MONTHYEARML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ML23163A1572023-06-0606 June 2023 In-service Inspection Request for Information ML23080A1382023-03-21021 March 2023 Notification of Inspection (NRC Inspection Report 05000483/2023003) and Request for Information IR 05000483/20220062023-03-0101 March 2023 Annual Assessment Letter for Callaway Plant (Report 05000483/2022006) ML23027A0362023-01-27027 January 2023 Information Request, Security IR 2023402 IR 05000483/20220052022-08-23023 August 2022 Updated Inspection Plan for Callaway Plant (Report 05000483/2022005) ML22173A0562022-06-22022 June 2022 Information Request, Security IR 2022402 IR 05000483/20210062022-03-0202 March 2022 Annual Assessment Letter for Callaway Plant (Report 05000483/2021006) ML21336A6392021-12-0202 December 2021 .05 Sec Doc Request ML21333A1572021-11-30030 November 2021 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000483/2022402 IR 05000483/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Callaway Plant (Report 05000483/2021005) ML21195A0252021-07-13013 July 2021 Email 7-13-21 Request for Information - Callaway EP Exercise Inspection - Sept 2021 ML21088A3872021-03-30030 March 2021 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000483/2021002) and Request for Information ML21069A3422021-03-11011 March 2021 Notification of Inspection (NRC Inspection Report 05000483/2021003) and Request for Information ML21055A0062021-03-0303 March 2021 Annual Assessment Letter for Callaway Plant (Report 05000483/2020006) ML20245E4402020-09-0101 September 2020 Cwy Inspection Schedule Mc 2020 IR 05000483/20200052020-09-0101 September 2020 Updated Inspection Plan for Callaway Plant (Report 05000483/2020005) IR 05000483/20190062020-03-0303 March 2020 Annual Assessment Letter for Callaway Plant (Report 05000483/2019006) ML19347D1482019-12-11011 December 2019 Cwy Security Inspection Information Request 2020410 IR 05000483/20190052019-08-30030 August 2019 Updated Inspection Plan for Callaway Plant Unit 1, Report No. 05000483/2019005 ML19199A1812019-07-18018 July 2019 Notification of NRC Design Base Assurance Inspection (Programs) (05000483/2019011) and Initial Request for Information IR 05000483/20180062019-03-0404 March 2019 Annual Assessment Letter for Callaway Plant (Report 05000483/2018006) ML19023A2032019-01-22022 January 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000483/2019001) and Request for Information IR 05000483/20170062018-03-0101 March 2018 Annual Assessment Letter for Callaway Plant (Report 05000483/2017006) IR 05000483/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000483/2017005) IR 05000483/20160062017-03-0101 March 2017 Annual Assessment Letter for Callaway Plant (Report 05000483/2016006) IR 05000483/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2016005) IR 05000483/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2016401) ML16237A0332016-08-31031 August 2016 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2016005) IR 05000483/20150062016-03-0202 March 2016 Annual Assessment Letter for Callaway Plant (Report 05000483/2015006) IR 05000483/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2015005) ML15244B0922015-09-0101 September 2015 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2015401) ML15023A0962015-01-23023 January 2015 Notification of Conduct of a Triennial Fire Protection Baseline IR 05000483/2015007 and Request for Information IR 05000483/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Callaway Plant (Report 05000483/2014006) IR 05000483/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Callaway Plant (NRC Physical Security Inspection Report Number 05000483/2014402) IR 05000483/20130012014-03-0404 March 2014 Annual Assessment Letter for Callaway Plant (Report 05000483/2013001) ML14027A2792014-01-27027 January 2014 Information Request for NRC Triennial Baseline Component Design Bases Inspection NRC Inspection Report 05000483-14-007 ML13269A4372013-09-26026 September 2013 Notification of TI-186 Inspection (NRC Inspection Report 05000483-13-405) and Request for Information IR 05000483/20134052013-09-26026 September 2013 Callaway Plant - Notification