IR 05000483/2021004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report - 05000483/2021004
ML21362A760
Person / Time
Site: Callaway Ameren icon.png
Issue date: 01/07/2022
From: Greg Werner
NRC/RGN-IV/DRP/RPB-B
To: Diya F
Ameren Missouri
References
IR 2021004
Download: ML21362A760 (23)


Text

January 7, 2022

SUBJECT:

CALLAWAY PLANT - INTEGRATED INSPECTION REPORT 05000483/2021004

Dear Mr. Diya:

On December 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Callaway Plant. On January 5, 2022, the NRC inspectors discussed the results of this inspection with Mr. B. Cox, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Gregory E. Werner, Chief Reactor Projects Branch B Division of Reactor Projects Docket No. 05000483 License No. NPF-30

Enclosure:

Inspection Report 05000483/2021004

Inspection Report

Docket Number:

05000483

License Number:

NPF-30

Report Number:

05000483/2021004

Enterprise Identifier:

I-2021-004-0041

Licensee:

Ameren Missouri

Facility:

Callaway Plant

Location:

Steedman, MO

Inspection Dates:

October 1 to December 31, 2021

Inspectors:

D. Antonangeli, Health Physicist

D. Bradley, Senior Resident Inspector

N. Greene, PhD, Senior Health Physicist

S. Janicki, Resident Inspector

J. Melfi, Project Engineer

E. Simpson, Health Physicist

R. Alexander, Emergency Preparedness Inspector

Approved By:

Gregory E. Werner, Chief

Reactor Projects Branch B

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Callaway Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Callaway operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time on-site as local COVID-19 conditions permitted.

As part of their on-site activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution, observed risk significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Condensate storage tank alignment to auxiliary feedwater systems including motor-driven pumps, the turbine-driven pump, and the non-safety pump on October 27, 2021
(2) Emergency diesel generator train A auxiliary systems, including starting air and jacket water, on November 17, 2021
(3) Class 1E air conditioner SGK05A, after planned maintenance, on November 17, 2021

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Control building elevation 2026' electrical penetration room B, fire area A-17 on November 10, 2021
(2) Control building elevation 2026' electrical penetration room A, fire area A-18 on November 10, 2021
(3) Auxiliary building elevation 2047', component cooling water surge tank area A and B, corridor and personnel hatch areas, rooms 1502, 1503, 1505 and 1507, fire area A-20 on November 10, 2021
(4) Auxiliary building, 2000' elevation, pipe penetration room A, fire area A-24, on November 23, 2021

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during:

Control rod exercising on November 19, 2021

Safety injection accumulator pressurization and emergent issue response to door DSK11273 failure on December 2, 2021

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator training in the simulator, including loss of coolant accident sequences, on October 13, 2021.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) Safety-related flow instrumentation, including Barton gauges, on November 18, 2021
(2) Environmental qualification of safety-related components subject to high energy line breaks outside of containment, including auxiliary feedwater, on November 29, 2021

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Elevated risk for a planned work window on train B emergency diesel generator and essential service water systems on October 12, 2021
(2) Elevated risk for a planned work window on train A emergency diesel generator and essential service water systems on October 26, 2021
(3) Elevated risk for a planned work window on B and D component cooling water pumps on November 1, 2021
(4) Elevated risk for a planned work window on train A diesel fire pump and train C air compressor on November 8, 2021

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Results from inspection of the condensate storage tank, including the floating cover, under Condition Report 202105839, on October 25, 2021
(2) Calculation error for instrumentation uncertainty values on a flow transmitter, under Condition Report 202106211, on November 16, 2021
(3) Residual heat removal pump B vibrations in the alert range, under Condition Report 202105531, on November 22, 2021

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Permanent modification to add in-line air filtration for flow control valves in the turbine-driven auxiliary feedwater system, under Modification Package 21-0017, on October 19, 2021
(2) Permanent modification to improve the reliability of the main feedwater regulating valve positioner, under Modification Package 21-0001, on November 29, 2021

