Final Groundwater Model Report October 31, 2008
- Attachment 2
- The following items are requested for the Occupational Radiation Safety Inspection at Callaway
(August 27
- 31, 2012) Integrated Report 2012004
- Inspection areas are listed in the attachments below.
- Please provide the requested information on or before August 17, 2012
.
- Please submit this information using the same lettering system as below.
- For example, all contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled
"1- A," applicable organization charts in file/folder "1- B," etc.
- If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at least 30 days later than the onsite inspection dates, so the inspectors will have access to the information while writing the report.
- In addition to the corrective action document lists provided for each inspection procedure listed below, please provide updated lists of corrective action documents at the entrance meeting.
- The dates for these lists should range from the end dates of the original lists to the day of the entrance meeting.
- If more than one inspection procedure is to be conducted and the information requests appear to be redundant, there is no need to provide duplicate copies.
- Enter a note explaining in which file the information can be found.
- If you have any questions or comments, please contact Natasha Greene at (817)200
-1154 or Natasha.Greene@nrc.gov.
- Currently, the other inspectors will be Larry Ricketson, John O'Donnell, and Louis Carson.
- PAPERWORK REDUCTION ACT STATEMENT
- This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150
-0011.
- 1. Radiological Hazard Assessment and Exposure Controls (71124.01)
- Date of Last Inspection:
- October 21, 2011
- A. List of contacts and telephone numbers for the Radiation Protection Organization Staff and Technicians
- B. Applicable organization charts
- C. Audits, self assessments, and LERs written since date of last inspection
, related to this inspection area
- D. Procedure indexes for the radiation protection procedures
- E. Please provide specific procedures related to the following areas noted below.
- Additional Specific Procedures may be requested by number after the inspector reviews the procedure indexes.
- 1. Radiation Protection Program Description
- 2. Radiation Protection Conduct of Operations
- 3. Personnel Dosimetry Program
- 4. Posting of Radiological Areas
- 5. High Radiation Area Controls
- 6. RCA Access Controls and Radworker Instructions
- 7. Conduct of Radiological Surveys
- 8. Radioactive Source Inventory and Control
- 9. Declared Pregnant Worker Program
- F. List of corrective action documents (including corporate and subtiered systems) since date of last inspection
a. Initiated by the radiation protection organization
b. Assigned to the radiation protection organization
- NOTE: The lists should indicate the significance level of each issue and the search criteria used.
- Please provide documents which are "searchable" so that the inspector can perform word searches.
- If not covered above, a summary of corrective action documents since date of last inspection involving unmonitored releases, unplanned releases, or releases in which any dose limit or administrative dose limit was exceeded (for Public Radiation Safety Performance Indicator verification in accordance with IP 71151)
- G. List of radiologically significant work activities scheduled to be conducted during the inspection period (If the inspection is scheduled during an outage, please also include a list of work activities greater than 1 rem, scheduled during the outage with the dose estimate for the work activity.) H. List of active radiation work permits
- I. Radioactive source inventory list
- 2.
- Date of Last Inspection:
- October 21, 2011
- A. List of contacts and telephone numbers for ALARA program personnel
- B. Applicable organization charts
- C. Copies of audits, self
-assessments, and LERs, written since date of last inspection
, focusing on ALARA
- D. Procedure index for ALARA Program
- E. Please provide specific procedures related to the following areas noted below
.
- Additional Specific Procedures may be requested by number after the inspector reviews the procedure indexes.
- 1. ALARA Program
- 2. ALARA Committee
- 3. Radiation Work Permit Preparation
- F. A summary list of corrective action documents (including corporate and subtiered systems) written since date of last inspection
, related to the ALARA program.
- In addition to ALARA, the summary should also address Radiation Work Permit violations, Electronic Dosimeter Alarms, and RWP Dose Estimates
- NOTE: The lists should indicate the significance level of each issue and the search criteria used.
- Please provide documents which are "searchable."
- G.
- List of work activities greater than 1 rem, since date of last inspection
.