of TI-186 Inspection (NRC Inspection Report 05000483-13-405) and Request for Information ML13246A2822013-09-0303 September 2013 Mid-Cycle Assessment Letter 2013 IR 05000483/20128012013-03-0404 March 2013 Annual Assessment Letter for Callaway Plant (Report 05000483/2012801) IR 05000483/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - Callaway Plant (05000483/2012006) IR 05000483/20120012012-03-0505 March 2012 Annual Assessment Letter for Callaway Plant (Report 05000483/2012001) ML1124401772011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - Callaway Plant IR 05000483/20110012011-03-0404 March 2011 Annual Assessment Letter for Callaway Plant (Report 05000483-11-001) ML1024403442010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Callaway IR 05000483/20100012010-03-0303 March 2010 (NRC Inspection Report 05000483-10-001) 2024-01-11
[Table view] Category:Letter
MONTHYEARULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 IR 05000483/20230042024-01-19019 January 2024 Integrated Inspection Report 05000483/2023004 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23317A0012024-01-12012 January 2024 Audit Summary Regarding LAR to Clarify Support System Requirements for the Residual Heat Removal and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23347A1212024-01-11011 January 2024 Issuance of Amendment No. 236 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Volume Values to Licensee Control EPID L-2023-LLA-0046) ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) ULNRC-06847, Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01)2023-12-21021 December 2023 Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01) ULNRC-06849, License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds2023-12-20020 December 2023 License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds ML23346A0392023-12-14014 December 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Relief from Requirements of ASME Code, Section Xl, Examination and Testing Unbonded Post-Tensioning System ULNRC-06844, Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification2023-12-0707 December 2023 Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification 05000483/LER-2023-001, Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications2023-11-29029 November 2023 Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications ULNRC-06827, Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029)2023-11-20020 November 2023 Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029) IR 05000483/20230102023-11-15015 November 2023 NRC License Renewal Phase 1 Inspection Report 05000483 2023010 IR 05000483/20233012023-11-0909 November 2023 NRC Examination Report 05000483-2023301 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23297A2502023-11-0606 November 2023 Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination and Opportunity for a Hearing (EPID L-2022-LLA-0176) - Letter IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) ML23293A2652023-10-24024 October 2023 3rd Quarter 2023 Integrated Inspection Report ML23240A3692023-10-0505 October 2023 Issuance of Amendment No. 235 to Revise Technical Specifications to Use of Framatome Gaia Fuel (EPID L-2022-LLA-0150) (Non-Proprietary) ML23234A1522023-10-0505 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2022-LLE-0030) (Letter) ML23305A0942023-10-0202 October 2023 10-CW-2023-09 Post-Exam Submittal ML23270B9662023-09-27027 September 2023 10 CFR 50.55a(z)(I) Request for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML23228A0252023-09-25025 September 2023 Issuance of Amendment No. 234 to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23261C3852023-09-25025 September 2023 Safety Evaluation for Operating Quality Assurance Manual Revision 36A ML23166B0882023-09-20020 September 2023 Issuance of Amendment No. 233 for Adoption of Alternative Source Term and Revision of Technical Specifications ML23206A1992023-09-15015 September 2023 Regulatory Audit Summary Regarding License Amendment and Regulatory Exemptions Request for Fuel Transition to Framatome Gaia Fuel (Epids L-2022-LLA-0150 and L-2022-LLE-0030) IR 05000483/20234012023-09-13013 September 