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Train B motor-driven auxiliary feedwater pump after a planned work window on October 6, 2021
(2) Train A emergency diesel generator and essential service water systems after a planned work window on October 27, 2021
(3) Component cooling water pump D after a planned work window on November 3, 2021
(4) Train A class 1E air conditioner SGK05A after a planned work window on November 17, 2021
(5) Instrument air compressor A after planned work window on October 26, 2021
(6) Train B emergency diesel generator and essential service water systems after a planned work window on October 13, 2021

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Residual heat removal train A surveillance under jobs 21508624 and 20503520 on November 23, 2021
(2) Instrument air accumulator leak rate determination surveillance on November 4,2021

RCS Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1) Post-outage leakage testing under jobs 21511241 and 21511360 on November 22, 2021

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted emergency action level and emergency plan changes:

Radiological Emergency Response Plan, Revision 53 (effective 10/19/2021; submitted to the NRC on 11/16/2021)

This evaluation does not constitute NRC approval.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors reviewed the following:

Radiation Work Packages

Job 21501208/500, steam generator blowdown resin changeout - sluice resin from FBM02C and FBM02D

Job 21003213/500, replace leaking relief valve (EP8855A) safety injection accumulator tank A pressure relief valve

RWP 21NewFuel, loading new fuel into vaults in fuel building Electronic Alarming Dosimeter Alarms

Reviewed a list of dose and dose rate alarms during the period, but none were deemed valid, or they were verified as expected Labeling of Containers Reviewed various drums filled with radioactive waste stored in the low-level drum storage area

Number 8690 - mixed waste from accumulator

Number 9008 - used sludge oil

Number 9449 - used oil from RCP C

Number 9559 - used oil from RCP D

Number 10018 - solidified waste

Number 16059 - spent sluiced resin

Number 16085 - steam generator blowdown resin

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) Observed workers exiting the RCA at the health physics access control area
(2) Observed workers smearing and surveying for contamination on new fuel bundles prior to storage in vaults

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) RWP 21BOP, miscellaneous tours, inspections, and low risk work
(2) RWP 21DRUMHOST, radwaste drum host activities
(3) RWP 21LHRA, locked high radiation area entry for miscellaneous minor work activities
(4) RWP 21RP, radiation protection on-shift and routine activities High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:

(1) Room 1313 - volume control tank room
(2) Room 7122 - waste hold up tank room
(3) Room 7218 - drum processing enclosure area
(4) Room 7220 - valve room Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements

71124.02 - Occupational ALARA Planning and Controls

Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (3 Samples)

The inspectors reviewed as low as reasonably achievable practices and radiological work controls. The inspectors observed the following activities:

(1) RWP 21ONLINERB, safety injection accumulator tank A pressure relief valve replacement
(2) RWP 21NEWFUEL, opening/inspection of new fuel assemblies
(3) RWP 21OPS, sluicing of low activity resin into B-25 containers

Radiation Worker Performance (IP Section 03.04) (1 Sample)

(1) The inspectors observed the following activities:

Radiation protection providing job coverage within the field

Radiation protection conducting radiological surveys

Radiation workers entering/exiting the radiologically controlled area

Radiation workers donning/doffing protective clothing

Radiation workers exiting a contaminated area

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (2 Samples)

The inspectors evaluated the configuration of the following permanently installed ventilation systems:

(1) Control room emergency ventilation and filtration system, Units A and B
(2) Technical support center heating, ventilation, and air conditioning and filter adsorber unit Temporary Ventilation Systems (IP Section 03.02)

The inspectors identified no temporary ventilation system in operation.

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS07: High Pressure Injection Systems (IP Section 02.06)===

(1) October 1, 2020, through September 30, 2021

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) October 1, 2020, through September 30, 2021

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) April 1, 2020 through September 30, 2021 OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)
(1) October 1, 2020 through September 30, 2021 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) October 1, 2020 through September 30, 2021

71152 - Problem Identification and Resolution (PI&R)

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in emergency diesel generator auxiliary systems, including starting air, that might be indicative of a more significant safety issue.