- Include original dose estimate and actual dose.
- H. Site dose totals and 3
-year rolling averages for the past 3 years (based on dose of record) I. Outline of source term reduction strategy
- 3.
- In-Plant Airborne Radioactivity Control and Mitigation (71124.03)
- Date of Last Inspection:
- April 30, 2010
- A. List of contacts and telephone numbers for the following areas:
- 1. Respiratory Protection Program
- 2. Self contained breathing apparatus
- B. Applicable organization charts
- C. Copies of audits, self
-assessments, vendor or NUPIC audits for contractor support (SCBA), and LERs, written since date of last inspection related to:
- 1. Installed air filtration systems
- 2. Self contained breathing apparatuses
- D. Procedure index for:
- 1. use and operation of continuous air monitors
- 2. use and operation of temporary air filtration units
- 3. Respiratory protection
- E. Please provide specific procedures related to the following areas noted below.
- Additional Specific Procedures may be requested by number after the inspector reviews the procedure indexes.
- 1. Respiratory protection program
- 2. Use of self contained breathing apparatuses
- 3. Air quality testing for SCBAs
- F. A summary list of corrective action documents (including corporate and subtiered systems) written since date of last inspection
, related to the Airborne Monitoring program including:
- 1. continuous air monitors
- 2. Self contained breathing apparatuses
- 3. respiratory protection program
- NOTE: The lists should indicate the significance level of each issue and the search criteria used.
- Please provide documents which are "searchable."
- G. List of SCBA qualified personnel
- reactor operators and emergency response personnel
- H. Inspection records for self contained breathing apparatuses (SCBAs) staged in the plant for use since date of last inspection.
- I. SCBA training and qualification records for control room operators, shift supervisors, STAs, and OSC personnel for the last year.
- A selection of personnel may be asked to demonstrate proficiency in donning, doffing, and performance of functionality check for respiratory devices.
- 4.
- Occupational Dose Assessment (Inspection Procedure 71124.04)
- Date of Last Inspection:
- September 24, 2010
- A. List of contacts and telephone numbers for the following areas: 1. Dose Assessment personnel
- B. Applicable organization charts
- C. Audits, self assessments, vendor or NUPIC audits of contractor support, and LERs written since date of last inspection, related to:
- 1. Occupational Dose Assessment
- D. Procedure indexes for the following areas
- 1. Occupational Dose Assessment
- E. Please provide specific procedures related to the following areas noted below.
- Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
- 1. Radiation Protection Program
- 2. Radiation Protection Conduct of Operations
- 3. Personnel Dosimetry Program
- 4. Radiological Posting and Warning Devices
- 5. Air Sample Analysis
- 6. Performance of High Exposure Work
- 7. Declared Pregnant Worker
- 8. Bioassay Program
- F. List of corrective action documents (including corporate and subtiered systems) written since date of last inspection
, associated with:
- 1. NVLAP accreditation
- 2. Dosimetry (TLD/OSL, etc.) problems
- 3. Electronic alarming dosimeters
- 4. Bioassays or internally deposited radionuclides or internal dose
- 5. Neutron dose
- NOTE: The lists should indicate the significance level of each issue and the search criteria used. G. List of positive whole body counts since date of last inspection, names redacted if desired H. Part 61 analyses/scaling factors
- Temporary Instruction 2515/185, Revision 1, Follow-Up on the Industry's Ground Water Protection Initiative As documented in the integrated Inspection Report
- 2009008, you had not fully implemented some of the objectives of Nuclear Energy Institute
- 07-07, at the time of the inspection.
- Please provide the status of each of these objectives.
- If the objective has not been fully implemented, please provide a copy of the corrective action document and specific corrective action assignment that ensures implementation of the objective.
- The following objectives were noted as incomplete:
(1) GPI Objective 1.1
- Site Hydrology and Geology.
(2) GPI Objective 1.2
- Site Risk Assessment.
(3) GPI Objective 1.3
- On-Site Ground Water Monitoring.
(4) GPI Objective 1.4
- Remediation Process.