|
---|
Category:Inspection Report
MONTHYEARIR 05000483/20230042024-01-19019 January 2024 Integrated Inspection Report 05000483/2023004 IR 05000483/20230102023-11-15015 November 2023 NRC License Renewal Phase 1 Inspection Report 05000483 2023010 IR 05000483/20233012023-11-0909 November 2023 NRC Examination Report 05000483-2023301 ML23293A2652023-10-24024 October 2023 3rd Quarter 2023 Integrated Inspection Report IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) IR 05000483/20234012023-09-13013 September 2023 NRC Security Baseline Inspection Report 05000483/2023401 IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 IR 05000483/20230022023-07-10010 July 2023 Integrated Inspection Report 05000483/2023002 IR 05000483/20230112023-06-15015 June 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000483/2023011 ML23122A3172023-05-0808 May 2023 Review of the Spring 2022 Steam Generator Tube Inservice Inspections IR 05000483/20230012023-04-12012 April 2023 Integrated Inspection Report 05000483/2023001 IR 05000483/20234022023-03-29029 March 2023 NRC Security Baseline Inspection Report 05000483/2023402 IR 05000483/20220062023-03-0101 March 2023 Annual Assessment Letter for Callaway Plant (Report 05000483/2022006) ML23019A0802023-01-19019 January 2023 Notification of Comprehensive Engineering Team Inspection (05000483/2023011) and Request for Information IR 05000483/20220042023-01-12012 January 2023 Integrated Inspection Report 05000483/2022004 IR 05000483/20220132022-11-15015 November 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000483/2022013 IR 05000483/20220032022-10-17017 October 2022 Integrated Inspection Report 05000483/2022003 IR 05000483/20220102022-10-12012 October 2022 Biennial Problem Identification and Resolution Inspection Report 05000483-2022010 - Draft IR 05000483/20224032022-09-27027 September 2022 Security Baseline Inspection Report 05000483/2022403 IR 05000483/20220052022-08-23023 August 2022 Updated Inspection Plan for Callaway Plant (Report 05000483/2022005) IR 05000483/20224022022-08-11011 August 2022 NRC Security Inspection Report 05000483/2022402 (Cover Letter Only) IR 05000483/20220112022-08-0202 August 2022 Triennial Fire Protection Inspection Report 05000483 2022011 IR 05000483/20220022022-07-27027 July 2022 Integrated Inspection Report 05000483/2022002 ML22157A0572022-06-0606 June 2022 Notification of NRC Design Bases Assurance Inspection (Programs) (05000483/2022013) and Request for Information IR 05000483/20220402022-05-0606 May 2022 95001 Supplemental Inspection Report 05000483/2022040 and Follow-Up Assessment Letter IR 05000483/20224012022-05-0505 May 2022 Cyber Security Inspection Report 05000483/2022401 IR 05000483/20220012022-04-26026 April 2022 Integrated Inspection Report 05000483/2022001 IR 05000483/20223012022-04-12012 April 2022 NRC Examination Report 05000483/2022301 ML22082A2012022-03-28028 March 2022 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000483/2022011) and Request for Information IR 05000483/20224042022-03-24024 March 2022 Final Security Baseline Inspection Report 05000483/2022404 (Letter) IR 05000483/20210062022-03-0202 March 2022 Annual Assessment Letter for Callaway Plant (Report 05000483/2021006) IR 05000483/20210042022-01-0707 January 2022 Integrated Inspection Report - 05000483/2021004 IR 05000483/20210032021-11-0808 November 2021 Integrated Inspection Report 05000483/2021003 IR 05000483/20214202021-10-29029 October 2021 NRC Security Baseline Inspection Cover Letter 050004832021420 IR 05000483/20214022021-10-26026 October 2021 Security Baseline Inspection Report 05000483/2021402 IR 05000483/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Callaway Plant (Report 05000483/2021005) IR 05000483/20210022021-08-0505 August 2021 Integrated Inspection Report 05000483/2021002 and Independent Spent Fuel Storage Installation Report 07201045/2021001 IR 05000483/20214012021-05-26026 May 2021 Security Baseline Inspection Report 05000483/2021401 IR 05000483/20210012021-05-11011 May 2021 Integrated Inspection Report 05000483/2021001 IR 05000483/20214032021-04-15015 April 2021 Material Control and Accounting Program Inspection Report 05000483-2021403 (Public) IR 05000483/20200042021-02-0909 February 2021 CWY2020004-RP-DSB, Callaway Plant - Integrated Inspection Report and Assessment Follow-Up Letter (05000483/2020004) IR 05000483/20200032020-11-0202 