INSPECTION RESULTS

Observation: Semi-Annual Trend Review 71152 The inspectors interviewed licensee staff and reviewed the licensees corrective action program, system health reports, and other documentation to identify trends that might indicate the existence of a more significant safety issue related to auxiliary systems supporting the emergency diesel generators (EDGs).

Background The auxiliary systems selected included starting air, lubrication oil, fuel oil, jacket water, and the intercooler for the EDGs. These subsystems are critical to the proper operation of EDGs, during normal and accident conditions, and have components that are both safety-related and nonsafety-related.

The inspectors interviewed corrective action program staff and reviewed existing trend analysis for any related to EDG subsystems over the last 2 years. At the time of the inspection, the licensee had 178 trend analysis condition reports. Of those, two condition reports were related to EDGs: air compressor leakage trends under Condition Report 202000344 and fuel oil chemistry/analysis trends under Condition Report 202007116.

In the review of the condition reports related to EDGs, the inspectors selected the starting air system for their focus since it had a large number of condition reports as compared to the other auxiliary systems. The EDG starting air system was comprised of air compressors, air dryers, pressurized air storage tanks/receivers, and the various valves that distribute the air to EDG components including the air start motor for the EDG. The EDG air compressors, although non-safety, provided the pressurized air that serves to both start the EDG, via the safety-related air tanks, and for instrumentation. Each EDG had two non-safety air compressors, for a total of four: CKJ01A and CKJ01B for EDG A, CKJ01C and CKJ01D for EDG B.

In reviewing the 68 starting air subsystem condition reports written over the last 2 years, the inspectors separated them into the following categories:

23 condition reports involving air issues including leaks in various locations and low air pressure conditions 22 condition reports involving oil issues including high oil levels in compressors due to water in the oil and low oil levels in compressors due to leaks 11 condition reports involving failures of components, either while in-service or during post-maintenance testing, including several compressors inability to maintain pressure and relief valves lifting outside setpoint 12 condition reports involving all other issues such as compressor motor-belt tension problems, temperature of components during service, procedure improvements, and the trend reviews discussed earlier The inspectors also sorted the same 68 starting air subsystem condition reports by component, and noted 26 of the condition reports, or nearly 40 percent, were related to air compressor CKJ01B. The next component, in terms of the largest numbers of condition reports written against it, was air compressor CKJ01A with eight condition reports.

The inspectors reviewed the maintenance history of the four non-safety EDG air compressors and found that there have been three replacements over the last 2 years. Periodic maintenance activities assigned to the air compressors are checking the oil level every 2 weeks, a clean/inspect including an oil change every 6 months, a compressor capacity test every 6 months, a thermography inspection every year, and a rebuild of the unloader valve every 10 years to prevent water intrusion. There was also an on-demand maintenance task to change the oil and flush the oil system if moisture was detected.

The inspectors also reviewed plant health and noted Health Issue 2019002 existed to address elevated moisture content in the EDG starting air tanks. Additionally, Condition Report 202003275 documented a periodic reevaluation of closed Health Issue 2016035 on moisture accumulation in air compressors.

Inspector Assessment The inspectors noted the air compressor leakage trend review, performed under Condition Report 202000344, only reviewed three examples of air leaks and was closed due to being evaluated as low consequence. The remaining condition reports, identified through the inspectors review, occurred after the condition report was written. Since there had not been an additional trend review condition report generated for air system leaks, these more recent condition reports had not been analyzed for a trend.

Similarly, the licensee had not reviewed the trends in oil levels including the adverse phenomenon of humid air introducing water to oil systems during compression. Although the health issue reevaluation under Condition Report 202003275 included several examples of moisture intrusion, it was not a formal trend review and did not capture more recent information since it was initiated in July 2020. The outcome of this reevaluation was to increase the frequency of oil changes and did not address the cause of the moisture intrusion.

