PNO-I-97-053, on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR22 August 1997PNO-I-97-053:on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR
PNO-I-90-094, on 901016,transfer of Fuel Assemblies Stuck in Upper Core Internals.No Apparent Damage to Dropped Fuel Assembly Occurred.Recovery Operations Secured17 October 1990PNO-I-90-094:on 901016,transfer of Fuel Assemblies Stuck in Upper Core Internals.No Apparent Damage to Dropped Fuel Assembly Occurred.Recovery Operations Secured
PNO-I-90-077, on 900906,unplanned Shutdown Greater than 48 H Occurred Due to RCS Packing Leak from Pressurizer Spray Valve.Plant Placed in Hot & Cold Shutdown.Licensee Activities Monitored & State of Ny Informed7 September 1990PNO-I-90-077:on 900906,unplanned Shutdown Greater than 48 H Occurred Due to RCS Packing Leak from Pressurizer Spray Valve.Plant Placed in Hot & Cold Shutdown.Licensee Activities Monitored & State of Ny InformedPacking leak
PNO-I-90-065, on 900814,licensee Reported That Licensed Reactor Operator Tested Positive for Marijuana as Result of Random Fitness for Duty Test.Operator Unescorted Site Access Suspended for 14 Days15 August 1990PNO-I-90-065:on 900814,licensee Reported That Licensed Reactor Operator Tested Positive for Marijuana as Result of Random Fitness for Duty Test.Operator Unescorted Site Access Suspended for 14 DaysFitness for Duty
PNO-I-90-063, on 900809,plant Shutdown Due to Potential Loss of Three Emergency Diesel Generators.Caused by Blown Control Power Fuse.Fuse Replaced9 August 1990PNO-I-90-063:on 900809,plant Shutdown Due to Potential Loss of Three Emergency Diesel Generators.Caused by Blown Control Power Fuse.Fuse Replaced
ML20245G21821 June 1989PNS-I-89-010:on 890621,Dept of Investigation in New York City Received Call Threatening Destruction of Plant & Ref 1977 Incident Where Damage Inflicted on Plant.Bomb Threat Contingency Procedures Implemented & Security Maintained
PNO-I-88-065, on 880617,unit Tripped Due to High Water Level in Steam Generator 22.Caused by Contractor Cleaner Inadvertently Activating Boiler Feed Pump.Licensee Elected to Enter Cold Shutdown to Repair Connoseals20 June 1988PNO-I-88-065:on 880617,unit Tripped Due to High Water Level in Steam Generator 22.Caused by Contractor Cleaner Inadvertently Activating Boiler Feed Pump.Licensee Elected to Enter Cold Shutdown to Repair Connoseals
PNO-I-88-003, on 880101,steam Generator (SG) 23 Boiled Dry During Plant Heatup.Cause Not Stated.On 880104,station Mgt Started Evaluating Safety Significance of Event & Best Method to Refill Generator.Sg 23 Refilled on 8801057 January 1988PNO-I-88-003:on 880101,steam Generator (SG) 23 Boiled Dry During Plant Heatup.Cause Not Stated.On 880104,station Mgt Started Evaluating Safety Significance of Event & Best Method to Refill Generator.Sg 23 Refilled on 880105
PNO-I-87-039, on 870430,licensee Identified Potential Circuit Failure Preventing Automatic Start of Auxiliary Feedwater Pumps by Loss of Main Feedwater or lo-lo Steam Generator Signals.Circuit Modified for Independent Relays1 May 1987PNO-I-87-039:on 870430,licensee Identified Potential Circuit Failure Preventing Automatic Start of Auxiliary Feedwater Pumps by Loss of Main Feedwater or lo-lo Steam Generator Signals.Circuit Modified for Independent Relays
PNO-I-87-025, on 870326,licensee Announced Plans to Shut Down Reactor on 870327 Due to Steadily Increasing Leakage on Reactor Coolant Pump Seal.Caused by Degraded Seal.Shutdown Expected to Last 10 Days26 March 1987PNO-I-87-025:on 870326,licensee Announced Plans to Shut Down Reactor on 870327 Due to Steadily Increasing Leakage on Reactor Coolant Pump Seal.Caused by Degraded Seal.Shutdown Expected to Last 10 Days