November 2020 Integrated Inspection Report 05000483/2020003 IR 05000483/20204112020-10-27027 October 2020 Security Baseline Inspection Report 05000483/2020411 IR 05000483/20203012020-10-13013 October 2020 NRC Examination Report 05000483/2020301 IR 05000483/20200052020-09-0101 September 2020 Updated Inspection Plan for Callaway Plant (Report 05000483/2020005) IR 05000483/20200022020-07-29029 July 2020 Integrated Inspection Report 05000483/2020002 IR 05000483/20200102020-06-12012 June 2020 Biennial Problem Identification and Resolution Inspection Report 05000483/2020010 IR 05000483/20204102020-04-24024 April 2020 NRC Security Inspection Report 05000483/2020410 IR 05000483/20200012020-04-20020 April 2020 Integrated Inspection Report 05000483/2020001 IR 05000483/20200112020-04-15015 April 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000483/2020011 2024-01-19
[Table view] Category:Letter
MONTHYEARULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 IR 05000483/20230042024-01-19019 January 2024 Integrated Inspection Report 05000483/2023004 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23317A0012024-01-12012 January 2024 Audit Summary Regarding LAR to Clarify Support System Requirements for the Residual Heat Removal and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23347A1212024-01-11011 January 2024 Issuance of Amendment No. 236 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Volume Values to Licensee Control EPID L-2023-LLA-0046) ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) ULNRC-06847, Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01)2023-12-21021 December 2023 Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01) ULNRC-06849, License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds2023-12-20020 December 2023 License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds ML23346A0392023-12-14014 December 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Relief from Requirements of ASME Code, Section Xl, Examination and Testing Unbonded Post-Tensioning System ULNRC-06844, Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification2023-12-0707 December 2023 Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification 05000483/LER-2023-001, Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications2023-11-29029 November 2023 Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications ULNRC-06827, Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029)2023-11-20020 November 2023 Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029) IR 05000483/20230102023-11-15015 November 2023 NRC License Renewal Phase 1 Inspection Report 05000483 2023010 IR 05000483/20233012023-11-0909 November 2023 NRC Examination Report 05000483-2023301 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23297A2502023-11-0606 November 2023 Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination and Opportunity for a Hearing (EPID L-2022-LLA-0176) - Letter IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) ML23293A2652023-10-24024 October 2023 3rd Quarter 2023 Integrated Inspection Report ML23240A3692023-10-0505 October 2023 Issuance of Amendment No. 235 to Revise Technical Specifications to Use of Framatome Gaia Fuel (EPID L-2022-LLA-0150) (Non-Proprietary) ML23234A1522023-10-0505 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2022-LLE-0030) (Letter) ML23305A0942023-10-0202 October 2023 10-CW-2023-09 Post-Exam Submittal ML23270B9662023-09-27027 September 2023 10 CFR 50.55a(z)(I) Request for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML23228A0252023-09-25025 September 2023 Issuance of Amendment No. 234 to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23261C3852023-09-25025 September 2023 Safety Evaluation for Operating Quality Assurance Manual Revision 36A ML23166B0882023-09-20020 September 2023 Issuance of Amendment No. 233 for Adoption of Alternative Source Term and Revision of Technical Specifications ML23206A1992023-09-15015 September 2023 Regulatory Audit Summary Regarding License Amendment and Regulatory Exemptions Request for Fuel Transition to Framatome Gaia Fuel (Epids L-2022-LLA-0150 and L-2022-LLE-0030) IR 05000483/20234012023-09-13013 September 2023 NRC Security Baseline Inspection Report 05000483/2023401 ML23240A7572023-08-31031 August 2023 NRC Initial Operator Licensing Examination Approval 05000483/2023301 IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 ULNRC-06824, Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A2023-08-17017 August 2023 Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A ML23219A1392023-08-15015 August 2023 Request for Withholding Information from Public Disclosure ULNRC-06830, Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak2023-08-15015 August 2023 Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak ML23215A1972023-08-0303 August 2023 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) ULNRC-06223, Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004)2023-07-25025 July 2023 Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004) ULNRC-06799, Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications2023-07-13013 July 2023 Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications IR 05000483/20230022023-07-10010 July 2023 Integrated Inspection Report 05000483/2023002 ML23174A1272023-06-23023 June 2023 Cw FFD Document Request List 2023 ML23171A9942023-06-22022 June 2023 Acceptance of Request for Approval of Operating Quality Assurance Manual Revision 36a ULNRC-06821, Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301)2023-06-21021 June 2023 Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301) IR 05000483/20230112023-06-15015 June 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000483/2023011 ULNRC-06822, Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a2023-06-14014 June 2023 Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ULNRC-06815, Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a2023-06-0505 June 2023 Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a ULNRC-06818, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate .2023-06-0505 June 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate . ML23093A0952023-05-10010 May 2023 Issuance of Amendment No. 232 Regarding Technical Specification Changes for Spent Fuel Storage ULNRC-06816, Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015)2023-05-0909 May 2023 Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015) ML23129A7942023-05-0909 May 2023 Post-Audit Supplement to License Amendment Request and Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (Iepid L-2022-LLA-0150 and EPID L-2022-LLE-0030) ML23122A3172023-05-0808 May 2023 Review of the Spring 2022 Steam Generator Tube Inservice Inspections ML23118A3492023-05-0808 May 2023 Request for Withholding Information from Public Disclosure 2024-01-29
[Table view] |
Text
March 29, 2023
SUBJECT:
CALLAWAY PLANT - SECURITY BASELINE INSPECTION REPORT 05000483/2023402
Dear Fadi Diya:
On March 9, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Callaway Plant and discussed the results of this inspection with Warren Witt, Senior Director, Nuclear Plant Support, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Signed by Kellar, Ray on 03/29/23 Ray L. Kellar, P.E., Chief Physical Security Branch Division of Radiological Safety & Security Docket No. 05000483 License No. NPF-30
Enclosure:
As stated
Inspection Report
Docket Number: 05000483 License Number: NPF-30 Report Number: 05000483/2023402 Enterprise Identifier: I-2023-402-0019 Licensee: Ameren Facility: Callaway Plant Location: Steedman Missouri Inspection Dates: March 06, 2023 to March 09, 2023 Inspectors: D. Holman, Sr Physical Security Inspector W. Tejada, Physical Security Inspector Approved By: Ray L. Kellar, P.E., Chief Physical Security Branch Division of Radiological Safety & Security Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Callaway Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.01 - Access Authorization
The inspectors evaluated the access authorization program. The following elements were evaluated:
Access Authorization
Main article: IP 71130.01
- (1) Tier I: All requirements Tier II: All requirements Tier III: All requirements
71130.02 - Access Control
The inspectors evaluated the access control program through completion of the following
inspection elements: Access Control
Main article: IP 71130.02
- (1) Tier I: All Requirements Tier II: All Requirements Tier III: All Requirement
71130.09 - Security Plan Changes
The inspectors evaluated the security plan changes through completion of the following procedure elements:
Security Plan Changes (1 Partial)
(1) (Partial)
The opportunity to apply this procedure was not available in accordance with IMC 0306.