The licensee had an on-demand maintenance task to flush and refill a compressors oil system if level increased and/or water was detected. The inspectors noted that this evolution occurred regularly. For example, EDG air compressor CKJ01B had the oil flushed and replaced 6 times in the last 12 months under this on-demand maintenance task. This flushing activity was in addition to the regularly scheduled semiannual oil change maintenance task which occurred three times in 2021. The frequency of changing the oil on CKJ01B, a total of nine times in 1 year, has not been reviewed for a trend by the licensee.

Additionally, the licensee had not reviewed trends in component failures. The inspectors noted that some of the in-service failures could be attributed to the impact of water in oil systems which decreases compressor life. Likewise, the post-maintenance testing failures of components potentially indicated issues with maintenance practices, design issues, or part quality which have not been evaluated for trends by the licensee.

The inspectors concluded that the licensee had not adequately reviewed the starting air system for trends, had tolerated a high rate of safety-related air system leaks, had not adequately addressed air compressor maintenance/design/operation that led to water collecting inside the system, and resulted in a work-around of oil flushing and replacement of compressors. This resulted in the licensees compressor maintenance being reactionary to water intrusion and not preventative.

The licensee did not have a specific timeline to modify the design of the compressors or otherwise address the repeated introduction of water into the system via compression. Plant Health Issue 2019002 may resolve the impacts of water in the starting air system, but it had not been fully approved, with funding, at the time of inspection.

Although there have not been any failures to maintain EDG starting air system pressure within technical specification limits in the last 2 years, the licensee has not prioritized addressing degraded conditions in the air start subsystem. The licensee current maintenance practices have the potential to lead to more significant safety concerns including unplanned inoperable equipment, impacting the availability and reliability of the EDGs.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On November 4, 2021, the inspectors presented the radiation safety inspection results to Mr. M. McLachlan, Senior Director, Plant Support, and other members of the licensee staff.

On November 18, 2021, the inspectors presented the emergency plan change review inspection results to Mr. G. Rauch, Manager, Emergency Preparedness, and other members of the licensee staff.

On January 5, 2022, the inspectors presented the integrated inspection results to Mr. B. Cox, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective

Action

Documents

Condition Reports

200803252; 202106332; 202106487

Miscellaneous

System Health Reports

Various

OTN-AL-00001

Auxiliary Feedwater System

OTN-AP-00001

Condensate Transfer and Storage System

71111.04

Procedures

OTN-NE-0001A

Standby Diesel Generation System

KC-100

Fire Safety Analysis Personnel Hatch and CCW Surge

Tank Area, Fire Area A-20

KC-97

Fire Safety Analysis Electrical Penetration Room B, Fire

Area A-17

Calculations

KC-98

Fire Safety Analysis Electrical Penetration Room A, Fire

Area A-18

Corrective

Action

Documents

Condition Reports

2105017; 202105129; 202105403; 202105665;

2105713; 202105837; 202105866; 202105881;

2106202

71111.05

Fire Plans

Fire Preplan Manual

and 40

Corrective

Action

Documents

Condition Reports

2106599

Miscellaneous

T61.08108

Simulator Training Scenario 21-5

9/9/2021

APA-ZZ-0395

Significant Operator Response Timing

E-0

Reactor Trip or Safety Injection

E-1

Loss of Reactor or Secondary Coolant

E-2

Faulted Steam Generator Isolation

Procedures

OSP-SF-00002

Control Rod Partial Movement

71111.11Q

Work Orders

21510969

NUMARC 93-01

Industry Guidelines for Monitoring the Effectiveness of

Maintenance

4F

Miscellaneous

PM0822012

Calibrate EFFI0055

71111.12

Procedures

APA-ZZ-00549

Guidelines Used to Determine Functional Importance of a

Component

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

APA-ZZ-00750

Hazzard Barrier Program

EDP-ZZ-01129,

Appendix 4

Maintenance Rule System Functions

ITG-ZZ-BT008

Barton Diff Press Ind 227/227A Manual

OSP-EF-P001A

ESW Train A Inservice Test

Work Orders

21004043; 21001811

Corrective

Action

Documents

Condition Reports

201605515; 201607825; 201801299; 201803204;