2023 NRC Security Baseline Inspection Report 05000483/2023401 ML23240A7572023-08-31031 August 2023 NRC Initial Operator Licensing Examination Approval 05000483/2023301 IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 ULNRC-06824, Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A2023-08-17017 August 2023 Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A ML23219A1392023-08-15015 August 2023 Request for Withholding Information from Public Disclosure ULNRC-06830, Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak2023-08-15015 August 2023 Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak ML23215A1972023-08-0303 August 2023 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) ULNRC-06223, Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004)2023-07-25025 July 2023 Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004) ULNRC-06799, Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications2023-07-13013 July 2023 Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications IR 05000483/20230022023-07-10010 July 2023 Integrated Inspection Report 05000483/2023002 ML23174A1272023-06-23023 June 2023 Cw FFD Document Request List 2023 ML23171A9942023-06-22022 June 2023 Acceptance of Request for Approval of Operating Quality Assurance Manual Revision 36a ULNRC-06821, Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301)2023-06-21021 June 2023 Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301) IR 05000483/20230112023-06-15015 June 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000483/2023011 ULNRC-06822, Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a2023-06-14014 June 2023 Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ULNRC-06815, Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a2023-06-0505 June 2023 Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a ULNRC-06818, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate .2023-06-0505 June 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate . ML23093A0952023-05-10010 May 2023 Issuance of Amendment No. 232 Regarding Technical Specification Changes for Spent Fuel Storage ULNRC-06816, Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015)2023-05-0909 May 2023 Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015) ML23129A7942023-05-0909 May 2023 Post-Audit Supplement to License Amendment Request and Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (Iepid L-2022-LLA-0150 and EPID L-2022-LLE-0030) ML23122A3172023-05-0808 May 2023 Review of the Spring 2022 Steam Generator Tube Inservice Inspections ML23118A3492023-05-0808 May 2023 Request for Withholding Information from Public Disclosure 2024-01-29
[Table view] |
Text
UNITED STATES NU C LE AR RE G ULATO RY C O M M I S S I O N rch 3, 2010
SUBJECT:
ANNUAL ASSESSMENT LETTER - CALLAWAY PLANT (NRC INSPECTION REPORT 05000483/2010001)
Dear Mr. Heflin:
On February 17, 2010, the NRC staff completed its performance review of Callaway Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2009. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security-Related Information" will include the security cornerstone review and resultant inspection plan.
Overall, Callaway Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through June 30, 2011. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
AmerenUE -2-If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 817-860-8141 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Geoffrey B. Miller, Chief Reactor Projects Branch B Division of Reactor Projects Docket Nos. 50-483 License Nos. NPF-30 Enclosure: Callaway Plant Inspection / Activity Plan Mr. Luke H. Graessle Director, Operations Support AmerenUE P.O. Box 620 Fulton, MO 65251 E. Hope Bradley Manager, Protective Services AmerenUE P.O. Box 620 Fulton, MO 65251 Mr. Scott Sandbothe, Manager Plant Support AmerenUE P.O. Box 620 Fulton, MO 65251 R. E. Farnam Assistant Manager, Technical Training AmerenUE P.O. Box 620 Fulton, MO 65251 J. S. Geyer Radiation Protection Manager AmerenUE P.O. Box 620 Fulton, MO 65251 John ONeill, Esq.
Pillsbury Winthrop Shaw Pittman LLP 2300 N. Street, N.W.
Washington, DC 20037