Specifically, although the licensee had initiated a physical security plan change, revision 13, in accordance with 10 CFR 50.54(p)(2), aspects of the change had not yet been fully reviewed by HQ/NSIR/DPCP/RSB in consultation with OGC.
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17) (1 Sample)
- (1) January 1, 2022 through January 31,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On March 9, 2023, the inspectors presented the security baseline inspection results to Warren Witt, Senior Director, Nuclear Plant Support, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71130.01 Corrective Action 202105504,
Documents 202105846,
2106129,
2200323,
2201049,
2202548,
2203412,
2203856,
2204062,
2204062,
2204359,
2204534,
2204592,
2204673,
2204882,
2204898,
2205100,
2208372
Miscellaneous NEI 03-01 Nuclear Power Plant Access Authorization Program Revision 3
Procedures APA-ZZ-00908 Fitness For Duty Programs Revision 039
APA-ZZ-01104 Access Authorization Program For Callaway Energy Center revision 051
SDP-SF-00050 Evaluation Of Background Investigation Data For Unescorted Revision 011
Access Authorization
SDP_SF-00050 Criteria For Reapplication After An Unescorted Access Revision 002
APPENDIX A Denial
71130.02 Corrective Action 202204674, Multiple
Documents 202204689,
2204673,
2204672,
2204587,
2207249,
2206004,
Inspection Type Designation Description or Title Revision or
Procedure Date
2201672,
2205526,
2206536,
2207023 ,
2207746,
2206949,
2208423
2300042,
2300833,
2205252,
2205341,
2205731,
2205848,
2205870,
2205931,
2206071,
2206075,
2206325,
2206331,
2206384,
2206994
Corrective Action 202301689, Multiple
Documents 202301719,
Resulting from 202301720,
Inspection
Miscellaneous Iris Scan Desktop Iris Scan 09/2021
Instructions
Procedures APA-ZZ-00020 CONDUCT OF SECURITY OPERATIONS Revision 036
APA-ZZ-00204 Revision 050
APA-ZZ-00907, PLANT ACCESS STATUS LEVELS Revision 009
APPENDIX B
APA-ZZ-01106 LOCK AND KEY CONTROL Revision 29
APA-ZZ-01107 PROTECTION OF PERSONAL INFORMATION AND Revision 17
ASSOCIATED ACCESS AUTHORIZATION AND FITNESS
Inspection Type Designation Description or Title Revision or
Procedure Date
FOR DUTY RECORDS
EIP-ZZ-SK001 RESPONSE TO SECURITY EVENTS Revision 15
HTP-ZZ-06001 HIGH RADIATION/LOCKED HIGH RADIATION/VERY HIGH Revision 056
RADIATION AREA ACCESS
SDP-PI-AR/PO ARMED RESPONDER/PATROL OFFICER Revision 035
SDP-PI-BADGE MAF BADGING Revision 025
SDP-PI-DOORS POSTING PORTALS/BARRIERS Revision 020
SDP-PI-ESCORT VEHICLE ESCORT Revision 004
SDP-PI-KIS01 KEY ISSUE STATION Revision 019
SDP-PI-MAFST MAF SEARCH TRAIN Revision 032
SDP-PI-SP/VB SALLY PORT/VEHICLE BARRIER CHECKPOINT Revision 009
SDP-PI-STORE STOREROOM OFFICER Revision 29
SDP-PI-SUPVS Actions for Discovery of Contraband Revision 23
Att. 5
SDP-PI-VEHAC VEHICLE ACCESS/CONTROL Revision 52
SDP-SF-00002 TESTING OF SECURITY EQUIPMENT Revision 40
SDP-SF-00022 REPORTING OF SAFEGUARDS EVENTS Revision 23
Self-Assessments Audit Report Nuclear Oversight Audit of Security I Cyber-Security 06/30/2022
AP22003 Programs AP22003
71151 Miscellaneous Nominalization Performance Indicators Nominalization Factors
Factors
7