201901097; 202102008; 202106027; 202106177

Corrective

Action

Documents

Condition Reports

2104999; 202105808; 202105930; 202106339;

2106362; 202106394; 202106545

Miscellaneous

NUMARC 93-01

Industry Guidelines for Monitoring the Effectiveness of

Maintenance at Nuclear Power Plants

4F

APA-ZZ-00315

Configuration Management Program

APA-ZZ-00322,

Appendix F

Online Work Integrated Risk Management

APA-ZZ-01250

Operational Decision Making

EDP-ZZ-01129

Callaway Energy Center Risk Assessment

ODP-ZZ-00002,

Appendix 1

Protected Equipment Program

71111.13

Procedures

ODP-ZZ-00002,

Appendix 2

Risk Management Actions for Planned Risk Significant

Activities

and 19

Corrective

Action

Documents

Condition Reports

2103398; 202104007; 202105531; 202105839;

2105982; 202106226; 202106211; 202106661;

2106788

M-22 EJ01

Residual Heat Removal PI&D

Miscellaneous

ULDB-ECCS

ECCS Design Basis Document

71111.15

Procedures

APA-ZZ-01250

Operational Decision Making

Corrective

Action

Documents

Condition Reports

201601712; 201701409; 202001783; 202004855;

2106554

M-11759-00009

Digital Feedwater System - MFRV

71111.18

Miscellaneous

M-22 EA01

Feedwater System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MP 21-001

Main Feedwater Regulating Valve Positioner

MP 21-0017

Install 3-micron filtration

Corrective

Action

Documents

Condition Reports

200400500; 200407421; 202101631; 201109634;

201800026; 202102441; 202103628; 202105931;

2105957; 202105995; 202106165

Miscellaneous

SOER 88-1

Instrument Air System Folders

APA-ZZ-00322,

Appendix E

Post-Maintenance Test Program

MPE-ZZ-QY045

Inspection, Test, and Calibration of Miscellaneous

Protective, Control, and Time Delay Relays

MPE-ZZ-QY124

Operational Test Sequence of Component Cooling Water

Pump Air Circuit Breaker

Procedures

OSP-NE-0001A

Standby Emergency Diesel Generator Periodic Tests

71111.19

Work Orders

20504947; 20507578; 21506897; 16505253; 21510017;

15502781; 21004019; 18512878; 20505701; 19510058;

20505700

ODP-ZZ-00029

RCS Leakage Action Level Guideline

ODP-ZZ-00036

Technical Specification Application for Containment

Isolation Valves

OSP-BB-00009

RCS Inventory Balance

Procedures

OSP-NE-0001A

Standby Diesel Generator A Periodic Tests

71111.22

Work Orders

21510017; 21511360; 21511241; 21508624; 20503520

Corrective

Action

Documents

Resulting from

Inspection

Condition Reports

2106364

Applicability Determination: RERP, Revision 53

09/30/2021

50.54(q) Effectiveness

Evaluation No.

20030

RERP, Revision 53 (Move of Montgomery County EOC)

10/31/2020

71114.04

Miscellaneous

50.54(q) Screening

No. 2020030

RERP, Revision 53 (Move of Montgomery County EOC)

10/31/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

50.54(q) Screening

No. 2021016

RERP, Revision 53 (Change 1)

09/30/2021

50.54(q) Screening

No. 2021017

RERP, Revision 53 (Change 3)

09/30/2021

50.54(q) Screening

No. 2021018

RERP, Revision 53 (Change 4)

09/30/2021

50.54(q) Screening

No. 2021019

RERP, Revision 53 (Change 5)

09/30/2021

50.54(q) Screening

No. 2021021

RERP, Revision 53 (Change 7)

09/30/2021

50.54(q) Screening

No. 2021022

RERP, Revision 53 (Change 8)

09/30/2021

71124.01

Corrective

Action

Documents

Condition Reports

2004693, 202004719, 202005532, 202005799,

2005827, 202100360, 202101466, 202101682,

2101938, 202103270, 202103818

71124.01

Corrective

Action

Documents

Resulting from

Inspection

Condition Reports

2106131, 202106132

Hot Spot Trending Log (RWST-1, Room 1109,

Room 1111)