AmerenUE -3-Missouri Public Service Commission P.O. Box 360 Jefferson City, MO 65102-0360 Dru Buntin Director of Government Affairs Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102-0176 President and Chief Executive officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Kathleen Logan Smith, Executive Director and Kay Drey, Representative, Board of Directors Missouri Coalition for the Environment 6267 Delmar Boulevard, Suite 2E St. Louis, MO 63130 Presiding Commissioner Callaway County Court House 10 East Fifth Street Fulton, MO 65251 Director, Missouri State Emergency Management Agency P.O. Box 116 Jefferson City, MO 65102-0116 Mr. Scott Clardy, Administrator Section for Disease Control Missouri Department of Health and Senior Services P.O. Box 570 Jefferson City, MO 65102-0570 Certrec Corporation 4200 South Hulen, Suite 422 Fort Worth, TX 76109 Mr. Keith G. Henke, Planner II Division of Community and Public Health 930 Wildwood Drive P.O. Box 570 Jefferson City, MO 65102
AmerenUE -4-Chief, Technological Hazards Branch FEMA Region VII 9221 Ward Parkway, Suite 300 Kansas City, MO 64114-3372 Lee Fritz Presiding Commissioner Callaway County Courthouse 10 East 5th Street Fulton, MO 65251 Gabe Craighead Eastern District Commissioner Callaway County Courthouse 10 East 5th Street Fulton, MO 65251 Donald "Doc" Kritzer Western District Commissioner Callaway County Courthouse 10 East 5th Street Fulton, MO 65251 The Honorable Charles M. Latham Mayor of Fulton Fulton City Hall P.O. Box 130 Fulton, MO 65251 William Johnson Fulton City Administrator P.O. Box 130 Fulton, MO 65251 Steve Myers Chief of Police Fulton City Hall P.O. Box 130 Fulton, MO 65251 Dennis Crane Sheriff, Callaway County P.O. Box 817 Fulton, MO 65251 The Honorable Tom Shackelford Mayor of Mokane P. O. Box 41 Mokane, MO 65059
AmerenUE -5-Daniel Dyer, Director Emergency Management Gasconade County Courthouse, Room 2 119 East First Street Hermann, MO 65041 Ron Jost Presiding Commissioner Gasconade County Courthouse 119 East First Street Hermann, MO 65041 Matt Penning Northern District Commissioner Gasconade County Courthouse 119 East First Street Hermann, MO 65041 Jerry Lairmore Southern District Commissioner Gasconade County Courthouse 119 East First Street Hermann, MO 65041 Randy Esphorst Sheriff, Gasconade County Gasconade County Courthouse, Room 22 119 East First Street Hermann, MO 65041 The Honorable Samuel Birk Mayor of Morrison 634 Highway 100 Morrison, MO 65061 Bob Bishop Emergency Management Director Montgomery County Courthouse 211 East Third Montgomery City, MO 63361 Charles Korman Presiding Commissioner Montgomery County Courthouse 211 East Third Montgomery City, MO 63361
AmerenUE -6-Rich Daniels First District Commissioner Montgomery County Courthouse 211 East Third Montgomery City, MO 63361 John Noltensmeyer Second District Commissioner Montgomery County Courthouse 211 East Third Street Montgomery City, MO 63361 Robert Davis Sheriff, Montgomery County Montgomery County Courthouse 211 East Third Street Montgomery City, MO 63361 The Honorable Steve Wehrle Mayor of Rhineland P.O. Box 384 Rhineland, MO 65069 Russell J. Scheulen Presiding Commissioner Osage County Courthouse P.O. Box 826 Linn, MO 65051 Elmer Senevey First District Commissioner Osage County Courthouse P.O. Box 826 Linn, MO 65051 Vince Sampson Second District Commissioner Osage County Administration Bldg.
P.O. Box 826 Linn, MO 65051 Carl Fowler Sheriff, Osage County Osage County Administration Bldg.
P.O. Box 619 Linn, MO 65051
AmerenUE -7-The Honorable James Wright Mayor of Chamois 105 S. Cherry Street Chamois, MO 65024 Federal Emergency Management Agency Mr. Dick Hainje, Regional Director Region VII 9221 Ward Parkway, Suite 300 Kansas City, MO 64114-3372 Paul Parmenter, Director State Emergency Management Agency P.O. Box 116 Jefferson City, MO 65102 Ronald L. McCabe, Chief Technological Hazards Branch National Preparedness Division DHS/FEMA 9221 Ward Parkway Suite 300 Kansas City, MO 64114-3372 Ms. Michelle Kidwell Emergency Preparedness Director Callaway County/Fulton P.O. Box 817 Fulton, MO 65251 Ms. Andi Rice Emergency Management Director Osage County Courthouse P.O. Box 192 Linn, MO 65051
AmerenUE -8-cc.