ML20207R1796 March 1987PNS-I-87-003:on 870306,security Officer at Offsite Training Ctr in Toddville,Ny Received Bomb Threat by Telephone.Search of Site Produced Negative Results.Local Law Enforcement Agencies Responded.Security Measures Heightened
PNO-I-87-010, on 870211,reactor Scrammed from Full Power During Transient Initiated by Loss of Instrument Bus.Safety Injection Signal Received on High Steam Flow Coincident W/Low Steam Line Pressure.Plant Stabilized in Hot Shutdown12 February 1987PNO-I-87-010:on 870211,reactor Scrammed from Full Power During Transient Initiated by Loss of Instrument Bus.Safety Injection Signal Received on High Steam Flow Coincident W/Low Steam Line Pressure.Plant Stabilized in Hot Shutdown
PNO-II-86-078, on 861021,2 Gallons of Hydrazine Spilled in Turbine Bldg.Caused by Leak in Deionized Water Mixing Valve Overflowing Mix Tank.Spill Cleaned Up22 October 1986PNO-II-86-078:on 861021,2 Gallons of Hydrazine Spilled in Turbine Bldg.Caused by Leak in Deionized Water Mixing Valve Overflowing Mix Tank.Spill Cleaned Up
PNO-I-86-084, on 861020,reactor Tripped.Caused by Failure of Safety Injection Logic Relay Which Demands Reactor Trip Upon Safety Injection Actuation.Difficulties Encountered W/Two of Three Auxiliary Feedwater Pumps21 October 1986PNO-I-86-084:on 861020,reactor Tripped.Caused by Failure of Safety Injection Logic Relay Which Demands Reactor Trip Upon Safety Injection Actuation.Difficulties Encountered W/Two of Three Auxiliary Feedwater Pumps
PNO-I-86-060, on 860806,vital Bus Normal Supply Breaker 6A Tripped Due to Indicated Bus Fault.Caused by Emergency Diesel Generator Supply Breaker Shorting Phase to Phase.Bus Repaired6 August 1986PNO-I-86-060:on 860806,vital Bus Normal Supply Breaker 6A Tripped Due to Indicated Bus Fault.Caused by Emergency Diesel Generator Supply Breaker Shorting Phase to Phase.Bus Repaired
PNO-I-86-049A, on 860706,forced Outage Entered When 18-inch Piece of Blade Foil from Low Pressure Turbine 1 Broke Off During Startup.Cause Unidentified.Options to Repair &/Or Replace Available Rotors Being Evaluated23 July 1986PNO-I-86-049A:on 860706,forced Outage Entered When 18-inch Piece of Blade Foil from Low Pressure Turbine 1 Broke Off During Startup.Cause Unidentified.Options to Repair &/Or Replace Available Rotors Being EvaluatedNondestructive Examination
PNO-I-86-051, on 860718,plant Operator Contaminated While Assisting in Repair of Gasket Leak in Steam Environ.Caused by Removal of Required Wet Gear & Respirator When Operator Passed Out from Heat Prostration.Operator Hospitalized18 July 1986PNO-I-86-051:on 860718,plant Operator Contaminated While Assisting in Repair of Gasket Leak in Steam Environ.Caused by Removal of Required Wet Gear & Respirator When Operator Passed Out from Heat Prostration.Operator Hospitalized
PNO-I-86-049, on 860706,18-inch Piece of Blading from Low Pressure Turbine 31 Broke Off During Main Generator Startup. Turbine Vendor Evaluating Damage.Repair Expected to Take at Least 1 Wk7 July 1986PNO-I-86-049:on 860706,18-inch Piece of Blading from Low Pressure Turbine 31 Broke Off During Main Generator Startup. Turbine Vendor Evaluating Damage.Repair Expected to Take at Least 1 Wk
PNO-I-85-071, on 850927,Hurricane Gloria Located 50 Miles East of Cape May,Nj.Reactor Facilities Located Along Coast Implementing Procedures Per Emergency Plans.Listed Plants Shutting Down.Oyster Creek Reduced Power Levels to 35%27 September 1985PNO-I-85-071:on 850927,Hurricane Gloria Located 50 Miles East of Cape May,Nj.Reactor Facilities Located Along Coast Implementing Procedures Per Emergency Plans.Listed Plants Shutting Down.Oyster Creek Reduced Power Levels to 35%