11/01/2021

Air Samples Log Since 10/19/2020

10/11/2021

List of Dose and Dose Rate Alarms - No Valid or As

Expected Alarms

11/02/2021

PM 1002835

Non-Special Nuclear Material Radioactive Materials

Stored in Spent Fuel Pool

10/11/2021

Miscellaneous

S120.0010

Radiation Key Inventory Form

11/02/2021

APA-ZZ-01000

Callaway Energy Center Radiation Protection Program

APA-ZZ-01004

Radiological Work Standards

APA-ZZ-01106

Lock and Key Control

HDP-ZZ-01200

Radiation Work Permits

HDP-ZZ-01500

Radiological Postings

71124.01

Procedures

HDP-ZZ-03000

Radiological Survey Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HTP-ZZ-01203

Radiological Area Access Control

HTP-ZZ-06001

High Radiation / Locked High Radiation / Very High

Radiation Area Access

CA-M-20161123-2

Room 7215 - Decant Tank Room

11/23/2016

CA-M-20190313-4

Room 7218 - Drum Processing Enclosure - Clean Oil

Level

03/13/2019

CA-M-20200727-1

Room 7121 - Waste Hold Up Tank - Flush Hot Spot

07/27/2020

CA-M-20210125-3

24 and 7123 Re-Lamp Primary Waste Evaporator

Bottoms Tank and Pump Rooms

01/25/2021

CA-M-20210825-2

Radwaste - F/D FEC01A FEC01B (Filters/Demineralizers)

08/25/2021

Radiation

Surveys

CA-M-20210826-9

Radwaste 2047 Filter Change - Radwaste Building

General Area

08/26/2021

Job 11509289500

Spent Fuel Pool Cooling Heat Exchanger Eddy Current

Testing

Job 19505696

Decontaminate Reactor Cavity

Job 19505914

Install Reactor Vessel Head IPTE (PCC) High Risk

Evolution

RWP 21BOP

Miscellaneous Tours, Inspections, and Low Risk Work

RWP 21DRUMHOST

Radwaste Drum Host Activities

RWP 21LHRA

Locked High Radiation Area Entry for Miscellaneous

Minor Work Activities

RWP 21NRC

NRC Tours and Inspections

RWP 21ONLINERB

On Line Support Activities in the Reactor Building

Radiation Work

Permits (RWPs)

RWP 21RP

Radiation Protection On-Shift and Routine Activities

2007247-031

Self-Assessment: HRA/LHRA Controls

06/15/2021

AP 21002

Nuclear Oversight Audit of Radiation Protection Program

03/06/2021

Self-

Assessments

Condition Report

2103270

Self-Assessment: HRA/LHRA Controls

06/09/2021

Corrective

Action

Documents

Condition Reports

2005644; 202005905; 202007218; 202100481;

2101186; 202101516; 202101645; 202102031;

2105305; 202105535; 202105548

APA-ZZ-01001

Callaway Plant ALARA Program

71124.02

Procedures

HDP-ZZ-01100

ALARA Planning and Review

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HDP-ZZ-01200

Radiation Work Permits

Survey CA-M-

210826-9

RW-2047 Filter Change

08/26/2021

Survey CA-M-

211104-5

RB-2047 - Support OPS hang WPA for EP885A

Replacement

11/04/2021

Survey CA-M-

211104-7

RB-2008AD - Support OPS hang WPA for EP8855A

Replacement

11/04/2021

Survey CA-M-

211104-8

RB-2000 - Support OPS hang WPA for EP88551

Replacement

11/04/2021

Radiation

Surveys

Survey CA-M-

211104-9

RB-2026A - EP8855A Job Coverage

11/04/2021

21NEWFUEL

New fuel Receipt prior to RF25. Includes associated

engineering and operation tasks.