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Chuck.Casto@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.goV)
DRS Director (Roy.Caniano@nrc.gov)
DRS Deputy Director (Troy.Pruett@nrc.gov)
Branch Chief, DRP/B (Geoffrey.Miller@nrc.gov)
Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov)
Senior Resident Inspector (David.Dumbacher@nrc.gov)
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Regional State Liaison Officer (Bill.Maier@nrc.gov)
RA Administrative Assistant (Lucy.Owen@nrc.gov)
DRA Administrative Assistant (Anita.Tannenbaum@nrc.gov)
Branch Chief, DRS/EB1 (Thomas.Farnholtz@nrc.gov)
Branch Chief, DRS/EB2 (Neil.OKeefe@nrc.gov)
Branch Chief, DRS/PSB1 (Michael.Shannon@nrc.gov)
Branch Chief, DRS/PSB2 (Greg.Werner@nrc.gov)
Branch Chief, DRS/OB (Mark.Haire@nrc.gov)
OEDO RIV Coordinator (Leigh.Trocine@nrc.gov)
Director, DIRS, NRR (Frederick.Brown@nrc.gov)
Director, DORL, NRR (Joseph Giitter@nrc.gov)
Deputy Director, DORL, NRR (Robert.Nelson@nrc.gov)
Chief, PLB IV, DORL, NRR (Michael.Markley@nrc.gov)
NRR Project Manager (Mohan.Thadani@nrc.gov)
RidsNrrDirslpab Resource@nrc.gov ROPreports.Resource@nrc.gov Congressional Affairs Officer (Jenny.Weil@nrc.gov)
mortensengk@INPO.org File located: R_Reactors\EOC2009\CWY.doc SUNSI Rev Compl. ; Yes No ADAMS ; Yes No Reviewer Initials GM Publicly Avail ; Yes No Sensitive Yes ; No Sens. Type Initials GM C:DRP/B D:DRS C:DRP/B D:DRP GMiller RJCaniano GMiller DDChamberlain
/RA/ /RA/MHay for /RA/ /RA/
2/24/10 2/23/10 2/25/10 2/25/10 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
Page 1 of 2 Callaway 02/18/2010 10:35:25 Inspection / Activity Plan Report 22 04/01/2010 - 06/30/2011 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB2-08P - INSERVICE INSPECTION 3 1 04/19/2010 04/23/2010 IP 2515/172 Reactor Coolant System Dissimiliar Metal Butt Welds 1 04/19/2010 04/23/2010 IP 7111108P Inservice Inspection Activities - PWR RP123 - OCCUPATIONAL RADIATION SAFETY 2 1 04/26/2010 04/30/2010 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 04/26/2010 04/30/2010 IP 71124.02 Occupational ALARA Planning and Controls 1 04/26/2010 04/30/2010 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 04/26/2010 04/30/2010 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 04/26/2010 04/30/2010 IP 71151-PR01 RETS/ODCM Radiological Effluent EB1-07T - TRIENNIAL HEAT SINK 4 1 06/07/2010 06/18/2010 IP 7111107T Heat Sink Performance EB1-17T - 50.59 AND MODS 6 1 06/07/2010 06/18/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications EP-1 - BIENNIAL EP PROGRAM INSPECTION 2 1 09/13/2010 09/17/2010 IP 7111402 Radiological Environmental Monitoring Program 1 09/13/2010 09/17/2010 IP 7111403 Emergency Response Organization Augmentation Testing 1 09/13/2010 09/17/2010 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 09/13/2010 09/17/2010 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 09/13/2010 09/17/2010 IP 71151-EP01 Drill/Exercise Performance 1 09/13/2010 09/17/2010 IP 71151-EP02 ERO Drill Participation 1 09/13/2010 09/17/2010 IP 71151-EP03 Alert & Notification System RP45 - RADIATION SAFETY 2 1 09/20/2010 09/24/2010 IP 71124.04 Occupational Dose Assessment 1 09/20/2010 09/24/2010 IP 71124.05 Radiation Monitoring Instrumentation 1 09/20/2010 09/24/2010 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 09/20/2010 09/24/2010 IP 71151-PR01 RETS/ODCM Radiological Effluent TSB-52B - BIENNIAL PI&R 4 1 10/18/2010 10/22/2010 IP 71152B Identification and Resolution of Problems 1 11/01/2010 11/05/2010 IP 71152B Identification and Resolution of Problems EB1-21 - COMPONENT DESIGN BASIS INSPECTION 1 1 02/07/2011 03/07/2011 IP 7111121 Component Design Bases Inspection EP1 - BIENNIAL EP EXERCISE INSPECTION 3 1 05/09/2011 05/13/2011 IP 7111401 Exercise Evaluation 1 05/09/2011 05/13/2011 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 05/09/2011 05/13/2011 IP 71151-EP02 ERO Drill Participation This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Callaway 02/18/2010 10:35:25 Inspection / Activity Plan Report 22 04/01/2010 - 06/30/2011 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP1 - BIENNIAL EP EXERCISE INSPECTION 3 1 05/09/2011 05/13/2011 IP 71151-EP03 Alert & Notification System 1 05/09/2011 05/13/2011 IP 71151-PP01 Protected Area Security Performance Index RP678 - RADIATION SAFETY TEAM 3 1 06/20/2011 06/24/2011 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 06/20/2011 06/24/2011 IP 71124.07 Public Radiation Safety 1 06/20/2011 06/24/2011 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.