PNO-I-85-043, on 850623,10 Indications of Unacceptable Size of Steam Generator Shell Transition Girth Weld Per ASME Section XI Found Through Ultrasonic Exam.Caused by pre-existing Flaws Present After 1983 Repairs26 June 1985PNO-I-85-043:on 850623,10 Indications of Unacceptable Size of Steam Generator Shell Transition Girth Weld Per ASME Section XI Found Through Ultrasonic Exam.Caused by pre-existing Flaws Present After 1983 Repairs
ML20197G90114 June 1984PNS-I-84-011A:on 840613,licensee Provided Update on Status of Investigation Re Falsified Records of Employment Ltrs. Licensee Will Request Unions to Conduct Background Investigations Per ANSI 18.17
PNO-I-80-135, on 800924,both Containment Spray Pumps Discovered in pull-to-lock Position After Tagging by Operators Per Containment Entry Procedure.Switches Returned to Automatic Position & Change to Procedure Initiated26 September 1980PNO-I-80-135:on 800924,both Containment Spray Pumps Discovered in pull-to-lock Position After Tagging by Operators Per Containment Entry Procedure.Switches Returned to Automatic Position & Change to Procedure InitiatedMission time
ML20217B0327 December 1978PNO-78-025:on 781207,licensee Commenced Plant Shutdown to Effect Repairs to One of Four Sgs.Primary to Secondary Sys Leak of 0.10 Gpm Indicated on 781206.No Release of Radioactivity to Environ Occurred
ML20216J73324 November 1978PNO-78-195:on 781124,small Leak Developed in Socket Weld on Drain Line from Seal Injection Headers to Reactor Pump.Leak Did Not Result in Any Radioactivity Release to Environ.State of Ny Informed
ML20217B19430 August 1978PNO-78-157:on 780829,leak Was Detected Upon Completion of Repairs to Manifold in Hydrogen Gas Storage Area & Small Explosion Occurred While Workers Tried to Stop Leak.State of New York & OSHA Informed.Region I Notified on 780830
ML20236E81813 April 1978PNO-78-081:on 780413,Region I Informed by Licensee That Maint Workers March Film Badge Result Indicated Exposure of 3.11 Rem That Would Give Individual Quarterly Exposure of 4.47 Rem.State of New York Informed
ML20248L25823 March 1978PNO-78-060:on 780321,three Offsite Licensee Maint Workers Were Reassigned to Plant to Work in Radiation Areas.Refusal of Assignment Resulted in Discharge for One Worker.Worker Was Interviewed by Radio & Television on 780321
ML20249A88722 November 1977PNS-77-047:on 771122,Westchester Business Ofc of Consolidated Edison Co,New York Received Telephone Call Re Bomb Threat from an Unidentified Male.Emergency Procedures in Effect.State of Ny Informed
ML20249A9114 August 1977PNS-77-030:on 770803,call Was Received Stating That Two Facilities Would Be Bombed.Bomb Threat Procedures Were Implemented.Site Was Searched & Threat Was Declared Over. Licensee Maintained Alert Status Through 770804
ML20151Y10815 July 1977PNO-77-126B:on 770714,electrical Output Added to Distribution Sys at Indian Point Unit 3.Reactor Power Level Increased Throughout Night as Customers Incrementally Added to Sys.Nrc Inspector Witnessing Operation Repts
ML20151X99814 July 1977PNO-77-126A:Inspectors on Site Determined That IPS Unit 3 Safety Sys Functioned Properly Following Reactor Trip & During Nearly 6 Hour Loss of Offsite Power.Licensee Held Press Conference on 770714.Reactor to Be Brought Critical
ML20151X62414 July 1977PNO-77-126:on 770713,unit 3 Reactor Tripped from 91% Power Due to Lightning Strike & Resulting Fire at Buchanan,Ny Substation Located 1/2 Mile from Indian Point Site. Caused by Power Blackout