21ONLINERB

On-line support activities in the reactor building

21OPS

Operations and radwaste routine activities including WPA,

technician rounds, and shipping activities

Radiation Work

Permits (RWPs)

21RP

Radiation protection on-shift and routine activities

Callaway Energy Center Refuel 23 ALARA Outage

Report

05/18/2019

Callaway Energy Center Refuel 24 ALARA Outage

Report

2/22/2020

Audit Report AP21002

Nuclear Oversight Audit of Radiation Protection Program

03/16/2021

Self-

Assessments

Surveillance Report

SP20004

Nuclear Oversight Performance Assessment of Refuel 24

Execution

03/04/2021

Calculations

HPCI-96-007

Emergency Response Facility Habitability Guidelines

Corrective

Action

Documents

Condition Reports

201806070, 201900689, 201901129, 201901289,

201901755, 201901985, 201904604, 201905248,

201905513, 201905530, 201906469, 201906706,

201906771, 201906935, 202000038, 202000136,

2001958, 202002124, 202002579, 202004078,

2004283, 202006934, 202103370, 202104083

A-UAT-19

Technical Support Center HVAC Plan

71124.03

Drawings

M-22GK01(Q)

Piping and Instrumentation Diagram Control Building

HVAC

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

M-22GK01(Q)

Piping and Instrumentation Diagram Control Building

HVAC

APA-ZZ-01004

Radiological Work Standards

APA-ZZ-01004,

Appendix C

General Instructions for Donning and Removing

Respiratory Equipment

EIP-ZZ-00240

Technical Support Center Operations

ESP-GK-03010

FGK01A In-Place Bypass Leakage Test

ESP-GK-03012

FGK01B In-Place Bypass Leakage Test

HDP-ZZ-03000,

Appendix D

Performing Airborne Radioactivity Surveys

HDP-ZZ-08000

Respiratory Protection Program

HTP-ZZ-03006

Use of Airborne Sampling Cart

HTP-ZZ-08002

Respiratory Protection Issue and Use

HTP-ZZ-08203

Testing Scott Regulators and Respirators Using the

Biosystems Posichek 3 USB Tester

HTP-ZZ-08300-DTI-

Airpak75

Scott Air-Pak 75 SCBA Respirator Inspection and Storage

HTP-ZZ-08300-DTI-

POST HYDRO

Post Hydrostatic Testing of Breathing Air Cylinders

HTP-ZZ-08300-DTI-

SKAPAK

SKA-PAK AT SCBA Respirator Storage and Inspection

HTP-ZZ-08501-DTI-

Air Test

Testing of Breathing Air

HTP-ZZ-08503-DTI-

UNIIICOMPRESSOR

Operation of Bauer Unicus III, 25 CFM Breathing Air

Compressor and Breathing Air Cascade System

ISF-GK-00R05

Control Room HVAC Radiation Monitor 'A' Train Channel

Operational Test

Procedures

ISL-GK-00R05

Control Room HVAC Radiation Monitor 'A' Train Channel

Calibration

Self-

Assessments

Audit No. AP21002

Nuclear Oversight Audit of Radiation Protection Program

03/16/2021

JOB 20500530.500

HEPA Filter Leak Test Results

09/14/2021

JOB 20501202.500

Radioiodine Penetration/Efficiency Test

07/01/2021

Work Orders

JOB 20501472.500

HEPA Filter Leak Test Results

09/29/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

JOB 20502786.500

Radioiodine Penetration/Efficiency Test

09/23/2021

Corrective

Action

Documents

Condition Reports

2105449

MSPI Summary Reports

Various

Miscellaneous

Callaway Energy Center 2020 Annual Radioactive

Effluent Release Report

04/28/2021

71151

Self-

Assessments

Audit 21002-RP21

Public and Occupational Exposure Controls and

Monitoring

03/06/2021

71152

Corrective

Action

Documents

Condition Reports

2105333; 202103060; 202101915; 202105736;

2106283; 202106298; 202106306; 202106437;

2106494

GW

JE

MH

DP

HG

AS

VG

FR

  • via email

DATE

CALLAWAY PLANT - INTEGRATED INSPECTION REPORT 05000483/2021004

January 7, 2022