ML20151X6535 July 1977PNO-77-120:on 770702,unit Shutdown Due to RCP Seal Failure. Approx 40,000 Gallons of RCS Water Was Leaked Over Period of 8 H Into Containment Via Failed Seal While Unit Being Placed in Cold Shutdown Condition
ML20236J87127 September 1976PNS-76-055:on 760925,an Automobile Was Driven Through Double,Closed,Locked & Manned Main Vehicle Gate at Owner Controlled Perimeter,Resulting in Damage to Both Gates. Plant Guards Apprehended Driver
ML20249B94822 September 1976PNO-76-162:while Shutdown for Scheduled Maint Outage,Minor Leak Was Observed in Vicinity of factory-made Weld on Outlet Nozzle of Boron Injection Tank.Insp & Radiographs Confirmed That Weld Joining Pipe safe-end to Tank Was Defective
ML20249B33030 April 1976PNO-76-081:while Reactor Shutdown,Between Five & Ten Gallons of Nonradioactive Borated Water Inadvertently Sprayed Inside Containment.Caused by Operator Error Due to Improper Valve Lineup
ML20249B3777 April 1976PNO-76-066:on 760406,initial Criticality Achieved.Region I Inspectors at Site Reported That Actual Boron Concentration Was in Close Agreement W/Predicted Values.State of New York Informed & Press Release Planned by Licensee
ML20249B20217 March 1976PNO-79-043:on 760317,nonisolable Leak in RCS Was Identified During Post Core Load Hot Functional Testing.Rcs Being Cooled Down to Make Repairs.Cause of Leak Has Not Yet Been Determined
ML20236F7991 March 1976PNS-76-005A:on 760229, Citizens for Protection of Environ Held Planned Demonstration at Entrance to Licensee Facility. Counter Demonstration by United Utility Workers of America, Local 3 Also Held at Same Time.No Physical Clash Occurred
ML20236F25124 February 1976PNS-76-005:on 760224,licensee Advised That Citizens for Protection of Environ Petitioned Buchanan,New York Police Dept for Permit to Demonstrate at Entrance to Facility on 760229.Permit Granted
ML20249B24623 January 1976PNO-76-012:on 760121 & 22,fish Mortality on Intake Screens of CWS Was 12,799 & 18,233 Respectively.One of Five Operating Circulating Water Pumps Was Shutdown to Reduce Mortality.State of Ny Informed
ML20236U9225 November 1975PN-75-118:on 751101-03,fish Mortality on Intake Screens of Circulating Water Sys Exceeded Environ TS Action Level of 5000 Per Day on Three Consecutive Days.Two Circulating Water Pumps Were Shutdown on 751103 & One Was Shut Down on 751104
ML20236V10520 October 1975PN-75-110:on 751016,unplanned Shutdown Instituted,Due to Electrical Fault in Main Generator.Short Found in C Phase, Apparently Caused by Metal Cylinder Found Lodged in Windings.Duration of Shutdown Not Yet Established
ML20236U85626 September 1975PN-75-098:on 750926,guard Received Call from Onsite Extension That Bomb Was in Plant.Bomb Threat Procedures Were Instituted.No Bomb Found
ML20236T98225 June 1975PN-75-041:for Several Weeks,Westinghouse Has Been Repairing Cladding Cracks in Sgs.Cracks Apparently Caused by Saltwater Intrusion Which Occurred When Generators Were Shipped by Barge Several Years Ago
ML20236T99218 June 1975PN-75-038:on 750617,fire Occurred in Temporary Const Bldg at Site.Ofc Equipment,Benches & Boxes of Insulation Destroyed. State of Ny Informed
ML20236U2342 June 1975PN-75-030:on 750602,Insp & Enforcement Ofc Was Informed That Reactor Tripped from Loss of 1 Source of Offsite Power. Janitor Was Found on Small Parapet W/Serious Burns Over Portion of Body & Has Been Hospitalized
ML20236U01716 April 1975PN-75-011:on 750416,licensee Reported That Bomb Threat Called Into New York Daily News Newspaper,To Effect That Three Bombs Placed at Two Power Plants of Consolidated Edison Co.No Bombs Found